Enterprise Programme Management Delivering Value
Enterprise Programme Management Delivering Value
Enterprise Programme Management Delivering Value
Management
Delivering Value
Any person who does any unauthorised act in relation to this publication may
be liable to criminal prosecution and civil claims for damages.
The authors have asserted their rights to be identified as the authors of this
work in accordance with the Copyright, Designs and Patents Act 1988.
A catalogue record for this book is available from the British Library.
A catalog record for this book is available from the Library of Congress.
10 9 8 7 6 5 4 3 2 1
13 12 11 10 09 08 07 06 05 04
Contents
1 Introduction 1
5 Project management 43
6 Programme architecture 47
9 Introduction 97
v
Contents
16 Introduction 243
Glossary 273
References and further reading 282
Index 283
vi
List of figures
vii
List of figures
viii
List of figures
ix
List of tables
x
List of tables
xi
Acknowledgements
T-Mobile UK
Compaq Computer Corporation
Primavera Systems Inc.
Benchmarking Partners
Transport for London
MyTravel plc
TUI UK
ABN-AMRO
xiii
Enterprise programme management
David Williams
Tim Parr
xiv
Foreword
One of the keys to the future of wealth creation in Britain and indeed the world
is the productivity of ‘UK plc’, that inter-related network of private and public
enterprise and endeavour that ultimately takes care of each of us in the coun-
try and many overseas. This is equally as true of private enterprise, which
generates the wealth, as it is of the public sector, which has a duty to utilise that
wealth as efficiently as possible. Productivity is probably today a more worry-
ing issue for the UK public sector than its private sector brother. At the CBI
we are, however, only concerned with giving British business a voice, so I will
confine my comments to the private sector of the UK economy.
Productivity improvement is the result of a number of factors ranging
from investments in capital equipment and technology to training, education
and enlightened employment practices for the workforce. However, simply
investing is not enough to realise the maximum productivity increase – the
process of bringing about change also needs to be as efficient and effective
as possible. It is this latter process, bringing about change in an organisation,
ranging from moving a factory, office, or warehouse site, implementing a
new computer system or way of working to a new organisational structure or
cultural change, that this book addresses.
The economic drivers pressing organisations into major change initiatives
in order to generate productivity improvements have never been greater.
Fierce competition, changing business models, new technology, deregula-
tion, cost pressures and globalisation are creating the need for organisations
to undertake more and more initiatives of unprecedented complexity and
with unprecedented speed. However, despite the increasing levels of invest-
ment being made by organisations in projects and programmes, a startling
number of initiatives either fail to deliver the expected value, never get imple-
mented, take substantially longer or cost substantially more than planned. So
many are currently in the too difficult box – so many are presented badly to
the point of self destruction.
The amount of wasted money, time and effort represents a huge opportu-
nity for organisations that are able to utilise effective programme
management techniques to maximise the likelihood of successful change. In
addition, there is an opportunity to be exploited by organisations that can
develop the agility to implement change more efficiently and effectively than
their competition.
xv
Enterprise programme management
Digby Jones
Director-General
CBI
xvi
1 Introduction
The economic drivers pressing organisations into major change initiatives have
never been greater. Fierce competition, changing business models, new tech-
nology, deregulation, cost pressures and globalisation are creating the need for
organisations to undertake more and more initiatives of unprecedented
complexity and with unprecedented speed. However, despite the increasing
levels of investment being made by organisations in projects and programmes,
a startling number of initiatives fail to deliver the expected value, never get
implemented, or cost substantially more and take substantially longer than
planned.
Although traditional programme and project management approaches and
techniques are being used by many organisations to manage and deliver
change, we believe that they are becoming less effective as the nature and chal-
lenges of change become greater. There are three trends that are driving the
need for new approaches to delivering change in organisations. First, changes
in organisations are becoming increasingly complex and interdependent.
Second, delivering real business benefits involves more cross-departmental or
functional coordination of change, usually changes to processes, systems and
structures, and quite often collaboration with third parties as either suppliers
or partners. Finally, existing organisational structures, processes and systems do
not support this type of working.
The proportion of an organisation’s resources that is committed to pro-
grammes and projects is increasing, and the succession of projects and
programmes is continuous. Senior executives now have to balance carefully
the management of existing ‘business as usual’ activities, and the resource
and focus on change activities. The impacts and conflicts of investments in
programmes and projects with the current business operations must be
understood and managed carefully.
Now more than ever, with pressure from shareholders and stakeholders on
CEOs and public officials to deliver their strategies and policies, there is a
need to focus investment on strategic objectives. This demands a much closer
link between the strategy and policy development processes and the delivery
mechanisms in organisations.
Traditional programme and project management methods and tech-
niques, which are primarily borrowed and developed from their engineer-
ing and construction heritage, do not fully address these new dynamics of
1
Enterprise programme management
2
Introduction
• We also recognise that managing people through change is often the key
determinate of whether benefits are delivered and the approach integrates
people change activities at all levels.
The book is structured around three main sections. In Part I, ‘The enterprise
programme management framework’, we discuss further the new challenges
in delivering organisational changes and value, and introduce the integrated
approach of enterprise programme management. Chapters 3 to 7 describe
each of the key elements of the integrated and organisation-wide approach.
While we recognise that current methods and techniques are important
within the framework, we do not go into detail about such approaches, as
there is an extensive body of knowledge available in many of these areas.
The practical application of enterprise programme management is illus-
trated by reference to T-Mobile UK, which is reviewed in Chapter 8. This
also acts as a summary of the ideas and approach outlined in subsequent
chapters, set in a real-life case.
In Part II, ‘Enterprise programme management essentials’, we have
selected a number of topics for further discussion. The subjects we have
chosen for inclusion in this section are either key capabilities that are funda-
mental to developing an enterprise programme management approach, such
as risk management, benefits management, resourcing strategies, and sup-
plier management and communications, or areas of new interest and
increasing importance in supporting an enterprise programme management
approach, such as programme management systems and the enterprise pro-
gramme management office. These chapters are supported by case studies
illustrating practical applications of the ideas introduced. The cases include
Compaq Computer Corporation, MyTravel plc, ABN-AMRO, Transport for
London and TUI UK.
In Part III, ‘Getting started’, we have focused on practical ways of
assessing your current organisational capabilities and situation. This will
hopefully enable you to start developing your own organisation’s plans for
developing enterprise programme management. We have also included a
chapter outlining a number of practical tips for programme managers in this
section.
3
Part I
The enterprise
programme management
framework
2 Why an enterprise approach is
required
7
The EPM framework
8
Why an enterprise approach is required
Many
Increasing
Outsourcing, amounts of
CRM organisations’
Number of people/amount of resource
committed to projects/programmes
9
The EPM framework
Change
capabilities
Core business
capabilities
Figure 2.3 The balance between core business capabilities and change capabilities
As the pace and scale of change increases, many organisations find themselves
devoting increasing effort towards change initiatives. Executives must learn
to balance operational and project needs in order to deliver strategic objec-
tives. Underpinning this is the need to build and deploy both core business
and change capabilities.
For the purposes of this book, we focus on helping businesses create agility
through understanding, building and deploying change capabilities.
10
Why an enterprise approach is required
• programme architecture
• change architecture.
11
The EPM framework
Strategic
initiatives
Strategic
management
Benefits
realisation Strategic portfolio
management
Ch ramm
Pro
an
ge
g
ar
ch
ite
ea
Outcomes Programme delivery management
ct
rch
ur
e
ite
ctu
re
Outputs Project management
organisation, and the strategic relevance and rationale for them. Strategic
portfolio management is a senior executive driven process, and is the
mechanism by which executives direct and control the organisation’s
investments to deliver future value.
It is critical at this level that decision-making is made with an under-
standing of strategic priorities, current initiatives, the impact on ‘business as
usual’ activities, and the organisational risks of change programmes.
Strategic portfolio management is a continual process of creating, man-
aging and evaluating a portfolio of strategic initiatives (investments) focused
on delivering an organisation’s strategic objectives. The approach is a cycle
of four phases:
12
Why an enterprise approach is required
13
The EPM framework
Project management
Project management is concerned with the definition and delivery of a spe-
cific project. When deployed within a wider programme management
approach, the project is framed within the context of the broader programme
objectives and management mechanisms. The project management discipline
is defined comprehensively in the standard text from the Project
Management Institute (PMI), the Project Management Body of Knowledge
(PMBOK Guide). Key processes include:
Programme architecture
As noted earlier, the above three processes are supported by programme
architecture. Programme architecture is the establishment of leadership
structures, team dynamics, behaviours and support mechanisms that enable
the delivery of programmes and projects. It also establishes the support
structures and mechanisms to allow effective programme leadership and pro-
vide the programme team with the environment, skills, tools and support it
needs in order to work effectively.
14
Why an enterprise approach is required
Change architecture
As with programme architecture, change architecture is a discipline focused
on the people aspects of the programme. However unlike programme archi-
tecture, change architecture is concerned with the human considerations of
those in the organisation who will be impacted by programmes and projects
beyond the delivery teams. For example, does the ‘customer’ organisation have
a clear and shared vision of the solution? What structures do we need to
establish within the organisation in order to embed the solution? Does the
proposed change fit with the current culture of the business?
Therefore, change architecture can be defined as the approach to the plan-
ning and coordination of the human elements of change within the wider
organisation. It is the process of understanding the overall strategic objec-
tives, context and capability to change, developing the approach that will
drive the required changes within the organisation, and then planning and
delivering the required people and change (P&C) activities to ensure that the
initiative is embedded within the business.
As a result, it is not just key at the start of a programme or project. It is an
ongoing process to review and evolve activities and infrastructures to ensure
the change is successfully realised and sustainable beyond the initiative’s
lifecycle.
There are three key phases in the change architecture discipline:
15
The EPM framework
These phases are repeated continuously as new programmes and projects are
considered and initiated, executed and deliver changes.
16
Why an enterprise approach is required
17
3 Strategic portfolio management
INTRODUCTION
‘How does each of your programmes and projects support your strategic
objectives?’ Not many executives can answer that question. Large organi-
sations may recognise the importance of the top and tail of the enterprise
programme management framework – defining the business strategy, and
running projects, respectively – and have no qualms investing substantial
time, money and effort in these activities. However, a common failing is to
ignore the value of creating strong alignment between the two. Enabling
strong links between the strategy and the web of projects will allow opti-
mal value to be realised from the projects, and create a business focus on
the delivery of the strategy. Most organisations have some fragments of the
interface already in place, but more often than not the links are weakest
where strategy meets the management of projects as a whole. Strategic
portfolio management is the first step in creating the alignment of strategy
to programmes and projects.
Gone are the days where organisations operated simple business models
and undertook few and manageable projects. Recent years have seen the
number and magnitude of strategic initiatives grow to such an extent that
even keeping track becomes almost impossible. The nature of these initiatives
has also evolved, from those that are function-specific to those that transcend
functional lines, which can lead to increased risks of conflicts and failures as
a result of the cross-function complexities.
Typical symptoms of an organisation that lacks this capability are:
18
Strategic portfolio management
1. Strategy translation.
2. Portfolio planning.
3. Portfolio management.
4. Strategy and portfolio re-evaluation.
19
The EPM framework
Strategy
Strategy
translation
Recommen- Portfolio
dations principles
io
lua rtfol
Strategic
Por
o
n
re- and p
Ch
pla
tio
portfolio
tfo
Pro
an
nn
lio
management
ge
ing
gy
eva
gra
ate
ar
mm
Str
ch
ite
ea
Results and Portfolio Portfolio of
ct
rch
ur
benefits strategic
e
management
ite
realisation initiatives
ctu
Programme delivery
re
management
Project management
• provide the essential link between the realisation of the business strategy
and key strategic initiatives to ensure congruency
• perform a prioritisation of strategic initiatives that best achieve the
targeted changes within budgetary and time constraints
• create a strong link between strategic development, investment decision-
making, business planning and delivery activities
• provide a cross-organisational approach to managing the risks, capabili-
ties and resourcing issues arising from the interdependencies of the
initiatives
• give senior management the ability to direct and manage a portfolio of
programmes, implementing the corporate objectives and strategy within
a dynamic environment
• focus on strategic initiatives rather than project inputs, and use perfor-
mance measures and reporting based on benefits realisation, rather than
direct programme deliverables/metrics
• prevent poor return on investment on programmes and projects that do
not support the overall strategy of the organisation.
20
Strategic portfolio management
Strategy translation
Before the portfolio of projects is put together, the business strategy needs to
be understood and then translated into guidelines for the portfolio composi-
tion. These guidelines will, among other things, outline the desired portfolio
mix of programmes and projects, agree the level of portfolio risk the business
is prepared to undertake, set business targets, budgets, and agree business key
performance indicators (KPIs) for monitoring and reviewing purposes.
Portfolio planning
Following the set-up of the guidelines, suitable programmes and projects are
identified to populate the portfolio. There are usually too many programmes
and projects suggested for a business to implement, especially within the
constraints of budgets, time and resources. Hence these initiatives must go
Strategy translation
tion
and portfolio re-evalua
Portfolio planning
Strategic
portfolio
management
tegy
Stra
Portfo t
lio Managemen
21
The EPM framework
through a filter process to assess the financial and strategic justifications for
undertaking the initiative, on both an individual and a comparative basis,
with those that pass through the process to make up the portfolio plan. Key
considerations of the filter mechanism are:
Portfolio management
Once the right programmes and projects are in place in the portfolio, the
next step is to manage and track their progress and performance. The port-
folio plan is executed and refined, required capabilities are developed, risks
and issues tracked and managed, dependencies coordinated, and progress
and outputs monitored. The prime focus of these activities is to ensure that
organisational risks are managed, and that results and benefits are being
realised as and when expected. The portfolio status is reported on a regular
basis to senior executives, and reviewed in the next phase.
22
Strategic portfolio management
Does the proposed initiative meet its agreed business case criteria?
Are there strategic objectives that have a greater weighting than others
when determining an initiative’s strategic fit?
23
The EPM framework
Portfolio planning
The portfolio planning phase is where the portfolio roadmap is developed,
whereby programmes and projects that best support the strategic intent of
the organisation are identified, scoped and scheduled into a plan. This phase
can be divided into three stages, creation, selection and sequencing, and is
illustrated in Figure 3.3.
Driven by
strategy/ Project desirability
vital actions
How much value will the initiative
In response bring to the organisation?
In the context
to an issue
of all other
projects, Portfolio
An when is the plan
identified best time to
Project feasibility/viability
opportunity deliver this
project?
Driven by Is the organisation capable of
external successfully delivering this initiative?
causes/
demand
Creation stage
The first step to creating the portfolio plan is to identify the potential
programmes and projects for it. Generating such ideas to improve the
business and its operations will never be exhaustive, and they can surface
from a multitude of sources. These ideas (that will become initiatives) can be
categorised into four types:
Identifying initiatives may be seen as an ad hoc exercise, but there are useful
tools that can assist in generating relevant and valuable initiatives, particularly
at the strategic level. These include:
24
Strategic portfolio management
Selection stage
Those ideas that are of most value to the organisation are translated into
initiatives, and implemented through programmes and projects. The purpose
of the selection stage is to weigh out the risk and rewards of carrying out
each initiative identified in the earlier stage, based on whether it is ideal and
pragmatic to do so.
This splits into two questions to address: ‘Is the initiative desirable?’ and
‘Is the initiative feasible?’ The initiative must meet both requirements before
it moves on to the next phase, in which it is placed into the portfolio. Failure
to meet either one will make the project a lost cause for investment. We dis-
cuss these two requirements, and the activities, tools and techniques that
support their assessment, in greater detail below.
Desirability
How much value would an initiative deliver to the organisation? By ascer-
taining the expected rewards and the certainty of the outcomes of each
initiative, the value of the proposed initiative can be understood. The objec-
tive of this first part is to assess the ‘attractiveness’ of the project to the
business in terms of its strategic fit and proposed benefits, factoring in the
likelihood of reaping those benefits. A combination of tools can be used:
25
The EPM framework
Feasibility
An initiative may be recognised as being highly desirable, but may not be
worthwhile to undertake if it is not feasible to implement. This second part
of the selection stage considers the ability of the business to undertake the
proposed initiative, by identifying the likely complexity, challenges and
constraints (the three Cs) the business will face in implementing the
project. The objective of this is to assess the implementation risk of the
initiative.
Identifying the three Cs includes assessing the following:
• Capability assessment. This evaluates whether the business has the nec-
essary level of physical and human resources required for the project, as
well as the capabilities and competencies that exist. Areas to consider
include the physical infrastructure, finance, people, resource expertise
and leadership capability. In the process, any additional capabilities that
need to be developed internally or procured externally should also be
identified.
26
Strategic portfolio management
• Change readiness assessment. This activity assesses the business and its
willingness to change, and identifies the challenges and risks. This includes
examining this organisation’s history of change, and the readiness of the
business to move to the desired changed state. This information can be
used to plan change strategies to mitigate the risks if the project is imple-
mented. More detail can be found later in the change architecture chapter.
Sequencing stage
A portfolio incorporating these initiatives is created once the initiatives have
been approved. Existing projects also have to be compared with the new
ones, to assess their priority relative to one another.
The goal of the prioritisation exercise is to create the optimal mix of pro-
grammes and projects, within a designated timeline, that will provide the
greatest contribution to the business goals while minimising any conflicting
demands on resources and maximising the use of the latter. The criteria
applied in this stage are based on the portfolio mix principles defined earlier
in the strategy translation phase.
