Anuj Seminar Final Report
Anuj Seminar Final Report
2018-2019
(17th May,2018 – 15th July,2018)
Under the guidance of Seminar in charge
Ms. Anamika Bhadauriya Ms. Anamika Bhadauriya
Submitted to: - Submitted by: -
Mr. Deepak Sharma Anuj Saini
(Head of Department) 15EAIEE017
Electrical Engineering B.Tech. IV Yr. / VII Sem.
RAJASTHAN TECHNICAL UNIVERSITY, KOTA
DEPARTMENT OF ELECTRICAL ENGINEERING
ARYA INSTITUTE OF ENGINEERING & TECHNOLOGY
SP-40, RIICO INDUSTRIAL AREA, KUKAS, JAIPUR, RAJASTHAN
(AIET/DOEE/2018-19/PTS/01)
DEPARTMENT OF ELECTRICAL ENGINEERING
ARYA INSTITUTE OF ENGINEERING &
TECHNOLOGY
SP-40, RIICO INDUSTRIAL AREA, JAIPUR
(RAJASTHAN) – 302028
CERTIFICATE
This is to certify that the Practical Training report for Practical Training taken at 132 kV Grid
Sub Station (Champapura),R.R.V.P.N.L. form 17th april 2018 to 15th July 2018 is submitted
by Mr. Anuj Saini (15EAIEE017) in partial fulfillment for the award of degree of Bachelor of
Technology in Electrical Engineering has been found satisfactory and is approved for submission.
(AIET/DOEE/2018-19/PTS/02)
(AIET/DOEE/2018-19/PTS/03)
ACKNOWLEDGEMENT
I express my sincere thanks to Assistant Engineer Mr. M.K. Saini for his enthusiastic
cooperation to make my training possible.
I would also like to thank Ms. Anamika Bhadauriya (PTS in charge and Assistant Professor of
Electrical Deptt.) for his contribution in preparing my practical training report and to guide me for
delivering the seminar. I would also like to thank Ms. Anamika Bhadauriya (PTS Guide.) for
his contribution in preparing my practical training report and to guide me for delivering the
seminar. I express sincere thanks to Mr. Deepak Sharma, Head of Electrical Department,
A.I.E.T. for giving me an opportunity for conducting the seminar of my summer training at 132
KV GRID SUBSTATION, CHAMPAPURA, JAIPUR.
I would like to express my deep gratitude to Management and Principal of Arya Institute of
Engineering & Technology for extending me the opportunity for vocational training and
providing all the necessary resources for this purpose.
ANUJ SAINI
B.Tech, 4th Year/VII Sem.
Electrical Engineering
(AIET/DOEE/2018-19/PTS/04)
ABSTRACT
Practical Training For a Period of 60 days in a Part of the B.Tech. (7th Sem.) Degree course in
“Electrical Engineering”. According to the Syllabus Worked out Practical cum industrial training
to which my Department is affiliated. I took a 60 working days at “132 GRID SUB-STATION
(G.S.S) CHAMPAPURA, JAIPUR. It is the one of 132 KV GSS of RVPNL in Rajasthan, The
Report is submitted as a Summary of what I observed and learnt there. The training was undergone
from 132KV Grid Sub-Station (G.S.S) Champapura, Jaipur.
The duration of this training was 60 days. Champapura gives the insight of real instrument like,
Transformer, CT, PT, CVT, LA, Relay, PLCC, Bus Bar, Reactor, Insulator, Isolator, control room
etc. There are various problems seen in substation while handling these instrument. There are
various occasion when relay operate and circuit breaker open, load shedding, shut down of feeder
in case of fault, shout down of total system , overheating of transformer, blasting of current
transformer in case of excessive current, transformer oil replacement aging of transformer oil,
wireless communication, insulator classification as per current rating, conductor requirement as
per rating, 2line and 3line transmission, how to put system on load and how to remove the system
from load, automatic resetting of relay, insulator operation on off-load.
GSS is the mean of connection between generating station and consumer by providing safety and
reliability of system in case of fault. This sub-station step-down the incoming voltage power
transmission to the required value and then is supplied to the consumer feeder or GSS done by
connecting auto transformer operation and requirement of various equipment have been include in
detail, further in case of report is the bus bar. Arrangement of different feeder level and
switchyards included information of bus bar arrangement of different level isolator and growing
substation also power transformer circuit breaker oil, filtration plant, and compression protection
control room and place are level.
