Wre-II Lecture Notes
Wre-II Lecture Notes
ON
Ms. B.NAVYA
Assistant Professor
1
UNIT-I
STORAGE WORKS-RESERVOIRS
Instructional objectives
On completion of this lesson, the student shall learn:
1. The usual classification of the zones of a reservoir
2. The primary types of reservoirs and their functions
3. The steps for planning reservoirs
4. Effect of sedimentation in reservoirs
5. What are the geological explorations required to be carried out for reservoirs
6. How to determine the capacities of reservoirs
7. How to determine the dead, live and flood storages of reservoirs
8. How to reduce the loss of water from reservoirs
9. How to control sedimentation of reservoirs
10. The principles to be followed for reservoir operations
Introduction
Water storage reservoirs may be created by constructing a dam across a river, along with suitable
appurtenant structures. However, in that lesson not much was discussed about fixing the size of
reservoir based on the demand for which it is being constructed. Further, reservoirs are also
meant to absorb a part of flood water and the excess is discharged through a spillway. It is also
essential to study the relation between flood discharge, reservoirs capacity and spillway size in
order to propose an economic solution to the whole project. These and topics on reservoir
sedimentation have been discussed in this lesson which shall give an idea as to how a reservoir
should be built and optimally operated.
Fundamentally, a reservoir serves to store water and the size of the reservoir is governed by the
volume of the water that must be stored, which in turn is affected by the variability of the inflow
available for the reservoir. Reservoirs are of two main categories: (a) Impounding reservoirs into
which a river flows naturally, and (b) Service or balancing reservoirs receiving supplies that are
pumped or channeled into them artificially. In general, service or balancing reservoirs are
required to balance supply with demand. Reservoirs of the second type are relatively small in
volume because the storage required by them is to balance flows for a few hours or a few days at
the most. Impounding or storage reservoirs are intended to accumulate a part of the flood flow of
the river for use during the non-flood months. In this lesson, our discussions would be centered
on these types of reservoirs.
2
These specific levels and parts are generally defined as follows:
Full Reservoir Level (FRL): It is the level corresponding to the storage which includes both
inactive and active storages and also the flood storage, if provided for. In fact, this is the highest
reservoir level that can be maintained without spillway discharge or without passing water
downstream through sluice ways.
Minimum Drawdown Level (MDDL): It is the level below which the reservoir will not be drawn
down so as to maintain a minimum head required in power projects.
Dead Storage Level (DSL): Below the level, there are no outlets to drain the water in the
reservoir by gravity.
Maximum Water Level (MWL): This id the water level that is ever likely to be attained during
the passage of the design flood. It depends upon the specified initial reservoir level and the
spillway gate operation rule. This level is also called sometimes as the Highest Reservoir Level
or the Highest Flood Level.
Live storage: This is the storage available for the intended purpose between Full Supply Level
and the Invert Level of the lowest discharge outlet. The Full Supply Level
3
is normally that level above which over spill to waste would take place. The minimum operating
level must be sufficiently above the lowest discharge outlet to avoid vortex formation and air
entrainment. This may also be termed as the volume of water actually available at any time
between the Dead Storage Level and the lower of the actual water level and Full Reservoir Level.
Dead storage: It is the total storage below the invert level of the lowest discharge outlet from the
reservoir. It may be available to contain sedimentation, provided the sediment does not adversely
affect the lowest discharge.
Outlet Surcharge or Flood storage: This is required as a reserve between Full Reservoir Level
and the Maximum Water level to contain the peaks of floods that might occur when there is
insufficient storage capacity for them below Full Reservoir Level.
Buffer Storage: This is the space located just above the Dead Storage Level up to Minimum
Drawdown Level. As the name implies, this zone is a buffer between the active and dead storage
zones and releases from this zone are made in dry situations to cater for essential requirements
only. Dead Storage and Buffer Storage together is called Interactive Storage.
Within-the-Year Storage: This term is used to denote the storage of a reservoir meant for
meeting the demands of a specific hydrologic year used for planning the project.
Carry-Over Storage: When the entire water stored in a reservoir is not used up in a year, the
unused water is stored as carry-over storage for use in subsequent years.
Silt / Sedimentation zones: The space occupied by the sediment in the reservoir can be divided
into separate zones. A schematic diagram showing these zones is illustrated in Figure 2 (as
defined in IS: 5477).
4
Freeboard: It is the margin kept for safety between the level at which the dam would be
overtopped and the maximum still water level. This is required to allow for settlement of the
dam, for wave run up above still water level and for unforeseen rises in water level, because of
surges resulting from landslides into the reservoir from the peripheral hills, earthquakes or
unforeseen floods or operational deficiencies.
The functions of reservoirs are to provide water for one or more of the following purposes.
Reservoirs that provide water for a combination of these purpose, are termed as „Multi Purpose‟
reservoirs.
Pumped storage hydropower schemes: in which the water flows from an upper to a lower
reservoir, generating power and energy at times of high demand through turbines, which
may be reversible, and the water is pumped back to the upper
5
reservoir when surplus energy is available. The cycle is usually daily or twice daily to meet
peak demands. Inflow to such a reservoir is not essential, provided it is required to replace
water losses through leakage and evaporation or to generate additional electricity. In such
facilities, the power stations, conduits and either or both of the reservoirs could be
constructed underground if it was found to do so.
Amenity use: this may include provision for boating, water sports, fishing, sight seeing.
Formally, the Bureau of Indian Standards code IS: 4410 (part 6)1983 “Glossary of terms relating
to river valley projects -Reservoirs" defines the following types of reservoirs:
Balancing Reservoirs: A reservoir downstream of the main reservoir for holding water
let down from the main reservoir in excess of that required for irrigation, power
generation or other purposes.
Detention Reservoir: A reservoir where in water is stored for a relatively brief period of
time, past of it being retained until the stream can safely carry the ordinary flow plus the
released water. Such reservoirs usually have outlets without control gates and are used for
flood regulation. These reservoirs are also called as the Flood Control Reservoir or
Retarding Reservoir.
6
control, power generation, navigation, pollution abatement, domestic and industrial water supply,
fish culture, recreation, etc.
It may be observed that some of these objectives may be incompatible in combination. For
example, water may has to be released for irrigation to suit crop growing seasons, while water
releases for hydropower are required to suit the time of public and industrial demands. The latter
will be affected not only by variations in economic conditions but also by variations over a day
and night cycle.
Compatibility between irrigation demand and flood control strategy in operating a reservoir is
even more difficult for a reservoir which intends to serve both, like the Hirakud Dam reservoir
on the river Mahanadi. Flood wave moderation requires that the reservoir be emptied as much as
possible so that it may absorb any incoming flood peak. However, this decision means reducing
the water stored for irrigation. Usually, such a reservoir would be gradually emptied just before
the arrival of monsoon rains, anticipating a certain flood and hoping that the reservoir would be
filled to the brim at the end of the flood season. However, this anticipation may not hold good
for all years and the reservoir does not get filled up to the optimal height. On the other hand, if
the reservoir is not depleted sufficiently well, and actually a flood of high magnitude arrives,
then the situation may lead to the flood inundations on the downstream.
Planning of reservoirs
The first step in planning the construction of a reservoir with the help of a dam is for the decision
makers to be sure of the needs and purposes for which the reservoir is going to be built together
with the known constraints (including financial), desired benefits. There may be social
constraints, for examples people‟s activism may not allow a reservoir to be built up to the desired
level or even the submergence of good agricultural level may be a constraint. Some times, the
construction of a dam may be done that is labour intensive and using local materials, which helps
the community for whom the dam is being built. This sort of work is quite common in the minor
irrigation departments of various steps, especially in the drought prone areas. The Food-for-
Work schemes can be utilised in creating small reservoirs that helps to serve the community. In
a larger scale, similar strategy was adopted for the construction of the Nagarjuna Sagar Dam on
the River Krishna, which was built entirely of coursed rubble masonry and using manual labour
in thousands.
The second step is the assembly of all relevant existing information, which includes the
following:
Reports of any previous investigations and studies, if any.
Reports on projects similar to that proposed which have already been constructed in the
region.
A geographical information system (GIS) for the area of interest may be created
7
using a base survey map of the region.
Topographical data in the form of maps and satellite pictures, which may be integrated
within the GIS.
Geological data in the form of maps and borehole logs, along with the values of relevant
parameters.
Seismic activity data of the region that includes recorded peak accelerations or ground
motion record.
Meteorological and hydrological data - of available parameters like rainfall, atmospheric
and water temperatures, evaporation, humidity, wind speed, hours of sunshine, river
flows, river levels, sediment concentration in rivers, etc.
For water supply projects, data on population and future population growth based on
some acceptable forecast method, industrial water requirement and probable future
industrial development.
For irrigation projects, data on soils in the project area and on the crops already grown,
including water requirement for the crops.
For hydropower projects, data on past demand and forecasts of future public and
industrial demand for power and energy; data on existing transmission systems, including
transmission voltage and capacity.
Data on flora and fauna in the project and on the fish in the rivers and lakes, including
data on their migratory and breeding habits.
Data on tourism and recreational use of rivers and lakes and how this may be encouraged
on completion of the proposed reservoir.
As may be noted, some of the data mentioned above would be needed to design and construct
the dam and its appurtenant structures which would help to store water behind the reservoir.
However, there are other data that decides the following:
How large the reservoir should be and, consequently, what should be the dam height?
What should be the size of the spillway and at what elevation the crest level of the
spillway be located?
How many and at what levels sluices be provided and they should be of what sizes?
Two important aspects of reservoirs planning: Sedimentation Studies and Geological
Explorations are described in detail in the following section.
8
into canals / water conveyance systems drawing water from the reservoir. Problems of rise in
flood levels in the head reaches and unsightly deposition of sediment from recreation point of
may also crop up in course of time.
In this regard, the Bureau of Indian Standard code IS: 12182 - 1987 “Guidelines for
determination of effects of sedimentation in planning and performance of reservoir” is an
important document which discusses some of the aspects of sedimentation that have to be
considered while planning reservoirs. Some of the important points from the code are as follows:
While planning a reservoir, the degree of seriousness and the effect of sedimentation at the
proposed location has to be judged from studies, which normally combination consists of:
In general, the performance assessment of reservoir projects has to be done for varying
hydrologic inputs to meet varying demands. Although analytical probability based methods are
available to some extent, simulation of the reservoir system is the standard method. The method
is also known as the working tables or sequential routing. In this method, the water balance of
the reservoir s and of other specific locations of water use and constraints in the systems are
considered. All inflows to and outflows from the reservoirs are worked out to decide the changed
storage during the period. In simulation studies, the inflows to be used may be either historical
inflow series, adjusted for future up stream water use changes or an adjusted synthetically
generated series.
9
ratio is more than 0.5 percent per year, the problem is usually said to be serious and special care
is required in estimating the sediment yields from the catchment. If it is less than 0.1 percent per
year, the problem of siltation may be insignificant and changes in reservoir performance. For
cases falling between these two limits, the sedimentation problem is considered significant and
requires further studies.
In the above, the following terms have been used, which are explained below:
Feasible Service Time: For a special purpose, the period or notional period for
which a reservoir is expected to provide a part of the planned benefit in respect of
storage in the reservoirs being impaired by sedimentation. Customarily, it is
estimated as the time after which the new zero elevation of the reservoir would equal
the sill of the outlet relevant for the purpose.
New Zero Elevation: The level up to which all the available capacity of the
reservoir is expected to be lost due to progressive sedimentation of the reservoir up
to the specified time. The specified time should be any length of time such as Full
Service Time, Feasible Service time, etc.
Full Service Time: For a specified purpose, the period or notional period for which
the reservoir provided is expected to provide, a part of the full planned benefit
inspite of sedimentation.
The following studies are required if the problem of sedimentation in the reservoir is assessed to
be significant, but not serious.
1. Both the full service time and feasible service time for the reservoir may be decided.
2. Simulation studies for conditions expected at the end of full service time may be
made to ensure that firm outputs with required depend ability are obtained. The
studies used also assess non-dependable secondary outputs, if relevant, available at
the end of this period. Studies without sedimentation, with the same firm outputs
should bring out the additional potential secondary outputs which may be used, if
required in economic analysis, using a linear decrease of these additional benefits
over the full service time.
3. No simulation studies beyond full service time, is required.
4. Sediment distribution studies required for feasible service time are essential.
10
1. All studies described for the „Significant‟ case have to be made.
2. The secondary benefits available in the initial years should be more in such cases. If
they are being utilized, for a proper assessment of the change of these, a simulation
at half of full service time should be required.
3. In these cases, the drop of benefits after the full service time may be sharper. To
bring out these effects, a simulation of the project at the end of the feasible service
time is required to be done.
11
structural strengthening, etc.) or other measures, if it is economically feasible to do so. If these
studies are done, the feasible service time may be extended.
Reconnaissance
In the reconnaissance stage, the objective of investigation is to bring out the overall geological
features of the reservoir and the adjacent area to enable the designers, construction engineers and
geologists to pinpoint the geotechnical and ecological problems which have to be tackled. The
scale of geological mapping for this stage of work need not be very large and the available
geological maps on 1:50,000 or 1: 250,000 scales may be made use of. It is advantageous to
carry out photo geological interpretation of aerial photographs of the area, if available. If a
geological map of the area is not available, a traverse geological map should be prepared at this
stage preferably using the aerial photos as base maps on which the engineering evaluation of the
various geotechnical features exposed in the area should be depicted.
12
A topographical index map on 1: 50 000 scales should be used at this stage to delineate the areas
which would require detailed study, subsequently.
To prevent an undesirable amount of leakage from the reservoir, the likely zones of such
leakage, such as major dislocations and pervious or cavernous formations running across the
divide of the reservoir should be identified at this stage of investigation for further detailed
investigations.
Major unstable zones, particularly in the vicinity of the dam in tight gorges, should be identified
at this stage for carrying out detailed investigations for the stability of the reservoir rim.
The locations for suitable construction material available in the reservoir area should be pin
pointed at this stage so that after detailed surveys such materials can be exploited for proper
utilisation during the construction stage prior to impounding of reservoir.
The rate of silting of the reservoir is vital for planning the height of the dam and working out the
economic life of the project. Since the rate of silting, in addition to other factors, is dependent on
the type of terrain in the catchment area of the reservoir, the major geological formations and the
ecological set up should be recognized at this stage to enable a more accurate estimation of the
rate of silting of the reservoir. For example, it should be possible to estimate at this stage that
forty percent of the catchment of a storage dam project is covered by Quaternary sediment and
that this is a condition which is likely to a yield a high silt rate or that ninety percent of the
catchment of another storage dam project is composed of igneous and metamorphic rocks and is
likely to yield a relatively low sediment rate. This information will also be useful in examining
whether or not tributaries flowing for long distances through soft or unconsolidated formations,
prior to forming the proposed reservoir, can be avoided and if not, what remedial measures can
be taken to control the silt load brought by these tributaries.
