Jadwal Audit: Menilai Produk Sesuai Dengan Undang-Undang, Peraturan Regulator, Dan Peraturan Kontrak

1. The document provides an audit schedule for PT. Calvary Abadi, a manufacturer of pre-cast concrete products located in Mojokerto, East Java. 2. The audit will be conducted from October 15-17, 2019 to assess the company's compliance with ISO 9001:2015 and ISO 14001:2015 standards. 3. A three person audit team led by Vera Marini as the lead auditor will audit various departments and processes over the three days, including management systems, production, purchasing, research and development, and quality control.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOC, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
76 views6 pages

Jadwal Audit: Menilai Produk Sesuai Dengan Undang-Undang, Peraturan Regulator, Dan Peraturan Kontrak

1. The document provides an audit schedule for PT. Calvary Abadi, a manufacturer of pre-cast concrete products located in Mojokerto, East Java. 2. The audit will be conducted from October 15-17, 2019 to assess the company's compliance with ISO 9001:2015 and ISO 14001:2015 standards. 3. A three person audit team led by Vera Marini as the lead auditor will audit various departments and processes over the three days, including management systems, production, purchasing, research and development, and quality control.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOC, PDF, TXT or read online on Scribd
You are on page 1/ 6

JADWAL AUDIT

PT. Global Inspeksi Sertifikasi

Nama Perusahaan PT. CALVARY ABADI


Alamat Perusahaan Dusun oto-oto, Desa Karangkuten, Kecamatan Gondong, Mojokerto Jawa Timur
Ruang lingkup Manufacture of article of concrete, cement, and plaster
(sesuai dengan NACE Code)
NACE Code C.23.6
Lingkup usaha spesifik Production of pre-cast concrete
(Deskripsi produk/jasa/proses yang
disertifikasi)
Standard sistem manajemen ISO9001:2015 dan ISO14001:2015
Objektif Audit Menilai kesesuaian produk dan sistem manajemen dengan kriteria standard
Menilai produk sesuai dengan undang-undang, peraturan regulator, dan peraturan kontrak
Menilai efektifitas dari sistem manajemen pelanggan dalam mencapai objektif yang telah ditentukan
Mengidentifikasi area yang dapat dilakukan perbaikan berkelanjutan dalam sistem manajemen pelanggan

FrM.9303/GIS-4
JADWAL AUDIT

PT. Global Inspeksi Sertifikasi

Jenis Audit Sertifikasi awal / Survailen / Re-Sertifikasi/ Perluasan *)


Tanggal Audit 15 – 17 Oktober 2019
Tim Audit Jabatan
1. Vera Marini 1. Lead auditor
2. Azil Awaluddin 2. Auditor
3. Irwan Mardiansyah 3. Auditor

Department /
Date Time Audit Clause Auditee Location Auditor
Division / Area
15 Oktober 09:00 – 09:30 All Department Opening Meeting All Personnel Office All
2019
09:30-10:00 All Department Factory visit All personnel Factory All
4.1- Understanding the organization and its context. Office VM
4.2- Understanding the needs and expectations of
interested parties.
4.3- Determining the scope of the environmental
management system.
4.4- Environmental management system.
5.1- Leadership and commitment.
5.2-Environmental policy.
5.3-Organizational roles, responsibilities and authorities.
10:00-11:00 Top Management 6.1-Actions to address risks and opportunities.
6.1.1-General.
6.1.2-Environmental aspects.
6.1.3-Compliance obligations.
6.1.4-Planning action.
6.2.1-Environmental objectives.
6.2.2-Planning actions to achieve nvironmental
objectives.

9.3-Management review.

FrM.9303/GIS-4
JADWAL AUDIT

PT. Global Inspeksi Sertifikasi

9.2-Internal audit. Office AA, IM


9.2.1-General.
9.2.2-Internal audit programme.

10-Improvement.
Management 10.1-General.
10.00-16:00 Representative 10.2-Nonconformity and corrective action.
Environment 10.3-Continual improvement.
7.5-Documented information.
7.5.1-General.
7.5.2-Creating and updating.
7.5.3-Control of documented
Information.
7.4.1-General. Factory AA,IM
7.4.2-Internal communication.
7.4.3-External communication.
Rabu, 16
Oktober 2019 Production 8.1-Operational planning and control.
10.00-12.00 8.2-Emergency preparedness and response.
9.1-Monitoring, measurement, analysis and evaluation.
9.1.1-General.
9.1.2-Evaluation of compliance.

8.3-Design and development of products and services. Research VM, IM


8.3.1-General.
and
8.3.2-Design and development planning.
Research and 8.3.3-Design and development inputs. Develpoment
14.00-16.00
Development 8.3.4-Design and development controls.
8.3.5-Design and development outputs.
8.3.6-Design and development changes.

FrM.9303/GIS-4
JADWAL AUDIT

PT. Global Inspeksi Sertifikasi

7.4.1-General. VM
7.4.2-Internal communication.
7.4.3-External communication.

8.1-Operational planning and control.


10.00-12.00 Purchasing 8.2-Emergency preparedness and response.
9.1-Monitoring, measurement, analysis and evaluation.
9.1.1-General.
9.1.2-Evaluation of compliance.

7.4.1-General. AA
7.4.2-Internal communication.
7.4.3-External communication.

14.00-.16.00 Maintance 8.1-Operational planning and control.


8.2-Emergency preparedness and response.
9.1-Monitoring, measurement, analysis and evaluation.
9.1.1-General.
9.1.2-Evaluation of compliance
7.4.1-General. QC AA, IM
7.4.2-Internal communication.
7.4.3-External communication.
Kamis, 17
Oktober 2019 Quality Control 8.1-Operational planning and control.
8.2-Emergency preparedness and response.
10.00-12:00
9.1-Monitoring, measurement, analysis and evaluation.
9.1.1-General.
9.1.2-Evaluation of compliance

FrM.9303/GIS-4
JADWAL AUDIT

PT. Global Inspeksi Sertifikasi

7.4.1-General. Office VM
7.4.2-Internal communication.
7.4.3-External communication.

10:00-12:00 Marketing 8.1-Operational planning and control.


8.2-Emergency preparedness and response.
9.1-Monitoring, measurement, analysis and evaluation.
9.1.1-General.
9.1.2-Evaluation of compliance
7.4.1-General. Gudang AA
7.4.2-Internal communication.
7.4.3-External communication.

8.1-Operational planning and control.


10:00-12:00 Logistic and Inventory 8.2-Emergency preparedness and response.
9.1-Monitoring, measurement, analysis and evaluation.
9.1.1-General.
9.1.2-Evaluation of compliance

7.1-Resources. Office IM
7.2-Competence.
10.00-12.00 HRD and GA 7.3-Awareness.

- New requirements of ISO 14001:2015, which are


different from ISO 14001:2004

- Office All
- Auditor Meeting

All Personnel Office All


13.00-... All Department Closing Meeting

Tangerang,14 Oktober 2019 Mengetahui,

FrM.9303/GIS-4
JADWAL AUDIT

PT. Global Inspeksi Sertifikasi

Ketua Tim, Pimpinan/Perwakilan Perusaha

(Vera M) (………………………………)

FrM.9303/GIS-4

You might also like