SRDC Construction Guidelines
SRDC Construction Guidelines
SRDC Construction Guidelines
1
Part 1 Basic Requirements to be submitted
A. PRE-
CONSTRUCTION 1. Submit colored storefront perspective on 15”x20” illustration
board, scale 1:50 to SKYRISE ADMINISTRATION OFFICE Cebu IT
Park, Apas Cebu City.
- Architectural Plan
- Electrical Plan
- Mechanical Plan (Aircon, Kitchens Hood/Exhaust/Ventilation, Fire
Alarm, Fire Protection) - Details of Signage
- Plumbing/ Sanitary (if any)
2. Once plans are approved, LESSEE must obtain the following and
submit to SKYRISE ADMINISTRATION OFFICE:
B.DURING
CONSTRUCTION 1. Permit to Construct. A copy to be posted on the conspicuous place.
2
C. POST
CONSTRUCTION /
PRE-OPERATION *1.Mayors’s Permit
*3.Certificate of Occupancy
*5. Fire and lighting insurance with other perils coverage. Comprehensive
general Liability Insurance (CGLI) Coverage for bodily injury and property
damage to third parties with a minimum coverage of Php 500,000.00.
Submit copy of policy and official receipt.
3
Part 2
Drawing Submission and Approval
A.DESIGN
DRAWINGS 1.LESSEE shall submit to SKYRISE ADMINISTRATION three (3) sets
of the Design and working Drawings for review and approval.
B.WORKING LESSEES is required to visit site and take actual measurement PRIOR to
DRAWINGS preparation of plans.
LESSEE’s Working Drawing shall include, but are not limited to the
following:
4
j. Branch chilled Water piping to Remain
k. New chilled water piping to be installed
l. Size of all piping shown on Drawing.
m. location of all piping accessories (i.e.; isolation
valves, control valves, pressure, Y-strainer and
temperature gauges, etc.) n. Proposed tapping point to main:
n.1 condensate piping showing size and slope of all piping from
fan coil units to drain
n.2 Equipment (with unique mark for each item of equipment)
o. Fan coil units (existing to remain and new)
p. Detailed drawing of hanger and supports.
4. PLUMBING PLAN 4.1 Design (that include length of pipe) and Specifications
4.2 Isometric Drawings (cold water and Sanitary lines)
4.3 Cold water and Sanitary line layout
4.4 Location of water meter, valves grease trap, etc.
4.5 Size of piping shown
4.6 Location of main stub-out
4.7 Slope of sanitary line up to the tapping point
4.8 Location of floor cleanouts
4.9 Detailed drawings and specification of grease trap
4.10 Location of floor drain
4.11 Detailed drawings of hangers and support
4.12 Legend
4.13 Centralized gas lines,
5. STRUCTURAL PLAN 5.1 Design and Structural load computation (duly certified by a
STRUCTURAL/CIVIL ENGINEER) Subjected to review and approval by
SKYRISE ADMINISTRATION.
5
6.1.7 Location of grease reservoirs
6.1.8 Slope of bottom of duct for all sections
6.1.9 Point of connection for new duct to existing duct
7. SPRINKLER PLAN 7.1 Design (indicate distance between sprinkler heads, and between
sprinkler head and lease line) & specifications
7.2 Isometric drawing
7.3 Location and size of cross main line
7.4 Location and size of branch line
7.5 Existing location of sprinkler heads
7.6 Proposed new location of Sprinkler heads
7.7 Location of additional sprinkler head
7.8 Detailed drawing of hangers and Supports
7.9 Detailed drawing of sprinkler heads termination to pipe (upright and
pendent) 7.10 Legend
4. Storefront-none
6
5.2 Non-Constructing tenants-LESSOR will provide enclosure
which shall be charge to LESSEE. LESSEE to get enclosure at the
end of construction.
Part 3
Construction
GENERAL LESSEE shall improve the lease premises following the latest trends in PROVISIONS
Architectural Design, using the most modern facilities that will give the feeling of elegance and
spaciousness. This will serve to integrate various sections into a unified whole, each space maintaining
its own character and identity.