As decisions are made on a comparative basis, the projects are initially
compared and ranked to produce a prioritised list. Using this prioritised list
together with the principles around the desired portfolio mix, we can then
formulate the portfolio and put together the schedule. Note that this priori-
tisation exercise is not an exact science, and there may well be a few possible
portfolios drawn up to be deliberated on by the board, which will choose one
of them.
Aside from the portfolio mix principles, we can apply some of the
following tools to assist in the portfolio scheduling:
27
The EPM framework
Portfolio management
Once the portfolio has been developed, (EPMO) enterprise-wide mechanisms
to monitor and control it need to be in place, to ensure the ongoing perfor-
mance and progress of the projects and the portfolio. The activities in this
phase are usually carried out by a portfolio management or enterprise
programme management office, the equivalent of a programme management
office, but at a portfolio level. This has the responsibility of maintaining the
plan, and tracking and reporting the portfolio’s progress and performance
against targets, and risks against portfolio tolerance levels. Most of the activi-
ties here are similar to those performed at the programme or project manage-
ment level (see programme delivery and project management chapters), but on
a portfolio scale instead. Key tools that are worth mentioning here are:
28
Strategic portfolio management
These reviews ought to take place on a regular basis to ensure that significant
deviations in the portfolio plan can be corrected in a timely manner, and that
the projects embarked on are in line with any changing market conditions or
events. The outputs of the reviews feed back into the strategy translation and
portfolio management phases, and are used to refine the strategy, portfolio
principles and portfolio plan where necessary.
Sample reporting mechanisms typically used for the reviews are outlined
below:
SUMMARY
A strategic portfolio management system can be designed using the
approach, activities and tools described in the chapter. However, the robust-
ness of a strategic portfolio management system also depends on other
factors:
29
The EPM framework
30
4 Programme delivery
management
INTRODUCTION
If strategic portfolio management is largely about ‘what’ organisations
should do to deliver strategy and policy through investments, then pro-
gramme delivery management is about ‘how’ to deliver. The focus of
programme delivery management is therefore on delivering maximum
business benefits from the investments made through multiple projects.
So what are programmes?
The process of translating
strategic objectives into Strategic
initiatives
initiatives will often identify Strategic
large-scale investments. The management
an
ar
mm
ch
Outcomes
ct
rch
ur
31
The EPM framework
32
Programme delivery management
The bottom line is that programmes are the mechanisms often used to
manage the execution of some of the largest investments that organisations
will ever make. Creating the programme management capability to maximise
effectively the value created from these investments should be a top priority
in our organisations today.
33
The EPM framework
• planning
• executing
• controlling.
Throughout the three process groups, tools and techniques from nine con-
trol areas are deployed as shown by the programme delivery framework
diagram (Figure 4.2). The three process groups can be described as follows.
Planning
This involves the creation of a series of documents that facilitate shared
understanding among programme stakeholders, and guide the execution and
g P
Change
in
lan
ll
tro
control
nin
Con
Risks and
Contingency
issues
mgt
Vendor Performance Financial
mgt mgt mgt
Knowledge Quality
mgt mgt
Release
mgt
Executing
34
Programme delivery management
• Top-down planning. This process takes the goals, objectives and expec-
tations that were defined in strategic portfolio management and
develops a logical plan of how those goals, objectives and expectations
will be delivered through a portfolio of interrelated projects.
• Bottom-up planning. This takes the output from the planning work
done at the individual project level, and rolls up the project plans into a
programme master plan. This allows for a focused and detailed analysis
of interdependencies and risks to take place.
• Infrastructure and policy planning. This establishes a plan describing
how the programme will be managed and executed, and detail protocols
and policies from the nine control areas illustrated in Figure 4.2. (Stan-
dards set out by an organisation’s enterprise programme management
office are tailored and agreed for this programme.)
Executing
This is supporting the execution of the programme plan. It involves initiating
new projects, closing out completed projects (or projects no longer relevant),
and tracking the success of the portfolio in achieving the programme’s goals
and objectives.
Controlling
This involves identifying, managing and reporting on programme risks,
issues, changes and costs, tracking deliverables and monitoring milestones.
Outputs of this phase include formal feedback to the strategic owners of the
programme in order for judgments to be made regarding the progress of the
strategic plan.
35
The EPM framework
Scope baseline Ensures that all items subject to change are identified,
organised, controlled, consistent, complete, correct,
visible, traceable and verifiable.
Change control Provides a formal process for requesting, reviewing
procedure and authorising changes. Ensures that up-to-date
records exist on what has been agreed thereby
allowing control to be maintained on the scope of
the programme. This will also mitigate risks as changes
will be assessed before being implemented, reducing
risk of unforeseen but dramatic impacts to other
project areas.
Change control Provides a formal process for publishing changes,
reporting and aiding team understanding of related changes.
36
Programme delivery management
37
The EPM framework
Approach, tools
and techniques Rationale/benefits
EVA (earned value Provides visibility of project status and early warning of
analysis) potential issues and risks.
Progress and expenditure Provides visibility of project status and performance to
reporting tools and allow appropriate interventions to be identified and
templates actioned. Also provides early warning of potential issues
and risks.
Milestone charts Provides visibility of project status.
Tracking Gantt charts Provides visibility of project status and performance
against baseline.
Resource histograms Snapshot view of amount of resources required versus
resources available.
Cumulative cost curves Provides visibility of project status.
38
Programme delivery management
39
The EPM framework
40
Programme delivery management
SUMMARY
This chapter has described the rationale for managing initiatives that require
multiple projects to deliver and build business capabilities as coordinated
programmes. The sequencing of these related projects, and the management
of their interdependencies and impact on the business to deliver benefits,
require a level of management coordination over and above individual
project management.
The basic management process of planning, executing and controlling
programmes was described and a number of tools and techniques that can
aid the process were outlined.
However programme delivery management is at the heart of the enterprise
programme management approach, and its success in an organisation
41
The EPM framework
42
5 Project management
INTRODUCTION
The entire framework described so far exists for one purpose, which is to enable
the right projects to deliver effectively within an organisation. Projects are the
individual efforts that deliver specific measurable results. Strategic portfolio
management and programme delivery management are concerned with ensur-
ing organisations invest in
the right initiatives to deliver
strategic value, and that the Strategic
initiatives
delivery is coordinated and Strategic
executed in a way that deliv- management
an
strategic aims, while manag- ge
gra
ar
mm
ch
ing the organisational risks ite
ea
ur
involved in business change.
e
ite
ctu
43
The EPM framework
• Programmes can be ongoing and do not end until they are judged com-
plete or no longer relevant.
• Programmes evolve as more information is obtained. Progressive defini-
tion of desired results and plan elaboration is a common feature.
• Programmes tend to be more complex and deliver multiple distinct
results, each of which has some value on its own, but which collectively
have a value that is greater than the sum of the individual parts.
44
Project management
sets out standards for component projects to follow. From a project’s per-
spective, if programme standards exist, they are taken and used; if they do
not exist, then the relevant structures are established for the project.
Figure 5.2 shows the five process groups (four phases) of project manage-
ment and the nine knowledge areas as defined in the PMBOK Guide.
Whereas programme delivery management follows three process groups,
planning, executing and controlling, project management follows two addi-
tional process groups, initiating and closing, reflecting the temporary,
defined start and end characteristics of the project.
SUMMARY
Project management has only been outlined briefly in this chapter. Standards
such as Project Management Body of Knowledge and PRINCE2 provide
very comprehensive approaches and methods of project management.
Project Management capability is a critical element of the enterprise pro-
gramme management framework, and developing a common approach,
standards and professional project managers within an organisation is key to
enhancing a delivery capability.
The application of project management methods should be done in the
context of the type of project and change programmes an organisation is
Pla
ing nn
at in
ti
Ini
Time
Human
Integration resources
Risk Procurement
ng
olli
Quality
nt r
co
Cl
sin
o
an
d
g
i ng
cut
Exe
Figure 5.2 The five process groups and nine knowledge areas of project
management
45
The EPM framework
46
6 Programme architecture
INTRODUCTION
Since 1995, the Standish Group have regularly published and updated a
report entitled Chaos, which studies the trends and factors that cause projects
and programmes to either succeed or fail. The top three critical success
factors that have repeatedly been identified are:
1. User/team involvement.
2. Executive support.
3. Clear statement of requirements.
The message is very clear. Getting team and leadership involvement right is
of critical importance, ranked here as being more important even than having
a clear statement of requirements! This reflects an obvious truth: no change,
no matter how well defined or planned, can be achieved without clear
accountability, commitment and support from both leadership and the
people who need to make it happen within the organisation. Programme
architecture is about implementing and using appropriate management and
leadership skills and mechanisms, so that programmes can be resourced and
managed effectively.
The design of the appropriate structures, roles, decision-making and
resourcing processes, team building approaches, human resource policies
and supporting infrastructure for programmes and projects in organisa-
tions is very contextual. The architecture must be integrated with the
approaches to strategic portfolio management, programme delivery
management and project management. The type of projects and
programmes undertaken will influence the appropriate architecture, as will
the need to integrate and dovetail with the ‘business as usual’ structures
and accountabilities.
This chapter therefore provides an overview of the key considerations
when designing programme architectures. It covers all the elements that
need to be considered relating to accountabilities, decision-making,
resourcing and managing people on projects and programmes. The specific
approach and mechanisms adopted should be customised to your own
organisation’s situation.
47
The EPM framework
• ‘People didn’t really understand how their project fitted into the bigger
picture.’
• ‘Nobody involved in the project really wanted to be working on it. As a
result they did not really commit to making it work.’
• ‘Nobody could make a decision. By the time a decision was made it was
too late.’
48
Programme architecture
Figure 6.1 illustrates how some of these symptoms interact to create vicious
cycles (failure paradigms), which lead to the establishment of ‘blaming’ cul-
tures, fear of accountability and ultimately a reduction in capability to deliver
change successfully.
There are also a number of environmental factors in organisations that, if
left unmanaged, will conspire to jeopardise the effectiveness of programme
leadership and programme teams. (See Table 6.1.) Programme architecture
proactively establishes effective responses to these risks.
Programme architecture can further be understood as the establishment of
five distinct programme support structures (see Figure 6.2):
Misalignment of
operational and
strategic aims
Difficult to Ineffective
exceed client programme
team Poor understanding
expectations of team dynamics/
cultures
49
The EPM framework
50
Programme architecture
Leadership and
governance
Team building
Communication Programme
and
infrastructure infrastructure
development
Programme
resourcing
51
The EPM framework
52
Programme architecture
53
The EPM framework
Communication infrastructure
Programme infrastructure
54
Programme architecture
Programme resourcing
55
The EPM framework
CEO/President
56
Programme architecture
to reflect the balance, and the need for leadership focus and support across
both programmes and operations.
CEO/President
Functional Functional
Manager Manager
Project/ Project/
Programme Programme
Manager Manager
Sales and
Editorial Production Distribution
marketing
Programme
Prog responsibility
Mgr A
Prog
Mgr B
Functional
responsibility
57
The EPM framework
• Works with the senior executive team in developing the design of the
programme portfolio based on the strategic plan.
• Prioritises programmes and projects in terms of strategic value, using
high-level financial and benefit assessments of alternatives.
• Initiates new programmes and projects.
58
Programme architecture
CEO/President
Functional Functional
Manager Manager
Project/ Project/
Programme Programme
Manager Manager
• Closes down or kills programmes and projects where the objectives have
either been met or are no longer considered relevant or important.
• Tracks the realisation of benefits from programmes, and the progress
against high-level plans.
• Creates ‘programme charter’ documentation that describes the
programme and priority, and details the nature of the authority that is
being given to the programme manager in order to take and deploy the
organisation’s resources.
• Ensures priorities are clearly understood by the organisation such that
resource is deployed in the most appropriate way.
59
The EPM framework
CEO/President
Functional Functional
Manager Manager Programme
Management
Office
Project/ Project/
Programme Programme
Manager Manager
CEO/President
60
Programme architecture
• Sets the PMO function as a critical process embedded into the organisa-
tion’s infrastructure, so that use of it cannot be bypassed. (Rules tend to
be more stringent for the directive model.)
• Develops and maintains processes and procedures for gathering and
reporting consolidated project data and schedules. Documents what
deliverables are being produced and when.
• Highlights key programme interdependencies.
• Aligns implementation plans across interdependent initiatives.
• Monitors all key decision points, the dates by which a decision is required,
and the impact of the decision, through maintenance of schedules.
• Performs regular project risk assessments by identifying future areas of
major risk and providing advice on potential corrective actions to mitigate
the risks.
• Manages the mechanism for early issue raising, issue communication and
issue resolution.
• Highlights the key critical issues that may impinge on the successful
delivery of the projects.
• Monitors changes in terms of their impact on scope, cost and delivery
time frames against the target schedule.
• Enhances problem solving by proposing alternative high-level solutions
and their associated implications.
• Assists in timely decision-making on the overall control of projects.
• Manages resource scheduling across the projects in a programme, and
sources new resources where required.
Steering group
This is a committee, usually composed of the programme or project sponsor
and other executives who have a legitimate stake and interest in the programme
or project. The role of the steering group is to monitor the progress of the
initiatives, act as a decision-making body for the resolution of issues, take a
strategic view of programme risk management and approve risk response strate-
gies. Typically, the steering group is responsible for authorising changes to the
programme or project budget and the use of contingency funds.
Criteria for successful steering groups include:
61
The EPM framework
SUMMARY
Independent research and our experience have shown that effective leader-
ship and team working are critical determinants of the success of
programmes and projects in delivering value in organisations. However these
areas are the least well developed in many organisations, and often little time
and effort is given to supporting programmes effectively.
We have identified five key areas that should be considered and
addressed in the design of the appropriate programme architecture to
support development of enterprise programme management capability.
The roles of senior executives in leading and supporting decision-making
need to be defined clearly and the appropriate governance bodies imple-
mented. These may be different from existing organisational structures, and
how they interrelate needs to be determined carefully. Senior executives may
need support in developing change leadership roles.
The development of high-performing programme and project teams needs
to be supported with the appropriate human resource policies addressing
recruitment, training, performance management, reward structures and
career development for those deployed onto projects and programmes.
62
Programme architecture
63
7 Change architecture: managing
the human side of change
Imagine you are in the midst of managing the biggest programme of your
career. However, some of the board members don’t support your plans –
they now have very different views on what the end game should be.
Employees are not making the changes you told them about. Is it because
they do not want to or are not able to? The current team structures do not
lend themselves to the new routines, so people are getting frustrated. You
worry that you are about to lose some of your best performers.
This scenario is more common than it needs to be. In today’s complex
business world, we tend to forget some basic logic:
• ensure that everyone in your business has a clear and shared vision of the
programme and its goals
• secure the commitment of top leadership and key stakeholders
• build organisational structures that will embed, rather than prevent, the
change
• communicate to the wider organisation so that they know what is going
on and when they need to take action
• maintain motivation in employees who might be weary of successive
changes
• develop a culture that will support the required change
• build a change capability that helps drive organisational agility in the
future.
The above is not a wish list – it is attainable, and for a successful programme it
is a must. The objective of this chapter is to guide you through a simple frame-
work to identify and manage the people challenges that will drive (or else
hinder) the success of your programme. We call this ‘change architecture’.
64
Change architecture
Each phase brings diverse human reactions, and requires the use of a variety
of change interventions, such as education, coaching, new team structures
and cultural change. We will return to the idea of acceptance throughout this
chapter, but be aware of the different phases as you build the change archi-
tecture for your own programme.
Figure 7.1 depicts the change acceptance process, as well as the risks of not
managing the change.
Second, there is no ‘one-size-fits-all’ approach to meeting the needs of
your programme. Change is situational. Both the magnitude of the change
and the organisation’s readiness for that change differ from company to com-
pany, from programme to programme. They probably differ in the following
two ways:
65
The EPM framework
Internalisation
Degree of support for the programme
Ownership phase
Adoption
Positive perception
Awareness phase
Understanding
Unawareness phase
66
Change architecture
management
ge me
67
The EPM framework
Time
Figure 7.3 The phases of change architecture
the indicators of change against the portfolio’s change strategy and plan, and
making adjustments where necessary.
In summary, however, we believe that there is a huge advantage in taking
the time to design the optimal change architecture, and then making
strategic adjustments as the programme progresses. This is where change
architecture differs from contemporary change management. The latter
often jumps to the what, why and how of the change plan, such as a detailed
organisation design or a new performance management system. In some
cases, these detailed areas can become independent work streams of their
own, with little strategic coordination. Change architecture avoids these pit-
falls by first designing the overall solution at a high level, then overseeing
design and implementation.
Why do we use the word ‘architecture’? Consider the role of the design
architects on a building development. They are responsible for interpreting
the client’s brief, developing a vision for what the building will look like,
then creating the blueprints that will bring that vision to life. Once the blue-
prints are agreed, the architects then commission builders, plumbers,
plasterers and electricians to bring the plan to life. The architects brief these
tradespeople, but they leave the details to the experts in each area. As the
building work proceeds, the architects closely monitor building progress,
making adjustments where necessary to ensure that the work continues to
reflect the overall vision.