The impounding of a reservoir may submerge economic/strategic mineral deposits occurring
within the reservoir area or the resultant rise in the water table around the reservoir may cause
flooding, increased seepage in quarries and mines located in the area and water logging in other
areas. It is, therefore, necessary that the economic mineral deposits, which are likely to be
adversely affected by the reservoir area, are identified at this stage of the investigation. For
example, if an underground working is located close to a proposed storage reservoir area, it
should be identified for regular systematic geo-hydrological studies subsequently. These studies
would establish whether the impoundment of the water in the reservoir had adversely affected
the underground working or not. References should also be made to various agencies dealing
with the economic minerals likely to be affected by the impoundment in the reservoir for proper
evaluation of the problem and suitable necessary action.
A dam and its reservoir are affected by the environment in which they are located and in turn
they also change the environment. Impoundment of a reservoir sometimes results in an increase
of seismic activity at, or near the reservoir. The seismic activity may lead to microtremors and in
some cases lead to earthquakes of high magnitude. It is, therefore, necessary to undertake the
regional seismotechtonic study of the project area. The faults having active seismic status
should be delineated at this stage.
13
Simultaneous action to plan and install a network of seismological observatories encompassing
the reservoir area should also be taken.
Preliminary Investigation
The object of preliminary investigation of the reservoir area is to collect further details of the
surface and subsurface geological conditions, with reference to the likely problems identified
during the reconnaissance stage of investigation by means of surface mapping supplemented by
photo geological interpretation of aerial photographs, hydro geological investigations,
geophysical investigations, preliminary subsurface exploration and by conducting geo-
seismological studies of the area.
On the basis of studies carried out during the reconnaissance stage it should be possible to
estimate the extent of exploration that may be required during the preliminary stage of
investigation including the total number of holes required to be drilled and the total number and
depth of pits, trenches and drifts as also the extent of geophysical surveys which may be
necessary. For exploration by pits, trenches, drifts and shafts guidelines laid down in IS 4453:
1980 Name of IS code should be followed.
The potential zones of leakage from the reservoir and the lateral extent of various features, such
as extent of aeolian sand deposits, glacial till, land slides, major dislocations or pervious and
cavernous formations running across the divide, should be delineated on a scale of 1: 50000.
The geo-hydrological conditions of the reservoir rim should be established by surface and sub-
surface investigation as well as inventory, as a free ground water divide rising above the
proposed level of the reservoir is a favourable condition against leakage from the reservoir. The
level of water in a bore hole should be determined as given in IS 6935: 1973.
The extension of various features at depth, wherever necessary, is investigated by geophysical
exploration and by means of pits, trenches, drifts and drill holes. For example, the resistivity
survey should be able to identify water saturated zones. The nature of the material is investigated
by means of laboratory and in situ tests, to determine permeability and assess the quantum of
leakage which may take place through these zones on impoundment of the reservoir. Moreover,
permeability of rocks/overburden in the reservoir area is determined from water table
fluctuations and pumping tests in wells. For determining in situ permeability in overburden and
rock, reference should be made to IS 5529 (Part I): 1985 and IS: 5529 (Part II): 1985
respectively. The information about permeability would enable the designers to estimate the
treatment cost for controlling leakage/seepage from the reservoir and to decide whether it would
be desirable to change the location of height of the dam to avoid these zones.
Major unstable zones along the reservoir identified during the reconnaissance stage and which
are of consequence to the storage scheme should be investigated in detail at this stage by means
of surface and sub-surface exploration.
The areas should be geologically mapped in detail on a scale of 1: 2000. The suspect
planes/zones of failure should be identified and explored by means of drifts, trenches
14
and pits. Disturbed and undisturbed samples of the plastic material should be tested for cohesion
(c) and angle of internal friction () as well as for other relevant properties. The stability of
slopes should also be evaluated considering the reservoirs operational conditions. These studies
should provide the designers with an idea of the magnitude of the problems that may be
encountered, so that they may be able to take remedial measures to stabilize zones or to abandon
the site altogether, if the situation demands.
The areas having potential economic mineral wealth and which are likely to be adversely
affected by the impoundment of the reservoir should be explored by means of surface and sub-
surface investigation to establish their importance both in terms of their value as well as strategic
importance. This information would be necessary for arriving at a decision regarding the
submergence, or otherwise, of the mineral deposit. The nature and amount of the existing
seepage, if any, in the existing mines and quarries in the adjacent areas of the reservoir should be
recorded and monitored regularly. This data is necessary, to ascertain whether or not there has
been any change in the quantum of seepage in the mines and quarries due to the impoundment of
water in the reservoir, directly or indirectly.
Large scale geological mapping and terrace matching across the faults with seismically active
status, delineated during the reconnaissance stage, should be carried out on a scale of 1 : 2000
and the trend, and behaviour of the fault plane should be investigated in detail by means of
surface studies and sub-surface exploration by pits, trenches and drifts etc. A network of geodetic
survey points should be established on either side of the suspected faults to study micro-
movements along these suspected faults, if any, both prior to and after impoundment of the
reservoir. Micro earthquake studies should be carried out using portable 3-station or 4-station
networks in areas with proven seismically active fault features.
On the basis of the studies carried out during the preliminary stage it should be possible to
estimate the quantum of exploration which may be required during the detailed stage of
investigation including the total number of holes required to be drilled and the total number and
depth of pits, trenches and drifts as also the extent of geophysical survey which may be
necessary.
Detailed surface and sub-surface investigation of all features connected with the reservoir should
be carried out to provide information on leakage of water through the periphery and/or basin of
the reservoir area.
Based on these investigations and analysis of data it should be possible to decide as to whether
the reservoir area in question would hold water without undue leakage. If, not, the dam site may
have to be abandoned in favour of suitable alternative site.
The zones, which on preliminary investigation are found to be potential zones of leakage/seepage
from the reservoir, and which due to other considerations cannot be avoided are geologically
mapped on a scale of 1 : 2 000 and investigated in detail at this stage by means of a close spaced
sub-surface exploration programme. The purpose of this stage of investigation is to provide the
designers sufficient data to enable them to plan the programme of remedial treatment. The sub-
surface explorations are carried out by means of pits and trenches, if the depth to be explored is
shallow, say up to 5 meters, and by drill holes and drifts, if the depth to be explored is greater
than 5 meters.
15
The unstable zones around the reservoir rim, specially those close to the dam sites in tight
gorges, should be explored in detail by means of drifts, pits and trenches so that the likely planes
of failures are located with precision. The physical properties including angle of internal friction
and cohesion of representative samples of the material along which movement is anticipated
should be determined. The above information would enable the designers to work out details for
preventive measures, for example, it may be possible to unload the top of the slide area or to
load the toe of the slide with well drained material, within economic limits.
Sub-surface explorations by drill holes, drifts, pits and trenches should be carried out at possible
locations of check dams and at the locations of other preventive structures proposed to restrict
the flow of silt into the reservoir. These studies would enable the designers to assess the
feasibility of such proposals.
Detailed plans, regarding the economic mineral deposits within the zones of influence of the
reservoir should be finalized during this stage by the concerned agencies. The seepage
investigations in the quarries and mines within the zone of influence of the reservoir should be
continued
16
g) Committed and future upstream uses;
h) Criteria for assessing the success of the project;
i) Density current aspects and location of outlets;
j) Data required for economic analysis; and
k) Data on engineering and geological aspects.
Estimation of average Sediment Yield from the catchment area above the reservoir
It is usually attempted using river sediment observation data or more commonly from the
experience of sedimentation of existing reservoirs with similar characteristics. Where
observations of stage/flow data is available for only short periods, these have to be suitably
extended with the help of longer data on rainfall to estimate as far as possible sampling errors
due to scanty records. Sediment discharge rating curve may also be prepared from hydraulic
considerations using any of the standard sediment load formulae, such as, Modified Einstein‟s
procedure, Young‟s stream power, etc. It is also necessary to account for the bed load which may
not have been measured. Bed load measurement is preferable and when it is not possible, it is
often estimated as a percentage generally ranging from 5 to 20 percent of the suspended
sediment load. However, actual measurement of bed load needs to be undertaken particularly in
cases where high bed loads are anticipated. To assess the volume of sediment that would
17
deposit in the reservoir, it is further necessary to make estimates of average trap efficiency of the
reservoir and the likely unit weight of sediment deposits, along with time average over the period
selected. The trap efficiency would depend on the capacity inflow ratio but would also vary with
the locations of controlling outlets and reservoir operating procedures. Computations of reservoir
trap efficiency may be made using the trap efficiency curves such as those developed by Brune
and by Churchill (see IS: 12182-1987).
Trap Efficiency
Trap efficiency of reservoir, over a period, is the ratio of total deposited sediment to the total
sediment inflow. Figures 1 and 2 given in Annex A of IS 12182 cover relationship between
sedimentation index of the reservoir and percentage of incoming sediment and these curves may
be used for calculation of trap efficiency.
Losses in Reservoir
Water losses mainly of evaporation and seepage occur under pre-project conditions and are
reflected in the stream flow records used for estimating water yield. The construction of new
reservoirs and canals is often accompanied by additional evaporation and infiltration. Estimation
of these losses may be based on measurements at existing reservoirs and canals. The measured
inflows and outflows and the rate of change of storage are balanced by computed total loss rate.
The depth of water evaporated per year from the reservoir surface may vary from about 400 mm
in cool and humid climate to more than 2500 mm in hot and arid regions. Therefore, evaporation
is an important consideration in many projects and deserves careful attention. Various methods
like water budget method, energy budget method, etc may be applied for estimating the
evaporation from reservoir. However, to be more accurate, evaporation from reservoir is
estimated by using data from pan-evaporimeters or pans exposed to atmosphere with or without
meshing in or near the reservoir site and suitably adjusted.
Seepage losses from reservoirs and irrigation canals may be significant if these facilities are
located in an area underlain by permeable strata. Avoidance in full or in part of seepage losses
may be very expensive and technical difficulties involved may render a project unfeasible. These
are generally covered under the conveyance losses in canals projected on the demand side of
simulation studies.
18
Demand, Supply and Storage
The demand should be compared with supplies available year by year. If the demand is limited
and less than the available run-off, storage may be fixed to cater to that particular demand which
is in excess of the run-off. The rough and ready method is the mass curve method for initial
sizing.
Even while doing the above exercise, water use data are needed to assess the impact of human
activities on the natural hydrological cycle. Sufficient water use information would assist in
implementing water supply projects, namely, evaluating the effectiveness of options for demand
management and in resolving problems inherent in competing uses of water, shortages caused by
excessive withdrawal, etc. Water demands existing prior to construction of a water resource
project should be considered in the design of project as failure to do so may result in losses apart
from legal and social problems at the operation stage.
19
benefit functions the benefit from unit utilisation of water can be determined. The spillway
capacity has to be adequate to pass the inflow design flood using moderation possible with
surcharge storage or any other unobstructed capacity in the reservoir without endangering the
structural safety as provided elsewhere in the standard. In the event of the inflow design flood
passing the reservoir, the design needs to ensure that dam break situation does not develop or
induce incremental damage downstream.
a) Engineering
1) Preliminary surveys to assess the catchment and reservoir,
2) Control surveys like topographical surveys,
3) Location of nearest Railway lines/Roads and possible access, and
4) Detailed survey for making area capacity curves for use in reservoir flood
routing.
b) Geology
1) General formations and foundation suitability;
2) Factors relating to reservoir particularly with reference to water tightness;
3) Contributory springs;
4) Deleterious mineral and salt deposits; and
5) Location of quarry sites, etc.
Important aspects of the methods are briefly described in the subsequent sections.
20
addition to live storage, it is ensured that the live storage although it contains sediment, will
function at full efficiency for an assigned number of years. The distribution pattern of sediments
in the entire depth of a reservoir depends upon many factors, such as slope of the valley, length
of reservoir, constriction in the reservoir, particle size of the suspended sediment and capacity
inflow ratio, but the reservoir operation has an important control over the factors. However, the
knowledge of the pattern is essential, especially, in developing areas, in order to have an idea
about the formation of delta and recreational spots.
The dead storage of a reservoir depends upon the sediment yield of the catchment. The
measurement of sediment yield is done as follows:
21
efficiency may be made using trap efficiency curves, such as those developed by Brune and by
Churchill (see IS: 12182-1987).
22
between the full reservoir level and the minimum draw-down level in the case of power projects
and dead storage in the case of irrigation projects.
The design of the line storage include certain factors, of which the most important in the
availability of flow, since, without an adequate flow, it is not possible to cope up with the
demand at all periods and seasons throughout the year. When adequate flow is available, there
may still be certain problems like the possible maximum reservoir capacity from physical
considerations may be limited and then this becomes the governing criteria. Even if an adequate
reservoir capacity may be possible to be built, the governing factor may have to be based on the
demand.
For fixing the live storage capacity, the following data should be made use of:
23
The working table calculations may be represented graphically by plotting the cumulative net
reservoir inflow exclusive of upstream abstraction as ordinate against time as abscissa. This
procedure is commonly called the Mass Curve Technique, where the ordinate may be denoted by
depth in centimeters or in hectare meters or in any other unit of volume. Discharge, with units of
10 days or a month may be used culmination in the mass curve. A segment of the mass curve is
shown in Figure 3.
The difference in the ordinate at the end of a segment of the mass curve gives the inflow volume
during that time interval. Lines parallel to the lines of uniform rate of demand are drawn at the
points b and c of the mass curve. At d, the following inferences can be made:
The inflow rate between a to b is more than the demand rate and the reservoir is full.
Reservoir is just full as the inflow rate is equal to the demand rate.
Reservoir storage is being drawn down between b and c since the demand rate exceeds
the inflow rate.
Draw down, S, is maximum at c due to demand rate being equal to inflow rate.
Reservoir is filling or in other words draw down is decreasing from c to d as the inflow
rate is more than the demand rate.
Reservoir is full at d and from d to b again the reservoir is over flowing because the
inflow rate exceeds the demand rate. The greatest vertical distance, S at c is the storage
required to make up the proposed demand.
The withdrawals from the reservoir to meet the irrigation demand are generally variable and in
such cases the demand line becomes a curve instead of a straight line. The demand mass curve
should be super-imposed on the inflow mass curve on the same time scale. When the inflow and
demand mass curves intersect, the reservoir may be assumed to be full. For emptying conditions
of the reservoir the demand curve would be above the inflow curve and the maximum ordinate
between the two would indicate the live storage capacity required.
Surcharge Storage
Surcharge storage is the storage between the full reservoir level (FRL) and the maximum water
level (MWL) of a reservoir which may be attained with capacity exceeding the reservoir at FRL
to start with. The spillway capacity has to be adequate to pass the inflow design flood making
moderation possible with surcharge storage.