(AIET/DOEE/2018-19/PTS/05)
CONTENT
DEPARTMENT CERTIFICATE 02
TRAINING CERTIFICATE 03
ACKNOWLEDGEMENT 04
ABSTRACT 05
CONTENT LIST 06
FIGURE LIST 10
TABLE LIST 11
Chapter 1 INTRODUCTION 12-14
1.1 INTRODUCTION OF RRVPNL 12
1.2 132 KV GRID SUBSTATION CHAMPAPURA 12
1.3 SINGLE LINE DIAGRAM 13
Chapter 2 LIGHNING ARRESTOR 15-18
2.1 INTRODUCTION 15
2.2 TRANSMISSION LINE PROTECTION 15
2.2.1 MOUNTING 16
2.2.2 HEALTH MONITORING OF THE LIGHTNING ARRESTER 16
2.3 SURGE MONITOR 17
2.4 OPERATING PRINCIPAL 17
2.5 RATING OF L.A. 17
2.6 GENERAL RATING OF L.A. 18
Chapter 3 TRANSMISSION LINE 19-20
3.1 TRANSMISSDION LINE 19
3.2 CONDUCTOR 19
3.3 THE WORK INVOLVEMENT IN LYING EHT 19
3.4 SELECTION OF TOWER 19
3.5 STARTING OF CONDUCTORS 20
Chapter 4 BUS BAR 21
4.1 SINGLE BUS BAR 21
4.2 SINGLE MAIN TRANSFER BUS 21
(AIET/DOEE/2018-19/PTS/06)
Chapter 5 TRANSFORMER 21-17
5.1 INTRODUCTION. 22
5.2 POWER TRANSFORMER. 23
5.3 CONSTRUCTIONAL PART 25
5.4 CORE CONSTRUCTION 25
5.5 CONSTRUCTIONAL FRAME WORK 25
5.6 WINDING 26
5.7 INSULATION 26
5.8 LEADS AND MATERIAL 26
5.9 BUSHING 27
5.10 CONSORVATOR 27
5.11 TRANSFORMER OIL 27
5.12 SYNTHETIC TRANSFORMERS 28
5.13 TRANSFORMER OPERATION 28
5.13.1 NOISE 28
5.14 SPECIFICATION OF TRANSFORMER 28
Chapter 6 INSTRUMENT TRANSFORMER 30-33
6.1 POTENTIAL TRANSFORMER 30
6.1.1 WORKING. 31
6.2 CURRENT TRANSFORMER 31
6.3 SELECTION OF C.T. 32
6.4 TYPES OF C.T. 32
6.4.1 TYPES OF C.T. 32
6.4.2 ROUTINE TEST 32
6.5 RATING OF C.T. 33
6.6 AUTO TRANSFORMER 33
Chapter 7 CAPACITIVE VOLTAGE TRANSFORMER 34
7.1 INTRODUCTION 34
7.2 RATING OF CVT 34
Chapter 13 RELAYS 46
13.1 PROTECTIVE RELAYS 46
Chapter 14 DC SUPPLY SYSTEM OF G.S.S 47-48
14.1 DC SYSTEM BATTERY SYSTEM 47
14.1.1 FLOAT CHARGER 47
14.1.2 BOOST CHARGER 47
14.1.3 DC POWER 47
(AIET/DOEE/2018-19/PTS/08)
14.2 BATTERY SET 48
14.3 SPECIFICATION OF BATTERY 48
Chapter 15 INSPECTION AND MAINTENANCE 49-51
15.1 POWER TRANSFORMERS 49
15.2 INSPECTION AND MAINTENANCE 50
15.3 MAINTENANCE TEST 51
Chapter 16 ANNUNCIATOR AND METERING 52
16.1 ANNUNCIATOR 52
(AIET/DOEE/2018-19/PTS/09)
FIGURE LIST
(AIET/DOEE/2018-19/PTS/010)
TABLE LIST
TABLE TABLE NAME PAGE NO.
TABLE 2 CONDUCTOR 20
TABLE 5 RATING OF CT 33
(AIET/DOEE/2018-19/PTS/011)
CHAPTER 1
1.1 INTRODUCTION
As well as food, water, air, shelter etc. for the live hood, we also need electricity in stable and
continuous form. In modern civilization we cannot think of life without electricity as it has
acquired it place next to oxygen. Though a big part of central and state revenue is being utilized
in power sector still the gape in demand and availability of electrical power is getting winder
and winder. the reason being date the rat of rise in demand in many fold then the total plant
availability in the system plus new plants under such a situation the best solution is to maintain
,operate and utilize the plant in most economical manner with high degree of efficiency and
stability ,which in other words Leeds to energy conservation .The network of electricity supply
to the consumer end is very complex one comprising of generating plant ,transmission and
sub- transmission lines ,grid sub-station, Sub-stations, Distribution network etc .each element
of the n/w has got direct bearing on the quality and continuance of electric power, but G.S.S is
the pivotal point it may be considered analogs to a railway N/w in pure Electrical Engg.