68
Change architecture
69
The EPM framework
The interventions fall into two categories: support infrastructures and people
interventions. Support infrastructures are underlying support networks to
enable people through the change (such as communications, stakeholder
management, and training and development). Support infrastructures are
usually only in place for the programme duration.
On the other hand, people interventions are specific solutions that are
designed and implemented for longer-term use. Examples include perfor-
mance management systems, reward strategies and organisational designs.
They exist beyond the programme and become part of the business as usual,
future state.
70
Change architecture
Emphasis
change architecture that will the change journey
Taking the time to find answers to these questions will provide a good con-
text for identifying the real needs of the business. It will also help you
71
The EPM framework
After answering these general questions, you will need to understand exactly
who will be impacted by the programme and how they should be involved.
72
Change architecture
How robust are our People and HR processes? Will they support the
change?
In some cases, programme resources and senior personnel will have the
answers. In other cases, you may need to hold focus groups or conduct staff
surveys to answer these questions.
The output for these steps should be a documented understanding of your
company’s context, the business case for change, and a preliminary assess-
ment of your company’s readiness to make the change. Based on the above,
you can then begin to shape the change strategy for the business.
These are hard questions which will take time to answer, and will also ben-
efit from the experience of those who have been through similar exercises.
73
The EPM framework
Executive summary
Introduction
The business case for change
Description of the future state
Programme requirements
Scope of the change activities
Guiding principles
Assumptions
Recommended interventions (and rationale)
Contribution management
Next steps
74
Change architecture
1 Purpose:
2 Objectives:
4 Requirements:
5 Stakeholders impacted:
7 Assumptions:
9 Risks:
10 Timeframes:
75
The EPM framework
This basic information will allow you to continue with your high-level
planning, and is also a good way to identify your resourcing needs. Be as spe-
cific as possible when detailing your resource requirements: skills, experience
and knowledge are critical when it comes to change management. Consider
the best strategy to acquire these skills: internal (already exist; develop skills;
recruit) and/or external (consultants, contractors). Once resources are
assigned, be sure to involve these people in your planning from now on.
When creating the high-level change plan:
How will the people activities be integrated with the overall plan?
What are the inter-dependencies between the people interventions?
What are the key milestones and deliverables?
What do these look like over time?
76
Change architecture
Attracts required
Reward Reward
strategy
Design reward elements Implement skills and motivates
employees
Assess ‘asis’ Develop retention strategy and plan
Retention Develop retention strategy elements
Implement Retain high
strategy performing employees
Review and evaluate retention
and turnover statistics
Assess
‘asis’
Operational Org. design and Ready and able to
finance competency model
support the business
Support implementation
Notes:
B o l d text = Critical areas of focus
Dependencies: Successful
Progressive ‘exit’ points completion of the above. People and
change activities are largely
dependent upon timely completion
of Process, Technology, Location,
Implementation and Migration
activities
APRIL 2001
1 Jul 1 Oct 1 Jan 1 Apr 1 Jul 1 Oct 1 Jan
2000 2000 2001 2001 2001 2001 2002
77
The EPM framework
You can translate the above into a high-level stakeholder management plan,
and mobilise resources to create and manage the detailed plan.
78
Change architecture
the programme, and interacting with them in an engaging and effective way.
Ask yourself the following questions:
Answering the above should give you an early view on the communications
needs of your programme, enabling you to agree first principles and mobilise
the appropriate resources to develop and execute the plan.
Communications – both internal and external – is a vital area of focus for
any programme. For advice on how to build a programme communications
capability, please refer to Chapter 14.
79
The EPM framework
The outcome of this exercise will be an understanding of the need for a net-
work, high-level principles for its operation, and potential resources. If you
decide to go ahead with this network, then you will want to assign resources
to its development.
The key outputs here are areas of focus for capability building as well as an
understanding of the extent of training and development required. You will
want to mobilise resources as early as possible.
• the shared attitudes people have towards their work and the organisation
• the behaviours that are predominant and valued
• the quality of relationships (both internal and external)
• what constitutes success and how it is recognised.
80
Change architecture
How would we describe a culture that would support the new vision and
strategy?
What would this ‘to be’ culture look, feel and sound like?
How would we describe the ‘as is’ culture?
Are there any disjoints between the ‘as is’ and ‘to be’?
Is cultural change needed? What interventions should we consider?
Key outputs include a high-level view of the gap between the ‘as is’ and ‘to
be’ as well as opportunities to close that gap.
• Scope: the processes and activities that each part of the business com-
pletes and is accountable for.
• Structure: the formal structures, boundaries, groupings and reporting
relationships required across the business to deliver the above scope.
• Roles and dependencies: the resources required to deliver the scope and
structure, including the purpose and dimensions of each role, and specific
indicators of performance.
What are the key structural implications of the change we are undertaking?
How are our competitors structured? Can we learn from them?
81
The EPM framework
The key outputs from this high-level analysis include an outline of the ‘to be’
performance and reward infrastructure, and an appreciation of the barriers
faced.
82
Change architecture
83
The EPM framework
84
Change architecture
SUMMARY
Delivering a programme means changing your organisation in some way. We
know that organisations are made up of people, so delivering a programme
means helping people to change. However, helping people to change is not
easy. Change is situational: no two programmes will have the same needs. No
two people will respond to change in the same way.
The key to success is to take the time to develop and deliver the appro-
priate change architecture that will meet the specific needs of your
programme:
85
8 Developing an enterprise-wide
approach to programme and
project management
The T-Mobile story in this chapter describes how the company has developed
its own specific and successful approach to enterprise programme management,
which suits its business challenges and environment. The case also illustrates
the practical and integrated application of many of the ideas contained in
Chapters 3 to 7, and acts as a real-life summary of the first section of this book.
86
Developing an enterprise-wide approach
87
The EPM framework
88
Developing an enterprise-wide approach
ment
anage Projec
t
M
M
nt
ana
Investme
gement
Choosing the Doing them
‘right’ things ‘right’
Achieving
the benefits
Pr ip
ojec
t Ownersh
Figure 8.1 The three elements of T-Mobile UK’s approach to enterprise
programme management
89
The EPM framework
The board that approves the project business case will usually be the same
board that reviews progress of the project, tracks the investments and reviews
the benefits delivered. This provides consistency in decision-making and
accountability throughout the lifecycle of the project, from investment
through to the delivery of business benefits.
Another key aspect of the T-Mobile UK’s investment process is its strong
integration with the annual business planning process. Once a year, the busi-
ness reviews its current portfolio of programmes and projects, and identifies
additional initiatives, including the investment required to achieve their
strategic objectives. These proposed activities are built into the yearly invest-
ment budget and resourcing plans, but their funding and resource allocation
are not signed off. The final allocation of funds and resources to commence
is only authorised through the investment process outlined above.
In order to ensure that the output of this planning is a selective set of initia-
tives focused on the organisation’s strategy, rather than a ‘wish list’, up to 80
per cent of the process is performed by the PDM and Finance functions. It is
also the responsibility of the PDM function to ensure that all these planned and
budgeted initiatives are developed into project proposals and assessed by an
investment board. Projects that are authorised for implementation are allocated
project resources and a programme or project manager by the PDM function
through joint consultation with line resource managers.
Where possible, T-Mobile UK schedules its project portfolio so that not
all activities are happening at the same time. However, for extenuating rea-
sons such as competitive pressures, there are occasions whereby the business
has to execute more projects than is viably sensible. In these cases, T-Mobile
UK attempts to mitigate the additional risks by strengthening management
controls and increasing the focus on change management processes.
90
Developing an enterprise-wide approach
91
The EPM framework
Being a project sponsor is like being the Queen: you turn up to launch a
ship, smash the champagne, wave goodbye and welcome it back to port
six months later. This attitude is totally inappropriate for leading projects
in our business environment. We need ownership that is one of passion and
continual involvement in order to drive maximum realisation of benefits
out of the project.
T-Mobile UK therefore fills the role with a manager who is senior enough
in the business to be effective in ensuring the delivery of the benefits, and
to manage the integration of the project outputs into normal business
operations.
The project manager is appointed from a central pool of trained project
managers, and is responsible for the quality and timely delivery of the pro-
ject within the budget. Project managers are all trained in a project
management approach developed internally by T-Mobile UK, which draws
some of the key concepts and best practice methods from PRINCE2.
A common risk for project managers is that they take on additional tasks,
as a result of insufficient resources, which are actually line rather than project
responsibility. Clarity of the roles of project managers, project owners and
business managers is hence critical to the business. Training these project
owners and managers with the skills to perform these roles is therefore key.
Much of the training at T-Mobile UK focuses on leadership and ‘softer’ man-
agement skills such as stakeholder management, coaching skills, and
influencing and negotiation skills.
T-Mobile UK has started to invest heavily in activities that enable those
involved in managing change programmes and projects to be equipped with
the necessary ‘people’ skills to support their project teams’ delivery, as well
as to overcome organisational resistance to change. During the large-scale
ERP implementation, the importance of investing in the skills to support
people through business change was vital to the organisation embracing the
new system. Initially, T-Mobile UK relied on external professional support in
this area. Since then, the business has set up a team of dedicated change man-
92
Developing an enterprise-wide approach
agement specialists within its Human Resource department, who have devel-
oped an approach and toolkit to support change management. These trained
change agents are deployed onto projects where there are major change
requirements or implications. They also train project managers in the change
management skills.
The PDM function includes a resource pool of process experts. These
experts in specific business process areas are also deployed onto projects to
act as architects and catalysts to help improve core business processes.
Supporting systems
With the building blocks of its enterprise programme management capability
in place, T-Mobile UK is now looking to improve the efficiency and quality
of its project management processes by implementing a programme man-
agement system. It is its intention that basic project processes such as
planning, scheduling, resourcing, issue and risk management are not only
automated, but also tied into its ERP financial applications. The objective is
to have a common platform of interaction between activity-level project con-
trol and financial information. The programme management system will
enable company-wide portfolio reporting and management information,
strengthening integration of the investment management and project process
– one of the key objectives of the T-Mobile UK approach. Currently, the
ERP system is the main tool for the financial management process of
managing allocation and tracking project spending.
93
The EPM framework
SUMMARY
Circumstances highlighted the organisation’s need for an enterprise pro-
gramme management approach, but identification of the issue was only the
beginning of its journey. We have seen T-Mobile UK’s model transform from
what used to be an approach foisted on the business in its early days to being
the de facto approach the business now embraces to initiate or manage busi-
ness change. The business has seen and acknowledged these processes to be
the easiest, most effective and objective way of approving and delivering
change in the business.
What was and still is key to T-Mobile UK’s success in implementing such
an organisation-wide approach and obtaining buy-in is not strangling the
business with bureaucracy and controls, but instead, providing support for
processes that enable the delivery of business change more quickly and with
greater benefit. This has been made possible through strong leadership
understanding, and support for development of programme management
capability as an effective means to control and focus investment and deliver
business value.
T-Mobile UK has grasped an excellent understanding of the need to
develop processes, structures, systems and personal skills to enhance its
organisational ability to deliver change and value as the company grew into
a multinational business. The challenge to improve and maintain its
programme management capability still continues.
Asher Rickayzen sums up what T-Mobile UK is constantly trying to
achieve:
94
Part II
Enterprise programme
management essentials
9 Introduction
97
EPM essentials
you. A case study provides a real example of what has worked for a successful
organisation managing a successful programme. The experiences of deliv-
ering London’s Congestion Charging provide a framework for dealing with
large, complex, time-critical and highly political programmes that have inter-
related social, economic, environmental, political, financial and technological
constraints. If these risk factors had not been managed proactively and
pragmatically, it is unlikely the programme would have been successful.
98
Introduction
99
10 Programme management
systems
INTRODUCTION
Almost everything in a modern organisation is automated, yet the activities
that can contribute most to an organisation’s success, strategic programmes,
are frequently run with little or no specific systems support. Organisations
that embrace the need for enterprise programme management must imple-
ment the necessary systems to support and drive the development of that
capability.
Programme management systems can provide assistance to:
100
Programme management systems
This chapter does not include a specific analysis of any of the currently-avail-
able software packages, beyond references to packages within the case
studies. The software solutions for programme management are developing
rapidly, and any specific analysis would likely be out of date before publica-
tion. In addition, any specific analysis would not address organisations’
requirements in their own context, and thus could be misleading.
101
Purchase Contract
order management
management
Direct costs
Budgeting and capture and Programme
planning status Communication
reporting (email)
Financial reporting
management Task/action
Expense
Financial capture and management
reporting reporting Programme
diary/events
management
Timesheet Scope mgmt
recording and change
Time control Diary
Resource Programme management
capture and management
Expense reporting communications
Issue forum
capture and
payment management Communication
(portal)
Programme Programme
HR/resource planning and library
management Risk
portfolio mgmt management
Quality
management Project Project Document
tracking and management/ Knowledge
planning management
reporting workflow
Programme Ongoing
Programme Project business Scope of PM
functions functions and project
functions functions systems
103
EPM essentials
To the right-hand side of Figure 10.1 are the existing collaboration and man-
agement tools that can assist programmes. Adopting existing systems and
processes in these areas (where they have the required capability) can speed
adoption of new processes due to user familiarity with existing systems, and
ensure knowledge acquired during the programme will be available to the
business after the programme has concluded.
One specific area where existing systems often do not have the required
capabilities is knowledge management. Leading programme management
solutions offer this functionality, with extended capability in the areas of
most relevance to programme effectiveness: for example, methodology
managers to capture project lessons and reuse these in future project plans.
104
Programme management systems
105
EPM essentials
Reducing risk
Major strategic programmes can be a ‘bet the company issue’ – in terms of
size of investment, competitiveness, and impact of issues on continuing oper-
ations. In these cases risk typically only needs to reduce by a few percentage
points to justify the additional expenditure.
There are a number of key risks areas where the effect of programme man-
agement systems can be quantified. These typically occur at different stages
of the programme:
106
Programme management systems
Improving efficiency
Efficiency benefits that apply to all programme resources arise in a number
of ways:
Streamlining administration
The key areas of programme administration where systems can help to
increase efficiency are:
107
EPM essentials
Table 10.2 explores the business case drivers for each logical component.
108
Programme management systems
109
EPM essentials
110
Programme management systems
such as ease of adoption and fit into existing technology can be equally
important, particularly for programmes within and across existing enter-
prises. The key selection criteria, and how they interrelate, are described in
Figure 10.2.
Selection process
Critical success factors for selecting programme management systems are:
111
Technical
Scope considerations
considerations Server Database
• Speed of access • Speed of access
• Scalability • Scalability
Potential • Ease of configuration • Ease of configuration
functional uses Functional fit • Supportability • Supportability
• Planning considerations
• Resource management
• Task management
• Issue and risk management Apps Operating system Hosting
• Financials development • In-house
• Document/version control requirements • Existing architecture? (within firewall)
• Document repository • Off-the-shelf?
• Security/access • In-house
• Communications considerations (outside firewall)
• Customisation
• Impact on existing • Third party
tools
Interface types
Financial/roll-out
• Fully integrated apps
• Manual interfaces considerations Vendor
considerations
Co-ordination with Financials
Interface with... existing project/ Vendor stability
programme initiatives • Licensing costs
• Finance systems • Support • Financial viability
and tools • Track record
• HR/resource • Training
management systems • Infrastructure • Support/partner
• Procurement Roll-out • Business case network
• Knowledge-sharing • Business acceptance • Upgrade path
apps. of need/benefit
• Ease-of-use/similarity
to existing tools
Start
Pilot release Release 1 Release 2
Key milestones Basic functionality Basic functionality for new Additional functionality and
limited group of key users and high-priority projects integration, more projects
Foundation Business engagement
Pilot design Pilot rollout Release 1 rollout
Business foundation Basic functional Limited number Begin with new projects
Policy implications solution, limited scope of users and high-priority areas
and process design Further
Release 1 design Release 2 design releases
Refine design for first Increase functionality, Ongoing
functional roll-out address more areas deployment
Technical set-up and
Application install, refinement
Pilot build and test Release 1 build and test Release 2 build and test
environment set-up Basic application Refine application Refine application
and data model design configuration config. for full roll-out config. for full roll-out
Characteristics of approach
• Phased roll-out of functionality with rapid deployment cycles gives faster delivery of benefits, reduced
risk, better adoption by users.
• Roll-out phased by project or impacted community.
• Data conversion and integration continues until data completely transferred, all required interfaces
in place.
113
EPM essentials
Invest in training
Many programmes make the mistake of not investing in training for all sys-
tems users. They thus fail to realise the benefits and the control that the
systems can bring. Training is essential, and should focus on programme
management processes and techniques, with systems training wrapped
around this. In this context, the training should be seen as an investment in
the development of programme management capability, rather than just a
requirement for roll-out.
114
Programme management systems
Communications infrastructure
One area of technology that does not fall strictly into the definition of ‘pro-
gramme management systems’ but which can greatly assist the effective
running of a multi-site programme is video conferencing and web confer-
encing. Given the one-off and developmental nature of many programmes,
informal communications between programme resources are at least as
important as formal communications.
Programme staff may be working as close colleagues with people on dif-
ferent continents that they have never met, and know little about, so
informal communication needs to be promoted actively. On a large multi-site
programme it is often impractical, if not impossible, to get programme staff
co-located even once in the life of the programme. Thus it is important to
make several channels of communication easily available, and persuade pro-
gramme staff to spend time working with each other via all available
communication media.