The methods that are generally used for estimate of the Design Flood for computing the Flood
Storage are broadly classified as under:
1. Application of a suitable factor of safety to maximum observed flood or maximum
historical flood.
2. Empirical flood formulae.
3. Envelope curves.
4. Frequency analysis.
5. Rating method of derivation of design flood from storm studies and application of the
Unit Hydrograph principle.
The important methods amongst the above have been explained in module 2. Nevertheless, these
methods are briefly reiterated below:
Application of a Suitable Factor of Safety to Maximum Observed Flood or
Maximum Historical Flood
The design flood is obtained by applying a safety factor which depends upon the judgement of
the designer to the observed or estimated maximum historical flood at the project site or nearby
site on the same stream. This method is limited by the highly subjective selection of a safety
factor and the length of available stream flow record which may give an inadequate sample of
flood magnitudes likely to occur over a long period of time.
Empirical Flood Formulae : The empirical formulae commonly used in the country are the
Dicken‟s formula, Ryve‟s formula and Inglis‟ formula in which the peak flow is given as a
function of the catchment area and a coefficient. The values of the coefficient vary within rather
wide, limits and have to be selected on the basis of judgement. They have limited regional
application, should be used with caution and only, when a more accurate method cannot be
applied for lack of data.
Envelope Curves: In the envelope curve method maximum flood is obtained from the envelope
curve of all the observed maximum floods for a number of catchments in a homogeneous
meteorological region plotted against drainage area. This method, although useful for
generalizing the limits of floods actually experienced in the region under consideration, cannot
be relied upon for estimating maximum probable floods for the determination of spillway
capacity except as an aid to judgement.
Frequency Analysis: The frequency method involves the statistical analysis of observed data of
a fairly long (at least 25 years) period. It is a purely statistical approach and when applied to
derive design floods for long recurrence intervals, several times larger than the data, has many
limitations. Hence this method has to be used with caution.
a. Analysis of rainfall and run-off data for derivation of loss rates under critical conditions;
b. Derivation of unit hydrograph by analysis (or by synthesis, in cases where data are not
available);
c. Derivation of the design storm; and
d. Derivation of design flood from the design storm by the application of the rainfall excess
increments to the unit hydrograph.
The Maximum Water Level of a reservoir is obtained by routing the design flood through the
reservoir and the spillway. This process of computing the reservoir storages, storage volumes
and outflow rates corresponding to a particular hydrograph of inflow is commonly referred to as
flood routing. The routing is carried out with the help of the
following data,
1. Initial reservoir stage
2. The design flood hydrograph
3. Rate of outflow including the flow over the crest, through sluices or outlets and through
power units, and
4. Incremental storage capacity of the reservoir.
The routing of flood through the reservoir and the spillway is done by solving the continuity of
flow within reservoir, which may simply be stated as:
Inflow to reservoir - Outflow to reservoir = Rise is water surface of the reservoir, that is an
increase in the storage of the reservoir. That is,
(I O) * t S (1)
Where, I is the inflow discharge (m3/s), O is the Outflow discharge (m3/s), s is the in
storage volume (m3/s) in time interval t (h).
If the inflow hydrograph is known, then we may read out the inflow ordinates at every time
interval (t. Suppose, the following values are known:
I1 = Inflow (m3/s) at the beginning of a time interval I2
= Inflow (m3/s) at the end of the time interval
O1= Outflow (m3/s) at the beginning of the time interval
S1= Total storage volume of the reservoir (m3/s) at the beginning of the time interval
S2= Total storage volume of the reservoir (m3/s) at the end of the interval O2=
Outflow (m3/s) at the end of the time interval
a) Vapour pressure difference_ between water surface and the layer of air above;
b) Temperature of water and air;
c) Atmospheric pressure;
d) Radiation;
e) Heat storage in water body; and
f) Quality of water,
have direct influence on the rate of evaporation.
Since the meteorological factors affecting evaporation cannot be controlled under normal
conditions, efforts are made for inhibition of evaporation by control of flow of wind over water
surface or by protection of the water surface area by physical or chemical methods. The methods
generally used are as follows:
a) Wind breakers,
b) Covering the water surface,
c) Reduction of exposed water surface,
d) Integrated operation of reservoirs, and
e) Treatment with chemical water evaporetardants (WERs).
Wind Breakers
Wind is one of the most important factors which affect rate of evaporation loss from water
surface. The greater the movement of air over the water surface, greater is the evaporation loss.
Planting of trees normal to windward direction is found to be an effective measure for checking
of evaporation loss. Plants (trees, shrubs or grass) should be grown around the rim of tanks in a
row or rows to act as wind breaker.
These wind breakers are found to influence the temperature, atmospheric humidity, soil
moisture, evaporation and transpiration of the area protected.
Plants to act as wind breakers are usually arranged in rows, with tallest plants in the middle and
the smallest along the end rows, so that more or less conical formation is formed.
Design of reservoirs
The capacity of reservoirs is governed by a number of factors which are covered in IS: 5477
(Parts 1 to 4). From the point of view of sediment deposition, the following points may be given
due consideration:
a) The sediment yield which depends on the topographical, geological and geo-
morphological set up,meteorological factors, land use/land cover, intercepting tanks,
etc;
b) Sediment delivery characteristics of the channel system;
c) The efficiency of the reservoir as sediment trap;
d) The ratio of capacity of reservoir to the inflow;
e) Configuration of reservoir;
f) Method of operation of reservoir;
g) Provisions for silt exclusion.
The rate of sediment delivery increases with the volume of discharge. The percentage of
sediment trapped by a reservoir with a given drainage area increases with the capacity. In some
cases an increased capacity will however, result in greater loss of water due to evaporation.
However, with the progress of sedimentation, there is decrease of storage capacity which in turn
lowers the trap efficiency of the reservoir.
The capacity of the reservoir and the size and characteristics of the reservoir and its drainage area
are the most important factors governing the annual rate of accumulation of sediment. Periodical
reservoir sedimentation surveys provide guidance on the rate of sedimentation. In the absence of
observed data for the reservoir concerned, data from other reservoirs of similar capacity and
catchment characteristics may be adopted.
Silting takes place not only in the dead storage but also in the live storage space in the reservoir.
The practice for design of reservoir is to use the observed suspended sediment data available
from key hydroIogica1 networks and also the data available from hydrographic surveys of other
reservoirs in the same region. This data be used to simulate sedimentation status over a period of
reservoir life as mentioned in IS 12182: 1987.
a) Engineering,
b) Agronomy, and
c) Forestry.
The engineering methods include:
a) Use of check dams formed by building small barriers or dykes across stream channels.
b) Contour bounding and trenching;
c) Gully plugging;
d) Bank protection.
The agronomic measures include establishment of vegetative screen, contour farming, strip
cropping and crop rotation.
Forestry measures include forest conservancy, control on grazing, lumbering, operations and
forest fires along with management and protection of forest plantations.
Preventive measures to check inflow of sediment into the reservoir include construction of by-
pass channels or conduits.
Check Dams
Check dams are helpful for the following reasons:
a) They help arrest degradation of stream bed thereby arresting the slope failure;
b) They reduce the veIocity of stream flow, thereby causing the deposition of the sediment
load.
Check dams become necessary, where the channel gradients are steep and there is a heavy inflow
of sediment from the watershed. They are constructed of local material like earth, rock, timber,
etc. These are suitable for small catchment varying in size from 40 to 400 hectares. It is
necessary to provide small check dams on the subsidary streams flowing into the main streams
besides the check dams in the main stream. Proper consideration should be given to the number
and location of check dams required. It is preferable to minimize the height of the check dams. If
the stream ha, a very-steep slope, it is desirable to start with a smaller height for the check dams
than may ultimately be necessary.
Check dams may generally cost more per unit of storage than the reservoirs they protect.
Therefore, it may not always be possible to adopt them as a primary method of sediment control
in new reservoirs. However, feasibility of providing check dams at a later date should not be
overlooked while planning the protection of-a new reservoir.
Gully Plugging
This is done by small rock fill dams. These dams will be effective in filling up the gullies with
sediment coming from the upstream of the catchment and also prevent further widening of the
gully.
Density Current
Water at various levels of a reservoir often contains radically different concentrations of
suspended sediment particularly during and after flood flows and if all waste-water could be
withdrawn at those levels where the concentration is highest, a significant amount of sediment
might be removed from the reservoir. Because a submerged outlet draws water towards it from
all directions, the vertical dimension of the opening should be small with respect to the thickness
of the layer and the rate of withdrawal also should be low. With a view to passing the density
current by sluices that might be existed, it is necessary to trace the movement of density currents
and observation stations (consisting of permanently anchored rafts from which measurements
could be made of temperature and conductivity gradient from the surface of the lake to the
bottom, besides collecting water samples at various depths) at least one just above the dam and
two or more additional stations in the upstream (one in the inlet and one in the middle) should be
located.
Waste-Water Release
Controlling the sedimentation by controlling waste-water release is obviously possible only
when water can be or should be wasted. This method is applicable only when a reservoir is of
such size that a small part of large flood flows will fill it.
In the design of the dam, sediment may be passed through or over it as an effective method of silt
control by placing a series of outlets at various elevations. The percentage of total sediment load
that might be ejected from the reservoir through proper gate control will differ greatly with
different locations. It is probable that as much as 20 percent of the sediment inflow could be
passed through many reservoirs by venting through outlets designed and con- trolled.
Scouring Sluicing
This method is somewhat similar to both the control of waste-water release and the draining and
flushing methods. The distinction amongst them care the following:
1) The waste-water release method ejects sediment laden flood flows through deep
spillway gates or large
under sluices at the rate of discharge that prevents sedimentation.
2) Drainage and flushing method involves the slow release of stored water from the
reservoir through small gates or valves making use of normal or low flow to entrain and carry the
sediment, and
3) Scouring sluicing depends for its efficiency on either the scouring action exerted by the
sudden rush of impounded water under a high head through under sluices or on the scouring
action of high flood discharge coming into the reservoir.
a) Small power dams that depend to a great extent on pondage but not on storage;
b) Small irrigation reservoirs, where only a small fraction of the total annual flow can be
stored;
c) Any reservoir in narrow channels, gorges, etc, where water wastage can be afforded;
and
d) When the particular reservoir under treatment is a unit in an interconnected system so
that the other
reservoirs can supply the water needed.
Excavation
The method involves draining most of or all the water in the basin and removing the sediment by
hand or power operated shovel, dragline scraper or other mechanical means. The excavation of
silt and clay which constitute most of the material in larger reservoirs is more difficult than the
excavation of sand and gravel. Fine-textured sediment cannot be excavated easily from larger
reservoirs unless it is relatively fluid or relatively compact.
Dredging
This involves the removal of deposits from the bottom of a reservoir and their conveyance to
some other point by mechanical or hydraulic means, while water storage is being maintained.
Dredging practices are grouped as:
a) Mechanical dredging by bucket, ladder, etc;
b) Suction dredging with floating pipeline and a pump usually mounted on a barrage;
and
c) Siphon dredging with a floating pipe extending over the dam or connected to an
opening in the dam and
usually with a pump on a barrage.
Reservoir operation
The flow in the river changes seasonally and from year to year, due to temporal and spatial
variation in precipitation. Thus, the water available abundantly during monsoon season becomes
scarce during the non-monsoon season, when it is most needed. The traditional method followed
commonly for meeting the needs of water during the scarce period is construction of storage
reservoir on the river course. The excess water during
the monsoon season is stored in such reservoirs for eventual use in lean period. Construction of
storages will also help in control of flood, as well as generation of electricity power. To meet the
objective set forth in planning a reservoir or a group of reservoirs and to achieve maximum
benefits out of the storage created, it is imperative to evolve guidelines for operation of
reservoirs. Without proper regulation schedules, the reservoir may not meet the full objective for
which it was planned and may also pose danger to the structure itself.
Control of flood is better achieved if the reservoir level is kept low in the early stages of the
monsoon season. However, at a later stage, if the anticipated inflows do not result the reservoir
may not get filled up to FRL in the early stages of monsoon, to avoid the risk of reservoir
remaining unfilled at later stage, there may be problem of accommodating high floods occurring
at later stage. In some cases while planning reservoirs, social and other considerations
occasionally result in adoption of a plan that may not be economically the best.
The common principles of single purpose reservoir operation are given below:
a) Flood control- Operation of flood control reservoirs is primarily governed by the
available flood storage capacity of damage centers to be protected, flood characteristics, ability
and accuracy of flood/ storm forecast and size of the uncontrolled drainage area. A regulation
plan to cover all the complicated situations may be difficult to evolve, but generally it should be
possible according to one of the following principles:
1) Effective use of available flood control storage: Operation under this principle aims at
reducing flood damages of the locations to be protected to the maximum extent possible, by
effective use of flood event. Since the release under this plan would obviously be lower than
those required for controlling the reservoir design flood, there is distinct possibility of having a
portion of the flood control space occupied during the occurrence of a subsequent heavy flood. In
order to reduce this element of risk, maintenance of an adequate network of flood forecasting
stations both in the upstream and down stream areas would be absolutely necessary.
2) Control of reservoir design flood: According to this principle, releases from flood control
reservoirs operated on this concept are made on the same hypothesis as adopted for controlling
the reservoir design flood, that is the full storage capacity would be utilized only when the flood
develops into the reservoir design flood. However, as the design flood is usually an extreme
event, regulation of minor and major floods, which occur more often, is less satisfactory when
this method is applied.
3) Combination of principle (1) and (2): In this method, a combination of the principles
(1) and (2) is followed. The principle (1) is followed for the lower portion of the flood reserve to
achieve the maximum benefits by controlling the earlier part of the flood. Thereafter releases are
made as scheduled for the reservoir design flood as in principle (2). In most cases this plan will
result in the best overall regulation, as it combines the good points of both the methods.
4) Flood control in emergencies: It is advisable to prepare an emergency release schedule that
uses information on reservoir data immediately available to the operator. Such schedule should
be available with the operator to enable him to comply with necessary precautions under extreme
flood conditions.
b) Conservation: Reservoirs meant for augmentation of supplies during lean period should
usually be operated to fill as early as possible during filling period, while meeting the
requirements. All water in excess of the requirements of the filling period shall be impounded.
No spilling of water over the spillway will normally be permitted until the FRL is reached.
Should any flood occur when the reservoir is at or near the FRL, release of flood waters should
be affected, so as not to exceed the discharge that would have occurred had there been no
reservoir. In case the year happens to be dry, the draft for filling period should be curtailed by
applying suitable factors. The depletion period should begin thereafter. However, in case the
reservoir is planned with carry- over capacity, it is necessary to ensure that the regulation will
provide the required carry-over capacity at the end of the depletion period.
