Commissioning Scheme For Synchronization System: Sichuan Tongneng Electric Science &technology Co., LTD
Commissioning Scheme For Synchronization System: Sichuan Tongneng Electric Science &technology Co., LTD
Part V
Commissioning Scheme for Synchronization System
1
India Tengda 2×330MW Coal-Fired Power Plant Project -- Electric Commissioning Scheme
Contents
1. Overview
2. Purpose of Commissioning
3. Commissioning standard
4. General Situation and Basic Technical Parameters of Equipment
5. Instruments & Equipment for Commissioning
6. Scope of Commissioning
7. Organization and Work Division
8. Requirements for commissioning
9. Commissioning Method and Working Procedures
10. Quality Control Measures
11. Safety Precautions in Commissioning
2
India Tengda 2×330MW Coal-Fired Power Plant Project -- Electric Commissioning Scheme
1 Overview
The juxtaposition point of dynamotor unit and power grid of India Tengda 2×330MW
Coal-Fired Power Plant Project is arranged on the outlet 220kV side breaker at the side of high
voltage of main transformer. To totally check the secondary equipments, automatic devices and
can run into operation reliably through the dynamotor synchronous test.
2 Purpose of Commissioning
2.1 Find out the danger possibly hidden in the synchronization circuit.
2.2 Check and verify the correctness and integrality of synchronization circuit.
3 Commissioning standard
3.1 Specifications for Start-up and Acceptance of Capital Construction Engineering of Thermal
3.2 Regulations for Start-up and Commissioning of Thermal Power Engineering DLBJSXTSJZ
[1996] No.40
3.3 Standard for Quality Inspection and Evaluation of Thermal Power Engineering Adjustment
3.4 Standard for Quality Inspection and Evaluation of Thermal Power Construction (Electric
Chapter)
3.5 Evaluation Standard for Reaching Set Standards and Going into Production of Thermal Power
3
India Tengda 2×330MW Coal-Fired Power Plant Project -- Electric Commissioning Scheme
3.6 Dynamic Evaluation Method for Reaching Set Standards and Going into Production of
3.7 Code of Safety Operation in Power Engineering Construction DL5009.96 (Part of thermal
power plant)
3.8 Code of Safety Operation in Power Engineering Construction (Electric part of power plant
and substation)
3.9 Technical Specification for Power Construction and Acceptance Check (Electric part)
3.10 Typical Outline for Quality Supervision and Inspection of Key Projects of Thermal Power,
3.11 Typical Outline for Quality Supervision and Inspection of Complete Set Commissioning
3.12 Standard for Electric Device Installation Engineering Electric Equipment Hand-over Test
GB50150
3.15 Inspection Rule for Relaying Protection and Power Grid Security Automatic Device
3.16 Measures for Accident Prevention of Relaying Protection and Security Automatic Equipment
in Electric System
3.17 Regulation for Fieldwork Security of Relaying Protection and Power Grid Security
Automatic Device
3.18 The technical data provided by manufacturer and relevant design drawing provided by design
4
India Tengda 2×330MW Coal-Fired Power Plant Project -- Electric Commissioning Scheme
unit
3.19 The relevant checking and acceptance document of quality management of the unit
4 General Situation and Basic Technical Parameters of Equipment (parameters are not
available at present)
5 Commissioning scope
The commissioning scope contains the automatic devices and relevant secondary circuits of
synchronous system of dynamotor-transformer unit, including the circuit connecting the DCS
instrument, WFLC-2B transient recorded waveform analyzing instrument of China Electric Power
7.1 The commissioning unit should be responsible for on-site direction and test work.
7.2 The power plant should be responsible to contact the operator and harmonize the operating
mode.
7.3 The power plant should be responsible for the work related to equipment operation.
5
India Tengda 2×330MW Coal-Fired Power Plant Project -- Electric Commissioning Scheme
8.1 The installation and commissioning of the primary and secondary equipment of
dynamotor--transformer have been accomplished and are accordance with the regulations and
8.2 The name and code of the electrical equipment in electriferous area are complete; the
electriferous equipments have clear symbol; the transformer substation and each distribution
8.3 The commissioning site has been cleared up completely; the falsework has been removed; the
road is smooth; the lighting is sufficient; the cable holes have been plugged; the cover plate of
cable trench has been well covered; and the fireproofing facilities have been checked and
accepted.
8.4 The tap position of main transformer and factory higher voltage transformer has been placed in
the setting position according to the operating requirements, and the DC resistance of setting
8.5 The failure oil discharge system of main transformer and factory higher voltage transformer is
qualified with using conditions. The gas relay has been blown off.
8.6 The fireproofing facilities in electriferous area are complete and qualified with using
conditions.
8.7 The big interlocking transmission test of dynamotor, boiler and electrical equipment is correct.
8.8 All electriferous area should be free of person and work ticket when the test is started up.
8.9 The relay protection device has been set in accordance with the Protection Setting List and is
8.10 The static commissioning of excitation regulator of dynamotor transformer unit has been
6
India Tengda 2×330MW Coal-Fired Power Plant Project -- Electric Commissioning Scheme
finished and is qualified with the requirements of manufacturer and relevant regulations.
8.11 The transmission test of the protection, excitation and control circuit of dynamotor
8.12 The static commissioning of synchronization device has been accomplished and the result is
8.13 The commissioning and setting of synchronization lock relay is accomplished and the result
8.14 The inspection of synchronization secondary circuit is finished with a correct result.
8.15 The simulation of synchronization system and the breaker test of relay have been
9.1.1 All personnel taken part in the test work of synchronization system should read this measure
carefully to learn the duty and question the confused part of this measure before start-up.