A.APPROVALS 1. LESSEE shall prepare three (3) sets of COMPLETE Construction plans for
approvals of SRDC Administration.
B.PERMITS AND LESSEE shall secure all government permit and licenses are required
LICENSES BEFORE and AFTER construction.
C.CODES All works shall be in accordance with the latest government regulations, National Building
Code, Fire Code, Electrical code and Mechanical Codes.
D. PUBLIC SAFETY 1. LESSEE shall confine construction work within the lease premises and shall
work in an orderly manner removing trash and debris from the project site
on a DAILY BASIS.
8
HOURS a. Regular construction hours-8:00 a.m to 5:00 p.m (Depending on
operational hours of existing tenants).
b. To expedite construction, extension can be requested by LESSEE in
writing to SKYRISE ADMINISTRATION accordingly. Secure work
permit with overtime Request Form, Two (2) days before implementation
of works.
Important: WORKERS MUST CONFINE THEMSELVES WITHIN THE
LEAST PREMISES.
I.UTILITIES AND Electricity and water consumption during construction must be charged to
FACULTIES LESSEE.
K. FINAL
INSPECTION OF
PREMISSES LESSEE shall request in writing to SKYRISE ADMINISTRATION
for technical inspection at the least area three (3) days prior to any
store opening.
Part 4
Architectural Standards
9
GUIDELINES and other approving bodies.
6. All approved plans shall present at the work site at all times.
B.ARCHITECTURAL 1. FLOOR
DESIGN CRITERIA 1.1 LESSEE may use vinyl, vitrified tiles, wood parquet, laminated
flooring, carpet or marble tile flooring materials indicated, specified or
necessary for a complete and finish installation.
1.2 If LESSEE elects to set back the door of LESSEE’s storefront or office
front from the lease line, LESSEE shall install flooring material identical in
quality, color and pattern to the building flooring within the area extending
from the lease line to such new store or office front line.
1.4 Existing slab is bare finish concrete flooring and concrete elevated
flooring is strictly not allowed.
1.5 LESSEE shall submit floor framing plan and load computation for
wooden elevated flooring subject to LESSOR’s approval. Maximum of
two steps up to 300mm or 30cm.
2.1 Tenants are given the freehand to design the entire with of their
designated office.
10
2.2 The flexibility of these guidelines will enable the tenant to come up
with office reflecting creativity and individuality.
2.3 Signage can be any of the material, dimension and location within the
office.
2.4 The tenant has the option to determine their office entrance width.
2.6 The LESSOR reserves the right to approved/disapprove the design and
construction of all office and stores.
3. ENTRANCES
4. CEILING
4.1 Ceiling height should have the minimum of 3.0 meters for shops and
2.70 meters for offices. (Refer to design criteria)
4.5 LESSEE shall provide access panels for service to LESSOR/ LESSEE’s
equipment and facilities, more particularly to those located above the
ceiling.
4.6 Ceiling partitions between common areas and leased areas. Tenants are
encouraged to install wire mesh for additional protection.
4.7 Provide hangers using 10mm round bars at 2 meters spacing on center.
5. SIGNAGE CRITERIA
11
5.1 Primary signage
a. Tenant has the option to design their primary signage box.
b. Signage box must be illuminated.
c. Tenants may choose from the following options
c.1 OPTION 1
Consider backlit acrylic light box to all side with computer cut vinyl
patterning and 3D lettering adhered to face and side of the box.
c.2 OPTION 2
Consider backlit acrylic light box to all sides with self adhesive
photographic image. Text /logo to be incorporated to side and front
elevations.
c.3 OPTION 3
Consider brush stainless steel with illuminated logo/lettering.
12
C.ELECTRICAL 1. FACILITIES CONNECTION
1.1 The electric meter shall be provided with the LESSOR but will be charge
on LESSEE’s account. Tapping of lessee’s feeder line to building provision
misy have a step down transformer to have an output of 220 volts. All these
works will on LESSEE’s account, tenant must have electrical room for their
equipment and panel board location. The electrical panel board, and
electrical system works shall be at LESSEE’s expense and must be clearly
indicated on submitted plans. The modification/upgrading of electrical
feeder line shall be at LESSEE’s expense and must be clearly indicated on
submitted plans for LESSOR’s evaluation and approval in advance.