Operation of multi purpose reservoirs: The general principles of operation of reservoirs with
these multiple storage spaces are described below:
1. Separate allocation of capacities- When separate allocations of capacity have been made
for each of the conservational uses, in addition to that required for flood control, operation for
each of the function shall follow the principles of respective functions. The storage available for
flood control could, however be utilized for generation of secondary power to the extent
possible. Allocation of specific storage space to several purposes with the conservation zone may
some times be impossible or very costly to provide water for the various purposes in the
quantities needed and at the time they are needed.
2. Joint use of storage space- In multi-purpose reservoir where joint use of some of the
storage space or storage water has been envisaged, operation becomes complicated due to
competing and conflicting demands. While flood control requires low reservoir level,
conservation interests require as high a level as is attainable. Thus, the objectives of these
functions are not compatible and a compromise will have to be effected in flood control
operations by sacrificing the requirements of these functions. In some cases parts of the
conservational storage space is utilized for flood moderation, during the earlier stages of the
monsoon. This space has to be filled up for conservation purpose towards the end of monsoon
progressively, as it might not be possible to fill up this space during the post-monsoon periods,
when the flows are insufficient even to meet the current requirements. This will naturally involve
some sacrifice of the flood control interests towards the end of the monsoon.
Where:
F WA
H = Head water
FV depth H’ = Tail
Water depth FWA
= Wave pressure
FW
force
FH = Horizontal hydrostatic force
F WA
W
FS = Silt/sediment pressure force
FH FEQ = Earthquake/Seismic force
F 'V
FW = Wind pressure force
FH’ = Tail water hydrostatic force
Fs F 'H
W = Weight of dam
Heel
F OD FOD = Internal pore water pressure
Toe
FU = Uplift pressure force [base of dam]
F U FV = Weight of water above dam [u/s]
FV’ = Weight of water above dam [d/s]
Figure 3-1 Representation of typical loads acting on Gravity dam
3.2.1 Water pressure
Water pressure is the force exerted by the water stored in the reservoir on the upstream and the
water depth at the tail of the dam.
i. External water pressure load
External water pressure can be calculated by the law of hydrostatics according to which in a static
mass of liquid the pressure intensity varies linearly with the depth of liquid and it acts normal to
the surface in contact with the liquid. For the non-overflow section of the dam water pressure
may be calculated as follows and for the overflow portion the loading will be discussed in section
six of the course.
FH = horizontal component of hydrostatic force, acting along a line 1/3 H above the
2
base = ½ wH
3
w = Unit weight of water (=10 kN/m )
Fv = Vertical component of hydrostatic pressure
= Weight of fluid mass vertically above the upstream face acting through the center of gravity
of the mass.
ii. Internal water pressure (Uplift Pressure)
Internal water pressure is the force exerted by water penetrating through the pores, cracks and
seams with in the body of the dam, at contact surface between the dam and its foundation, and
with in the foundation. It acts vertically upward at any horizontal section of the dam as well as its
foundation and hence it causes a reduction in the effective weight of the portion of the structure
lying above this section.
The computation of internal pressure involves the consideration of two constituent elements, i.e,
Hydrostatic pressure of water at a point
The percentage C, area factor, of the area on which the hydrostatic pressure acts Both these
elements are discussed below.
Hydrostatic pressure
In practice dams are usually provided with cut-off walls or grout curtains to reduce seepage and
drain to relieve pressure downstream from the cutoff. Actually cutoff and grout curtains may not
be perfectly tight and hence fail to dissipate the head (h1 – h2)
Usually a distribution like 1-2-3-4 is used with 3-4 a straight line as shown in Figure 3-3.
Opinions about the value of uplift reduction factor, (Zeta), are varied, the tendency is to take:
= 0.85 (for normal loading cases)
= 1.00 (for exceptional loading cases like earthquake)
h
h 2 2
h 1
W hen flow fro m u /s to d/s face is allow ed W ith u/s effective cutoff
h 1 h 2 h 2
h 1
Figure 3-2 Uplift pressure distribution for perfectly tight cutoff walls.
Figure 3-3. Uplift pressure distribution for less tight cutoff.
Uplift area factor, C
The value of area factor for concrete has been determined experimentally by several investigators.
However, for the foundation rock the value of area factor is not determinable experimentally and
hence the same has been estimated on the basis of theoretical considerations.
Some of the earliest investigators recommended, for both concrete and rock, a value of area factor
ranging from one third to two-thirds of the area to be considered as effective area over which the
uplift pressure acts. However, Harza, Terzaghi and Lelivakey have indicated that, for both
concrete and rock, the value of area factor is nearly equal to unity.
Table 3-1Values suggested for uplift area factor are
Value of C Suggested by
0.25 to 0.40 Henry
1.00 Maurice Levy
0.95 to 1.00 Terzaghi
As such the present practice followed in the design of dams is that the uplift pressure is assumed
to act over 100 percent of the area with in the body of the dam as well as its foundation. Hence,
under all conditions, the value C = 1.00 is recommended.
3.2.2 Wight of Structure
For a gravity dam the weight of the structure is the main stabilizing force, and hence the
construction material should be as heavy as possible.
Structure self weight is accounted for in terms of the resultant, W, which acts through the centroid
(center of gravity) of the cress-sectional area. The weight of the structure per unit length is
W = c * A
Where:c is the unit weight of concrete
A is the cross-sectional area of the structure
3
The unit weight of concrete may be assumed to be 24 kN/m in the absence specific data from
laboratory test trials. For final designs the specific weights shall be based on actual test data.
Where crest gates and other ancillary structures or equipments of significant weigh are present
they must also be accounted for in determining the weight of the structure.
It is essential to make sure that the actual specific weight obtained for the construction material is
more than or at least equal to that assumed in the design.
3.2.3 Earth and silt pressure
The gradual accumulation of significant deposits of fine sediment, notably silt, against the face of
the dam generates a resultant horizontal force, F s. The magnitude of this force in additional to
water load, FWH, is a function of the sediment depth, hs, the submerged unit weight, ss, and the
active pressure coefficient, Ka, and is determined according to Rankine‟s formula.
2
Fs = ½ Kass hs
Where Ka = (1-sin) / (1+sin)
= angle of internal friction of material.
3.2.4 Wind pressure
When the dam is full, wind will act only on the downstream face, thus contributing to stability.
When the dam is empty, wind can act on the upstream face, but the pressure is small compared to
the hydraulic pressure of the water. Hence for gravity dams wind is not considered. For buttress
dams, wind load on the exposed buttresses has to be considered.
3.2.5 Wave pressure and wave height
Wave exerts pressure on the upstream face. This pressure force, Fwv depends on fetch (extent of
the water surface on which the water blows) and wind velocity. It is of relatively small magnitude
and, by its nature, random and local in its influence. An empirical allowance for wave load may
be made by adjusting the static reservoir level used in determining F WV. According to Molitor the
following formula could be used to determine the rise in water level, hw
for f 32 km
1/4
h w 0 .763 0 .032 vf 0 .271 f
for f 32 km
hw
0 .032 vf
2
F 2 .0 h
wz w w
where: hw in meters
v wind velocity in km/hr and
f fetch in km
E arthquake D irection
D irection of vibraion
Figure 3-5 Direction of ground acceleration and the respective horizontal earthquake force on
gravity dam
As a result of 1, inertia effects will generate an additional hydrodynamic water load acting
downstream, plus a further inertia load attributable to the mass of the dam and also acting in a
downstream sense. Foundation acceleration downwards, 2 above, will effectively reduce the mass
of the structure. The more important recurring seismic shock waves have a frequency in the range
1-10Hz. Seismic loads consequently oscillate very rapidly and are transient in their effect. The
strength of seismic event can be characterized by its magnitude and its intensity.
Ground motions associated with earthquakes can be characterized in terms of acceleration,
velocity or displacement. Only peak ground acceleration, pga, generally expresses as a portion of
gravitational acceleration, g, is considered in this course. It has been suggested that in general
seismic events with a high pga of short duration are less destructive than seismic events of lower
pga and greater duration.
The natural frequency of vibration, fn, for a triangular gravity profile of height H (m) and base
thickness B(m) constructed in concrete with an effective modulus of elasticity E=14GPa can be
approximated as
2
fn = 600 B/H (Hz)
For a dam of H = 500m and B = 375m, fn = 0.9 Hz. But the most important recurring seismic
shock waves are in the order of magnitude of 1-10Hz. Hence resonance (the frequency of
vibration of the structure and earthquake are equal) of an entire dam is unlikely and is not a series
concern in design. But vulnerable portion of the dam should be detailed.
There are two methods to determine the seismic load on a dam
Pseudostaic (equivalent static load) method: inertia forces are calculated based on the
acceleration maxima selected for design and considered as equivalent to additional static loads.
This method generally is conservative and is applied to small and less vulnerable dams.
The acceleration intensities are expressed by acceleration coefficients h (Horizontal) and
v(vertical) each representing the ratio of peak ground acceleration. Horizontal and vertical
accelerations are not equal, the former being of greater intensity (h = (1.5 – 2.0v).
Based on the vertical and horizontal acceleration, the inertial force will be
Horizontal force = ±h * (static mass)
Vertical force = ±v * (static mass)
Three loading cases can be used for the assessment of seismic load combination:
7.1 Peak horizontal ground acceleration with zero vertical ground acceleration
7.2 Peak vertical ground acceleration with zero horizontal acceleration
7.3 Appropriate combination of both (eg. Peak of the horizontal and 40-50% of the
vertical)
Inertia forces
1. Mass of dam
Horizontal Feqh = ±hW
Vertical Feqv = ±vW
2. Water body
As analyzed by Westerguard(1993)
Py k ' ' h
w H.y
2 y H.yk'
F ewy h w '
3
where k” = earthquake factor for the water body
k" 0 .816
H 2
1 7 .75
1000
T
Where: T = period of earthquake
3
w = in tone/m
H, y in meters
The force acts at 0.4y from the dam joint being considered.
For inclined upstream face of dam
Figure 3-6 Foundation reaction for reservoir full and empty loading
P ' , P " W Mc
A
For empty reservoir P ' , P " W 1 6e
I
For full reservoir W 6 W .e
2 B B
B B
W 6e
1
B B
W
Requirements for stability
A masonry of plain concrete dam must be free from tensile stress, i.e. neither P’ nor P” shall be
negative, or
e ≤ B/6 (law of the middle third)
To limit compressive stress with in the dam body use:
P‟, P” if uplift always acts to the fullest extent.
P‟v , P”v if uplift does not act always.
Horizontal forces must be resisted both by shear and friction in the dam joint or in the foundation.
3.5 Rules Governing the Design of Gravity Dams
The following are basic assumptions that should be considered relative to the design of
important masonry/concrete dams.
1. The rock that constitutes the foundation and abutments at the site is strong enough to carry
the forces imposed by the dam with stresses well below the elastic limit at all places along
the contact planes.
2. The bearing power of the geologic structure along the foundation and abutments is great
enough to carry the total loads imposed by the dam without rock movements of detrimental
magnitude.
3. The rock formations are homogeneous and uniformly elastic in all directions, so that their
deformations may be predicted satisfactorily by calculations based on the theory of
elasticity, by laboratory measurements on models constructed of elastic materials, or by
combinations of both methods.
4. The flow of the foundation rock under the sustained loads that result from the construction
of the dam and the filling of the reservoir may be adequately allowed for by using a
somewhat lower modulus of elasticity than would otherwise be adopted for use in the
technical analyses.
5. The base of the dam is thoroughly keyed into the rock formations along the foundations and
abutments.
6. Construction operations are conducted so as to secure a satisfactory bond between the
concrete and rock materials at all areas of contact along the foundation and abutments.
7. The concrete in the dam is homogeneous in all parts of the structure.
8. The concrete is uniformly elastic in all parts of the structure, so that deformations due to
applied loads may be calculated by formulae derived on the basis of the theory of
elasticity or may be estimated from laboratory measurements on models constructed of
elastic materials.
9. Effects of flow of concrete may be adequately allowed for by using a somewhat lower
modulus of elasticity under sustained loads than would otherwise be adopted for use in
technical analyses.
10. Contraction joints are properly grouted under adequate pressures, or open slots are properly
filled with concrete, so that the dam may be considered to act as a monolith.
11. Sufficient drains are installed in the dam to reduce such uplift pressures as may develop
along areas of contact between the concrete and rock materials.
12. Effects of increases in horizontal pressures caused by silt contents of flood waters usually
may be ignored in designing high storage dams, but may require consideration in designing
relatively low diversion structures.
13. Uplift forces adequate for analyzing conditions at the base of the dam are adequate for
analyzing conditions at horizontal concrete cross sections above the base.
14. Internal stresses caused by natural shrinkage and by artificial cooling operations may be
adequately controlled by proper spacing of contraction joints.
15. Internal stresses caused by increases in concrete temperature after grouting are beneficial.
16. Maximum pressures used in contraction joint grouting operations should be limited to such
values as may be shown to the safe by appropriate stress analyses.
17. No section of the Ethiopia may be assumed to be entirely free from the occurrence of
earthquake shocks.
18. Assumptions of maximum earthquake accelerations equal to one tenth of gravity are
adequate for the design of important masonry dams without including additional allowances
for resonance effects.
19. Vertical as well as horizontal accelerations should be considered, especially in designing
gravity dams.
20. During the occurrence of temporary abnormal loads, such as those produced by earthquake
shocks, some increases in stress magnitudes and some encroachments on usual factors of
safety are permissible.
21. Effects of foundation and abutment deformations should be included in the technical
analyses.
22. In monolithic straight gravity dams, some proportions of the loads may be carried by twist
action and beam action at locations along the sloping abutments, as well as by the more
usually considered gravity action.
23. Detrimental effects of twist and beam action in straight gravity dams, such as cracking
caused by the development of tension stresses, may be prevented by suitable construction
procedure.
24. In monolithic curved gravity and arch dams, some proportions of the loads may be carried
by tangential shear and twist effects, as well as by the more usually considered arch and
cantilever actions.
25. The distribution of loads in masonry dams may be determined by bringing the calculated
deflections of the different systems of load transference into agreement at all conjugate
points in the structure.
The aforementioned assumptions are rephrased as rule/guideline for design of concrete gravity dam
as described below:
Rule1: Location of the resultant: No tension in any joint of the dam under all loading conditions
(i.e. for full and empty reservoir). Thus, resultant of all forces (including uplift) must intersect the
joint within the middle third.
Rule2a: Resistance to sliding when shear is neglected: the tangent of the angle between the vertical
and the resultant (including uplift) above horizontal plane shall be less than the allowable
coefficient of frictional force „f‟. If empirical values are taken, factor of safety, S f = 2.
