A1G3W2 - DMAL-P21-PR-CN-74-0014.01R Shore Approach Dredging QC Plan
A1G3W2 - DMAL-P21-PR-CN-74-0014.01R Shore Approach Dredging QC Plan
A1G3W2 - DMAL-P21-PR-CN-74-0014.01R Shore Approach Dredging QC Plan
QC PLAN - SURVEY
Document No: MW-310690-103-MT
Contractor:
Company Project No: 310690
McNally – Tideway Joint Venture
Contractor Project No: M-154
Company:
Table of Contents
1 Introduction........................................................................................................................... 3
1.1 General .............................................................................................................................. 3
1.2 Scope of this QC Plan - Survey ......................................................................................... 3
2 Reference Documents ...........................................................................................................4
2.1 Company & Client Documents/Specifications.................................................................. 4
2.2 Contractor Documents/Procedures .................................................................................... 4
3 Definitions and Abbreviations ............................................................................................. 4
3.1 Definitions ......................................................................................................................... 4
3.2 Abbreviations .................................................................................................................... 4
4 Responsibilities and Organization....................................................................................... 5
5 Notes for guidance ................................................................................................................ 6
6 Inspection Codes ................................................................................................................... 7
Allseas Canada Ltd. Title: QC Plan - Survey
Shore Approach Services Document No: MW-310690-103-MT
Deep Panuke Pipeline Project Revision: B1 3 of 9
1 INTRODUCTION
1.1 General
The Deep Panuke Project involves the installation of the facilities required to produce natural
gas from the Deep Panuke field, located about 175 kilometres offshore Nova Scotia. Produced
gas will be transported by subsea pipeline to Goldboro, N.S., where it will be transported via the
Maritimes & Northeast Pipeline (M&NP) to markets in Eastern Canada and the north-eastern
United States. First gas from the project is expected in 2010. For more information on EnCana,
please visit www.encana.com.
The offshore gas export pipeline shall be installed in the 2009 season by Allseas Canada Ltd. and
tied into the PFC during the 2010 season by others. The offshore export pipeline will be 559
mm (22-inch) diameter, with a wall thickness varying from 14.3mm to 17.5mm, and is 173 km in
length. It will be installed in varying water depths up to a maximum of 145m. The pipeline will
comprise a fusion bonded epoxy (FBE) corrosion coating and concrete weight coating of
nominal density 3050Kg/m3 and thickness varying from 60mm to 85mm. Part of the landfall
pull-in section may have a concrete coating thickness of 100mm.
McNally-Tideway JV (MTJV) has been awarded the subcontract for the onshore and near shore
trench excavation, pipe pull-in and backfilling. The trench will have a maximum depth of 4m
below the seabed on the near shore portion. From onshore to approximately 90m offshore, the
trench will be excavated by first building a causeway over the proposed trench. Once the
causeway has been constructed to a water depth of 3-4m, the excavation will commence back to
shore, removing both the causeway and excavating the trench. The near shore portions will be
excavated from approximately 90m offshore to 890m offshore using a long reach excavator
dredger. The excavated material will be cast to the side of the trench. Once the trench
excavation is complete, the pipeline will be pulled from an off shore Allseas vessel to onshore
using a linear pull winch. Prior to installation of the pull-in wire, the minimum excavation depth
needs to be verified and accepted by ACAN/ECA. Upon completion of the pipeline pull-in and
acceptance of the vertical pipeline position to the original natural seabed, the trench will then be
backfilled using the material that was cast to the side of the trench in order to obtain the required
Top of Pope (TOP) cover.
2 REFERENCE DOCUMENTS
3.2 Abbreviations
ACAN Allseas Canada Ltd.
EIS Environmental Impact Statement
HSE Health, Safety and Environment
MT McNally – Tideway Joint Venture
QA Quality Assurance
QC Quality Control
Allseas Canada Ltd. Title: QC Plan - Survey
Shore Approach Services Document No: MW-310690-103-MT
Deep Panuke Pipeline Project Revision: B1 5 of 9
Quality Control Plans are prepared as brief charts to indicate key activities within a work
package and the characteristics that should be examined to accept that activity. The QCP’s do
not include all steps within a work package, but only those that are critical for acceptance. The
quality planner will prepare the QCP’s by completing the boxes in the chart for each activity.
6 INSPECTION CODES
Inspection codes are given by an alphanumeric coding. This indicates the degree of inspection
intervention required.
Hold(H) A point at which further work within a particular process may not proceed until
approval has been gained. Approval will be recorded as a separate letter or
signature on an inspection report/certificate of completion.
Monitor(M) An activity that requires intermittent observation and supervision to verify that
process parameters are being maintained.
Review(R) An engineering activity where witness and/or other reports and certification are
reviewed so that a judgment can be made on the adequacy of a process.
Allseas Canada Ltd. Title: QC Plan - Survey
Shore Approach Services Document No: MW-310690-103-MT
Deep Panuke Pipeline Project Revision: B1 8 of 9
Act. Inspection/ Test Activity Procedure Reference Quality Acceptance Criteria Responsible Person Verifying Document MT Allseas Client
No Characteristics to of MT QC QC QC
be Verified Action Action Action
Calibration of total station by
Procedure of Manufacturer Calibration
1 manufacturer Criteria of Manufacturer Survey Party Chief R R
Manufacturer Specifications Certificate
Notification to Landowners through
2 Client Site access Site Access Project Manager Company Approval R H
3 Field Test MW-310690-102-MT Inspection Report Within Tolerances Survey Party Chief Inspection Report R W R
Pre-Topographic/Hydrographic Survey
Survey Party Chief /
9 incl. verification of existing services MW-310690-102-MT n.a. MW-310690-102-MT Drawings/DPR R W R
Environmentalist
Act. Inspection/ Test Activity Procedure Reference Quality Acceptance Criteria Responsible Person Verifying Document MT Allseas Client
No Characteristics to of MT QC QC QC
be Verified Action Action Action
Post-Dredge Survey
Applicable
14 MW-310690-102-MT Within tolerances Survey Party Chief Charts W, R W
procedures
Pre-Installation Survey
Applicable
15 MW-310690-102-MT Within tolerances Survey Party Chief Charts W, R H H
procedures
Post-Installation Survey
Applicable
16 MW-310690-102-MT Within tolerances Survey Party Chief Charts W, R H H
procedures
DB-310690-310-
18 Log sheet for each survey operation DB-310690-310-MT DB-310690-310-MT Survey Party Chief Log-sheet R
MT
As-Built Report
DB-310690-310-MT / Applicable
19 AB-310690-305-MT Project Manager AB-310690-305-MT R R R
AB-310690-305-MT procedures