1.2 The communication line provision (1-voice and 1-data) shall provide by
LESSOR from IDF/TTC up to the termination box on LESSEE’s area.
Requirements for additional provision line must be with a written request
from the LESSEE and shall be charged to LESSEE’s account.
1.3 Before constructing – secure the tapping permit from the LESSOR for
the temporary electrical power supply. LESSEE to provide electric meter,
50A to 100A at Circuit breaker in NEMA – I enclosure for protection and
writing from the tapping point of LESSEE’s area.
2. DESIGN CRITERIA
2.1 Connected and actual load should not exceed 80% of over current
advice and impact of the cable.
2.3 Use bolt-on type electrical panel board. Circuit breaker should also
be size based on kaic system calculation. Number of over current device
and construction of electrical panel board shall conform to code standards
(capacity of bus bar should be size and cut base on standard, crimp bus bar
is not allowed.)
2.5 Open wiring, open pull box and junction-box RX wires and PVC
conduit are not allowed.
2.6 Provide independent rigid support and hangers, for round bar, use
minimum 10mm diameter with maximum of 3 meters spacing and must be
painted with rust converter.
13
2.7 Compute load schedule base on office tenant’s guidelines (basic
electrical feeder line provision) for normal and emergency power system.
If computed load is more than the specified guidelines, justification must
be clearly indicated on submitted plans for LESSOR’s evaluation in
advance.
OFFICE TENANT:
AREA
NORMAL/EMERGENCY
a.350 Sq & below 70AT,3PH,380V
b.Over 350 Sq.m to 760 Sq.m 125AT,3PH, 380V
c.Over760 Sq.m to 1200 Sq.m 800AT, 3PH, 380V
SHOPS TENANTS:
AREA
NORMAL/EMERGENCY
a. 40Sq.m & below (100AT, 3PH, 240V)
a. Balancing of load
b. Current reading during learn and peak load (main and branches)
c. Insulation Resistance Testing (main and branches)
d. Voltage reading (main and branches)
e. Tagging of loads using manual electronic dymo machine.
2. DESIGN CRITERIA
14
2.2 All modifications to existing branch duct and/ or diffusers and taps
to existing main ducts shall be at the lessee’s expenses.
2.4 All air-conditioning branch duct work shall be design and constructed
and to conform fully to local codes and requirement to the most current
SRDC guidelines “HVAC DUCT CONSTRUCTION STANDARDS-
METAL AND FLEXIBLE” for 11NWG Pressure Class or greater.
2.5 All branch ducts (and taps to existing main ducts) shall be
Properly sealed to prevent air leakage in excess of that required by
SRDC leakage class C with CL =24 CFM/100FT^2 at 1.0 INWG.
2.8 All Fan Coil Units (FCU) shall be installed with two ways control
valves properly size for Cv corresponding to the flow they serve and a
wide open pressure drop of 10FTWG.
2.11 Condensate drain pipes (with traps properly sized) shall be installed
for all fan coils. These drain pipe (and traps) shall conform to local
codes and accept engineering practice. Minimum drain pipe size shall be
25mm. All condensate drains shall terminate and nearby floor-drain
through an indirect connection with air gap.
2.12 The lessee will provide an exhaust air system for all comfort
rooms. Exhaust air quantities shall be in accordance with the local codes
but shall not be less than 50 CFM per water closet urinal.
15
3.TESTING AND COMMISIONING
1.1 Static and total air pressure in the Lessee’s Ductwork point connection to the AC supply air main
ducts
1.1 All steam, vapors, heat, odors and moisture producing areas and
high heat producing equipment and appliance must be exhaust systems.
(Type-I Exhaust Hood: designed to collect and remove all types of
cooking effluent from the exhausted air and type- II Exhaust Hood:
Designed to collect and remove only steam, Vapors, heat and odor).
16
side of the hood is also recommended for char broilers when
the equipment is located at the end of the cook line. (The
recommended overhang around the perimeter of an island
hood installed over solid fuel cooking equipment is 12”).
