Defect 1557983477
Defect 1557983477
In the construction industry, the team defects or defective works as referred to in many standard form of construction contract, is usually collectively referred to as defects, imperfections,
shrinkages or any other faults in the construction works. Essentially, defective works is about the works failing or being deficient in standard and quality of workmanship, materials and/or design
as specified in the contract. Defects may also occur in failing to comply with the requirements of the drawings, bill of quantities, specifications, etc.
Defect can be classified into two broad categories, namely Patent Defect and Latent Defect, as described and explained below.
Patent Defect
In construction contracts, the Superintending Officer or relevant project consultants such as Architect or Engineer (depending on the form of contract used, but hereinafter referred as “SO”),
sometimes assisted by a Clerk of Works, do carry out or instruct for relevant inspection, observation, testing and/or examination to ensure that the construction works executed by the Contractor
are in compliance with the contract requirements prior to certifying practical completion. Typical examples are concrete honeycombing, hairline plaster cracks, uneven flooring, etc.
Latent Defect
Latent defect is defined as “a defects which is not discoverable during the course of ordinary and reasonable examination but which manifest itself after a period of time” (Powell-Smith).
Essentially, such defects are defective works that cannot be seen or discovered by normal inspection, observation, testing and/or examination.
Latent defects are usually neither obvious nor apparent during the defects liability period but become apparent or manifest themselves after the expiry of the defects liability period. Typical
examples are rainwater leakage through roof, damp wall, structural crack, tilted foundation, electrical wiring faults, etc.
In order to discover or to establish such defects, it may be necessary to subject the defective works to exhaustive and meticulous inspection, testing and/or detailed examination instead of normal
inspection, observation, testing and/or examination as defined under patent defect above. Usually, it is unlikely to be latent defect if it can be discovered by normal inspections and/or tests
specified in the contract.
However, in some cases, latent defects may become patent or undiscovered patent defects discovered or surfaced after handing over of the works to the Employer. Such defects, where the
Contractor is culpable, are breaches of contract which the latter is liable and must put right or otherwise be subject to diminution in value.
There are distinctions or differences between outstanding and not compliant works against defective works, both patent and latent in nature. Outstanding and non-compliant works are essentially
works that are part of the contract, which a contractor has undertaken to carry out and complete accordingly prior to certification of practical completion, but had failed to do so. If the Contractor
had carried out and complete the works accordingly, and should there be any defects in the works, then the Contractor shall be contractually obliged or responsible and liable to rectify or remedy
these defects during the defects liability period under the contract.
However, in practice, the distinction between outstanding and non-compliant works against defective works are often confused, blurred and/or mixed up by many SOs and project consultants, so
much so that such confusion and ambiguity have led to unnecessary delays in the certifying of practical completion. Often these outstanding and/ or non-compliant works are expressly stated or
included as defective works in schedule or list of defects to be rectified/ remedied by the Contractor concern.
The following tabulations are examples of outstanding/ non-compliant works against patent and latent defects commonly occurring during construction and after completion of a building:
Under most standard forms of construction contract, the Contractor is liable to make good, remedy or rectify any defective works which are non-compliant with the contract requirements. However, if
the defective works are not the results of the Contractor’s fault or breach of contract, then the Contractor is to be paid for the making good, remedial or rectification works. In the event, the Contractor
fails or is reluctant to undertake such works, the Employer can employ a third party contractor to do so and set-off any costs associated with such works from the Contractor’s payment account or
recover as a debt due, thereafter.
Defects, for which the Contractor is contractually responsible to put right, are described in various other terms such as imperfections, shrinkages, any other faults, etc. Defects, irrespective of whether
they are patent or latent, usually occur in the quality of materials, standard of workmanship and design (Harban Singh):
• Quality Of Material
The quality of material expected of the Contractor are either expressly stated or implied. The former being in the documents such as the specifications and the latter can be implied to be of
`merchantable’ and fit for their purpose.
• Standard of Workmanship
The standards of workmanship expected of the Contractor are as prescribed in the contract and/or implied to be of `workmanlike quality’ reasonably expected of an ordinarily skilled and experience
Contractor.
• Standard of Design
Where the Contractor undertakes some aspects of the design, the standard of design expected are as stipulated in the contract and/or implied that the works to be fit for their purpose.
Therefore if the Contractor breaches either the express or implied obligations, he is responsible and liable for the rectification and the defects that had occurred.
Notwithstanding, not all defects are the responsible of the Contractor. The following are the categories of defects for which the Contractor is neither responsible nor liable for under most construction
contracts (Harban Sigh):
• Waiver by Employer
When the Employer, at his absolute discretion, had waived his rights, whether express or implied, to seek redress for defective works either under the Contractor’s contractual liability or common law
liability, the Employer cannot then make the Contractor responsible and/or liable or the consequences of the said defective works.
The defendant, the roofing subcontractor, had entered into contract with the Plaintiff for the supply and install of roofing by using specified roof tiles. No defects were found when the roof
tiles ware supplied; the roof tiles were found defective only when the defect manifested itself later. The plaintiff, the main contractor, filed a lawsuit against the defendant for supplying and
installing defective roof tiles.
The House of Lord clarified that under the implied term of the Sale of Goods Act 1893 and the successor to this Act, the Supply of Goods Act 1973, the seller should warrant that their goods are
fit for purpose if the buyer had disclosed the purpose of goods ordered to the seller and the goods should be merchantable quality.
For this particular case, the House of Lord decided that the defendant was excluded the obligation of fit for purpose because the tiles was specified by the Plaintiff. However, the defendant
was held liable for roof tiles which not of merchantable quality.
b. Standard of Workmanship
The plaintiff entered into an agreement with the defendant for the construction of a house according to drawings and specifications prepared by the plaintiff’s architect. The plaintiff had
commenced proceedings against the defendant to recover the amounts due for works completed under the agreement. The defendant’s complaints were the plaintiff’s defective workmanship
and the use of sub-standard materials.
It was held that there was no provision in the agreement whereby the plaintiff must execute the works to the satisfaction of the defendant. The only instructions that the plaintiff may comply
with were those of the architect’s.
Teh Khen On & Anor v Yeoh & Wu Development Sdn Bhd & Ors [1995] 2 MLJ 663
The plaintiffs, the purchasers, entered into a sale and purchase agreement with the first defendant, the builder, to purchase a house which was found to be defective. The builder admitted his
liability and carried out repairs to remedy the problems, but was ineffective.
The purchasers then brought an action against the builder for, inter alia, rescission of the agreement, refund of the purchase price and damages. As a defence, the defendants argued that they
were not liable, as the damage had occurred after 12-month defect liability period under clause 23 of the agreement.
It was held that the builder was in breach of an express condition in the agreement which provided that the house must be constructed in a good and workmanlike manner. The builder was
also in breach of the three implied conditions of the agreement, i.e. that it would do its work in a good and workmanlike manner, that it would supply good and proper materials, and that the
house would be reasonably fit for human habitation. The expiry of the 12-month defect liability period provided in the contract, would not take away the right of the purchaser to sue for
defects which were not discoverable within that period.
From the aforesaid standard forms, since the Architect/Engineer/SO is not entitled to issue further written instructions to the Contractor to make good defects after the issuance of Schedule of
Defects or after fourteen days from Defects Liability Period expiry, is the Contractor still liable for rectification of latent defects after this period, even after Final Certification?