115
EPM essentials
Enterprise programme
For a programme that is performed substantially within the context of a single
enterprise, the links into existing systems are far more important. In the first
instance, user adoption will be much easier, and later on it is more likely that the
new programme management capabilities will become successfully embedded if
the systems deployed link seamlessly into ‘business as usual’.
A typical application architecture in this scenario is outlined in Figure
10.5. The extent to which existing ERP/financial/MIS solutions are used to
provide programme management functionality is largely dependent on the
capability of the specific systems already in place.
CONCLUSION
Programme management systems are very valuable tools for supporting an
enterprise programme management approach. To support multiple cross-
organisational projects the systems must, in addition to planning, scheduling
and resourcing, support workflow/collaborating knowledge management
and management reporting. Integration of programme management systems
with other business applications is becoming increasingly important to
provide consistent and consolidated information.
Programme management systems add value by reducing risks, improving
efficiency and streamlining administration. It is important to consider
carefully the selection of appropriate systems, based on rigorous selection cri-
teria including scope and functional fit, integration feasibility, business case,
vendor suitability and technical considerations.
The following case study illustrates many of these points and shows the
successful use of programme management systems in a multi-project global
environment.
116
Purchase Contract Core programme and project management application
order management
management
Quality
management Project Document/
Project tracking and Knowledge
planning management
reporting workflow management
Financial
application*
* where significant external Programme Project Programme Standard Scope of PM
reporting requirements exist functions functions and project business systems
functions functions
Registered trademarks
Primavera, the Primavera Sundial logo, and Primavera Enterprise are registered
trademarks of Primavera Systems, Inc. All other product names and brand
names are trademarks (™) or registered trademarks (®) of their respective
companies.
Benchmarking Partners, Championship Mobilization, Champion-Centered
Selling, and DSET are trademarks of Benchmarking Partners.
119
EPM essentials
Acknowledgements
Primavera Systems sponsored research performed in support of this case
study. We would like to thank all the employees of Compaq who contributed
their time and insights to this process.
Company profile
Compaq Computer Corporation, acquired by Hewlett-Packard Company in
May 2002, was a leading global provider of enterprise technology and
solutions. With annual sales of US$33.6 billion, Compaq was the third
largest computer company in the world. Compaq designed, developed, man-
ufactured, and marketed hardware, software, solutions, and services that
were sold in more than 200 countries.
Global Business Solutions (GBS) provided Corporate IT support to the
entire organisation. The Worldwide Programme Management Office (PMO)
was created in 1999 to better control project management throughout the
entire enterprise and was charged with developing consistent project
methodologies and processes to improve project performance.
The Compaq PMO matrix consisted of 24 PMO offices across the enter-
prise responsible for over 1100 active projects. Over 1400 project managers
and 3000 team contributors were part of this organisation (Figure 10.6).
Project background
Challenges of corporate IT
Information technology (IT) executives around the world are facing
increasing pressure to contain costs, manage operations more tightly, and
create more visible value from disparate projects. In order to achieve these
objectives, IT executives are treating their operations more like independent
businesses – focusing more than ever before on project planning, disciplined
delivery of services, and satisfying their internal customers.
For many global corporations, corporate IT managers are responsible for
thousands of projects on a daily basis. At the same time, they are relying
120
Programme management systems
Worldwide PMO
Project managers
Team contributors
121
EPM essentials
Selection process
Robert Napier, Compaq’s CIO, played an active role in the selection process
because he believed that enterprise project management was central to the
department’s future direction. Napier, along with Kingsberry and a large
number of worldwide PMO managers and project managers from the geo-
graphically dispersed PMOs (with dotted line responsibility to the
Worldwide PMO) formed the selection team.
The selection team’s activity was organised in four main steps:
122
Programme management systems
Based on analyst research and market share analysis, the selection team iden-
tified the top four players in the enterprise project management market. Despite
some apparent similarities in functions and features, Kingsberry was unsure if any
of the solutions could handle the volume of users Compaq anticipated.
To decide the final outcome, he tested the claims made by each product
through pilot programmes. ‘After the completion of each pilot program, Primav-
era TeamPlay® was clearly the winner due to its enterprise scalability, multi-user
functionality, and vendor commitment to do whatever it takes’, says Kingsberry.
The implementation
Compaq began implementation with the installation of Primavera’s database
and the convergence of existing project information into Primavera TeamPlay
structures. During the pilot, the department, in close cooperation with Primav-
era, had clarified its needs for defined policies, procedures and guidelines on
how to use Primavera TeamPlay, as well as training requirements and needs for
system support plans.
Apr. 1999 Sept. 1999 Nov. 1999 Dec. 1999 to Mar. 2000 Nov. 2000 Jan. 2002
Feb. 2000
Started Started Completed Developed Began Complete Complete
pilots Primavera pilots and methodology, rollout and bulk of integration
concurrently TeamPlay evaluated planned training rollout with
with top Pilot performance imple- financial,
four solution mentation, and human
providers configured resources
system
Based on early positive results, John Buda, Vice President of Strategy &
Planning, supported an aggressive schedule for a global rollout of Primavera
TeamPlay on a phased basis. In addition, Buda played a key part in
mobilising the organisation behind that effort.
By December 2001, over 3000 Compaq employees had been trained to
use Primavera TeamPlay.
Miguel Peralta, the Operations Manager in the PMO, reports that the
implementation process exceeded the unit’s expectations. (According to an
internal survey conducted by Corporate IT, 93 per cent of users were satisfied
with Primavera TeamPlay’s functionality and 96 per cent were satisfied with the
process whereby their project activities were brought into Primavera TeamPlay.
According to Peralta users no longer had to manually re-enter data. Projects
and resources were, for the first time, all in one central database.) By agreeing,
in advance, within their organisation on how they wanted to use the software,
123
EPM essentials
Compaq was able to redirect its culture. Through the use of Primavera Team-
Play, said Peralta, ‘we were able to rapidly institute a whole host of changes that
would not otherwise have been possible. This was our way of getting every-
one on board.’
To show his support, Compaq’s CIO, Robert Napier, signs every training
certificate issued upon completion of the training programme. Napier sees
his active involvement as contributing to each user’s understanding of the
necessity of the Primavera solution to achieving his wider objectives.
As the benefits of the Primavera TeamPlay implementation have been
recognised throughout the enterprise, Kingsberry reports that other business
units are expressing interest in using enterprise project management to
improve their business processes. Several have purchased additional licenses
and have begun to use the system for many different types of projects. Areas
that include the solution in their processes range from Human Resources to
New Product Development. In addition, Primavera TeamPlay has been fully
integrated with Compaq’s internal IT help desk software (Remedy) and is in
the process of being integrated with SAP and PeopleSoft.
Benefits achieved
Primavera TeamPlay has facilitated, in a way that was not before pos-
sible, the Global PMO’s goal of bringing its overarching principles into
practice. ‘Programme and project plans now accurately reflect the work
our people accomplish.’
Don Kingsberry (Director of the GBS Worldwide
Programme Management Office – PMO)
124
Programme management systems
not formally planned and were managed with task lists. Project plans were
not in a single database and actual project status was often unknown or
unavailable.
Projects not being managed with a consistent methodology hindered
comparisons and progress assessment. Executives or managers seeking
actual project costs often found that they could not be determined with
any certainty or timeliness.
By using Primavera TeamPlay, Kingsberry reports that the Worldwide
PMO increased its percentage of projects meeting deadlines, budget and tar-
gets while accountability increased.
According to Kingsberry, ‘The PMO’s improved project performance is
apparent even to people who are not Primavera TeamPlay users. Through
web publishing, we are able to share our project plans and supporting
documentation with our customers.’
Within the first year after the implementation, Primavera TeamPlay sur-
passed (by a factor of 15) the ROI that Compaq projected for the
software in its Business Case. The Global PMO’s business performance,
also (measured by an averaged ROI) was significantly improved.
Don Kingsberrv reports that the initial benefits of the TeamPlay implemen-
tation have far exceeded Compaq’s expectations. Compaq does not publicly
disclose its ROI numbers, but the calculator revealed that within the first year
after the implementation, Primavera TeamPlay surpassed (by a factor of 15,
according to Kingsberry) the ROI that Compaq projected for the software
in its Business Case. The Global PMO’s business performance, also
(measured by an averaged ROI) was significantly improved.
Standardised reporting
Prior to using Primavera TeamPlay, the PMOs used a desktop solution that
did not provide the level of project information that was needed on a large,
global scale. The work involved in gathering information on project status
was manual and required multiple updates from project contributors. The
125
EPM essentials
time it took to prepare this information was considerable and the results were
insufficient to meet Compaq’s fast-paced needs.
The PMOs were spending an enormous amount of time reacting to the
needs of their internal customers. They often responded to ‘fire drills’, where
project performance reporting was needed on an ‘emergency’ basis by var-
ious business units. Now, the PMOs use Primavera TeamPlay to standardise
and update responses to such requests.
Originally, the PMO implemented the executive level program scorecard,
a CIO Program Dashboard, with a manual process using a spreadsheet. Now
this weekly executive reporting is generated directly from Primavera
TeamPlay and the result is a web-based report that is easily viewable around
the world.
Today, through TeamPlay features such as Reporting Wizard and Issue
Management capabilities, the PMOs have been able to lessen the number of
fire drills by proactively providing weekly scorecards in a more timely fashion.
The scorecards created an objective standard for measuring project perfor-
mance, which has become an increasingly important corporate requirement.
Instead of taking weeks to assemble specific project information, it now
takes only a few hours. By dramatically reducing this unproductive time, the
PMOs are now able to be more active in managing deeper levels of their
projects and better monitor critical path issues.
126
Programme management systems
127
EPM essentials
its web-based training as its single standard, Compaq was able to reduce
classroom training and all its attendant costs (such as travel and work
disruption).
‘Primavera TeamPlay’s web-based TeamPlay training is one of the best
implementations we’ve seen,’ says Peralta. ‘With its dynamic screens, the
users are actually performing the functions and the built-in tests confirm
overall competency.’
‘Moving classroom training to the web enabled us to reduce the cost of
training by 80 per cent,’ says Peralta. ‘In addition, users are now able to
access training independent of time and place, taking advantage of certain
training modules only when needed and proceeding at their own pace.’
Enterprise benefits
Portfolio management
Prior to Primavera TeamPlay, Compaq had no common executive level status
reporting programme and no master plans for GBS programs.
Now, programmes are all instituted in a standardised format, using master
plans accessible to senior executives and customers as appropriate. The stan-
dardised weekly scorecard generated by Primavera TeamPlay enables
executive level reporting on every project that makes up the portfolio.
Portfolio management takes alignment to another level. The priorities of
senior management are better able to influence both high-level decision-
making and the most granular level execution.
Primavera TeamPlay helps managers, wherever they are located within
Compaq’s organisational structure, to consolidate disparate project informa-
tion, to drill down into the details at whatever level is required and to take
slices into varying layers of depth or breath.
Compaq has been able to improve its monitoring and decision-making on
projects by systematically coding projects as strategic, legacy, or support.
Similarly, Primavera TeamPlay allows Compaq to code projects based on
their motivators (e.g., cost saving, revenue generating, direct business model
support and compliance). Senior management is, thus, able to analyse the
mix and learn what proportion of spending is going into each category.
A major benefit of Primavera TeamPlay, reports Kingsberry, is Compaq’s
ability to ‘increase the percentage of its resources directed at the company’s
primary goals’.
128
Programme management systems
Managers now have the ability to view their entire project portfolio and
determine if there are duplications in project effort across the enterprise.
In addition, as business needs change, they have the added flexibility to
change the course of projects and replace those who do not address
company needs.
For example, through portfolio management, the department has been
able to redeploy resources to more strategic projects. In addition, they were
able to better see when key project requests should be addressed, given the
overall view into the programs they were supporting. And lastly, they were
able to evaluate those projects that did not fit into the timing and direction
of the current business agenda and cancel them before they were begun.
Overall, by having an enterprise view into corporate IT’s project portfolio,
reports Kingsberry, IT executives have been able to reallocate resources result-
ing in cost savings of US$15 million over the course of three business quarters.
With Primavera TeamPlay, Compaq has a better capability to shift the
reporting responsibilities of entire teams without disrupting work and, at the
same time, allow flexible visibility. Multiple vice presidents, for example, can
simultaneously view the work of project teams whose output is important to
them. Primavera TeamPlay enables a vice president with responsibilities for
Europe and a vice president responsible for the Global Business Units to both
view an entire program and all its constituent projects. Each can drill down for
visibility into those aspects of the work that concern them the most.
Improved coordination
Primavera TeamPlay facilitates global management through its unified data-
base, allowing units in Latin America or Asia, for example, to be managed
129
EPM essentials
Alignment
Winfiele sees Primavera TeamPlay’s standard reporting tool as a powerful
unifier, often cutting through unintentional miscommunication with instru-
ments such as Primavera TeamPlay’s Project Lifecycle Reports, which
Compaq prints out weekly.
Prior to Primavera TeamPlay, reports of completion levels were heavily
dependent on subjective assessments. ‘In one instance’, he points out, ‘a pro-
ject was being loosely reported as being on the order of 60 per cent
complete. Once we entered all the data into Primavera TeamPlay and ran the
report, it was actually less than 10 per cent complete.’
Previously, Winfiele reports, it was not possible to get everyone to use the
same project management approach and tools. Now, all Compaq IT Project
Managers understand that for their work to show up on the single radar used
by senior management, they must be in Primavera TeamPlay. Winfiele sug-
gests that by using Primavera TeamPlay as they have, Compaq ‘created a
totally different atmosphere in managing new projects.’
The entire organisation is now influenced by using Primavera TeamPlay to
standardise the format for consistently and comprehensively describing
opportunities, scope, analysis, and decision-making. With Primavera
TeamPlay, according to Winfiele, every project can be audited in a consistent,
commonly understood framework.
Now, with a consistent system for all project reporting, everyone can rely
on data with more certainty – for everything from budgeting through
130
Programme management systems
Being named to this list, far ahead of the next hi-tech organisation at #19, helps
differentiate Compaq in the marketplace. Moreover, says Kingsberry, this
131
EPM essentials
Conclusion
Primavera TeamPlay is delivering tangible and strategic benefits to Compaq’s
corporate IT executives, PMOs, project managers and the company as a whole.
Compaq’s Global Business Solutions organisation has quantified ROI in
both its usage of Primavera TeamPlay and the overall project portfolio.
Using Primavera TeamPlay’s capabilities for project standardization, stan-
dardised reporting and full project visibility, corporate IT has realised reduc-
tions in resource costs, training costs and project risk, with increases in resource
utilisation, improvements in project management, process repeatability and
deployment efficiencies.
As a result, corporate IT is able to run its operations more like a separate
business entity and, simultaneously, increase the satisfaction of its internal
customers. Both the corporate IT staff and senior management associate the
implementation of Primavera TeamPlay with increasing sophistication of
project management within the organisation.
Furthermore, the enterprise as a whole is deriving additional benefits from
portfolio management enabled by Primavera TeamPlay. Specifically, they
have been able to improve decision-making, flexibility, coordination, and
alignment.
By using Primavera TeamPlay, Compaq’s corporate IT division already
dramatically and substantively improved its internal processes, qualitatively
and strategically increased its enterprise-wide impact at the executive level,
and enhanced Compaq’s overall competitive position in the marketplace.
132
11 Managing programme risk
INTRODUCTION
Much has been written on the subject of managing risk in projects. The tools
and techniques for project risk management are well documented and devel-
oped. Nonetheless many large, complex projects still fail because of a lack of
understanding of end-to-end risk management.
In a large programme, not only are the difficulties faced by projects com-
pounded, a whole new swathe of potential problems can be encountered.
Conflicting objectives within the programme; demands on critical resources;
maintaining balanced and sustained sponsorship; managing the ‘business as
usual’ while focusing on strategic change; communicating the right mes-
sages; and managing risks across the extended enterprise are just some of the
challenges.
This chapter provides an introduction to risk management, giving defini-
tions of risk and risk management. Our approach goes ‘back to basics’ with
a look at some of the fundamentals needed to close the gap between theory
and reality. We look at some of the key challenges faced when managing risk
across the programme, and identifies effective ways of rising to the challenge.
Through discussion of appropriate techniques for identifying, assessing,
communicating and managing risk, some developed from project disciplines,
some unique to programmes, you will see what approaches are suitable for
you. A case study provides a real example of what has worked for a successful
business managing a successful programme. The experiences of delivering
London’s Congestion Charging scheme provides a framework for dealing
with large, complex, time-critical and highly political programmes that have
interrelated social, economic, environmental, political, financial and techno-
logical constraints. Without managing these risk factors proactively and
pragmatically, the programme would be unlikely to succeed.
Throughout this chapter, emphasis is placed on the attributes required of
programme teams, their management and their sponsors, and how to
develop these attributes to deliver the desired benefits. Risk management is
not treated as a management add-on, a function within the programme
office. It is given its rightful place as an integral part of the programme, per-
tinent to programme objectives, crucial to programme strategy and
decision-making, and practised by the programme executive.
133
EPM essentials
RISK RISK
Risk
Risk mitigation
mitigation – reduce
– avoid impact Business
Risk controls
mitigation
– reduce Business
probability contingency plan
ontingency
pecific c
ness s
Busi
134
Managing programme risk
not to remove all risk, but to remove avoidable risk, leaving the desired
level of intrinsic risk. This approach also serves to reduce the uncertainty,
or the ‘unknown unknowns’ that may exist in an business’s external
context.
