0% found this document useful (1 vote)
326 views1 page

Project Responsible Matrix

This document outlines the responsibilities and roles for various positions on a construction project. It assigns responsibility levels from 1 to 4 for specific tasks to positions like the project manager, site manager, engineering manager, and others. Key responsibilities include daily site safety management, document distribution, issuing letters and reports, construction planning and scheduling, quality control, and non-conformance reporting. The matrix is intended to define position accountabilities to ensure effective project execution and management.

Uploaded by

li xian
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (1 vote)
326 views1 page

Project Responsible Matrix

This document outlines the responsibilities and roles for various positions on a construction project. It assigns responsibility levels from 1 to 4 for specific tasks to positions like the project manager, site manager, engineering manager, and others. Key responsibilities include daily site safety management, document distribution, issuing letters and reports, construction planning and scheduling, quality control, and non-conformance reporting. The matrix is intended to define position accountabilities to ensure effective project execution and management.

Uploaded by

li xian
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 1

Site Responsibility Matrix

Project Date Issued 2/15/2019


Project Manager Revision No. A

Legend:

Schedule Control-E&P
Cost Control Engineer
Construction Manager
Procurement Manager
Engineering Manager
1 Responsible

Commissioning Mgr

Schedule Control-C

Discipline Engineer

Document Control
2 Supports/Assitance

Quality Inspector
Control Manager

Warehouse Staff
Project Manager

QA/QC Manager

HSE Supervisor
Admin Manager

Contract Admin
3 Notified

HSE Manager
Site Manager
4 Approval

SN Task Description Responsible


1 Daily Site HSE Management 1
2 Site Docs Distribution
3 Issue Letters 1
4 Site Office and Dorm/Camp Admin management
5 Local Staff Work Management 1
6 Construction Execution Plan & Related Procedures 2
7 Pre-Comm&Commissioning Procedure 2
8 Site Organization Chart & Responsibility
9 Construction HSE Plan & Procedures
10 Construction Quality Plan & ITB 2
11 Construction Level III Schedule 2
12 Construction Progress Measurement & WBS
13 Discipline&Area Daily Report 1
14 Overall Construction Daily Report
15 Construction Weekly & Monthly Report
16 Issue NCR 2
17 Issue OSD Report 1
18 Verify Subcontractors Progress Payment 2
19 Approval of Subcontractors Progress Payment
20 Review & Approval Subcontractors Level IV Schedule 2
21 Updated&Tracking Overall Project Level III Schedule 2
22 Updated&Tracking Overall Construction Level III Schedule 2
23 Updated&Tracking Dedicate Schedule 2
24 Site Progress Pictures & Vedio
25 Review Subcontractors Submitted MS & Procedures 1
26 Collect Vendor Prints
27 Verify Vendor Prints 1
28 Design Change Status Log
29 TQ Status Log
30 Letter Status
31 Issue Site Procurement Request 1
32 Vendor Representative Request 1
33 Subcontractors Admin 2
34 Overall Plotplan Management
35 Weekly Coordination Meeting with Subcontractors 2
36 Weekly HSE Inspection and Meeting With Subcontractors
37 Weekly Quality Meeting With Subcontractors 2
38 Weekly Pre-comm & Commissioning Meeting 2
39 Quality Inspection As Per ITP 1
40 Daily Site Quality Inspection Patrol 1
41 Responsibility of Design Change or Site Change 1
42 Coordination of Subcontractors on Discipline Wise 1
43 Monitor and Coordinate Subcontarctors Daily Activities 1
44 Verify and Control Discipline Materials 1
45 Sign off Subcontractors Materterials Request Slip 1
46 Technical Review Together With Subcontractors 1
47 Joint Inspection of CHENGDA incoming EQ&Materials 1
48 Review & Approval Subcontractors Incoming Materials 1
49 Review Subcontractors Manpower&EQ Plan 2
50 Management of Vendor Representative 1
51 All Staff Time Sheet Record
52 Extra Work sheet 1
53