Table 3-2 Some values of Coefficient of friction f
Surface f
Masonry on masonry or masonry on good rock or concrete on concrete 0.75
Concrete or masonry on gravel 0.50
Concrete or masonry on sand 0.40
Concrete or masonry on clay 0.30
However, the value of f for specific cases should be obtained by test
P tan f
For foundation on earth, Sf is taken as 3
W Sf
Rule 2b: Resistance to sliding when shear is considered
The total friction resistance to sliding on any joint plus the
ultimate shearing strength of the joint, must exceed the total
horizontal force above the joint by a safe margin, i.e.
f W r .S n .
P
A
S
sf
R
Where: Sn – ultimate shearing strength of material
Ssf = shear friction factor of safety
A = cross sectional area of joints
r = ratio of average to maximum shearing strength
Recommended values Ssf = 5, r = 0.5
2
rSsf = 200 to 500t/m
While analyzing resistance to sliding, first compute tan and if tan > f apply Rule 2b. In that
case, Ssf should equal or exceed the allowable value.
Rule 3: Governing compressive stresses: P‟ v, or P”v (maximum vertical stresses) are not the
maximum stresses in the structure. The maximum stresses occur at the end joints, or inclined
planes, normal to the face of the dam.
Maximum stress for downstream face, reservoir full:
Pi ' Pv' (1 tan 2 ' )
Maximum stress for upstream face, reservoir full
Pi " Pv" (1 tan 2 " )
The inclined compressive stresses in the dam and foundation shall not exceed the allowable
values.
Ultimate stress, ‟c = 14 to 31 MPa (after 28 days curing)
Working stress c = ‟c/6
For foundation materials some indications for allowable stress are:
Limestone -------------200 to 350 t/m3
Granite -------------250 to 300t/m3
Rule 4: Governing internal tension: The dam shall be designed and constructed in such a manner
as to avoid or adequately provide for tension on interior planes, inclined, vertical or horizontal.
Rule 5: Margin of safety: all assumptions of forces acting on the dam shall be unquestionably on
the safe side, all unit stresses adopted in design should provide an ample margin of safety against
rupture and the shear-factors shall be considered.
Rule 6: Detail of design and methods of construction: all details shall support and confirm to the
assumptions used in design; masonry should be of quality suited to the stresses adapted,
protection against overflowing water shall be ample.
3.6 Theoretical versus practical section of a dam
Considering only the two major forces acting on the dam, i.e. the weight of the dam and the
hydrostatic water pressure, the required section of the dam for its stability will be a triangle of
base width,
H
B
Apr-13 39
Addis Ababa University Hydraulic Structures I
that the principal stress at the downstream face may exceed the allowable limit. If one reaches
this zone during design, it is better to avoid it and start again with a fresh design with increased
crest width and/or better quality concrete.
Zoning of overflow dams (Spillways)
Zone I: the resultant in the reservoir full condition is outside the middle third point both
horizontal and vertical forces are existing. End of zone I is at a depth where resultant intersects
downstream middle third point. Upstream face needs reinforcement to take tension.
Zone Ia: this is the zone below zone1. The end of zone Ia is established by the plane where only
friction is sufficient to resist sliding.
Zone II: similar to zone II of non overflow dam with the only difference that the downstream
face is inclined in overflow dams. The rest of the zones are similar to those of non-overflow
dams.
3.7.3 Single Step Method
This method considers the whole dam as a single block. It is used for final design of very high
dams that extend well beyond zone V. it can also be used with an accuracy of 2 to 4% on the safe
side; for preliminary designs to obtain the area of the maximum section of the dam.
The dam designed by single step method has a straight downstream face. When extended it
intersects upstream face at the headwater surface.
Consider the sketch given:
L = 10-15% of h1
H10 = 2L (when earthquake is considered)
= 3L (when earthquake is not considered)
H6 = 1.33L
When designing (analyzing) a dam in the single step method, the dam is considered as a single
block; and dam dimensions are determined in such a way that rules of Zone IV are satisfied.
Figure 3-7 Gravity dam section relationship in single step method of design
Comparison of Single step and Multiple step design of gravity dam
Dams of smaller height can be designed economically by Multiple step method
High dams beyond zone IV are designed by Single step method so that convex curvature of
downstream face and excessive flat slope of upstream face are avoided
It may be economical to increase the concrete strength through the use of more expensive
material, so that even a high dam designed by dividing it into only four zones, thus eliminating
zone V and VI.
UNIT III
EARTH DAMS & SPILLWAYS
Instructional objectives
On completion of this lesson, the student shall learn:
1. The functions of a spillways and energy dissipators in projects involving diversion and
storage projects
2. Different types of spillways
3. How to determine the shape of an ogee-crested spillway and compute its discharge
4. The spillway profile in the presence of a breast wall
5. Criteria for selecting a particular type of spillway
6. Different types of energy dissipators
7. Design procedure for hydraulic jump and bucket-type energy dissipators
8. Protection measures against science downstream of energy dissipators
Introduction
The previous lessons dealt with storage reservoirs built by impounding a river with a dam and
the common types of dams constructed by engineers. However, in rare cases only it is
economical or practical for the reservoir to store the entire volume of the design flood within the
reservoir without overtopping of dam. Hence, a dam may be constructed to that height which is
permissible within the given topography of the location or limited by the expenditure that may be
possible for investment. The excess flood water, therefore, has to be removed from the reservoir
before it overtops the dam. Passages constructed either within a dam or in the periphery of the
reservoir to safely pass this excess of the river during flood flows are called Spillways.
Ordinarily, the excess water is drawn from the top of the reservoir created by the dam and
conveyed through an artificially created waterway back to the river. In some cases, the water
may be diverted to an adjacent river valley. In addition to providing sufficient capacity, the
spillway must be hydraulically adequate and structurally safe and must be located in such a way
that the out-falling discharges back into the river do not erode or undermine the downstream toe
of the dam. The surface of the spillway should also be such that it is able to withstand erosion or
scouring due to the very high velocities generated during the passage of a flood through the
spillway.
The flood water discharging through the spillway has to flow down from a higher elevation at the
reservoir surface level to a lower elevation at the natural river level on the downstream through a
passage, which is also considered a part of the spillway. At the bottom of the channel, where the
water rushes out to meet the natural river, is usually provided with an energy dissipation device
that kills most of the energy of the flowing water. These devices, commonly called as Energy
Dissipators, are required to prevent the river surface from getting dangerously scoured by the
impact of the outfalling water. In some cases, the water from the spillway may be allowed to
drop over a free overfall, as in Kariba Dam on Zambezi River in Africa, where the free fall is
over 100m.
In some projects, like the Indira Sagar Dam on River Narmada, two sets of spillways are
provided – Main and Auxillary. The main spillway, also known as the service spillway is the one
which is generally put into operation in passing most of the design flood. The crest levels of the
auxillary spillways are usually higher and thus the discharge capacities are also small and are put
into operation when the discharge in the river is higher than the capacity of the main spillway.
Sometimes, an Emergency or Fuse Plug types of spillway is provided in the periphery of the
reservoir which operates only when there is very high flood in the river higher than the design
discharge or during the malfunctioning of normal spillways due to which there is a danger of the
dam getting overtopped.
Usually, spillways are provided with gates, which provides a better control on the discharges
passing through. However, in remote areas, where access to the gates by personnel may not be
possible during all times as during the rainy season or in the night ungated spillways may have to
be provided.
The capacity of a spillway is usually worked out on the basis of a flood routing study, explained
in lesson 4.5. As such, the capacity of a spillway is seen to depend upon the following major
factors:
The inflow flood
The volume of storage provided by the reservoir
Crest height of the spillway
Gated or ungated
According to the Bureau of Indian Standards guideline IS: 11223-1985 “Guidelines for fixing
spillway capacity”, the following values of inflow design floods (IDF) should be taken for the
design of spillway:
For large dams (defined as those with gross storage capacity greater than 60 million m 3 or
hydraulic head greater than 60 million m3 or hydraulic head between (2m and 30m), IDF
should be based on the Standard Project Flood (SPF).
For intermediate dams those with gross storage between 10 and 60 million m3 or hydraulic
head between (2m and 30m), IDF should be based on the Standard Project
Flood (SPF).
For small dams (gross storage between 0.5 to 10 million m3 or hydraulic head between 7.5m
to 12m), IDF may be taken as the 100 year return period flood.
The volume of the reservoir corresponding to various elevation levels as well as the elevation of
the crest also affects the spillway capacity, as may be obvious from the flood routing procedure
shown in Lesson 4.5.
If the spillway is gated, then the discharging water (Q) is controlled by the gate opening and
hence the relation of Q to reservoir water level would be different from that of an ungated
spillway. In the example of Lesson 4.5, an ungated spillway considered. Where as, in most
practical cases, spillways are provided with gates and the gate operation is guided by a certain
predetermined sequence which depends upon the inflow discharge. Hence, for an actual spillway
capacity design, one has to consider not only the inflow hydrograph, but also the gate operation
sequence.
Apart from spillways, which safely discharge the excess flood flows, outlets are provided in the
body of the dam to provide water for various demands, like irrigation, power generation, etc.
Hence, ordinarily riverflows are usually stored in the reservoir or released through the outlets,
and the spillway is not required to function. Spillway flows will result during floods or periods of
sustained high runoff when the capacities of other facilities are exceeded. Where large reservoir
storage is provided, or where large outlet or diversion capacity is available, the spillway will be
utilized infrequently. This feature may be contrasted with that of a diversion structure-like a
barrage-where the storage is almost nil, and hence, the spillway there is in almost continuous
operation.
Spillways are ordinarily classified according to their most prominent feature, either as it pertains
to the control, to the discharge channel, or to some other component. The common types of
spillway in use are the following:
1. Free Overfall (Straight Drop) Spillway
2. Overflow (Ogee) Spillway
3. Chute (Open Channel/Trough) Spillway
4. Side Channel Spillway
5. Shaft (Drop Inlet/Morning Glory) spillway
6. Tunnel (Conduit) spillway
7. Siphon spillway
These spillways are individually treated in the subsequent sections.
The water flowing down from the spillways possess a large amount of kinetic energy that is
generated by virtue of its losing the potential head from the reservoir level to the level of the
river on the downstream of the spillway. If this energy is not reduced, there are danger of scour
to the riverbed which may threaten the stability of the dam or the neighbouring river valley
slopes. The various arrangements for suppressing or killing of the high energy water at the
downstream toe of the spillways are called Energy Dissipators. These are discussed at the end of
this lesson.
Overflow Spillway
The overflow type spillway has a crest shaped in the form of an ogee or S-shape (Figure 5). The
upper curve of the ogee is made to conform closely to the profile of the lower nappe of a
ventilated sheet of water falling from a sharp crested weir (Figure 6). Flow over the crest of an
overflow spillway is made to adhere to the face of the profile by preventing access of air to the
underside of the sheet of flowing water. Naturally, the shape of the overflow spillway is designed
according to the shape of the lower nappe of a free flowing weir conveying the discharge flood.
Hence, any discharge higher than the design flood passing through the overflow spillway would
try to shoot forward and get detached from the spillway surface, which reduces the efficiency of
the spillway due to the presence of negative pressure between the sheet of water and spillway
surface. For discharges at designed head, the spillway attains near-maximum efficiency. The
profile of the spillway surface is continued in a tangent along a slope to support the sheet of
flow on the face of the overflow. A reverse curve at the bottom of the slope turns the flow in to
the apron of a sliding basis or in to the spillway discharge channel.
An ogee crest apron may comprise an entire spillway such as the overflow of a concrete gravity
dam (Figure 7), or the ogee crest may only be the control structure for some other type of
spillway (Figure 8). Details of computing crest shape and discharges of ogee shaped crest is
provided in Section 4.8.9.
Chute Spillway
A chute spillway, variously called as open channel or trough spillway, is one whose discharge is
conveyed from the reservoir to the downstream river level through an open channel, placed
either along a dam abutment or through a saddle (Figure 9). The control structure for the chute
spillway need not necessarily be an overflow crest, and may be of the side-channel type
(discussed in Section 4.9.4), as has been shown in Figure 10. However, the name is most often
applied when the spillway control is placed normal or nearly normal to the axis of the open
channel, and where the streamlines of flow both above and below the control crest follow in the
direction of the axis.
Generally, the chute spillway has been mostly used in conjunction with embankment dams, like
the Tehri dam, for example. Chute spillways are simple to design and construct and have been
constructed successfully on all types of foundation materials, ranging from solid rock to soft
clay.
Chute spillways ordinarily consist of an entrance channel, a control structure, a discharge
channel, a terminal structure, and an outlet channel. Often, the axis of the entrance channel or
that of the discharge channel must be curved to fit the topography. For further details, one may
refer to the Bureau of Indian Standards Code IS: 5186- 1994 “Design of chute and side channel
spillways-criteria”.
Side channel Spillway
A side channel spillway is one in which the control weir is placed approximately parallel to the
upper portion of the discharge channel, as may be seen from Figure 10. When seen in plan with
reference to the dam, the reservoir and the discharge channel, the side channel spillway would
look typically as in Figure 11 and its sectional view in Figure 12. The flow over the crest falls
into a narrow trough opposite to the weir, turns an approximate right angle, and then continues
into the main discharge channel. The side channel design is concerned only with the hydraulic
action in the upstream reach of the discharge channel and is more or less independent of the
details selected for the other spillway components. Flow from the side channel can be directed
into an open discharge channel, as in Figure 10 or 11 showing a chute channel, or in to a closed
conduit which may run under pressure or inclined tunnel. Flow into the side channel
might enter on only one side of the trough in the case of a steep hill side location or on both sides
and over the end of the trough if it is located on a knoll or gently sloping abutment.
Discharge characteristics of a side channel spillway are similar to those of an ordinary overflow
spillway and are dependent on the selected profile of the weir crest. Although the side channel is
not hydraulically efficient, nor inexpensive, it has advantages which make it adoptable to
spillways where a long overflow crest is required in order to limit the afflux (surcharge held to
cause flow) and the abutments are steep and precipitous.
Shaft Spillway
A Shaft Spillway is one where water enters over a horizontally positioned lip, drops through a
vertical or sloping shaft, and then flows to the downstream river channel through a horizontal or
nearly horizontal conduit or tunnel (Figure 13). The structure may be considered as being made
up of three elements, namely, an overflow control weir, a vertical transition, and a closed
discharge channel. When the inlet is funnel shaped, the structure is called a Morning Glory
Spillway. The name is derived from the flower by the same name, which it closely resembles
especially when fitted with anti- vortex piers (Figure 14). These piers or guide vanes are often
necessary to minimize vortex action in the reservoir, if air is admitted to the shaft or bend it may
cause troubles of explosive violence in the discharge tunnel-unless it is amply designed for free
flow.