While risk management may be easy to describe, it is very difficult to
achieve. Recent history shows us that up to 70 per cent of programmes are
late, over budget or ineffective, especially if the programme is large, complex,
critical and incorporating major change.
Enterprise Enterprise
Strategy
development
Portfolio Business
Translating
t
en
strategy and
gem
managing
a
an
portfolio
km
Programmes Divisions
r is
Delivering
e
successful
tiv
tia
programmes
Ini
Projects Departments
Completing
successful
projects
Before we take a closer look at the approach to risk management used by the
Congestion Charging programme, it is important to understand the four
different levels:
At every level, there will be the requirement to integrate and link with the
‘business as usual’ risk.
135
EPM essentials
Enterprise risk
At the enterprise level, we bring together the assessment and management of
strategic risk within the ‘business as usual’ and initiative (programmes) sides
of the enterprise to recognise dependencies, realise synergies, and integrate
with the strategic risk management.
Portfolio risk
We see two types of risk within the portfolio. The first are simple, high-level
faults that are generic in nature. These are often the cause of failure.
Examples are a programme with inconsistent targets for delivery time, cost
and performance, and programmes with incompatible targets. The other cat-
egory of risk is detailed, project-specific risk that is not easily predicted or
mitigated. At the portfolio level, the focus is the potential of the portfolio of
initiatives (programmes and projects) to realise and implement business
strategies within an effective and efficient approach. Figure 11.3 highlights
the five key questions behind effective portfolio risk management.
The review of portfolio risk also includes aggregating and integrating the
escalated individual project and programme risks.
Risk management at the portfolio and enterprise level represents a central
component of strategic portfolio management. The principal steps involved in
repeatable portfolio optimisation, of collecting information, analysing the port-
folio, prioritising projects, and communicating and reporting, are supported
by the risk management undertaken while monitoring the competitive
environment.
Figure 11.3 Five key questions for effective portfolio risk management
136
Managing programme risk
Programme risk
As mentioned earlier, risk management is fundamental to programme and
project management. Within the programme arena, the principal balance
is between investment, benefits realisation, and risk. Rapid top-down
identification and mitigation early in the programme should run concur-
rently with the establishment and maintenance of programme lifetime risk
management. Key risk responses at the high level include changing the
programme scope, goals and approach, realistic re-planning, significant
alteration of resources availability, amendment to the programme organ-
isation, management processes and communication mechanisms. Key
actions to reduce the intrinsic risk for the delivery of programme benefits
include:
The initial routes for identification of risk are the explicit and implicit
assumptions in the programme set-up; historical review of a programme’s
performance; analysis of the programme roadmap; and diagnosis of the pro-
gramme management capability. The use of periodic external diagnostics/
validations is an extremely powerful method of risk reduction.
Project risk
At the project level the emphasis moves to strict time, cost, quality and scope
criteria. Project risk management needs effectively to filter the identified pro-
ject risks to identify those whose impact is critical at the programme level, or
that could influence other projects across the programme.
137
EPM essentials
(insurance and banking), the military, and in audit and health and safety
functions. More recently, partly attributable to the Turnbull Report, it has
entered mainstream management activity across both public and private sec-
tors. Risk has moved from being seen as a technical subject to being viewed
as central to managing the whole organisation. There are strong parallels
with other disciplines such as financial management and project manage-
ment, which have increasingly become seen as necessary mainstream
management skills (albeit supported by professional experts). In each of
these areas the benefits of a systematic approach are well established and
widely recognised.
Despite these advances, it is clear from the research and the experiences
of programme managers that there is a significant gap between what is
published in a plethora of risk management books and journals, and
real-life programmes. The gap between reality and theory is often a
chasm. This section presents a number of key themes that seek to bridge
this gap:
138
Managing programme risk
139
EPM essentials
Recognising risk
The nature of the industry, competitive position and shareholder expectation
will be major determinants in the appropriate mind-set, culture and focus of
risk management. This will allow a view of the necessary risk appetite (target
degree of risk) and tolerance (limits of unacceptable risk). This is most effec-
tively realised through embedding in the mind-set, rather than through
enforcing a methodology. This requires an emotional connection with the
risks and business objectives.
Some cultures encourage the proactive identification of challenges and
risks; in others this is tantamount to an admission of failure. The most impor-
tant factor is the matching of environment, expectation and action. The
quest for higher returns requires the acceptance of greater risk. The demand
for faster benefits realisation is incompatible with the emphasis on cost min-
imisation or the elimination of uncertainty. For some, these require major
mind-set shifts.
In most situations there is usually a warning signal that leads to a chain of
events, which may or may not be noticed. Sensitivity to pick up signals, or
the absence of signals, is required for optimal decision-making in dealing
with risk.
Managing risk
The culture of the business and the specific mind-set of the people involved
determine the priority given and the quality and value derived from the risk
management enablers, and influence the decision options and outcomes.
Risk management must be seen as important, and an ongoing responsibility.
It must integrate with the planning, goal setting, progress tracking,
resourcing and benefits realisation elements of programme management. It
must be much more than a paper exercise, undertaken to be seen to meet the
regulated management requirements. Ownership of risks must be real,
proactive and meaningful. Immersion by the risk team and the programme
leadership team in the purpose and the methods of the customers is essential
to creating the right foundation for risk management.
140
Managing programme risk
Risk appetite
and tolerance
Approach
Identity
Manage
Analyse
Plan
Processes using the six Ps (prior preparation and planning prevent poor per-
formance) are essential to get the right information to the right person at the
right time. It is difficult to overestimate the importance of completeness of
process in risk management.
What is at risk?
In order for the identification and analysis of risk to be meaningful it is
necessary to have a clear understanding of what is at risk. This requires a
clear definition of goals, objectives, scope, strategy and the programme
environment.
141
EPM essentials
95 % max
return
Expected
Return
return
Uncertainty
95 % min
Risk approach
The approach to risk management will depend on all the above decisions,
and will define the scale, scope, resourcing and importance of risk
management. The output from this step will be confirmation that the
proposed approach is appropriate, and a documented description of the
risk management approach, plan and processes.
142
Managing programme risk
Identify
The risks should be identified as comprehensively as is possible, yet this
should be achieved in a practical and cost-effective manner. Confidence in
the thoroughness of the identification process is necessary to give the risk
management process validity. Normally all stakeholders should be included
in the identification process. Wherever possible, lessons learnt from previous
programmes or general enterprise experience should be sought, assessed and
utilised.
Analyse
The risks and responses need to be described and characterised sufficiently to
allow effective risk planning to be conducted. To the extent that is practical
and value-adding, quantitative and qualitative assessments need to be made
of the probability of occurrence, impact (time, cost, performance, related
risks and issues) and time to impact (net of mitigation lead time).
Typical tools include the probability, impact, and time grid to both com-
municate risk criticality and prioritise risk activity. These can prioritise time
or scale of risk (and benefit). Simultaneously, risk management should be
identifying the principal uncertainties in the baseline activity plans and cost
schedules.
Plan
The typical responses of mitigate, monitor and ignore need to be consid-
ered for each risk. The chosen risk response plans provide a direct input
and revision to the programme and work package plans. Contingency plan-
ning should be undertaken for critical risks, and these provide supplemen-
tary plans to the base plans. Contingency planning must include defined
triggers and structured decision rules for initiating reactive contingency
responses.
Manage
The key aspects of this iterative phase are implementing the risk action plans,
and frequent, meaningful monitoring of programme progress, risk action
progress and the underlying residual risk, driven by unambiguous allocation
of responsibility to nominated individuals. This is the area that is most fre-
quently inadequate. We believe that risk management, although well
understood in theory, has yet to realise its full potential in many companies
in practice. As part of the ongoing risk management process, it is important
to monitor the effectiveness of the process and compare the risks arising with
the original estimates of likelihood and probability.
143
Project: Programme level and occupation %; 2 1–20%; 3 20–50% Sort by L-I rating Avoid,
Sort by Active,
Updated: 09-May-02 Reduce,
risk no 4 50–90%; 5 > 90 % Standardised to 0-100% Monitor,
Monitor,
= L 1/2*I Closed
Post mitigation Ignore
Title L-I rating
Risk Risk Risk Owner Respon. Adopted Management action
Ur
Description, inc. cause Likelihood Impact This Last entity Status
no. area cat. person strategy with named action owners
impact and assumptions month month Initial
84 Occ Migration Insufficient DR capacity in xx: although there will be plenty 4 5 89% 89% 63% ES Active Reduce ACTION: forecast space (power, heat) requirements
of space at HDC, no production migration can occur unless understand problem better
DR is in place at HH or xx. There is a risk, given the ACTION: identify initiatives to significantly increase spare
environmental constraints, that this constrains the migration capacity
to a dual site strategy and embarrassingly prevents
businesses taking advantage of the xx capacity.
61 Occ Migration FSU delivery: the FSU project currently has insufficient 5 4 89% 80% 46% ES Active Reduce ACTION: get agreement on who will own the project, and
planning and coherence which is delaying implementation of provide resources
the FSU. This has dramatically reduced the number of ACTION: highlight dependencies on FSU
consolidations from xx, resulting in increased migration costs,
and some businesses finding alternatives to the FSU. The
delay, assuming this leads to no FSU consolidations, will
significantly increase the total PUAM cost.
74 Occ Migration Intelligent space planning: There is a risk that space 5 4 80% 80% 54% ES Active Reduce We need to ascertain who will do the intelligent space
allocation is sub-optimal, if no single person owns all planning and allocation; and then integrate with xx and
allocation, if the xx process is not fully integrated with that the xx team
person, and if migration allocation is not integrated with new ACTION ON xx space planning guidelines still in progress
kit.
77 Prog Purchase authorisation: The delayed procurement 3 5 77% 77% 72% ES Active Reduce xx are reviewing the procurement process for x related
authorisation for the xx kit needed to migrate from xx has kit/services - chase up
significantly delayed the migrations and put at severe risk the ACTION: more clearly identify time critical purchases;
vacation of xx by the end of June. The remaining xx storage track their way through the system; ensure no blockages
elements that are still subject to approval and if delayed will within the x team
impact the migration from xx and other locations, as well as
impact the credibility/utility of the SAN.
115 Occ Migration Last minute cancellations: There have been a number of last 4 4 72% 72% 89% ES Monitor Reduce ACTION: ensure authorised business representatives
minute cancellations, often due to preventable reasons. This is communicate to all involved
partly due to an apparent lack of timely communication with all. ACTION: ensure much more urgency in responding to the?
Tools
The use of risk tools is a significant enabler for long-term success. This
includes quantitative analysis of plans, cost breakdowns, risk logging, priori-
tisation and tracking, risk action management and reporting. The
appropriate tool may be an Excel spreadsheet, an Access database, a
commercially available programme risk management tool or an enterprise-
wide risk tool, depending on the size, complexity, duration, criticality, risk
appetite and risk management maturity of the initiative and enterprise under
consideration.
We frequently see inadequate use of standard tools, reducing efficiency
and effectiveness, or alternatively the implementation of risk tools without
the shifts in behaviour required to drive through an effective risk manage-
ment approach. Tool implementation may offer an opportunity to embed
the culture and ways of working required around it.
The paradox of programme risk management is that the simple often
seems complex, whereas the trick is to make the complex seem simple.
Good software tools can help to achieve this; bad tools can distract and
confuse.
People
The skill-set, capability and motivation of an organisation’s people are crit-
ical to the successful function of risk management. Inconsistencies, gaps
and deficiencies in skills, motivation and training must be addressed to
create the capability for risk management to function. The selection of risk
management staff must be done with due consideration.
Structure
For risk management to be effective, a continuous self-sustaining process for
risk management must permeate all levels of the organisation, ultimately
driven by the board and the CEO. Key to the establishment of a dynamic risk
management system is an appropriate governance structure through which
to feed relevant information and make decisions. Imperfect organisations
create new risks for themselves, and tend not to manage existing risks as well
as they could.
The risk manager is a core part of the overall programme and portfolio
management. In a programme environment, the risk manager works day to
day with the PMO (at project or enterprise level), facilitating the risk man-
agement processes, working with the programme team in identifying and
analysing new and changed risks, and liaising with those responsible for plan-
ning, resourcing and benefits within the PMO. The links to planning and
benefits management are particularly critical.
145
EPM essentials
Programme
director
Programme PMO
Programme PMO
manager manager
Resourcing Benefits
manager manager
Additionally, the risk manager should have regular risk reviews with the
programme manager and/or director (as this is often the only way to achieve
the real benefits of risk management). Risk owners must be in a position to
facilitate and manage the risk mitigation actions.
Information
The availability of up-to-date and accurate information, and the ability to
analyse and aggregate, are key to helping the risk management decision-
making process: garbage in, garbage out. Elements of the information may
be held in a central repository created from the various tools available, as dis-
cussed in the tools section.
The single most important factor is the maintenance of good communica-
tions. The best results come from having a strong emphasis on face-to-face
communication wherever possible.
146
Managing programme risk
Uncertainty
Sensitivity
147
EPM essentials
Enterprise diagnostic
This is performed to identify the risks to and within the project portfolio.
These include risks of poor alignment, conflict, omission and duplication. This
diagnostic is supported by the transformational alignment matrix (TAM). The
TAM maps activity to the core objectives and targets of the business. The TAM
allows us to identify the contribution of the portfolio to the desired key
organisational capabilities, and identify gaps and inappropriate focus.
148
Managing programme risk
Decision management
Effective decision-making is critical to delivery of the desired outcomes,
whether they are strategic, programme or at a project level. Treating decisions
as critical mini projects can significantly speed up and improve decision-
making, and we have a number of tools to do so, including a decision-making
diagnostic. This can remove a significant amount of systemic risk.
MAKING IT HAPPEN
Implementing business-wide change to create the risk management mind-set
and culture requires a structured approach to enable individual stakeholders
to understand the logic behind the risk management system.
149
EPM essentials
Change
The visualisations provide useful ideas
Emotionally charged that hit people at a deeper level than
ideas change the surface thinking. They evoke a visceral
behaviour or reinforce Feel response which reduces emotions
changed behaviour that block change and enhances
those that support it
This approach is based on the ‘See, Feel, Change’ model (see Figure
11.10) developed by Deloitte. It aims to enable and motivate individuals
to recognise the importance of risk management within the business
through visualisation, dramatisation creating emotion and then changed
behaviour.
150
Managing programme risk
151
EPM essentials
The success
To the credit of the Transport for London (TfL) directors and their team,
Central London Congestion Charging Scheme went live on 17 February
2003 on time, within budget, and achieved the technical specification to
meet the required customer service levels. Heralded as a huge success, it has
reduced traffic in Central London by a steady 16 per cent within the zone,
shortening delays by 40 per cent and generating revenues of up to £3 mil-
lion per week. All net revenues are to be reinvested into London’s transport
infrastructure.
So what was the risk methodology underpinning the programmes’
successful programme risk management?
Contingency/continuity planning
In anticipation of Scheme Go-Live, we helped TfL to make the transition
from a focus on project and implementation risks to active contingency plan-
ning. Key operational risk scenarios, along with appropriate owners,
mitigations and contingencies, were identified through a series of workshops,
interviews and discussion documents. Advanced modelling simulation was
also used to test results. Contingencies were signed off by project sponsors
to enable a swift response in the event that a risk scenario arose during live
operations. These scenarios were entered into a customised version of the
central Risk Register for ongoing reference.
Stakeholder interest in the Congestion Charging Scheme was very high,
and responding to it was an important part of our role throughout the pro-
curement and implementation phases. We managed a comprehensive
consultation process, first engaging key stakeholder organisations, including
London boroughs, the emergency services and business representatives, and
then engaging the general public. The public consultation included distrib-
uting leaflets, articles in newspapers, broadcasts on radio and television,
public meetings, notices, an exhibition and a call centre to answer any
152
Key Milestone 1 Milestone 2 Milestone 3 Milestone 4 Current
start
Milestones
Possible event 1 Possible event 2 Possible event 3 Possible event 4
Risks
Opposition
Appeals to wins appeal STOP
House of Lords 50%
? Opposition appeals to
European court
?%
Opposition 20%
Scenario A Accepts 50%
= Unknown
Opposition loses appeal
No change
wins appeal STOP Opposition ?
on dates
?
?% loses appeal
20% 60%
Opposition Opposition appeals to 80%
Scenario C
appeals House of Lords Opposition
Start: End of May
stops
80% 30%
= Key event
Win 80% 40%
Opposition Opposition
loses appeal STOP
wins appeal
80% 20%
70%
Continue as Scenario B1
JR Opposition Opposition
per Scenario A Milestone 2: Jan
stops stops
Start: Easter
20% STOP
20% Accepts 20%
Lose
Lose
60%
Appeal Scenario B2
Milestone 2: Jan
90%
40% Start: Easter
Opposition
= Programme suspended
stops
STOP
10%
Programme
suspended?
Legend
15/07 31/07 01/08 31/10 01/11 15/04 16/04 31/05
2 wks 1 day 13 wks 1 day 18 wks 1 day 6 wks Note: Timeline not to scale
queries. As part of the ongoing risk mitigation strategy, the programme con-
tinues to work very closely with key stakeholder groups to ensure that the
scheme meets the needs of specific customer groups such as drivers of black
cabs, people with disabilities and fleet operators. The provision of compre-
hensive reports to the Greater London Assembly’s scrutiny committee has
also been an important aspect of ensuring that the scheme meets stakeholder
requirements.