9.1.2 The testing personnel should prepare relevant drawing, data, testing instrument, test
9.1.3 In order to prevent incorrect electricity transporting and voltage stepping up, the high (low)
voltage breaker and isolating switch of transformer and dynamotor should be kept at the
disconnecting place and the 6kV side breaker and isolating switch of factory higher voltage
transformer should be kept at the out pulling place. No body could start the operation unless
7
India Tengda 2×330MW Coal-Fired Power Plant Project -- Electric Commissioning Scheme
9.1.4 To verify there’s no open-circuit phenomenon in the secondary current circuit and
9.1.5 To adjust and connect the recording oscillograph so as to check the correctness of
synchronization system and record the dynamotor voltage and the relationship between
amplitude, phase and frequency of system voltage at the paralleling point when the
juxtaposition operation.
9.2.1 To check and verify that the 220kV outgoing wire isolating switch at the side of high voltage
of main transformer is kept at the disconnecting place, the 220kV outgoing wire grounding
switch at the side of high voltage of main transformer is kept at the disconnecting place, and
the 220kV outgoing wire breaker at the side of high voltage of main transformer is kept at
9.2.2 To check and verify that the switch at the neutral point of main transformer is kept at the
connecting place.
9.2.3 To check and verify that the PT and primary and secondary fuse have been put in the
dynamotor outlet; to check and verify that the power fuses of all protective circuit and
control circuit of dynamotor transformer unit should be well, the specification should be in
accordance with the design requirements, and enough spare parts should be provided.
9.2.4 To check and verify that all protections have been put in the dynamotor transformer unit.
9.2.5 To check and verify that the excitation system has been provided with the electriferous
8
India Tengda 2×330MW Coal-Fired Power Plant Project -- Electric Commissioning Scheme
9.2.6 To check and verify that the PT of 220kV bus has been electriferous.
9.2.7 To trigger the dynamotor and increase the voltage to a rating value, 24kV for primary and
110V for secondary; the primary voltage at the side of high voltage of main transformer is
9.2.8 To operate the synchronous operating switch on DCS to guide into the 220kV bus PT
synchronous voltage, and observe the action status of synchronous lock relay TJJ.
9.2.9 To use the automatic synchronous operating switch on DCS to operate the
9.2.10 To observe whether the direction of voltage regulating and frequency regulating of
and periodic waveform difference or not. When the condition is qualified, use the
9.2.11 To exit the automatic synchronizing switch and synchronizing switch on DCS.
9.2.12 To start aside the 220kV breaker at the side of high voltage of main transformer and revert
or verify relevant signal, and there should be no abnormal signal or failure signal.
9.3.1 Close the grounding switch at the neutral point of main transformer in accordance with the
operating requirements.
9.3.2 Check and verify that the 220kV isolating switch at the side of high voltage of main
transformer is closed.
9.3.3 Check the voltage of dynamotor, the rating value should be: 24kV for primary and 110V for
9
India Tengda 2×330MW Coal-Fired Power Plant Project -- Electric Commissioning Scheme
secondary; the primary voltage at the side of high voltage of main transformer is 235KV, and the
9.3.4 Operate the synchronizing switch to guide into the 220kV bus PT synchronous voltage.
9.3.5 Contact the operator for approval of parallel operation and contact the technical personnel of
9.3.6 When the condition is qualified, use the automatic synchronous switch to operate the
9.3.7 After the parallel operation signal of unit is verified, disconnect the automatic synchronizing
9.3.8 After the juxtaposition of dynamotor and system is accomplished, the operation should be
done with the initial load. To revert or verify relevant signal, and there should be no
10.1 During the test, the simulation test of breaker, speed adjusting system and excitation system
of synchronization system should be operated and accomplished on the electric DCS. Check
10.2 The relevant regulations and quality management and control documents should be strictly
10
India Tengda 2×330MW Coal-Fired Power Plant Project -- Electric Commissioning Scheme
11.1.2 Strictly observe the Code of Electric Safety Operation and the Regulation for Fieldwork
11.2.1 The personnel for testing must carefully learn the commissioning measures and
test scheme and know the test methods, steps and safety precautions well
11.2.2 All personnel taken part in the test must do examination and preparation works well before
11.2.3 The main equipments used in the test should be looked after by appointed person, and the
11.2.4 The connections should be strictly done in accordance with the requirements of the
scheduled scheme or drawings. The test should be stopped immediately if occurs abnormal
phenomenon. Do not carry on the test until the reasons have been found.
11.2.5 Pay attention to cooperate with the technical personnel of dynamotor, boiler and thermal
equipment during the test to prevent the unit from some abnormal status, e.g. abnormity in
speed adjusting circuit, reverse power of dynamotor, and ensure the safety of the unit.
11.2.6 Cut off the power supply and remove all temporary connections for test use after the test.
11.2.7 The works of fireproofing, burglarproof and safety protection should be done well.
11
India Tengda 2×330MW Coal-Fired Power Plant Project -- Electric Commissioning Scheme
11.3.1 The operation should be strictly done in accordance with the operating instructions and
regulations of instruments.
11.3.2 The power supply and voltage for test use should meet the requirements of instruments.
11.3.3 Clean the exterior of the instruments after use, pack the instruments and put
12