1.6 All fans used in grease duct systems and fresh air system
must be of a type that permits adjustment to capacity during
the final testing and balancing. Fans testing capacity records
(i.e; fan curve and other documents) should be available.
1.7 Fans should be constructed for purpose of exhaust system. It
should have a cleanout openings equipped with tight fitting
doors (with latches that will hold the door tightly closed).
1.8 Rigid ceiling manhole and catwalk along exhaust duct and
blower should be provided for effective maintenance.
1.9 All ductwork used on grease systems must be at least 16
gage carbon steel or 18 gage stainless steel with all joints and
seams made with continuous liquid-tight welded on the
external surface of the ductwork. Any portion of the ducting
that is inaccessible from the duct entry or discharge shall be
provided with cleanout openings. Cleanout openings shall be
equipped with tight fitting doors that are constructed of the
same material and thickness as the ducting. The doors shall
be equipped with the latches that will hold the door tightly
closed. Doors shall be design so that can be opened without
the use of tools.
1.10 The vertical distance between the lower lip of the hood and
the cooking equipment surface shall not exceed 4-feet.
1.11 Air velocity in sections of grease duct shall be maintained
between a minimum of 500 FPM and a maximum of 2,500
FPM.
1.12 All horizontal grease ductwork must be properly slopped to
the hood it serves or an approved grease reservoirs. Slope
shall be at least 2% for runs less than 75 feet between
reservoirs and 8.3% for runs greater than 75 feet between
reservoirs, per attached guidelines.
1.13 No dampers of any type may be installed in grease ducts.
1.14 All grease hoods and associated ducts system must, through
either clearance or fire rated insulation, conform to all local
codes AND the Kitchen exhaust system guide as follows:
Exception: Fans listed and labeled as power roof ventilators for restaurant
cooking appliances
Fan motor. Exhaust fan motors shall be located outside the exhaust
airstream.
17
-The maximum total developed length of the duct or duct fitting measured
along the center line shall not exceed three times the vertical dimension of
the fan outlet.
-The duct or duct fitting shall be provided with openings at the lowest
point to permits drainage of grease to approved collection device.
1.18 Joints and seams of grease ducts. Joints and seams of grease
duct shall be made with a continuous liquid-tight weld or
braze made on the external surface of the duct system. A
vibration isolation connector shall consist of noncombustible
packing in a metal sleeve joint of an approved design.
1.19 Grease duct supports. Grease duct bracing and support shall
be of noncombustible material securely attached to the
structure and designed to carry gravity and seismic loads
within the stress limitations of the building code. Bolts,
screws, rivets and other mechanical fasteners shall not
penetrate ducts walls.
1.20 Non grease ducts. Non grease ducts and plenums serving
Type II hoods shall be constructed of rigid metallic materials.
Duct bracing and supports shall comply. Ducts subjects to
positive pressure shall be adequately sealed.
1.23 Cleanouts and other openings. Grease duct system shall not
have openings therein other than those required for proper
18
operation and maintenance of the system. Any portion of
such system having sections in accessible from the duct entry
or discharge shall be provided with cleanout openings.
Cleanout openings shall be equipped with tight-fitting doors
constructed of steel having a thickness not less than that
required for the duct. Doors shall be equipped with the
substantial method of latching, sufficient to hold the door
tightly closed. Doors shall be design so that they are operable
without the use of a tool.
1.27 Air velocity. Grease ducts system serving a type one hood
shall be design and installed so as to provide an air velocity
within the duct system of not less than 1,500 feet per minute
(7.6m/s) and not greater than 2,500 feet per minute (13m/s).
19
M.1 All interconnected hoods are located within the same storey:
M.2 All interconnected hoods are located within the same room or in
adjoining rooms; and
M.3 Interconnecting ducts do not penetrate assemblies required to be
fire-resistance rated.
1.31 All grease hoods must conform to local fire codes with respect to the
fire suppression and extinguishing systems.
1.33 All hood filters shall be baffle type and shall be installed at an angle
not less than 45(>) from the horizontal and shall be equipped with a
drip side gutter and oil collector tray and avoid grease dripping into
the food. Filters shall be installed in frame or holders with handles so
as to be readily removable without the use of tools, except where the
system is designed for in-place cleaning. All grease collecting
equipment should be accessible for cleaning.