SUMMARY
Risk management is an approach to creating competitive advantage, oppor-
tunity and flexibility while minimising risk exposure and nugatory expense.
Fully effective risk management will shape the plans of the business, test the
plans of the business and realise learning from the outcomes.
Risk management depends on a number of parallel capabilities, and this
often requires fundamental changes in the decision-making process and pri-
orities, especially at the senior management level. People, process, mind-set
and tools must operate as a system to drive executive decision-making within
the organisation.
Thus it is concluded that risk management is an integral part of the change
programme, central to its objectives, crucial to strategic portfolio manage-
ment and programme delivery management. Risk management is key for
enabling decision makers to take the right decisions at the right time to
ensure delivery to schedule, quality and cost criteria, whilst protecting the
existing business or organisational activities.
154
12 Benefits management
INTRODUCTION
Analyses and post-mortems of programme failure tend to concentrate on
whether the programme delivered the product as specified on time, on
budget and to a certain quality. In other cases, a post implementation review
may conclude that the programme has been delivered successfully, the team
are successfully redeployed, suppliers have been paid and the impacted users
or stakeholders are reasonably happy. Much more rarely does the most per-
tinent question of all get asked: that is, did the programme really deliver the
benefits that were outlined and predicted when the investment was sanc-
tioned? A ‘successful’ programme that does not deliver the intended benefits
is akin to that cliché of medical black humour, ‘the operation was a complete
success; unfortunately the patient died’. This chapter on benefits manage-
ment discusses the processes required to ensure that the survival of the
patient is identified as a key success measure, that the pulse is taken
throughout the course of the operation, and the patient’s well-being is
monitored for a relevant post-operative period of time.
The Office of Government Commerce estimates that 30–40 per cent of
projects designed to support business change deliver no benefits whatso-
ever, and one must assume a not dissimilar percentage fail to meet the
anticipated benefits. Benefits management is challenging, and often over-
looked, not least because it spans a time period greater than what is often
seen as the overall lifecycle of the programme. Thus the enterprise
programme management pyramid view, topped by the business strategy of
the organisation, is a useful framework with which to consider benefits
management. Benefits management begins with benefits identification
before a specific programme is initiated, and continues with measurement
even after the programme has delivered and ‘business as usual’ has
reasserted itself. To add to the difficulty, benefits management may require
different skill-sets and mind-sets from those needed for other aspects of
programme delivery.
Benefits management, within the enterprise programme management con-
text, directs business change towards valuable, desired results by translating
business objectives into identifiable, measurable benefits and systematically
tracking and communicating the results.
155
EPM essentials
Vision statement
and strategic
initiatives
Strategic
management
Business case
and objectives Strategic portfolio
management
Ch ramm
Pro
an
ge
g
arc
hit
Benefits
ea
ec
realisation plan Programme delivery management
rch
tu
re
ite
ctu
re
Delivery of Project management
benefits
156
Benefits management
It is often the case that once a business case defining benefits is signed off,
the emphasis becomes on managing delivery time and cost. One of the
reasons for this is the isolation of business case development from the
resulting delivery of the programme. The other usual stage in the tradi-
tional approach is the post-delivery or post-implementation review. Again,
this is too often done in isolation and fails to reveal the true benefits from
the programme, focusing instead on time, cost and quality of the
programme delivery. Establishing a continuous programme management
approach, where the business case is integral to the business outcomes, can
mitigate these risks.
A benefits plan that is quite separate from the programme management
process is a common pitfall. The two must be aligned, dynamic processes
with reporting on benefits integrated into the programme reporting process
from the start. The integrated plan needs visibility and ownership at the
sponsor level, as well as at the delivery level.
The scope of the process for managing the benefits of a programme will
vary according to the type and size of the programme, and the organisation
in which it is being implemented. There are however some fundamental prin-
ciples that apply to all change programmes, which we will discuss in this
chapter. We look at the overall approach, key tools and techniques, required
roles and responsibilities, and highlight some common pitfalls.
157
EPM essentials
Vision statement
Benefits
management
Financials strategy
Programme plan
Quantifying benefits
Privately, programme sponsors and managers sometimes admit that benefits
management does not receive the focus it should because quantifying bene-
158
Benefits management
fits is simply ‘too difficult’. Similarly, being on the hook to deliver benefits
quantified by a strategist keen to receive programme sign-off is just too
painful or too risky.
Quantification can be made easier by having a clear understanding of the
categories into which benefits can fall. Ensuring involvement and continuity
of the relevant stakeholders throughout the benefits management process
also enables ownership and buy-in to quantified benefits.
Many different types of benefits may accrue to an organisation, enabled by
the introduction of new ways of working. The importance attached to indi-
vidual types of benefits will depend on what the organisation is trying to
achieve. These are the outcomes that the organisation is seeking – not nec-
essarily a saving in cash terms, although it will often include this. Identifying
and quantifying potential benefits can be difficult when you start to look
away from just the return on investment benefits. A robust approach is there-
fore needed, a prerequisite of which is understanding and communicating
what the intended benefits are.
Benefits fall into three categories:
Customer satisfaction
Reduction in costs
Corporate ‘image’
Accommodation savings
Better access to information
Better cash management
Improved processes
Increased revenue
Increased competitiveness
Access to markets
Direct/tangible Indirect/intangible
159
EPM essentials
Tangible benefits
Financial and direct non-financial benefits are relatively easy to identify and
quantify. Direct financial benefits can be compared with each other in cost
terms, or to other potential investments (to assess the opportunity cost).
Non-financial benefits, such as improving market share percentage, must be
justified more aggressively to ensure stakeholder buy-in. Gartner Group
points out that implementing automated computer systems will not neces-
sarily result in direct cost savings, but has enabled many other benefits to the
organisation to be realised, such as an improvement in productivity. To fully
assess the overall contribution, it is important to identify, measure and value
benefits in terms of their contribution to business value.
Intangible benefits
Indirect or intangible benefits must be identified and prioritised, even
though there may be no common currency between them. To do so requires
that their contribution to business objectives be assessed. For a clear
meaningful linkage to be made, the objectives themselves should be stated in
the most specific and measurable way possible. Even so there will remain a
qualitative aspect to documenting and comparing intangible benefits.
During the benefits management process, intangible benefits must be
tested continually against business strategies and objectives in order to ensure
they are robust, relevant and in some way measurable, even if against an
artificial scale aligned to a business objective.
Different benefits will have a different profile for their delivery and
realisation, and this profile in terms of timing, ease of measurement and
likelihood of achievement will be defined as part of the identification
process. This will be used to input to the timing and structure of benefits
reviews.
• The objectives define the overall programme aims and reasons for
investing in change. These will not normally change throughout the
length of the programme.
• The success criteria are key measurements which, when achieved, are
indicative of whether the task/project/programme has accomplished
what it was set out to do (the stated objectives and benefits). These are
160
Benefits management
APPROACH
The key steps in an effective benefits management approach begin before
the programme is initiated and continue throughout the lifecycle of the
programme and even beyond it.
• Initial planning for how the benefits will be delivered. The programme
and project business cases should describe how the organisation wishes
to manage and achieve benefits. This should include key benefits state-
ments and stakeholder analysis, benefit models, the benefits register and
schedule for delivery, and alignment with other programmes or projects
and the business case. Structuring the phasing of the projects and ben-
efits delivery should aim to maximise the speed of delivery of benefits
while taking into account resource constraints and risks.
• Benefits identification and definition. For each programme, the bene-
fits must be tied back to the overall strategic business objectives. The
needs and expectations of the stakeholders, which may not be explicit in
the programme definition, must be understood and defined. This
involves assessing what the programme outputs will actually mean in
business terms, understanding their dependencies and linkages, and
prioritising them using appropriate measures.
• Realising and tracking benefits. A process for developing detailed action
plans for the delivery of benefits should be developed. The progress against
the benefits realisation plan should be reviewed throughout the
programme lifecycle. This should continue after the delivery of the usual
project deliverables and post implementation organisation changes.
161
EPM essentials
Key steps
Plan and structure benefits management plan
The benefits management process needs to be anchored to the vision and
strategic objectives of the organisation. A vision statement for the pro-
gramme should be produced to describe how the implementation of the
programme will contribute to the achievement of these objectives.
For each programme, an appropriate benefits management strategy should
be framed, to answer the following questions:
• Why is the programme being undertaken and how does it align to the
vision and strategic objectives?
• What are the anticipated business improvements from the programme?
• Can these be quantified and is there a financial value?
• Who should be responsible for delivery of each benefit or improvement?
• What changes are needed to obtain it?
• Who will be affected by the changes?
• How can the benefits be achieved?
• When can the changes be implemented?
162
Grow revenue
Gather and Manage Manage
manage brands customers
knowledge Grow Acquire and
contribution retain profitable Sell
per customer customers product
Deliver Deliver
brand customer
message comms
Availability dimension
Develop
Plan and
Manage Increase ideas
execute
categories distribution Implement
promotions
ideas
Develop and
Demand dimension launch new
concepts
Assure
quality and Shareholder Introduce
Grow brands
safety value brands
Maximise consumer Optimise
demand portfolio Acquire and
integrate
Reduce cost Maximise the brands Manage assets
bottom line Operational and risk
effectiveness
164
Benefits management
165
EPM essentials
Establish baseline
Establishing a baseline involves collating key organisational, financial and
operational metrics against which improvements can be measured objec-
tively, and the establishment of a control tool or mechanism for managing
changes to costs and benefits through the implementation.
Key activities and tasks to establish the baseline are:
Where baseline data is not available, an initial programme phase for collec-
tion of data, with a checkpoint for authorisation to proceed after it is
collected, should be considered.
166
Benefits management
Prioritise benefits
A key input to programme planning will be the prioritisation of benefits
delivery. For example, proof of early benefits may be essential to secure
continued programme funding, even though delivering early benefits may
have a higher cost than a programme approach that defers them. Similarly,
programme activities that relate to benefits impacting business areas or
objectives that are subject to change may be scheduled for later in the
programme.
Prioritisation of benefits should be a structured process that compares a
number of options, or analyses one option based on the benefits and the like-
lihood of realisation. Benefits should be analysed according to a number of
criteria, typically including:
The aim of this analysis is to get the best pace of programme, taking into
account the investment needed and resistance/acceptance to change.
167
EPM essentials
latter may be relevant within this timescale, or may only begin after the
programme has formally delivered.
Tracking and reporting on the likelihood and achievability of benefits
requires more than reporting on the status of programme delivery; it needs
to include the influence of factors external to the programme on the bene-
fits that are predicted. This reporting should be regular and periodic, though
generally less frequent than programme status reporting. It requires revis-
iting the business case, having an understanding and familiarity with those
factors and initiatives that will impact the anticipated benefits, and applying
analysis and reporting skills. The output from the process will feed into the
benefits review and evaluation.
Tracking and reporting actual benefits realised may take place while the
programme is still in the delivery phase, or may commence after delivery. In
either case, giving responsibility for tracking and reporting actual benefits to
the business unit impacted yields a number of benefits. This approach
encourages ownership of the solution and associated benefits within the rel-
evant business area, reduces the risk of ‘optimistic’ reporting from within the
programme delivery team, and enables the benefits reporting to be assimi-
lated within regular management reporting. Where the programme is still in
the delivery phase and actual benefits are being measured, a feedback loop
mechanism to programme planning needs to be in place to ensure variance
from expected results can be used as an input to programme planning.
168
Benefits management
sudden
incremental
transient
Time/effort
potential ambiguity between tasks for the delivery team, and tasks for the
operational business. Moreover, as alluded to above, there is a benefit in
recognising the difference between a delivery capability, and a capability that
seeks to assess whether that delivery has resulted in the intended benefits.
This is not to say that the benefits management process needs to be run by
individuals outside the programme delivery function, in a checking or
auditing capacity; only that the different roles and behaviours required must
be recognised even if they are to be enacted by the same individuals.
Key roles that are required for successful benefits management are
described below.
169
EPM essentials
Sponsor
As the champion and ultimate owner of the programme and associated business
case, the sponsor must look beyond delivery of the programme to delivery of the
associated benefits. The sponsor’s role in scope setting and issue resolution must
be informed by the likely impact on the programme benefits. The sponsor must
also exercise leadership in the communication of the anticipated benefits, and the
required ‘benefits focus’ from the programme delivery and operational teams.
Programme manager
The programme manager is a vital role within the benefits management frame-
work, because he or she will be responsible for flexing, amending and fine
tuning the programme plan in response to the outputs of the benefits manage-
ment process. The programme manager will work closely with the business
benefits manager, since the analysis of programme status with regard to likely
achievement of benefits will require the input of both. As part of programme
delivery, the programme manager is responsible for ensuring the stakeholder
management and communication mechanisms are in place to facilitate
continued buy-in to the programme through a focus on business benefits.
170
Benefits management
a means to an end. Benefits management helps ensure that the best portfolio
of projects to meet the strategic objectives of the business can be selected and
maintained. Structured benefits management is thus a vital navigational aid
on the journey to achieving strategic objectives.
Benefits management addresses the risk of operational areas failing to
commit to the benefits, by involving key stakeholders from these areas
throughout the process. This in turn reduces the likelihood of unrealis-
tic benefits being forecast at programme inception in a desire to secure
investment. In addition, benefits management lends the ability to fine
tune, replan or even abandon programmes that do not look as though
they will achieve sufficient benefit. As projects and programmes become
an increasing part of many business endeavours, benefits management
provides a key input to the learning organisation, helping build a knowl-
edge base of the characteristics of programmes that deliver sustained
business benefits.
To increase the likelihood of gaining the value from structured benefits
management, the following can act as an essential checklist.
171
EPM essentials
Manage expectations
Do not assume that all stakeholders will be as committed to benefits man-
agement and realisation as the programme sponsor and team. Stakeholder
management and ongoing two-way communication of anticipated and
achieved benefits are vital if benefits management is to be accepted
throughout the enterprise.
SUMMARY
Benefits realisation is a structured, repeatable process applied to corporate
initiatives to maximise the likelihood of achieving the expected business
benefits. Benefits management includes:
172
Benefits management
173
13 Managing suppliers
INTRODUCTION
It is rare for any one organisation to possess all the people it needs to deliver
a programme. This is particularly the case when a programme brings
together information technology (IT), processes and organisational changes
to achieve an overall strategic business imperative. The larger the IT element,
the more likely it is that the programme will need to bring together a multi-
tude of internal organisations and external service providers (ESPs). IT-heavy
programmes tend to have the most common requirement for significant
involvement of multiple ESPs – very few organisations have all the skills,
experience and resources required to deliver a large and complex IT solution
for an overall strategic business change.
It is one thing delivering a programme involving multiple internal organ-
isations, with the usual conflicting priorities, organisational boundaries,
internal politics and ‘history’. When it comes to working with external
providers, particularly multiple ESPs, in a business change programme with
tight commercial and delivery demands, there are a huge number of new
challenges for the programme team to understand and manage. These chal-
lenges arise from differences in style, cultural, contractual and commercial
pressures, as well as more familiar problems such as coordination and issue
resolution.
In this chapter, we consider the practical approaches that programme
leaders should adopt when managing suppliers in a complex, integrated and
IT-heavy programme. We consider the lifecycle of supplier engagement from
initial sourcing strategies through to managing deliverables and post-launch
support. The context for this chapter is complex and integrated business pro-
grammes with a significant element of IT delivery, concentrating mainly on
the IT suppliers. These programmes tend to be most complex from a pro-
gramme management perspective, and also have most likelihood of going
wrong.
We will follow through a recently completed programme that involved
many internal and external IT service providers to deliver a new online
Internet business for an existing global travel and leisure company. The
Solution Build Stream of this programme involved 22 separate service
providers working over 18 months. In this chapter we will use this pro-
174
Managing suppliers
• Recognise and accept capability gaps in your own organisation and for-
mulate approaches on how to fill the gaps and the type of ESPs you will
engage.
• Contract in the right way. This includes commercial/legal consideration,
solution design and programme processes.
• Integrate everyone into one united programme team with shared
understanding of key processes, tools and working methods.
• Manage and behave as an integrated team covering business, process
and IT.
• Clearly understand cross-ESP issues, risks and changes, and actively
micro-manage to resolve them before they become showstopper issues.
Before we explore these topics in detail, let us provide you with an overview
of the case study.
175
EPM essentials
The technical solution for Mytravel.com contained five major integrated sub-
systems.
These subsystems and related components (such as content feeds, testing and
systems management) were designed and delivered by 22 different external
service providers.
• Use your own people and potentially supplement with specialist contract
or secondment staff where gaps exist in your own capabilities or avail-
ability. This approach keeps most of the programme activity internal to
the organisation, helping with post-programme support and increased
business integration, and builds programme delivery capability within
the organisation. This approach is similar to the in-sourcing approach
adopted by some organisations for their IT.
• Appoint a single supplier to undertake all of the work packages. The
appointed supplier may engage the services of other suppliers to deliver
its contractual commitments. This approach is similar to an outsourcing
arrangement. This type of arrangement has been common for some large
and complex programmes, particularly in the public sector, where a
prime supplier is appointed to deliver the overall programme.
