Power Sector Cerc Report
Power Sector Cerc Report
Power Sector Cerc Report
1. Default in payment of dues has been a major issue in power sector. The
Government of India has taken steps to resolve this issue by prescribing a
scheme for settlement of SEB dues by securitization through State Government
bonds guaranteed by RBI. In March, 2001 it was resolved in a conference of Chief
Ministers to set up an expert group to recommend a one time settlement of all
outstanding dues of CPSUs. On the recommendation of the expert group, a
scheme was brought about w.e.f. 17.04.02, to ensure timely payment of current
dues. The scheme provided for signing of Tripartite Agreement between the
Government of India, the respective State Governments of India and Reserve
Bank of India. This scheme had provisions for reduction in supply in case of non-
payment of dues of Central Public Sectors Undertakings (CPSU) or non-
maintenance of the required Letter of Credit by State Utilities. This scheme is
effective upto 31.10.2016.
2. The Commission, vide letter dated 16.12.1999, had directed CTU to forward the
procedure for regulation of power supply due to non-payment of dues. CTU, vide
letter dated 16.06.2000, forwarded draft generic procedure. The Commission vide
Order dated 21.06.2000, gave an interim approval for this procedure, to be
followed till the final approval of procedure after hearing of the interested parties.
This procedure was based on physical regulation by opening of transmission
lines/ICTs.
3. After hearing the interested parties, the Commission, vide Order dated
11.01.2002, have the final approval of the generic procedure for power supply
regulation on commercial grounds. The validity of this generic procedure had
been extended by the Commission from time to time. But it is felt that this
page1 of 4
mechanism should be specified through regulations instead of extending our
order repeatedly.
4. Though this procedure had taken care of technical as well as commercial aspects,
there were few inherent problems of physical regulation in this procedure. As
mentioned in the Order, it was extremely difficult to control power flow for the
purpose of curtailment of power supply to a specified beneficiary during the time
of regulation, in view of the fact that power would find an alternative path in the
integrated grid to the regulated entity. Further, the opening of lines/ICTs for the
purpose of regulation would had an impact on grid security..
5. A draft regulation on “Generic Procedure for Curtailment of Power Supply” was
issued by the Commission on 19.05.2005, seeking objections /suggestions
/comments of the stakeholders with the objective of formalizing the procedure
specified earlier. However, the regulation could not be finalised due to some
unresolved issues regarding physical regulation.
6. Meanwhile a committee constituted by Government of India in May,07, under
Chairmanship of Shri A.K. Khurana, AS, MoP had inter-alia given following
recommendation regarding provision for Payment Security Mechanism (PSM) in
Standard Bidding Documents relating to developing transmission lines through
tariff based competitive bidding:
“In case of default by the procurer of the transmission services i.e.
default in payment of transmission charges , a trigger point of default
can be defined in the Transmission Service Agreement (TSA) . A
provision can be incorporated in the TSA whereby ( once the trigger
point is reached) the procurer of the transmission service would
authorise the concerned RLDC for altering the schedule of despatch of
lowest cost power of the defaulting utility from Central Generating
Stations . The quantum of electricity to be rescheduled for dispatch wil
be equal to the amount of default of the transmission charge. The
electricity will then be dispatched to other utilities by the concerned
RLDC during the peak hours i.e 7 p.m. to 10 p.m. The price of
electricity rescheduled will be determined as per the Unscheduled Inter
page2 of 4
Change rate. If the amount so realized is more than the amount of
default of transmission charge then the excess will be credited to the
defaulting utility and amount equal to the default will be credited to the
Transmission Service Provider.”
page3 of 4
the procedure is simplified and would require less time for implementation in
comparison to the earlier procedure.
c. The regulation of power supply in case of non - payment of dues of the
Generator is proposed to be made effective, by reducing the drawl schedule
of the defaulting entity . This surplus power can be sold to other beneficiaries
or other buyers in market. In case no buyer is found then generation may be
reduced.
d. The regulation of power supply in case of non payment of dues of the
transmission company is proposed to be made effective, by reducing the
drawl schedule of the defaulting entity. This surplus power can be sold to
other beneficiaries or other buyers in market. The amount received from sale
of this power shall be use to pay the transmission company as first charge
basis and after payment of energy charges of generator , balance if any shall
be passed on to defaulting entity.
e. The commercial principles for settlement of the dues are prescribed in the
regulation, keeping in view the present power market scenario. In deficit
market condition the power can easily be sold to other buyer. Earlier, in non-
ABT regime this type of arrangement was not possible.
f. The proposed procedure would also be applicable for non-maintenance of
Letter of credit (LC) also, besides for non-payment of dues by the
beneficiaries in view of the provisions in Tripartite Agreement and
observations of the Hon’ble Appellate Tribunal of Electricity in order dated
28.04.2009 in Appeal No. 102 of 2008. The earlier procedure had provision
for regulation of power supply in case of non-payment of dues only. There
was no provision for regulation of power supply for non-maintenance of LC.
page4 of 4