Discharge characteristics of the drop inlet spillway may vary with the range of head. As the head
increases, the flow pattern would change from the initial weir flow over crest to tube flow and
then finally to pipe flow in the tunnel. This type of spillway attains maximum discharging
capacity at relatively low heads. However, there is little increase in capacity beyond the designed
head, should a flood larger than the selected inflow design flood occur.
A drop inlet spillway can be used advantageously at dam sites that are located in narrow gorges
where the abutments rise steeply. It may also be installed at projects where a diversion tunnel or
conduit is available for use.
Tunnel Spillway
Where a closed channel is used to convey the discharge around a dam through the adjoining hill
sides, the spillway is often called a tunnel or conduit spillway. The closed channel may take the
form of a vertical or inclined shaft, a horizontal tunnel through earth or rock, or a conduit
constructed in open cut and backfilled with earth materials. Most forms of control structures,
including overflow crests, vertical or inclined orifice entrances, drop inlet entrances, and side
channel crests, can be used with tunnel spillways. Two such examples have been shown in Figs.
15 and 16. When the closed channel is carried under a dam, as in Figure 13, it is known as a
conduit spillway.
With the exception of those with orifice or shaft type entrances, tunnel spillways are designed to
flow partly full throughout their length. With morning glory or orifice type control, the tunnel
size is selected so that it flows full for only a short section at the control and thence partly full for
its remaining length. Ample aeration must be provided in a tunnel spillway in order to prevent a
fluctuating siphonic action which would result if some part of exhaution of air caused by surging
of the water jet, or wave action or backwater.
Tunnel spillways are advantageous for dam sites in narrow gorges with steep abutments or at
sites where there is danger to open channels from rock slides from the hills adjoining the
reservoir.
Conduit spillways are generally most suited to dams in wide valleys as in such cases the use of
this types of spillway would enable the spillway to be located under the dam very close to the
stream bed.
Siphon Spillway
A siphon spillway is a closed conduit system formed in the shape of an inverted U, positioned so
that the inside of the bend of the upper passageway is at normal reservoir storage level (Figure
17). This type of siphon is also called a Saddle siphon spillway. The initial discharges of the
spillway, as the reservoir level rises above normal, are similar to flow over a weir. Siphonic
action takes place after the air in the bend over the crest has been exhausted. Continuous flow is
maintained by the suction effect due to the gravity pull of the water in the lower leg of the
siphon.
Siphon spillways comprise usually of five components, which include an inlet, an upper leg, a
throat or control section, a lower leg and an outlet. A siphon breaker air vent is also provided to
control the siphonic action of the spillway so that it will cease operation when the reservoir water
surface is drawn down to normal level. Otherwise the siphon would continue to operate until air
entered the inlet. The inlet is generally placed well below the Full Reservoir Level to prevent
entrance of drifting materials and to avoid the formation of vortices and draw downs which
might break siphonic action.
Another type of siphon spillway (Figure 18) designed by Ganesh Iyer has been named after him.
It consists of a vertical pipe or shaft which opens out in the form of a funnel at the top and at the
bottom it is connected by a right angle bend to a horizontal outlet conduit. The top or lip of the
funnel is kept at the Full Reservoir Level. On the surface of the funnel are attached curved vanes
or projections called the volutes.
Special types of spillways
Apart from the commonly used spillways, a few other types of spillways are used sometimes for
a project, which are explained below.
Saddle Spillway
In some basins formed by a dam, there may be one or more natural depressions for providing
spillway. They are sometimes preferred for locating main spillway or emergency or auxiliary
spillways. A site which has a saddle is very desirable and economical, if the saddle is suitable for
locating the spillway. An example for such a spillway may be seen in Figure 9.
Fuse plug
It may be a simple earth bank, flash board or other device designed to fail when overtopped.
Such plugs may be used where the sudden release of a considerable volume of water is both safe
and not over destructive to the environment. “For example, the saddle spillway of Figure 9 may
be constructed as an earthen embankment dam, with its crest at a slightly higher elevation than
the High Flood Level (HFL) of the reservoir. In the occurrence of a flood greater than the design
flood which may cause rise in the reservoir water would overtop the earthen embankment dam
and cause its collapse and allow the flood water to safely pass through the saddle spillway.
Sluice Spillway
The use of large bottom openings as spillways is a relatively modern innovation following the
greater reliance on the safety and operation of modern control gates under high pressure. A
distinct advantage of this type of spillway is that provision can usually be made for its use for the
passage of floods during construction. One disadvantage is that, once built, its capacity is
definite whereas the forecasting of floods is still indefinite. A second disadvantage is that a
single outlet may be blocked by flood debris, especially where in flow timber does not float.
Figure 20 shows an example of a sluice spillway.
Duck-bill Spillway
This is a spillway with a rectangular layout projections into the reservoir comprising three
straight overflow lengths intersecting at right angles. The layout could be trapezoidal in which
case the corner angles will be other than 90 degree. The flow from the three reaches of the
spillway interacts in the trough portion and is further conveyed through a discharge carrier on to
a terminal structure to provide for energy dissipation. An example of this type of spillway is
shown in Figure 21.
Shape and Hydraulics of Ogee-Crest
Crest shape
The ogee shaped crest is commonly used as a control weir for many types of spillways-
Overflow (Figure 5), Chute (Figure 8), Side Channel (Figure 12) etc. The ogee shape which
approximates the profile of the lower nappe of a sheet of water flowing over a sharp-crested weir
provides the ideal form for obtaining optimum discharges. The shape of such a profile depends
upon the head, the inclination of the upstream face of the flow section, and the height of the
overflow section above the floor of the entrance channel (which influences the velocity of
approach to the crest). The ogee profile to be acceptable should provide maximum possible
hydraulic efficiency, structural stability
and economy and also avoid the formation of sub atmospheric pressures at the surface (which
may induce cavitations).
Ogee crested control structures are also sensitive to the upstream shape and hence, three types of
ogee crests are commonly used and shown in Figure 21. These are as follows:
1. Ogee crests having vertical upstream face
2. Ogee crests having inclined upstream face
3. Ogee crests having over hang on up stream face
However, the same general equations for the up stream and down stream quadrants are
applicable to all the three cases, as recommended by the Bureau of Indian Standards code IS:
6934-1998 “Hydraulic design of high ogee over flow spillways- recommendations” and are
outlined in the following paragraphs.
1. Ogee crests with vertical upstream face
2. Ogee crests with sloping up stream face
In this case, the desired inclination of the upstream face is made tangential to the same
elliptical profile as provided for a crest with a vertical face. The down stream face
equation remains unchanged.
3. Ogee crests with overhang
Whenever structural requirements permit, the upstream vertical face of an ogee crested
spillway (Figure 22) may be offset inside, (Figure 24). It is recommended that the ratio of
the rises M to the design head Hd, should be at least 0.6 or greater for flow conditions to
be stable. The crest shapes on the up stream and downstream may be provided the same
as for an ogee crest with vertical up stream wall if the condition M/ H d >0.6 is satisfied.
For an ogee crested control weir for a spillway without any control with a gate, the free flow
discharge equation is given as
Where Q is the discharge (in m3/s), Cd is the coefficient of discharge, Le is the effective length
of crest (in m), including velocity of approach head. The discharge coefficient, C d, is influenced
by a number of factors, such as:
1. Depth of approach
2. Relation of the actual crest shape to the ideal nappe shape
3. Upstream face slope
4. Downstream apron interference, and
5. Downstream submergence
The effect of the above mentioned factors on the variation of discharge and calculation for
effective length are mentioned in the following paragraphs.
Where the crest piers and abutments are shaped to cause side contractions of the overflow, the
effective length, Le, will be the net length of the crest, L. The effect of the end contractions may
be taken into account by reducing the net length of crest as given below:
Le L 2N p a e
Where L, Le and H have been explained before, N is the number of piers and Kp and Ka are the
pier and abutment contraction coefficients. The reason for the reduction of the net length may be
appreciated from Figure 32.
The pier contraction coefficient Kp depends upon the following factors:
1. Shape and location of the pier nose
2. Thickness of the pier
3. Head in relation to the design head
4. Approach velocity
For the condition of flow at the design head, the average values of pier contraction coefficients
may be assumed as shown in Figure 33.
The abutment contraction coefficient is seen to depend upon the following factors:
1. Shape of abutment
2. Angle between upstream approach wall and the axis of flow
3. Head, in relation to the design head
4. Approach velocity
For the condition of flow at the design head, the average value of abutment contraction
coefficients may be assumed as shown in Figure 33.
For flow at head other than design head, the values of Kp and Ka may be obtained from
graphical plots given in IS: 6934-1973 “Recommendations for hydraulic design of high ogee
overflow spillways”.
Discharge characteristics of ogee crests-controlled spillway
The discharge for gated crests at partial gate opening is similar to flow through a low- head
orifice and may be computed by the following equation recommended by the Bureau of Indian
Standards code IS:6934-1998 “Hydraulic design of high ogee overflow spillways-
recommendations”.
Q C g G0 L
2ge (4)
H
e
Where Q is the discharge (in m3/s), Cg is the gated coefficient of discharge, G0 is the gate
opening (in m), Le is the effective length of crest, g is the acceleration due to gravity, and He is
the hydraulic head measured from the centre of the orifice (in m).
Usually for high head spillways, radial gates are common and Figure 34 shows the position of a
partially opened radial gate over an ogee-crested spillway. The gate opening G0 may be seen to
be measured as the shortest distance from the gate lip to the ogee crest profile meeting at G. The
angle is seen to be measured between the tangent at G and the tangent of the radial gate at gate
lip. Figure 35 presents a curve relating the coefficient of gated discharge Cg with the angle .
The curve presents an average value of Cg determined for various approach and downstream
conditions and may be used for preliminary design purposes. In fact, it may be noticed that the
discharge equation mentioned above for calculating flow through a gated spillway as
recommended in IS: 6934-1998 may not be strictly correct as the gate opening becomes larger,
comparable to the hydraulic head Hc.
2 2
3 X 3Y 1 (5)
A2 B2
3 3
where
A3 = 0.541 D (Hd/D)0.32
0.04 and
Discharge Computation
The discharge through the breast wall spillway may be estimated by the equation:
⎧2 ⎛ 2 a⎞
V 0.5
Q Cb L D⎨ g c
g2⎟
⎜ (12)
⎪
⎝ ⎠
The following equation relates Ch with the parameter (H/Hd) in the range of H/Hd = 0.8 to 1.33.
0.80 0.696
1.00 0.769
1.15 0.797
1.33 0.829
Selection of spillways
The Bureau of Indian Standards code IS: 10137-1982 “Guidelines for selection of spillways and
energy dissipators” provide guidelines in choosing the appropriate type of spillway for the
specific purpose of the project. The general considerations that provide the basic guidelines are
as follows:
Type of Dam
This is one of the main factors in deciding the type of spillway. For earth and rockfill dams,
chute and ogee spillways are commonly provided, whereas for an arch dam a free fall or morning
glory or chute or tunnel spillway is more appropriate. Gravity dams are mostly provided with
ogee spillways.
Purpose of Dam and Operating Conditions
The purpose of the dam mainly determines whether the dam is to be provided with a gated
spillway or a non-gated one. A diversion dam can have a fixed level crest, that is, non-gated
crest.
Ogee Spillway
It is most commonly used with gravity dams. However, it is also used with earth and rockfill
dams with a separate gravity structure; the ogee crest can be used as control in almost all types of
spillways; and it has got the advantage over other spillways for its high discharging efficiency.
Chute Spillway
a) It can be provided on any type of foundation,
b) It is commonly used with the earth and rockfill dams, and
c) It becomes economical if earth received from spillway excavation is used in dam
construction.
The following factors limit its adaption:
a) It should normally be avoided on embankments;
b) Availability of space is essential for keeping the spillway basins away from the dam paving;
and
c) If it is necessary to provide too many bends in the chute because of the topography, its
hydraulic performance can be adversely affected.
Siphon Spillway
Siphon spillways can be used to discharge full capacity discharges, at relatively low heads, and
great advantage of this type of spillway is its positive and automatic operation without
mechanical devices and moving parts.
The following factors limit the adoption of a siphon spillway:
It is difficult to handle flows materially greater than designed capacity, even if the reservoir head
exceeds the design level; Siphon spillways cannot pass debris, ice, etc; There is possibility of
clogging of the siphon passage way and breaking of siphon vents with logs and debris; In cold
climates, there can be freezing inside the inlet and air vents of the siphon; When sudden surges
occur and outflow stops; The structure is subject to heavy vibrations during its operation needing
strong foundations; and Siphons cannot be normally used for vacuum heads higher than
8 m and there is danger of cavitation damage.
Energy dissipators
Different types of energy dissipators may be used along with a spillway, alone or in combination
of more than one, depending upon the energy to be dissipated and erosion control required
downstream of a dam. Broadly, the energy dissipators are classified under two categories –
Stilling basins or Bucket Type. Each of these are further sub- categorized as given below.
The shapes of the different types of bucket-type stilling basins have been given in section 4.8.14.
Usually the hydraulic jump type stilling basins and the three types of bucket-type energy
dissipators are commonly used in conjunction with spillways of major projects. The detailed
designs of these are dealt in subsequent sections.
Since energy dissipators are an integral part of a dam‟s spillway section, they have to be viewed
in conjuction with the latter. Two typical examples have been shown in Figures 45 and 46,
though it must be remembered that any type of energy dissipator may go with any type of
spillway, depending on the specific site conditions.
Design of Hydraulic Jump Stilling Basin type energy dissipators
A hydraulic jump is the sudden turbulent transition of supercritical flow to subcritical. This
phenomena, which involves a loss of energy, is utilized at the bottom of a spillway as an energy
dissipator by providing a floor for the hydraulic jump to take place (Figure 47). The amount of
energy dissipated in a jump increases with the rise in Froude number of the supercritical flow.
The two depths, one before (y1) and one after (y2) the jump are related by the following
expression:
y1 1
1 1 8F 2
1 (14)
y2 2
V1
Where F1 is the incoming Froude number =
gy1
Alternatively, the expression may be written in terms of the outgoing Froude number F 2
⎛ ⎞
⎜ V 2 ⎟ as
⎜ ⎟
⎝ gy2 ⎠
y2 1
1 1 8F 2
2
y1 2
(15)
where V1 and V2 are the incoming and outgoing velocities and g is the acceleration due to
gravity.
The energy lost in the hydraulic jump (EL) is given as:
y y
3
EL 2 1 (16)
4 y1 y2
In most cases, it is possible to find out the pre-jump depth (y1) and velocity (V1) from the given
value of discharge per unit width (q) through the spillway. This is done by assuming the total
energy is nearly constant right from the spillway entrance up to the beginning of the jump
formation, as shown in Figure 47. V1 may be assumed to be equal
to 2gH1 , where H1 is the total energy upstream of the spillway, and neglecting friction
losses in the spillway. The appropriate expressions may be solved to find out the post- jump
depth (y2) and velocity (V2).