1.36 Pop rivets, metal screws, or other similar exposed fastener shall not
the internal surface of the hood.
20
1.37 Every hood shall be securely fastened in place by non combustible
supports. Exposed support hangers shall be an easily clean able
design and construction. Threaded rods and chains are not acceptable.
1.38 Lighting fixtures installed inside exhaust hoods shall be marked, “For
use within commercial cooking hoods”, or equivalent explosion proof
fixture.
2.1 Where required. Hoods shall installed at or above all commercial Food
heat-processing equipment. Included are deep fat fryers; broilers: fry
grills; steam-jacket kettles; hot-top ranges; ovens; barbeques; rotisseries;
dishwashing machines and similar equipment. For the purpose of this
section, a food-processing establishment shall include any building or
portion thereof used for the processing of food.
Exception: Food heat-processing equipment installed within a
dwelling unit.
2.2.1.b Other type hoods. Factory built commercial exhaust hoods that
are not tested in accordance with UL 710 shall conform to all of the
requirements.
2.2.4 Solid fuel. Type I hood for use over solid fuel-burning cooking
equipment shall discharge to an exhaust system is dependent to of
other exhaust systems.
21
2.4 Materials. Type I and II hoods shall be constructed of materials
conforming D.1 or D.2 or other approved materials.
2.6 Joints and seams. External joints and seams shall be welded liquid
tight.
2.7 Cleaning and grease gutters. A hood shall be designed to provide for
through cleaning of the entire hood. Grease gutters shall drain to an
approved receptacle that is fabricated, designed and installed to be
accessible for cleaning.
2.8 Clearance for Type 1 hood. Type I hood shall be installed with a
clearance to combustible of not less than 18 inches (457 mm), or not less
than 3 inches (76 mm) where the combustible material is protected with
noncombustible material having a minimum of 1-hour fire- resistance
rating on the hood side. Hoods located less than 12 inches (305 mm) from
ceiling or wall shall be flashed solidly with materials specified in D.1 and
D.2 or noncombustible materials having a minimum 1-hour fire resistance
rating.
2.10 Grease filters. Type I hoods shall be equipped with approved grease
filters designed for the specific purpose. Grease-collecting equipment shall
be accessible for cleaning. He lowest edge of a grease filter located above
the cooking surface shall be not less than the height specified.
Minimum Distance between the lowest Edge of a Grease Filter and the
cooking Surface or the Heating Surface.
22
For SI: 1foot=304.4 mm
2.13 Non canopy size and location. Non canopy –type hoods shall be
located a maximum of 3 feet (914 mm) above the cooking surface.
The edge of the hood shall be set back a maximum of 1 foot (305
mm) from the edge of the cooking surface.
23
2.15.2 High Temperature. The minimum airflow for type 1 hoods used
for high-temperature appliances such as deep- fat fryers shall be
determined as follows:
2.15.4 Low temperature. The minimum airflow for type 1 hoods used
for low temperature appliance such as a medium –to-
lowtemperature ranges, roaster ovens, pastry ovens and equipment
approved for use under a type II hood, such as pizza ovens. Shall
be determined as follows:
2.17 Exhaust outlet. Exhaust outlets located within the hood shall be
located so as to optimize the capture of particulate matter. Each
outlet shall serve not more than a 12-foot (3658 mm) section of
hood.
E.SPRINKLER
SYSTEM 1. FACILITIES CONNECTION
Basic sprinkler heads provision- 165 degrees F PENDENT TYPE to be
provided by the Lessor. Any modification / Adjustments works to be at
lessee’s expense and must be clearly indicated on submitted plans for
Lessor’s approval.
2. DESIGN CRITERIA
2.1 Use 212 degrees F sprinkler head for kitchen
2.2 Use upright sprinkler head for tenants with open ceiling
and pendent sprinkler head for tenant with ceiling.
2.3 Maximum distance between sprinkler heads should be
3meters. Radius covered by sprinkler head is 1.5-meter; design a
number of sprinkler heads to cover/ serve all the area.
