30 Sample Questions - RMP
30 Sample Questions - RMP
Sample Questions
2. Using the PMBOK® Guide definition of contingency reserve, which of the following
statements about contingency reserves is false?
A. A contingency reserve is a separately planned quantity of money or time that has been
set aside to allow for future situations which may be planned for only in part.
B. Contingency reserves are used to reduce the risks of overruns of project objectives to
a level acceptable to the organization.
C. Contingency reserves may be set aside for known risks.
D. Contingency reserves can be included in the project’s cost and schedule estimates
without any identifying documentation.
3. Which of the following is not a tool or technique used during the Quantitative Risk Analysis
process?
A. Earned value analysis
B. Interviewing
C. Decision Trees
D. Sensitivity Analysis
6. The inherent chances for both profit or loss associated with a particular endeavor is called:
A. Favorable risk
B. Opportunity risk
C. Pure risk
D. Business risk
8. Deflection or transfer of a risk to another party is part of which of the following risk
response categories?
A. Mitigation
B. Acceptance
C. Avoidance
D. Transference
12. A risk probability or impact scale that uses rank-ordered values such as very low, low,
moderate, high, and very high is called:
A. An ordinal scale
B. A cardinal scale
C. A nonlinear scale
D. All of the above
13. Organizations that desire very much to avoid high-impact risks may use which of the
following techniques during qualitative risk analysis? Choose the best answer.
A. Avoidance
B. Data precision ranking with low precision
C. A probability-impact risk rating matrix using nonlinear scales
D. The organization would not use any techniques
14. What is the Delphi technique as it relates to the risk identification process?
A. An information-gathering technique where experts perform a Strengths, Weaknesses,
Opportunities, Threats (SWOT) analysis.
B. An information-gathering technique where experts are briefed about the project and
then interviewed for their opinions.
C. An information-gathering technique where experts meet and generate ideas about
project risk.
D. An information-gathering technique where experts participate anonymously and ideas
about project risk are gathered via a circulated questionnaire.
15. Which of the following are considered tools and techniques for qualitative risk analysis?
A. Risk probability and impact, probability-impact risk rating matrix, and data precision
ranking
B. Interviewing, sensitivity analysis, decision tree analysis, and simulation
C. Avoidance, transference, mitigation, and acceptance
D. Checklists, sensitivity analysis, and simulation
16. A contingency plan has a 20% chance of failing. The corresponding risk event has a 30%
chance of occurring. What’s the probability for the risk to occur AND the contingency plan
to fail?
A. 50%
B. 25%
C. 6%
D. 10%
17. The independence of two events in which the occurrence of one is not related to the
occurrence of the other is called:
A. Event phenomenon
B. Independent probability
C. Statistical independence
D. Statistical probability
18. Which of the following documents is primarily used as an input into the Risk Identification
Process?
A. Risk Management Plan
B. WBS
C. Scope Statement
D. Contingency Plan
21. By using Project Risk Management techniques, project managers can develop strategies
that do all but which of the following:
A. Significantly reduce project risks
B. Eliminate project risks
C. Provide a basis for better decision making on overruns
D. Identify risk, their impact(s) and any appropriate responses
22. In the following network, all three tasks, A, B and C, each have a duration 5 days. The
value ‘p’ indicates the probability of each task finishing on schedule. If all 3 tasks start on
day 1, what is the probability that all 3 tasks will finish in 5 days?
A. p = .4
B. p = .003
C. p = .014
D. Probability cannot be determined from the data given
Task A
p=0.1
Task B p=0.2
1 2
Task C p=0.15
24. An analysis has identified four different options for reducing project costs. Given the
following decision tree, which option should be selected ?
P=0.7
Option A value $100
P=0.1 Option B value $1,000
P=0.4
P=0.2 Option C value $ 5,000
A. Option A
B. Option B
C. Option C
D. Option D
27. When developing a risk response plan, which risks should you focus on first? Choose the
best answer.
A. Near term risks with a high probability of occurrence
B. High impact risks with a low probability of occurrence
C. Risks with a high risk score
D. a and c
28. Warning signs that indicate a risk has occurred or is about to occur are called:
A. Risks
B. Triggers
C. Sign posts
D. Stop gaps
30. A project of $1.5 million has an adverse event that has a probability of 0.07 of occurring
and a potential loss of $15,000. This represents an expected negative monetary value of
how much?
A. $100,500
B. $105
C. $1,050
D. $15,000
Answer Sheet
1. a b c d 16. a b c d
2. a b c d 17. a b c d
3. a b c d 18. a b c d
4. a b c d 19. a b c d
5. a b c d 20. a b c d
6. a b c d 21. a b c d
7. a b c d 22. a b c d
8. a b c d 23. a b c d
9. a b c d 24. a b c d
10. a b c d 25. a b c d
11. a b c d 26. a b c d
12. a b c d 27. a b c d
13. a b c d 28. a b c d
14. a b c d 29. a b c d
15. a b c d 30. a b c d
Answers
®
1 C PMBOK Guide, pg. 127
2 D PMBOK® Guide, Glossary and pg. 143, pg. 73
3 A PMBOK® Guide, pg. 128 Earned value analysis is used as part of Risk
Monitoring and Control
4 B Project & Program Risk Management by R. Max Wideman, Editor
5 A A workaround is an unplanned response to a negative risk event. Option C is
the definition of a checklist.
6 D Project & Program Risk Management by R. Max Wideman, Editor. glossary
7 C PMBOK® Guide, pg. 142
8 D PMBOK® Guide, pg. 142
9 D PMBOK® Guide, pg. 131
10 B
11 B PMBOK® Guide, glossary
12 A PMBOK® Guide, pg. 135
13 C PMBOK® Guide, pgs. 134-136. A nonlinear scale can provide a greater risk
score for risks with high impacts and probabilities. This allows the organization
with high-impact risk aversion to better rank and focus on these risks. The use
of data with low precision as suggested in Option B may lead to qualitative risk
analysis of little use to the project manager. Option A is a type of risk response.
14 D PMBOK® Guide, pgs. 132-133
15 A PMBOK® Guide, pg. 128
16 C 0.2 x 0.3 = 0.06, Project & Program Risk Management by R. Max Wideman,
Editor, decision tree analysis
17 C
18 A PMBOK® Guide, pg. 128.
19 B PMBOK® Guide, pg. 143. Option A is transference; Option C is mitigation.
20 C PMBOK® Guide, pg. glossary
21 B Risks can never be completely eliminated on a project.
22 B 0.1 x .2 x .15 = .003
23 C PMBOK® Guide, glossary
24 D a. Option A Expected value of Opportunity = (.4)(.7)($100) = $ 28
c. Option B Expected value of Opportunity = (.4)(.1)($1000) = $ 40
b. Option C Expected value of Opportunity = (.4)(.2)($5000) = $ 400
d. Option D Expected value of Opportunity = (.6)($2000) = $1200
25 C PMBOK® Guide, pg. 142
26 D PMBOK® Guide, pg. 140
27 D
28 B PMBOK® Guide, pg. 133
29 B PMBOK® Guide, pg. 134, Wideman pg. VII-2
30 C $15,000 x .07 = $1,050
Total _________