The length of the jump (Lj) is an important parameter affecting the size of a stilling basin in
which the jump is used. There have been many definitions of the length of the jump, but it is
usual to take the length to be the horizontal distance between the toe of the jump upto a section
where the water surface becomes quite level after reaching a maximum level. Because the water
surface profile is very flat towards the end of the jump, large personal errors are introduced in the
determination of the jump length.
Bradley and Peterka (1975) have experimentally found the length of hydraulic jumps and plotted
them in terms of the incoming Froude number (F1), and post-jump depth (y2) as shown in Figure
48. It is evident that while Lj/y2 varies most for small values of F1, at higher values, say above 5
or so, Lj /y2 is practically constant at a value of about 6.1.
The depth of water in the actual river downstream of the stilling basin (y2*) is determined from
the river flow observations that have been plotted as a stage-discharge curve (Figure 49).
Subtracting the stilling basing apron level from the stage or water level corresponding to the total
discharge passing through the spillway gives the tail-water depth (y2*). Since the stage-discharge
curve gives indications about the tail-water of the spillway, it is called the Tail-Water Rating
Curve (TRC), usually expressed as the water depth (y2*) versus unit discharge (q), as shown in
Figure 50(a).
At the same time, using the formula relating unit discharge (q) with the post-jump depth (y2), a
similar graph may be obtained, as shown in Figure 50(b). Since this graph gives indication about
the variation of the post-jump depth, it is called the Jump Rating Curve (JRC).
In general, the JRC and TRC would rarely coincide, if plotted on the same graph, as shown in
Figure 51.
At times, the TRC may lie completely below the JRC (Figure 52), for all discharges, in which
case the jump will be located away from the toe of the spillway resulting in possible erosion of
the riverbed.
If the TRC is completely above the jump would be located so close to the spillway to make it
submerged which may not dissipate the energy completely. (Figure 53)
It may also be possible in actual situations that the TRC may be below the JRC for some
discharges above for the rest, as shown in Figs. 54 and 55.
In these cases two, favourable location of jump may not be possible. In view of the above
situations, the following recommendations have been made for satisfactory performance of the
hydraulic jumps.
An upturn solid bucket is used when the tailwater depth is much in excess of sequent depth and
in which dissipation of considerable portion of energy occurs as a result of formation of two
complementary elliptical rollers, one in bucket proper, called the surface roller, which is
anticlockwise (if the flow is to the right) and the other downstream of the bucket, called the
ground roller, which is clockwise.
In the case of solid roller bucket the ground roller is more pronounced and picks up material
from downstream bend and carried it towards the bucket where it is partly deposited and partly
carried away downstream by the residual jet from the lip. The deposition in roller bucket is more
likely when the spillway spans are not operated equally, setting up horizontal eddies downstream
of the bucket. The picked up material which is drawn into the bucket can cause abrasive damage
to the bucket by churning action.
For effective energy dissipation in a solid roller bucket, both the surface or dissipating roller and
the ground or stabilizing roller, should be well formed. Otherwise, hydraulic phenomenon of
sweep out or heavy submergence occurs depending upon which of the rollers is inhibited.
Design Criteria - The principal features of hydraulic design of solid roller bucket consists of
determining:
a) The bucket invert elevation,
b) The radius of the bucket, and
c) The slope of the bucket lip or the bucket lip angle.
Drawal of Bed Materials - A major problem with the solid roller bucket would be the damage
due to churning action, caused to the bucket because of the downstream bed material brought
into the bucket by the pronounced ground roller. Even in a slotted roller bucket downstream
material might get drawn due to unequal operation of gates. The channel bed immediately
downstream of the bucket shall be set at 1 to 1.5 m below the lip level to minimize the possibility
of this condition. Where the invert of the bucket is required to be set below the channel general
bed level the channel should be dressed down in one level to about 1 to 1.5 m below the lip level
in about 15 m length downstream and then a recovery slope of about 3 ( horizontal ) to 1 (
vertical ) should be given to meet the general bed level as shown in Figure 62. Careful model
studies should be done to check this tendency. If possible, even provision of solid apron or
cement concrete blocks may be considered to avoid trapping of river bed material in the bucket
as it may cause heavy erosion on the spillway face, bucket and side training wall.
In the case of slotted roller bucket a part of the flow passes through the slots, spreads laterally
and is lifted away from the channel bottom by a short apron at the downstream end of the bucket.
Thus the flow is dispersed and distributed over a greater area resulting in a less violent ground
roller. The height of boil is also reduced in case of slotted roller bucket. The slotted bucket -
provides a self-cleaning action to reduce abrasion in the bucket.
In general the slotted roller bucket is a improvement over the solid roller bucket for the range of
tailwater depths under which it can operate without sweepout or diving. However, it is necessary
that specific model experiments should be conducted to verify pressure on the teeth so as to
avoid cavitation conditions. In case of hydraulic structures in boulder stages slotted roller
buckets need not be provided. Heavy boulders rolling down the spillway face can cause heavy
damage to the dents thereby making them ineffective and on the contrary, increasing the chances
of damage by impact, cavitation and erosion.
An upturned bucket with teeth in it used when the tailwater depth is much in excess of sequent
depth and in which the dissipation of energy occurs by lateral spreading of jet passing through
bucket slots in addition to the formation of two complementary rollers as in the solid bucket.
In the slotted roller bucket, a part of the flow passes through the slots, spreads laterally and is
lifted away from the channel bottom by a short apron at the downstream end of the bucket. Thus
the flow is dispersed and distributed over a greater area providing less violent flow
concentrations compared to those in a solid roller bucket. The velocity distribution just
downstream of the bucket is more akin to that in a natural stream, that is, higher velocities at the
surface and lower velocities at the bottom. While designing a slotted roller bucket, for high head
spillway exceeding the total head of 50 m or so, specific care should be taken especially for
design of the teeth, to ensure that the teeth will perform cavitation free. Specific model tests
should therefore be conducted to verify pressures on the teeth and the bucket invert should
accordingly be fixed at such an elevation as to restrict the subatmospheric pressures to the
permissible magnitude.
Design Criteria - The principal features of hydraulic design of the slotted roller bucket consists
of determining in sequence:
a) bucket radius;
b) bucket invert elevation;
c) bucket lip angle; and
d) bucket and tooth dimensions, teeth spacing and dimensions and profile of short apron.
An example of the use of a slotted roller bucket is the energy dissipator provided in the Indira
Sagar Dam Spillway (Figure 63).
Hydraulic Design of Trajectory Bucket Type Energy Dissipator
An upturn solid bucket used when the tailwater depth is insufficient for the formation of the
hydraulic jump, the bed of the river channel downstream comprises sound rock and is capable of
withstanding, without excessive scour, the impact of the high velocity jet. The flow coming
down the spillway is thrown away from toe of the dam to a considerable distance downstream as
a free discharging upturned jet which falls into the channel directly, thereby avoiding excessive
scour immediately downstream of the spillway. There is hardly any energy dissipation within the
bucket itself. The device is used mainly to increase the distance from the structure to the place
where high velocity etc. hits the channel bed, thus avoiding the danger of excessive scour
immediately downstream of the spillway. Due to the throw of the jet in the shape of a trajectory,
energy dissipation takes place by
a) internal friction within the jet,
b) the interaction between the jet and surrounding air,
c) the diffusion of the jet in the tailwater, and
d) the impact on the channel bed.
When the tailwater depth is insufficient for the formation of the hydraulic jump and the bed of
the channel downstream comprises sound rock which is capable of withstanding the impact of
the high velocity jet, the provision of a trajectory bucket is considered
more suitable as provision of conventional hydraulic jump type apron or a roller bucket involves
considerable excavation in hard strata forming the bed. It is also necessary to have sufficient
straight reach in the downstream of a skijump bucket. The flow coming down the spillway is
thrown away in air from the toe of the structure to a considerable distance as a free discharging
upturned jet which falls on the channel bed d/s. The hard bed can tolerate the spray from the jet
and erosion by the plunging jet would not be a significant problem for the safety of the structure.
Thus, although there is very little energy dissipation within the bucket itself, possible channel
bed erosion close to the downstream toe of the dam is minimized. In the trajectory bucket, only
part of the energy is dissipated through interaction of the jet with the surrounding air. The
remaining energy is imparted to the channel bed below. The channel bed should consist of
sound, hard strata and should be free from laminations, joints and weak pockets to withstand the
impact of jet. The design of the trajectory bucket presupposes the formation of large craters or
scour holes at the zone of impact of the jet during the initial years of operation and, therefore, the
design shall be restricted to sites where generally sound rock is available in the river bed. Special
care shall be taken to concrete weak pockets in the bed located in a length of
Design Criteria - The principal features of hydraulic design of tra jectory bucket consist of
determining:
a) Bucket shape,
b) Bucket invert elevation, radius or principal geometrical parameters of the bucket, lip
elevation and exit angle, trajectory length, and
c) Estimation of scour downstream of the spillway.
An example of the use of a trajectory bucket is the one provided in the Srisailam Dam Spillway
(Figure 64).
Further details about the design of bucket type energy dissipators may be had from the Bureau of
Indian Standards Code IS: 7365-1985 “Criteria for hydraulic design of bucket type energy
dissipators”
1. Training Walls at the Flanks of the Spillways- Training walls extended beyond the end-sill of
the stilling basins or buckets generally serve to guide the flow into the river channel, protect the
wrap-rounds of the adjacent earth dams,
river banks or power house bays and tail race channels. To this extent, the training walls are -
considered to be downstream protection works.
Figure 65 shows the various types of protection works that may typically be used downstream of
a spillway.
The importance of providing protection below a spillway, especially of the trajectory type may
be noted from the incidence of deep scour on the downstream of the Srisailam dam spillway.
Case Study
Srisailam dam spillway (Figure 64) across river Krishna was constructed during 1977-
83. It is a 137 m high concrete dam, with 12 spans of 18‟3 m x 16‟8 m. The river bed is
composed of quartzites and shales. In the immediate downstream vicinity of the spillway, there
were horizontal shear zones 0‟2 m to 0‟9 m thick, where the quartzites are crushed and sheared.
During the monsoons of 1977 to 1980, the construction stage flood passed over the partially
constructed spillway bays, spilling over 7 bays which
were at different levels having a maximum difference of level of 23 m. The difference
in level between the lip of the ski-jump bucket and downstream rock was about 44 m.
Shorter throw of the water spilling over the bucket lip, as a cascading flow caused
deep scour in the immediate vicinity of the bucket lip. During subsequent floods, the
scour holes were concreted and leveled as protective aprons in some part of the
spillway. Such aprons were however, subjected to repeated damage and undermining.
By April 1985, depth of scour below blocks 11 to 13 reached from 9 m to 22 m below
the protective apron. Cavities of undermining below the apron were also present at a
depth of 6 to 9 m.
The protection work consisted of providing an underwater massive concrete block
touching the apron and filling the eroded cavities below the apron. The water level at
downstream toe varied from the top of existing apron to about 1.5 m below it.
The scheme involved forming 4 cells with steel cylinder walls and filling concrete in
each cell followed by concrete capping. Heavy concrete blocks (approximate 1 metre
cube) were placed downstream of the cylinder watls to further protect the rock from
the water jump damage.
Since the construction of the above protection works, the spillway was completed to
final levels and crest gates have also been installed. Hydraulic model studies were
conducted to evolve an operation of the spillway in such a way that the throw of the
trajectory fall further away from the toe of the dam. This together with the protective
measures already implemented is expected to prevent further erosion at the toe of the
dam.
Outlet works enable stored water to be released from the reservoir to users, and also to
empty the dam within a reasonable period for safety reasons. Multilevel draw-offs are
frequently provided to draw well-oxygenated water from just below the surface of the
reservoir.
1. Introduction
The main purpose of a spillway is to safely pass moderate floods and to prevent a dam
from failing during very major floods. It is therefore essential that the spillway designer
cope with frequent flood releases without significant CHAPTERS erosion or other
related damage.
provides a structure that complies with all safety requirements at the least combined
lifetime cost of the spillway and dam (see Large Dams).
The spillway system has to safely pass the Recommended Design Flood (RDF) with
adequate freeboard. However, when the system passes the Safety Evaluation Flood
(SEF), it might not cause the dam to fail catastrophically, but could cause substantial
damage to the structure and its surroundings.
2. Spillway Types
2.1 Service spillways can be either uncontrolled or gated spillways - both are able to
flood peaks, as well as being cheaper to build and maintain. Free overspill crest
spillways, shaft spillways and syphon spillways also fall into this category.
2.3 Gated spillways should be backed-up by auxiliary spillways as the gates may be
subject to automatic operation malfunction, human error and debris blockage. These
spillways enable storage to be maximised by controlling water levels. They also allow
pre-releases, but if incorrectly operated, can aggravate downstream flooding. Gated
spillways are generally more complex and more costly to build and maintain than
uncontrolled spillways.
2.4 Auxiliary spillways are uncontrolled spillways used in combination with service
spillways and sometimes also with flood outlets, specifically at dams without a service
spillway. The auxiliary spillway might take the form of either a fuse plug or fuse gate,
which must be designed to function automatically when required without aggravating
downstream floods.
The choice of a spillway type depends on a number of factors including the dam type, topography, geology,
flood discharge and the frequency and duration of overflows. The main components of spillways influenced by
these factors and which have to be combined in the most economically effective manner are the following as
shown in Figure 1:
The design of spillways is conveniently also divided into the above mentioned components shown in Figure 1
as follows:
UNIT IV
DIVERSION HEAD WORKS
Diversion Head Works
The works, which are constructed at the head of the canal, in order to divert the river water towards the
canal, so as to ensure a regulated continuous supply of silt-free water with a certain minimum head into the
canal, are known as diversion heads works.
CREST
CREST LEVEL = POND LEVEL POND LEVEL SHUTTER
PONDING BY CREST LEVEL
CREST SHUTTER P2
P1 = P PONDING BY TOTAL
TOTAL PONDING
P2 = 0 RAISED CREST P1 PONDING (P)
BY RAISED CREST WEIR WITHOUT
SHUTTERS
P1 >>>> P2
(a) Fig: Weir without shutters (b) Fig: Weir with shutters
PONDING BY P1 = 0
CREST P1 P2 = P
P1 <<<< P2 (BARRAGE)
(c) Fig: Barrage with a small raised crest (d) Fig: Barrage without any raised crest
1
Weir
5.
If the major part or the entire ponding of water is achieved by a raised crest and a smaller part or nil part
of it is achieved by the shutters, then this barrier is known as a weir.