2.4 Provide rigid hangers and supports.
2.5 Sprinkler pipe should be schedule 40 and painted red. G.I.
pipe is not allowed.
2.6 Provide rigid hanger 12” from the sprinkler head.
1.1 Lessee’s sanitary system, vent and domestic water piping should to all
local requirements and code standards.
1.2 Check stab-out provisions (potable water line, vent, kitchen waste and
domestic waste) on-site before preparation of drawing plans.
1.3 Use G.I Schedule 40 pipe or Zero leak Fusion type pipe for cold water
line. Indicate on the plan location of water meter.
1.4 Provide 3-ply water proofing on all kitchen, toilet, sink and lavatory
areas.
1.5 Provide 5-galloons minimum capacity of grease traps on all kitchen
sinks.
1.6 Provide floor clean-out for every change indirection and for every
3length of pipe for straight line connection.
25
1.7 Use cast iron pipe for sewer line using steam washing and PVC for
ordinary sewer line.
1.8 Provide rigid supports and hangers for installation.
1.9 Building floor cleanout should not be fully covered with tiles.
1.10 All floor- drain should be provided with bolted strainer.
1.11 Provide MCWD calibrate water meter.
1.12 Use color coding of utility:
Fire Protection-RED
Potable cold water line(painted all throughout )-BLUE
Vent pipe (2” strip at every 1-meter )-GREEN
Downspout/storm drain pipe (2”strip at every 1-meter)-ORANGE
H.KITCHEN 1. Provide CHB and fire bricks/ fire insulation (from floor to slab) of
all surrounding walls of cooking equipment.
2. Provide adequate and appropriate fire extinguisher for kitchen in
accordance with PD 1185.
I.CENTRALIZED
GAS SYSTEM I.FACILITIES CONNECTION (where Applicable)
2 DESIGN CRITERIA
2.1 All pipeline joint shall be full welded except for thread and flange
connections such as ball valves meters, regulators, etc.
2.2 PIPING WORKS-PIPES-B.I., Seamless, and schedule 80 from tank to
1st stage regulator to equipment. TANK FITTING (elbows,
tees.etc.)Schedule 80 from tank to 1st stage regulator, schedule 40 1st stage
regulator to equipment. FLANGES-Welded Neck ASME 300 lbs before
1st stage regulator, ASME 150 lbs after 1st stage regulator. GASKET-
Spiral Wound Gasket. FLANGE TYPE BALL VALVE-ASME 150 lbs.
After 1st stage regulator. THREADED TYPE VALVE -1000WOG Ratings
Stainless Steel Single
Piece body. STUD BOLTS-BOLTS-B7, tool steel.
2.3Gas line shall not embedded in walls and floors.
26
2.4 Provide rigid supports for every pipe bend and for every meter run of
pipe. Bracket shall be installed with a minimum distance of 3 meters or as
per required. All pipeline seated on support shall hold tightly using u-bolt.
2.5 Provide ball valve for every branch outlet.
2.6 Do not use rubber hose for connection to cooking equipment. Use
heavy duty hose or metal braided hose rate at 300 psi 2.7Provide
pressure gauge at main manifold.
2.8 Install Anti-leak Safety Device ay main manifold and branch.
2.9 Branch outlets shall be not lower than 60cm from the floor finish.
2.10 Gas hoses or flexible connectors shall not sag more than 10 cm.
2.11 Maximum length of flexible connector shall be 30 cm.
2.12 Painting of gas line- QDE paint-two (2) coats. Lemon Yellow on
Pipes, Black on Pipe Support, PRIMER-Two (2) coats.
3.1 Leak test pipeline before 1st regulator manifold at 150 psi for a
minimum period of 12 hrs. and 100psig at 1st stage regulator manifold
for a minimum period of 2hrs. using nitrogen. Submit certificate of
leak testing from LPG pipeline contractor/installer.
3.2 LESSEE shall submit to Skyrise Administration office a certification
on the safe operation of their gas system signed by both LESEE’s gas
contractors.
3.3 LESSEE shall not be allowed to open without their gas system
undergoing leak testing and a certificate submitted to Skyrise
Administration Office.
27