• Appoint a series of suppliers based on the ‘best of breed’ approach, where
the overall programme is parcelled up into a series of packages or work
streams, and suppliers contract to deliver one or more of them. This
arrangement is similar to selective sourcing, whereby a supplier is engaged
based on the unique specialist expertise it brings to the programme.
176
Managing suppliers
This book does not focus on offshore suppliers: an entire book could be
written about this subject alone. The key point is that a selective sourcing
strategy should consider the use of an offshore supplier, particularly for the
IT element of the overall solution. The more traditional professional
services organisations can then focus on the business and process pieces
and the support for the programme management team.
177
EPM essentials
178
Managing suppliers
As a result of this planning phase, the programme team was confidently able
to define its resource needs from the internal business and IT organisations
as well as each supplier. Each supplier was then able to contract with the right
understanding of its commitments.
179
EPM essentials
180
Managing suppliers
181
EPM essentials
• Each supplier team has its own culture, approach and processes. No two
suppliers are the same.
• The legal and contractual frameworks often prevent openness and flexi-
bility for the greater good.
• There are individual capabilities, styles and positional jockeying, as is
often the case on any project.
So what can you do? This is where the programme leader and programme
office can make a major difference.
Induction role
The programme team should always have on hand a current pack of infor-
mation for introducing new people into the programme. This should detail
the structure of the programme, the teams and key individuals, the various
programme processes, current status and forward plans. This pack is critical
not just at the start of the programme, but also during delivery. For example,
on Mytravel the programme started with around 40 people and added an
average of 10 people each month, reaching something like 150 people
directly involved and some additional 30 to 50 with minor roles or interests.
The programme induction pack served as a key tool for delivering a consis-
tent picture of the programme and its forward plans. The programme team
also encouraged the individual suppliers to use the pack as they brought in
their new people behind the scenes.
182
Managing suppliers
a long period of time, the strengths and weakness of each individual should
be understood, and development encouraged. This will not directly support
the delivery of the programme, but it makes the process a positive and devel-
opmental one for the individuals involved. This may appear to conflict with
the contractual arrangements, but without it the contract will become a
stumbling block to the success of the programme, which ultimately depends
on the performance of individuals in their specific roles.
Within Mytravel, the programme team took several steps to promote this
kind of behaviour:
• It built on role models and good examples. The team often made a small
positive contribution or success into something very big, and then used
it as an example of individual behaviour to encourage others. As an
example, the way the wider team worked together to agree the web page
design was highlighted to others.
• It supported supplier team leaders with facilitating key meetings and
workshops. This is a skill often lacking among very technical people, but
key to engaging with a wide range of business and IT people.
• It provided formal feedback directly to individuals and their leaders,
around specific development needs or areas to improve in the context of
the programme.
Even with these processes and standards in place, some suppliers will fail to
deliver. For example, on Mytravel one supplier was contracted to deliver a
solution design document (SDD) for the content management engine. The
structure and content of their document was significantly below required
standards because it had failed to follow the programme guidelines. As a
result the users, sponsor and programme team all started to lose confidence
in the supplier’s ability to understand the requirements and deliver the
183
EPM essentials
The solution architect should be the custodian of the detailed blueprint that
each supplier is meant to be delivering against. This is a critical role. While
the programme manager owns the delivery processes, there need to be indi-
viduals on the programme team who own and can resolve the
solution-related issues, be these technical, infrastructure, data, processes or
business.
The basic premise for the programme team should be that the individual
supplier teams will be focusing on their specific component of the solution,
and pushing as much as possible onto other suppliers. The role of the solu-
tion architect is to focus each supplier’s solutions to achieve an overall
integration. Again, this will be helped tremendously if the contract has been
set up with a degree of flexibility.
In the case of Mytravel, a key element of the solution was the interface
between the content management solution being delivered by one supplier
and the Broadvision subsystem being delivered by another supplier. The ini-
tial interface was defined at a high level during the early phase of the
programme. As is often the case, the devil is in the detail! The mapping logic
in the interface can only be done at one end or the other. Once the pro-
gramme reached the implementation stage, there was significant friction
between the two suppliers. Each supplier was pushing the other to write the
logic. The role of the programme team was critical. The solution architect
micro-managed each issue, and worked in detail with each supplier through
negotiation and compromises. The programme solution architect was able to
find and build on a sufficient basis to move each supplier in different areas to
deliver the overall solution. Looking back, it would have been better to con-
tract with one supplier to perform the intelligent processing, and the other
to act as the dumb recipient/sender of data.
184
Managing suppliers
Architects, architects …
They say that everything is created twice, initially on paper (such as an architect
creates the plan for a house) and then in real life (as a builder and project manager
build the house). It is important for the programme to pull together technical
representatives from each major supplier into a technical design authority (TDA)
to make decisions and resolve issues around the overall solution. The TDA
should also include the overall solution architect from the programme team.
185
EPM essentials
Change is also a difficult subject: a change from one supplier may impact
timescales and costs for another supplier. It is also usually an emotive subject.
A clear and robust process coupled with programme management leadership
will help.
186
Managing suppliers
supplier deliverables will be much more difficult and costly to fix during
integration testing.
We have come across two effective techniques for managing programme-
level issues with suppliers:
187
EPM essentials
If the programme management has done a good job, then the supplier team
will be working and behaving as part of one overall team. However, back at
base, there will be pressures to manage tightly to contract, look for oppor-
tunities for additional revenue through scope changes, and at the same time
manage any internal delivery or people-related problems at arm’s length
from the programme leadership. The question is, how do you manage in this
environment?
The programme leader needs to be able both to manage the contract and to
operate with a team mind-set. This is a subtle area: getting it wrong can cause
all sorts of issues. Getting it right will help smooth the path delivery.
SUMMARY
In this chapter, we have outlined a number of approaches to working with
suppliers as part of a large integrated programme. In summary, the key to
successful engagement of suppliers is to balance the team and contractual
188
Managing suppliers
management with a focus on both the delivery processes and the final
solution. We recommend programme leaders and teams ensure they
address the following areas in any programmes involving one or more
suppliers:
189
14 Building a communications
capability
INTRODUCTION
Consider for a moment these recent business trends:
These trends mean that today’s organisations are spending more money, more
often and on bigger programmes. You have probably had some level of involve-
ment in these initiatives, perhaps as a project manager or as a recipient of the
change. However, greater experience with change may not always necessarily
mean that you are better able to deal with it and deliver maximum benefits.
As discussed in earlier chapters, a startling number of programmes still fail
to deliver the expected value. They go over budget and over time. Probable
reasons for this are:
190
Building a communications capability
an
ge
ar
mm
ch
ite
ur
e
ite
191
EPM essentials
Organisational benefits
• Provides clarity around communication roles and responsibilities.
• Contributes toward developing appropriate levels of commitment to the
programme.
192
Building a communications capability
Individual benefits
• Prepares and manages expectations about the upcoming changes.
• Facilitates a sense of community.
• Promotes morale and feeling of value.
• Links management to employees.
• Builds buy-in and ownership for change.
• Helps people understand how they fit into the change, are impacted by
the change and what they need to do to contribute to the change.
The rest of the chapter will show how these types of benefits can be obtained
by developing a programme communications capability.
You may hear this referred to as the ‘resistance pyramid’. Within your
company, different people will be at different states, or levels, of the pyramid.
In fact, they may be in more than one state at the same time. Programme
193
EPM essentials
Not
willing
Not able
Not knowing
194
Building a communications capability
At different points in the programme, you will need to initiate different types
of communications activities, although usually more than one type in par-
allel. Bear in mind, however, that people within your organisation are likely
195
EPM essentials
STAGES
Unawareness
to awareness Understanding Try-out Adoption Internalisation
to be at different stages of the change process at any one time. Even people
within one audience group may be at varying stages. As you will see later in
this chapter, it is important to focus on both general and individual face-to-
face communications to address this issue.
As we move through the remainder of the chapter, keep two concepts in
mind: the resistance pyramid (responding to resistance issues) and the
change acceptance process (proactively building commitment). Building
these concepts into your communications approach will help you deliver
meaningful and practical communications.
196
Building a communications capability
will find helpful. In addition, we include some examples to bring the ideas
to life: a merger of two companies, a technology implementation and a
customer-focused brand re-launch. To achieve these outcomes, this chapter
will guide you through the process shown in Figure 14.4.
Build/access the
necessary infrastructure
197
EPM essentials
Once you have a solid grasp of the programme strategy and goals, translate
these into the high-level communication requirements:
These questions are designed to provide the initial direction; the answers
will be refined later. Moreover, the answers to these questions are very situ-
ational. They depend on the nature of the programme you are undertak-
ing and the context of your business. For example, Table 14.1 lists some
priorities identified by three different programmes.
Once the high-level objectives and priorities have been defined, consider
the next set of questions:
What will be the benefits to the programme and the business if these
objectives are achieved?
What issues will be critical to the success of programme communication?
What are the existing barriers that programme communication must
overcome?
The answers to these questions will form the opening section in the pro-
gramme communications strategy document. You will want to revisit and
198
Building a communications capability
review these answers once you have analysed the detailed communication
needs of the business.
You should of course create a document that works for you and your busi-
ness, but as a starting point you may want to reproduce each of these section
headings in your own document.
For example, when one of our clients undertook a brand relaunch, some of
their communication guiding principles included:
199
EPM essentials
Your communication principles might be quite different from the above, per-
haps more general or more detailed. The critical step is to define those that
make the most sense for the programme and business.
Who are the stakeholders of this programme, both internal and external
to your business?
Who are the audiences that will be impacted, both internal and external
to your business?
Your two lists might be drawn from the following, but remember to be as
specific as you can (naming names where possible).
• programme management
• programme team members
• board and senior executives
• middle management
200
Building a communications capability
• team leaders
• employees (usually distinguished by function)
• trade union representatives
• suppliers
• customers
• shareholders
• city analysts
• government or regulatory bodies
• local community.
201
EPM essentials
Which one do you choose? Consider the advantages and disadvantages listed
in Table 14.3.
202
Building a communications capability
What are the current communications channels used within your business?
How effective are they?
Who in the organisation is responsible for developing communication
content, and managing activities and infrastructure?
What messages have already been communicated about the programme
– how have they been received?
Formal:
• steering committees
• annual general meetings
• team progress reports
• annual reports
• intranet/Internet
• general emails
• magazines and newsletters
• bulletin boards
• general memos
• general voicemails.
Face to face:
• team meetings
• one-on-one coaching sessions
• senior management briefing sessions
• training courses
• video conferences
• management walkarounds.
203
EPM essentials
Personal:
For a recent merger programme, we helped our client to populate the simple
matrix shown in Table 14.4. You may find it helpful to capture this informa-
tion in a similar way. Once the assessment is complete, validate the
information with people from all levels within the business. These meetings
can also serve as an opportunity to elicit information about the hot topics
within the business.
Ultimately, you need to decide the extent to which you can use the
existing communications infrastructure to meet the programme needs.
204
Building a communications capability
Also, based on our experience it appears that the greater the degree of
personal change expected, the better people respond to face-to-face and
personal communications. Build these considerations into the plan by
looking for methods that involve one-on-one, personalised interaction.
To answer this question, refer back to your objectives, priorities and guide-
lines as well as the stakeholder and audience assessment. For example, during
a recent merger of two multinational businesses, the priorities of the com-
munications plan were to communicate the leadership structure quickly, deal
with the ‘Have I got a job?’ and ‘What is my role?’ questions, and share the
future strategy and business priorities. As a result, the communications team
identified key messages that would need to be transmitted via the various
channels:
How do you know what the relevant messages are? In most cases, you
will use the knowledge of programme personnel and senior management
to identify the most appropriate messages. These messages must support
the programme’s vision and strategy, as well as being meaningful to the
recipients (see Figure 14.6, and your stakeholder and audience analysis
for ideas).
• Strategy of the firm and how we are working to • How we are, and should be, working together to
achieve this achieve the new strategy
• New value proposition and resultant action plan • Networking opportunities
Performance Aspirational/motivational
• Wins and successes in the marketplace • Why this is a great place to work
• Performance against plan and utilisation figures • Why you should want to stay with the firm
Marketplace People
205
EPM essentials
Consider language and style use. The language used is one of the most pow-
erful factors in whether people understand the message or not. As a general
rule, keep it simple.
A useful tip is to get someone from the intended audience to review each
communications piece before it is published. Opportunities for this will
depend on the content and confidentiality of the message. This is a good
technique for weeding out any jargon and ensuring the communication
messages are explained in a way that can be understood by the target
audience.
206
Building a communications capability
How will you identify if the sponsors and executives are committed to
the programme’s objectives?
What mechanisms can you use to determine whether the communication
strategy is achieving the programme’s objectives?
How will you ensure that objectives are achieved and the working
philosophy is adhered to?
207
EPM essentials
Build/access the
Message
necessary infrastructure
What messages are needed:
Deliver the communications
strategy and plan recommended messages
Review and improve the that need to be communi-
communication strategy and plan
cated to the audiences, and
the purpose for providing
Figure 14.7 Creating a programme them with this information.
communications plan
Desired outcome
Why these are needed: the desired result we hope to achieve by sending the
communication.
Audience(s)
Who needs information: specific audiences being impacted by the business
transformation.
Event
Where the message is going to be communicated: the event that gives the
sender the opportunity to communicate the required message.
208
Building a communications capability
Timeframe
When each message should be delivered: recommended timeframe for
implementing each communication vehicle during the implementation.
Method
How these messages can be delivered most effectively: recommended com-
munication vehicles for delivering these messages to the appropriate
audiences.
Feedback mechanism
How the information is to be gathered: the most effective way to gather
feedback from the audience regarding the communicated message.
Developer
Who will develop the message: specific person(s) responsible within your
business for preparing the message and the material needed to present the
message.
Sender
Who should send each message: specific person(s) most effective in commu-
nicating each message to the appropriate audiences.
The plan can take many forms; however a spreadsheet matrix or project plan
is probably the easiest to manage.
At this point, the strategy and planning phases – often the most time-
intensive phases – should be complete. The next three phases are simply
about turning those plans into reality. This involves working out the
resources and infrastructure needed, executing the plan, and reviewing and
improving.
209
EPM essentials
210
Building a communications capability
211
EPM essentials
Communication strategy
• Segment and assess the impacted change on audiences and stakeholders.
• Conduct a communications audit.
• Develop and document an overall communications strategy for each
phase of the change process.
• Assess the effectiveness of the communication strategy on a regular basis.
• Assign somebody to be responsible for the overall execution of the
strategy.
Communications plan
• Be clear on what messages to send, when.
• Increase message credibility by using the appropriate sender and
involving leadership.
212
Building a communications capability
• Use the most effective methods to convey messages: this often means
using existing channels where buy-in already exists.
• Set up effective feedback mechanisms to help the sender understand
whether the message was received and how it was accepted.
• Document and regularly update your plan.
Communications infrastructure
• Ensure roles and responsibilities are clearly defined.
• Utilise existing communications resources where possible.
• Link to external communications.
• Consider using an editorial team.
Delivery
• Mobilise the communication team with the necessary skills and Key
Performance Indicators (KPIs).
• Develop communication content based on previous analyses of stake-
holder and audience needs, particularly the stages of change acceptance
and resistance.
• Ensure that the communications plan is flexible enough to cope with
future changes.
SUMMARY
Effective programme communications is about communicating with the
right people at the right time in order to secure their involvement and buy-
in to the programme. It means understanding what is important to those
who have an influence over the initiative, and interacting with them in an
engaging and effective way. Securing their buy-in can help the programme to
achieve its objectives and deliver the intended benefits.
But achieving this buy-in requires careful thought as to the most appro-
priate communications strategy, plan and infrastructure for the programme
at hand. It means establishing communication mechanisms that are relevant
to the programme, rather than just using ‘business as usual’ processes. The
high-level process outlined in this chapter can help you achieve this:
213
EPM essentials
Company background
In 2000, Preussag AG bought Thomson Travel Group, Thomson being the
largest travel group in the UK. In 2002 Preussag AG formally changed its
name to TUI AG, and Thomson Travel Group became TUI Northern Europe.
The UK-based operation, TUI UK, has remained the largest travel and tourism
company in the UK and is the name behind many popular brands. Its retailers
include Lunn Poly, Travel House and Manchester Flights. It also owns tour
operators including Thomson Holidays and the Specialist Holidays Group,
with brands such as Magic, Crystal, Thomson and Austravel. TUI UK had
revenues of £3270 million in 2001 and over 10,000 employees UK-wide.
Programme background
The travel industry has been hard hit in recent times, with significant world
events sending holiday bookings on a downward spiral. As profit margins
214
Building a communications capability
have been eroded, travel organisations have been forced to reduce the overall
costs of their business, with a particular emphasis on reducing back-office
infrastructure costs.
Deloitte worked with TUI Northern Europe’s senior management to
transform the finance organisation, enabling it to reduce costs across the
business and support greater business consolidation. The initiative was called
Project Enterprise. Achieving these strategic objectives involved:
215
EPM essentials
• Target senior managers within the finance team to obtain their buy-
in and support to ensure effective management of the finance teams
during the project.
• Minimise any negative press coverage that may arise as a result of fol-
lowing Project Enterprise recommendations (for example, moving
to SSC model and corresponding redundancies).
Figure 14.11 helped explain the principles behind the Project Enterprise
communications strategy:
honest and
Visible
• Leadership endorsed and Open, Varied media
Most appropriate
ly mmunication
c o
supported
• Delivered by line time channel e.g.