Types of weirs
Masonry weirs with vertical drop
Rock-fill weirs with sloping aprons
Concrete weirs with sloping glacis
2
Rock-fill weirs with sloping aprons
It consists of masonry breast wall which is provided with adjustable crest shutter. The upstream
rock-fill portion is constructed with boulders forming a slope of 1 in 4. The boulders are grouted with
cement mortar. The downstream sloping apron consists of core walls. The intermediate spaces between the
core walls are filled up with boulders maintaining a slope of 1 in 20. The boulders are grouted properly
with cement mortar.
Concrete weir
Now-a-days, the weir is constructed with reinforced cement concrete. The impervious floor and the
weir are made monolithic. The cut off walls are provided at the upstream and downstream end of the floor
and at the toe of the weir. Sheet piles are provided below the cut-off walls. The crest shutters are also
provided which hare dropped down during the flood.
Barrage
If most of the ponding is done by gates and a smaller or nil part of it is done by the raised crest, then
the barrier is known as a barrage or a river regulator.
3
Afflux:
1. The rise in the highest flood level (HFL) upstream of the weir due to construction of the weir
across the river is called.
1. In case of weir, the afflux caused during high floods is quite high. But in case of a barrage, the
gates can be opened during high floods and the afflux will be nil or minimum.
SL Barrage Weir
(a) Low set crest High set crest
(b) Ponding is done by means of gates Ponding is done against the raised crest or
partly against crest and partly by shutters
(c) Gated over entire length Shutters in part length
(d) Gates are of greater height Shutters are of smaller height, 2 m
(e) Gates are raised clear off the high floods to pass floods Shutters are dropped to pass floods
(f) Perfect control on river flow No control of river in low floods
(g) Gates convenient to operate Operation of shutters is slow, involve labour
and time
(h) High floods can be passed with minimum afflux Excessive afflux in high floods
(i) Less silting upstream due to low set crest Raised crest causes silting upstream
(j) Longer construction period Shorter construction period
(k) Silt removal is done through under sluices No means for silt disposal
(l) Road and/or rail bridge can be constructed at low cost Not possible to provide road-rail bridge
(m) Costly structure Relatively cheaper structure
4
Marginal bund
joined to high
contours
Guide bank
RIVER FLOW
Weir divided
into
Fish ladder
bays with piers
Length divided into ways by
piers. Each way is provided
with a gate so as to act as an
opening of controlled height
Fig: Typical layout of diversion head-works
Weir Proper:
It is a barrier constructed across the river. It aims to raise the water level in order to feed the canal.
Under-sluices:
The under sluices are the openings provided at the base of the weir or barrage. These openings are
provided with adjustable gates. Normally, the gates are kept closed. The crest of the under-under sluice
portion of the weir is kept at a lower level (1 1.5 m) than the crest of the normal portion of the weir. The
suspended silt goes on depositing in front of the canal head regulator. When the silt deposition becomes
appreciable the gates are opened and the deposited silt is loosened with an agitator mounting on a boat.
The muddy water flows towards the downstream through the scouring sluices. The gates are then closed.
But, at the period of flood, the gates are kept opened.
The main functions of under-sluices are:
i. To maintain a well defined deep channel approaching the canal head regulator.
i. To ensure easy diversion of water into the canal through the canal head regulator even during low
flow.
1. To control the entry of silt into the canal
i. To help scouring and of the silt deposited over the under-sluice floor and removing towards the
downstream side.
To help passing the low floods without dropping the shutters of the weir.
The divide wall:
o
The divide wall is a masonry or concrete wall constructed at right angle to the axis of the weir.
p
The divide wall extends on the upstream side beyond the beginning of the canal head regulator;
and on the downstream side, it extends upto the end of the loose protection of the under-
sluices.
q
The divide wall is a long wall constructed at right angles in the weir or barrage, it may be
constructed with stone masonry or cement concrete. On the upstream side, the wall is extended
just to cover the canal head regulator and on the downstream side, it is extended up to the
launching apron.
5
The main functions of the divide walls:
o It separates the „under-sluices‟ with lower crest level from the „weir proper‟ with higher crest
level.
o It helps in providing a comparatively less turbulent pocket near the canal head regulator, resulting in
deposition of silt in this pocket and, thus, to help in the entry of silt-free water
into the canal.
a It helps to keep cross-current, if any, away from the weir.
Fish Ladder
iii.
It is device by which the flow energy can be dissipated in such a manner as to provide
smooth flow at sufficiently low velocity, not exceeding 3 to 3.5 m/s.
iv.
A narrow opening including suitable baffles or staggering devices in it is provided adjacent
to the divide wall.
v.
The fish ladder is provided just by the side of the divide wall for the free movement of
fishes. Rivers are important source of fishes.
vi.
There are various types of fish in the river. The nature of the fish varies from type to type.
But in general, the tendency of fish is to move from upstream to downstream in winters and
from downstream to upstream in monsoons. This movement is essential for their survival.
Due to construction of weir or barrage, this movement gets obstructed, and is detrimental to
the fishes.
vii.
In the fish ladder, the fable walls are constructed in a zigzag manner so that the velocity of
flow within the ladder does not exceed 3 m/sec
viii.
The width, length and height of the fish ladder depend on the nature of the river and the
type of the weir or barrage.
..
6
The water from the under-sluice pocket is made to enter the regulator bays, so as to pass the full supply
discharge into the canal. The maximum height of these gated openings, called head sluices will be equal to
the difference of Pond Level and Crest Level of the regulator.
The entry of silt into the canal is controlled by keeping the crest of the head regulator by
about 1.2 to 1.5 meters higher than the crest of the under-sluices.
If a silt-excluder is provided, the regulator crest is further raised by about 0.6 to 0.7 meter.
Silt gets deposited in the pocket, and only the clear water enters the regulator bays.
The deposited silt can be easily scoured out periodically, and removed through the under-
sluice openings.
7
(a) Guide Bank
When a barrage is constructed across a river which flows through the alluvial soil, the guide banks must
be constructed on both the approaches to protect the structure from erosion.
Guide bank serves the following purposes:
It protects the barrage from the effect of scouring and erosion.
It provides a straight approach towards the barrage.
It controls the tendency of changing the course of the river.
It controls the velocity of flow near the structure.
Marginal Bunds
The marginal bunds are earthen embankments which are constructed parallel to the river bank on one or
both the banks according to the condition. The top width is generally 3 m to 4 m. The side slope on the
river side is generally 1.5: 1 and that on the country side is 2:1.
The marginal bunds serve the following purposes:
It prevents the flood water or storage water from entering the surrounding area which may be
submerged or may be water logged.
It retains the flood water or storage water within a specified section.
It protects the towns and villages from devastation during the heavy flood.
It protects valuable agricultural lands.
8
i. Timber Spur: In this type, a box like compartment is prepared by driving timber piles at 15 cm to
30 cm centre to centre. The piles are secured by wooden bracings. The hollow space is filled up
by boulders. This spur is permeable but stable. This is recommended for bi rivers with high
velocity of flow. The length of the timber piles depend on bed condition.
ii. Boulder Spur: In this type of spur, boulders are enclosed in G.I wire net in circular shape. The
boulder should be heavy, varying from 30 kg to 50 kg and the wire net should be made of 4 mm
o o
diameter G.I wires. It is laid from the river bank towards the bed making an angle of 60 -75 with
the bank. This type of spur is recommended for the rivers where velocity of flow is very high.
a. Groynes
The function of groynes is similar to that of spur. But these are impervious permanent structures
constructed on the curve of a river to protect the river bank from erosion. They extend from the bank
o o
towards the bed by making an angle of 60 to 75 with the bank. The angle may be towards the upstream
or downstream. Sometimes, it is made perpendicular to the river bank. These are constructed with rubble
masonry in trapezoidal section and the surface is finished with stone pitching or concrete blocks.
G The stone pitching or the concrete blocks are set with rich cement mortar. o
The length of the groyne depends on the width and nature of the river.
o The top width varies from 3 m to 4 m. The side slope may be 1½: 1 or 2:1.
o The groynes are provided in series throughout the affected length of the river bank.
o The spacing between the adjacent groynes is generally kept as 2L, where L is the length of the
groyne.
o These are recommended for the river where the permanent solution of erosion control is extremely
necessary.
9
The groynes may be designated as follows:
I Attracting Groyne: The groyne which is constructed obliquely to the bank by making an angle of
60 to 75o towards the downstream is known as attracting groyne, here the flow of water is
attracted towards the bank, and the velocity of flow is reduced to such a extent that it can not
cause any erosion to the bank. However, a bank protected of stone pitching is provided for safety.
o o
= Repelling Groyne: A groyne which is aligned towards upstream at an angle of 60 to 75 with
the river bank is known as repelling groyne. A still water pocket is formed on the upstream where
silting takes place. Here, the bank protection is not necessary, because the flow of water does not
touch the bank and there is no effect of erosion on the bank. But still boulder pitching should be
provided for safety.
= Deflecting Groyne: The groyne which is constructed perpendicular to the river bank is known as
deflecting groyne. Here the flow of water is deflected from bank by the perpendicular obstruction
i.e. groyne. The flow of water follows an undulating path just outside the head of the groyne. An
eddy current is formed on the upstream side of the groyne. This eddy current will not affect the
river bank. But the bank protection is provided for safety.
10
Modification of Groyne:
Denehy’s Groyne or T-Headed Groyne: After long investigation in different sites, Denehy
developed a groyne in the shape of a T. The length of the head is kept as ½, where L is the length
of groyne. A still water pocket is formed on the upstream side where silting takes place. It is
constructed with rubble masonry in trapezoidal section. The upstream face is finished with
concrete blocks with cement mortar.
Hockey Head Groyne: Another development is hockey head groyne. Here, the head of the
groyne is curved towards the downstream in the shape of a hockey stick. It behaves like an
attracting groyne. But it allows the water to flow smoothly over the head of the groyne. It is also
constructed with rubble masonry in trapezoidal section. Here, the bank protection by stone
pitching is necessary.
Pond Level
The water level required in the under-sluice pocket upstream of the Canal Head Regulator, so as to feed
the canal with its full supply, is known as Pond Level.
The FSL of the canal at the head depends upon the level of the irrigated areas and the slope of the
canal. Pond Level = Canal FSL + 1.0 to 1.2 m
11
Silt Regulation works
The entry of silt into a canal, which takes off from a head works, can be reduced by constructed certain
special works, called silt control works.
These works may be classified into the following two types:
Silt Excluders
Silt Ejectors
(a) Silt Excluders
Silt excluders are those works which are constructed on the bed of the river, upstream of the head
regulator. The clearer water enters the head regulator and silted water enters the silt excluder. In this type
of works, the silt is, therefore,, removed from the water before in enters the canal.
12
(b) Silt Ejectors
Silt ejectors, also called silt extractors, are those devices which extract the silt from the canal water after
the silted water has traveled a certain distance in the off-take canal. These works are, therefore, constructed
on the bed of the canal, and little distance downstream from the head regulator.
UNIT V
CANAL FALLS & REGULATIONS – DRAINAGE WORKS
Definition:
A cross drainage work is a structure carrying the discharge from a natural stream across
a canal intercepting the stream.
Canal comes across obstructions like rivers, natural drains and other canals.
The various types of structures that are built to carry the canal water across theabove
mentioned obstructions or vice versa are called cross drainage works.
types:
1. An Aqueduct
2. Siphon Aqueduct
Aqueduct
When the HFL of the drain is sufficiently below the bottom of
the canal such that the drainage waterflows freely under gravity,
the structure is known as Aqueduct.
In this, canal water is carried across the drainage in a trough supported on piers.
Bridge carrying water
Provided when sufficient level difference is available between the canal and natural
and canal bed is sufficiently higher than HFL.
Siphon Aqueduct:
In case of the siphon Aqueduct, the HFL of the drain is much higher above the canal bed, and
water runs under siphonic action through the Aqueduct barrels.
The drain bed is generally depressed and provided with pucci floors, on the upstream side, the
drainage bed may be joined to the pucca floor either by a vertical drop or by glacis of 3:1. The
downstrean rising slope should not be steeper than 5:1. When the canal is passed over the drain,
the canal remains open for inspection throughout and the damage caused by flood is rare.
However during heavy floods, the foundations are succeptible to scour or the waterway of drain
may get choked due to debris, tress etc.
Cross Drainage Works
Super passage
Canal siphon or called syphon only
Super passage:
Canal Syphon:
If two canals cross each other and one of the canals is siphoned under the other, then
the hydraulic structure at crossing is called “canal siphon”. For example, lower Jhelum
canal is siphoned under the Rasul-Qadirabad (Punjab, Pakistan) link canal and the
crossing structure is called “L.J.C siphon”
In case of siphon the FSL of the canal is much above
the bed level of the drainage trough, so that the canal
runs under the siphonic action.
The canal bed is lowered and a ramp is provided at the
exit so that the trouble of silting is minimized.
Reverse of an aqueduct siphon
In the above two types, the inspection road cannot be
provided along the canal and a separate bridge is required
for roadway.
For economy, the canal may be flumed but the drainage trough is never flumed.
The factors which affect the selection of suitable type of cross drainage works are:
Relative bed levels and water levels of canal and drainage
Size of the canal and drainage.
The following considerations are important
When the bed level of the canal is much above the HFL of the drainage, an
aqueduct is the obvious choice.
When the bed level of the drain is well above FSL of canal, super passage is provided.
The necessary headway between the canal bed level and the drainage HFL can be
increased by shifting the crossing to the downstream of drainage. If, however, it is not
possible to change the canal alignment, a siphon aqueduct may be provided.
When canal bed level is much lower, but the FSL of canal is higher than the bed
level of drainage, a canal siphon is preferred.
When the drainage and canal cross each other practically at same level, a level crossing
may be preferred. This type of work is avoided as far as possible.
1. The considerations which govern the choice between aqueduct and siphon aqueduct are:
2. Suitable canal alignment
3. Suitable soil available for bank connections
4. Nature of available foundations
5. Permissible head loss in canal
6. Availibility of funds
Compared to an aqueduct a super passage is inferior and should be avoided whenever possible.
Siphon aqueduct is preferred over siphon unless large drop in drainage bed is required.
Depending upon the nature of the sides of the aqueduct or siphon aqueduct it may be
classified under three headings:
Type I:
Sides of the aqueduct in earthen banks with complete earthen slopes. The length of culvert
should be sufficient to accommodate both, water section of canal, as well as earthen banks of
canal with aqueduct slope.
Sides of the aqueduct in earthen banks, with other slopes supported by masonry wall. In this
case, canal continues in its earthen section over the drainage but the outer slopes of the canal
banks are replaced by retaining wall, reducing the length of drainage culvert.
Type II:
Sides of the aqueduct made of concrete or masonry. Its earthen section of the canal is discontinued
and canal water is carried in masonry or concrete trough, canal is generally flumed in this section.