• Face to face meetings
management/senior • Roadshows
stakeholders for • Electronic (email
maximum impact and CLICK intranet)
Involvement
• Business design • Memos and
workshops newsletters
• CLICK intranet Q & A
database
• Local/regional meetings
focus groups
and surveys
Direct
• Relevant Clear vision
to audiences and message
• Answers “What’s • Accurate
in it for me?” for all H ig n • Make sense to the
recipients h impact content and desig specific audience
• Senior stakeholders to • Interesting and make it
share relevant experience R egular feedback ‘real’ for TUI employees
216
Phase one: model office Phase two: design and build Phase three: pilot implementation Phase four: future implementation
Launch SSC - What does Launch news-
project to hound monthly
Launch SSC
Communicate it mean? Poster
Finance campaign update newsletter
decision to TUI
UK finance
employees Roadshow
for business
to sites to
Update to Launch explain
finance from employees changes
project feedback SSC customer SSC customer SSC customer SSC customer
sponsor Communicate scheme
CCS decision site visits site visits site visits site visits
Recruit TUI
takers TUI talker activities
Involvement and
training
updates
Regular use of All impacted
communication activities
business employees
communication Recruitment activities Business
channels training
Senior team
aware of
project n enterprise
Finance involvement i
Initial
audience Prepare newsletter communications
assessment
Carry out current Plan and develop cascade materials
communication Plan project
channel visit launch event
Communicate changes to internal
and external customers and suppliers
Set up communications
infrastructure and roles Plan launch of feedback
Develop and manage site visits for SSC customers (internal and external)
and support mechanism Run involvement groups for
Develop feedback for finance employees transferring finance employees
mechanisms Develop
Establish Develop detailed communication
Develop TUI briefing
and involvement plan talker approach packs for Develop TUI talkers meeting packs (notes; posters; handouts)
involvement and
communication • Timing TUI talkers
team and agree • Message
• Audience
roles • Mechanism Ongoing gathering of feedback and communication plan revision to meet needs (event feedback/surveys/unsolicited feedback)
• Feedback
Supporting activities
• Sender
Plan new SSC launch event
Prepare poster Design and develop
campaign roadshow for business
Prepare stakeholder updates and circulate/attend meetings
Prepare press release Statutory consultation
Table 14.5 was used within the programme to help distinguish between the
Steering Committee and Stakeholder Board.
In addition, Project Enterprise effectively leveraged existing TUI resources
to support its communication efforts. The team:
218
Building a communications capability
219
15 The enterprise programme
management office
INTRODUCTION
Leading enterprises today have established and mature organisation
structures which reflect the core skills and capabilities the organisation
possesses, and are focused
on efficiently delivering the
Strategic
initiatives
core products or services
Strategic that the organisation exists
management
to produce. In this book we
Benefits
Strategic portfolio
have discussed at length the
realisation
management idea that the core capabili-
Ch
Pro
an
ar
mm
ch
ur
e
Outputs
isations to manage complex
Project management
programmes of change.
This chapter examines
Figure 15.1 The enterprise programme the role, benefit and value
management framework of an enterprise-wide pro-
gramme management office
(EPMO) in providing, maintaining and developing an organisation’s pro-
gramme management capability and infrastructure. In using the term EPMO
we are referring to an enterprise programme management function and capa-
bility. This deliberately goes beyond the traditionally accepted definition of a
programme management office (PMO).
An EPMO enables organisations to develop and integrate the essential
disciplines described in the PM framework.
220
The enterprise programme management office
Programme architecture
An EPMO is an organisational function which represents the portfolio of
change programmes with authority and voice at the most senior levels of an
organisation’s leadership. The EPMO is also responsible for establishing the
systems and infrastructure that the organisation needs to be able to deliver
change programmes consistently and efficiently.
Change architecture
The EPMO function maintains a ‘big picture’ perspective of all change activ-
ity in an organisation, and uses it to plan and manage the implementation and
acceptance of change within the organisation.
221
EPM essentials
The degree to which the modern PMO has arisen out of relatively new and
project-intensive business functions, such as IT, cannot be overstated. The
pressures for project speed and success upon such functions have supported
the evolution of the PMO concept.
In summary, modern PMOs have typically arisen either to support specific
temporary programmes or to support specific project-intensive functions. In
both scenarios the PMO represents a tactical investment (or overhead) put
in place to support delivery of a specific set of results. In neither case has the
PMO arisen from a need to support a sustained strategic advantage.
222
The enterprise programme management office
223
EPM essentials
In short, the traditional PMO may enable the exceptional delivery of the
wrong project. and in the process, miss critical dependencies and fail to
deliver the expected benefits.
224
The enterprise programme management office
• People get pulled into project roles from the regular business and end up
losing the career and personnel infrastructure that they had. This can act
225
EPM essentials
226
Consumer
products
manufacturer -
executive
Warehousing Treasury
and distribution
Facilities
management
Programmes require the development of new and unique ideas into new
and unique products, services and capabilities. Delivering programmes
involves undertaking unfamiliar and exploratory processes. It should be no
surprise that major programme failures are so common, when the area of
organisational activity that represents the highest risk, traditionally operates
with the weakest organisational representation.
The modified organisation chart in Figure 15.4 illustrates (shaded)
how a EPMO would fit into the existing top-level organisation structure.
The EPMO is responsible for providing the following four programme
management capabilities to the enterprise.
These processes are often seen as the domain of business strategists and not
programme managers. However, a business strategy (other than a do-
nothing one) is delivered through execution of projects and business change
programmes. The closeness between strategy and programme planning
cannot be overstated. A strategic programme director and strategy director
are likely to need to work very closely together.
228
Consumer
products
manufacturer -
executive
Product Operations Human resources Strategic Finance directorate Information Other corporate
development directorate directorate programme technology
directorate directorate directorate
Accounting Legal
Marketing and sales Planning and and reporting
New technology recruitment Strategic portfolio Applications
research Real estate
management Accounts payable/
Planning and property
Training and accounts Infrastructure
Market research development Strategic retrievable and comms
Purchasing resource Public relations
planning and press office
New product Performance Contracts Support and
development Manufacturing management, and budgets disaster recovery
reward and Corporate
renumeration programme
Quality control Internal audit
infrastructure
Figure 15.4 Revised organisation structure for a consumer products manufacturing company
EPM essentials
Facilities
Legal
Enterprise
PMO
HR
IT
Finance
230
The enterprise programme management office
231
EPM essentials
232
The enterprise programme management office
Leadership
The role of a EPMO must have 100 per cent support from an organisa-
tion’s leadership. Once responsibility for the organisation’s portfolio has
been established with the PMO, leaders need to enforce and reinforce the
working of the EPMO. Acceptance of maverick pet projects, hidden agen-
das and non-standard working practices will undermine the authority of
the PMO.
233
EPM essentials
Managing
board
ABN-AMRO recently reviewed the strategy for the bank. The revised
strategy includes intentions to grow the business both by opening up new
markets and by broadening the bank’s offering to existing customers by cap-
italising on existing relationships within other SBUs. The strategy also
addresses a need for the bank to operate more efficiently and to exploit
opportunities for synergy between the SBUs.
ABN-AMRO found it needed to address one of the most common prob-
lems facing organisations about to embark on implementing a strategic
programme: how to get business functions which traditionally operate as
silos to work effectively together, while balancing demands with the need to
keep control of the everyday business.
Challenges
There were a number of obstacles that, if not addressed, would have
impaired ABN-AMRO’s ability to execute this strategy effectively.
234
The enterprise programme management office
• Previous synergy initiatives had been sponsored outside the SBUs. There
was therefore no accountability for success placed upon SBU leadership.
• There was a history of failed cross-SBU synergy initiatives. 75 per cent
of early initiatives had failed to deliver against expectations, and this
reinforced cynicism from within the SBUs.
• There was evidence that many early initiatives represented good ideas
which were not properly researched in terms of value to the business
versus cost. Hence there was a perception that the failure to deliver value
was partly attributable to choosing to do the wrong things, compounded
by a tendency to overestimate benefits while underestimating costs.
• Many of the common project and programme pitfalls regarding insuffi-
cient resources and inconsistent or ineffective project management were
also being experienced.
235
EPM essentials
The task force identified good practice around the bank, and existing project
and programme management support systems that had the potential to be
extended across the enterprise (in itself delivering synergies for the bank).
236
The enterprise programme management office
Main board
Board owner/
decision forum
Spaghetti/
council steering
group
Accountable
Task force SEVP SEVP SEVP SEVP
SBU delivery
teams
Projects
cies and reporting on costs and benefits. A key function of the Spaghetti
Council was to solve issues relating to inter-SBU working by managing
communications and ‘opening doors’.
Each initiative was assigned a sponsoring SEVP, who was made account-
able for the successful implementation of the initiative. This responsibility
was reflected in the SEVP’s contract and performance targets. The organisa-
tion model implemented was designed to ensure a line of report and visibility
between projects being delivered and the senior bodies responsible for
setting strategy and determining priorities.
• within scope
• materiality
• achievability
• level of interest.
237
6. Monitoring and
1. Opportunity 2. Analysis and 3. Business case 4. Planning, design 5. Build and
performance
identification evaluation development and architecture roll-out
measurement
Accountable SEVP
identified Rapid Task force Review by
pressure Spaghetti
? analysis Implementation
Potential tests Council
synergy OK OK
opportunity NO
One page Review by Spaghetti
Council and identification
OK Full business Funding
business
of an accountable SEVP case request
case where required
STOP
NO NO NO
Weak proposition and/or ‘orphan’ (no SEVP)
Outcomes
ABN-AMRO found that the organisation structures set up to support the
programme started to bridge gaps between the SBUs, both in terms of pro-
gramme effectiveness and also in broadening general understanding and
communication across the bank.
The commitment of SBU leadership has slowly but consistently risen
through demonstration of value from both the approach and the initiatives
themselves.
The establishment of the enterprise programme management structures
was itself a demonstration of the synergy strategy, and has helped make the
strategy understandable and accessible to those the bank are relying on to
deliver it.
239
Part III
Getting started
16 Introduction
In this section we have focused on how you could start to use some of the
ideas we have introduced in this book in a practical way in your organisation.
First, in Chapter 17 we introduce the enterprise programme management
capability check, based on the enterprise programme management frame-
work. The answers to the 60 questions will help you understand where to
focus to enhance your organisation’s capability.
In Chapter 18 we discuss issues relating to the different types of pro-
grammes organisations may be engaged in, and the priorities associated with
this context.
In the final Chapter 19 we share some practical hints for delivering pro-
grammes successfully, based on the experience of the authors and their
colleagues at Deloitte in managing large-scale programmes over many years.
243
17 Enterprise programme
management capability check
244
EPM capability check
245
Getting started
246
EPM capability check
247
Getting started
248
EPM capability check
249
Getting started
250
EPM capability check
251
Getting started
252
EPM capability check
253
Getting started
254
EPM capability check
255
Getting started
256
EPM capability check
YOUR COMMENTS
The following section provides an opportunity for you to write any com-
ments or thoughts about your company’s programme management
capability. Please write your comments in the section below.
End of questionnaire
257
18 Making sense of your current
situation: knowing where to
start
258
Making sense of your current situation
Unclear Clear
Approach
Enabling
Project 1 project 1
259
Getting started
Project 1 Outcome A
Exploratory programme:
Project 2 Outcome B
A series of
Project 3 Outcome C interdependent and
unrelated projects
Project 4 Outcome D
260
Making sense of your current situation
Common vision
Project 1 Outcome A
Expeditionary programme:
Project 2 Outcome B
A series of interdependent,
Project 3 Outcome C unrelated projects with
a common vision
Project 4 Outcome D
REORGANISATION
Wherever an organisation is starting from, it is vital that the programmes are
clearly related to delivering value aligned to the vision and strategic objec-
tives, and that there is a clear approach or path by which this will be achieved.
This means that an exploratory programme will evolve to an expeditionary
programme, as the vision and objectives are clarified, and may then transit to
an integrated programme. (See Figure 18.5.)
261
Getting started
Clear Integrated
Expeditionary
vision programme
programme
All projects and
programmes should
become part of an
integrated programme
clearly linked to delivering
the organisation’s vision
and strategic objectives
if value is to be created
in the most efficient way
Unclear Exploratory Movie from initiatives.
vision programme (rare)
Unclear Clear
approach approach
262
19 Practical steps for success
In the course of working with many clients across the globe, Deloitte is often
asked to review existing programmes and to articulate the reasons they are not
delivering the results that were anticipated. We have summarised our experi-
ence from a number of these situations to establish a set of practical sugges-
tions that could help to drive success in programmes. In this section, we outline
some practical considerations concerning strategic portfolio management,
programme architecture and programme delivery management.
263
Getting started
PROGRAMME ARCHITECTURE
Building the right balance of power
Many organisations are built along fairly traditional functional or business
unit lines, with fairly strong barriers between organisational units. This is a
reasonable organisational structure in a time of steady state, when the busi-
ness only needs to focus on delivering financial results for the current quarter
or fiscal year. However, most organisations are now faced with perpetual
change driven by the forces outlined above. However, companies have not
updated their organisation structures in response to the combined need
simultaneously to deliver financial results and drive business change. This can
lead to a number of potentially fatal issues for change programmes.
264
Practical steps for success
265
Getting started
266
Practical steps for success
This will encourage business buy-in to the plan, ensure that middle
management understands that senior management is very serious about
achieving success in this programme, and generate a much greater level of
certainty in the business case and in the plans that support it. This docu-
ment should then form the ‘guiding star’ of the programme, ensuring that
the rationale and reasoning behind the programme is robust and built on
solid foundations. This document can very easily be updated to reflect
changing circumstances in the marketplace that might justify fine-tuning
the plan at a future point.
267
Getting started
Managing suppliers
Most large programmes involve integrating the services, support and prod-
ucts of a number of third-party suppliers. Managing the inputs and
contributions of consultants, vendors and contractors is fundamental to the
success of programmes. Organisations often fail to get real value from their
268
Practical steps for success
Resource 1
Resource 2
Resource 3
Resource 4
Example RACI
Work item 1 R C C
Work item 5 A C R I
Work item 6 R C C A
269
Getting started
270
Practical steps for success
• progress reporting
• issues tracking
• risk management
• earned value analysis.
However, in our experience this is not done formally very often, and where
some of these policies are in place, they are often inadequate.
It is important, however, that processes and templates for reporting are
simple and easy to complete and that these processes create the minimum of
bureaucracy, and provide quality useful information to all those involved in
programmes.
Ensure that the business benefits of each project are achieved before
closing each project
When each project in the programme is closed, a formal assessment should
be carried out to ensure that the benefits of the project have been achieved,
and establish what actions need to be taken.
271
Getting started
272
Glossary
273
Glossary
274
Glossary
275
Glossary
276
Glossary
277
Glossary
278
Glossary
279
Glossary
280
Glossary
281
References and further reading
282
Index
283
Index
284
Index
285
Index
286
Index
287
Index
skills 48, 49, 50, 55, 73, 92, 107, 230, at ABN-AMRO 236–7
231, 253 appraisal 53, 249
matrix 53 building and development 15, 50,
software 100–4, 152, 222 52–3
see also individual programs/manu- charter 53, 281
facturers coordination of 32
Solution Build Stream 174–5 core programme 178
sourcing strategy 176–7 editorial 210–11
sponsor see champions including external suppliers within
staff, project 59 175
see also appraisal, teams induction pack 53, 281
stakeholders 8, 32, 72, 73, 90, 143, involvement 47
152, 159, 190–1, 195, 200–1, 248, joint working 210
252, 281 review meetings 53
board 218–19 roles within programme delivery
expectations and objectives 265 169–71
management 76–8, 281 room 180
standards 183–4, 221 structures 64
Standish Group 47 SWAT 187
steering group 61–2 TeamPlay 122–32
strategic technical design authority 185, 281
fit 25 technology 55
requirements 23 and Compaq 120–32
strategy 18–20, 24, 71, 205, 231, 245 telephones, mobile 96–94
business 71, 195, 205 templates 54, 115, 222, 249
change 71–4 tendering 40
driving programmes and projects testing 181
24, 70 user acceptance 127, 185
non-alignment with people and Thomson Travel Group see TUI
processes 18–19 time
translation 12, 21, 22–3, 281 to benefit 267
structure, organisational 56–9, 73, capture and reporting 103, 109
81–2, 145, 220, 225–9, 234, 237, to implement change 66, 72
239 scale for planning 28, 61, 263, 267
supporting business as usual 1, 7–8 tracking systems 103, 108, 161, 167–8
success criteria 160–1 training and development 80, 91, 114,
see also key performance indicators 127–8, 182–3, 195, 225–6, 248
suppliers 265 cost management 127–8
engagement plan for 177–80 transitions, individual 78
management of 33, 98–9, 174–89, see also change
268–9 Transport for London (TfL) 152–4
offshore 177 Transport Strategy for London 151
relationship issues 187–8, 270 travel business 175–87, 214–19
sourcing strategy 176–7, 230 TUI 214–19
systems see programme management Turnbull Report 138
systems
vendor management 39–40
T-Mobile UK 86–94 vision statement 162
Tandem Computer 121
task management 103, 108 Winfield, Jonathan 129–30
teams 133, 191, 212, 249–50, 265, 270 workshops 41, 52, 179, 183
288