Terminology GSS is called a node.
(AIET/DOEE/2018-19/PTS/012)
SINGLE LINE DIAGRAM OF CHAMPAPURA G.S.S
(AIET/DOEE/2018-19/PTS/013)
There are two feeders/lines of 132 kV voltage level:-
132 KV Heerapura-Champapura
132 KV Hingonia-Champapura
There are four O/G feeders of 33kv voltage level:-
33kv Kalwar
33kv Sunderiyawas
33kv Champapura
33kv Hathoj
Again power is synchronized and the step down here by Power Transformer (132/33KV,
20/25MVA)
Including above the yard consists of following equipment:-
Bus bar i.e. Main & Auxiliary.
Lightning arrester
Current transformer
Potential transformer(PT)/Capacitive Voltage transformer(CVT)
Wave trap
Isolator
Circuit breaker
132/33kv power transformer
Insulators
Control Panel
Miscellanies Kiosk (M.K.)
Capacitor
(AIET/DOEE/2018-19/PTS/014)
CHAPTER 2
REPORT ON LIGHTNING ARRESTER PERFROMANCE
2.1 INTRODUCTION
High voltage power systems in general exp. Over voltages that originate from the system
instability/fault conditions, switching operations and lightning discharges. The duration of the
over voltages varies from microseconds depending upon the type of surges.Besides direct
lightning stroke, the sub station equipment have also to be protected against traveling waves due
to lightning strokes on the lines entering the sub station. The most commonly used equipment for
this purpose is the lighting arrester.
The lightning arrester should be installed as near to the equipment as possible particularly the
transformers, which is the costlier equipment in a sub station against direct lightning strokes the
spikes and earth wire should be suitably placed so as to provide coverage to the entire sub station
equipment. Generally angle of shield of about 45 degrees for the area between two spikes and
earth mats or ground wires and dig. For other areas is considered adequate for the lightning
protections system.
Along the way some of the current may dissipate to ground through utility equipments when the
traveling wave reaches tower the line insulator can undergo flashover resulting in interruption.
Note that several poles are generally sub. To the insulation flashover in the transmission line can
be reduced by increasing the insulation, using multiple overheads shielding wires or by reducing
the tower footing resistance. however, these method do not eliminate flashover problems
completely installation of zinc oxide arresters across the line insulation.
(AIET/DOEE/2018-19/PTS/015)
2.2.1 MOUNTING:-
The lightning arrester is mounted on an insulting base where surge monitor is to be connected in
series with the arrester .if surge monitor is not used for any reason bottom, the arrester should be
directly to station earth. The surge monitor is to be fixed at a height of 1.5mtr. from the ground
level for better view.
1. For effective discharge of the high surge current the arrester should be Proper connected
ground of a good low resistance grounding system without a proper grounding system, there
is no way to protect against surges.
2. The arrester should be connected with shortest possible directly on both the line and ground
side to reduce the inductive effects while discharging large surge current.
3. The connecting lead between lightning arrester and surge monitor should be insulating for
voltage up to 3 kv insulating aluminum cable of 35 sq mm cross section is adequate as
connecting lead.
4. The surge connector housing should be connected to the common earth system.
5. Each lightning arrester should also be separately connected to nearest earth electrode by
shortest straight connections.
For transformers winding protection it is desirable to inter-connect the ground lead of the arrester
with tank and also the neutral of the secondary. The inter connection reduces the stress imposed
on the transformers winding by the surge current to the extent of the drop across the earth
resistance and the inductive drop across the ground lead.
The lightning arresters normally do not require any maintenance during their lifetime. The
measurements of the resistive component of the continuous leakage current provide the most
accurate method. for checking of the arrester condition in service under normal system condition
the arrester conducts less than 1 mA.t hence it dictates the life of the arrester increased leakage
current increases the temperature of zinc oxide elements ,which the turn increases the leakage
current further . Once the leakage current reaches a critical level, the arrester would result in a
thermal run away condition resulting in the failure. Therefore the Rate of change of leakage
current is an important parameter from the view point of reliability the leakage current of an
arrester is known to increase with time.
(AIET/DOEE/2018-19/PTS/016)
2.3 SURGE MONITOR:-
The primary function of the discharge counter is to count the surge that appears across the
arrester. The surge counter operates only at impulse current above certain amplitude of 100 Amp.
and above the surge monitor is an instrument used in conjunction with lightning arrester to
continuously keep track of the condition of the arrester while it is energized . arrester under steady
state voltage condition, while the counter indicates the number of operations under by the arrester.
2.4 OPERATING PRINCIPLE:-
When the arrester discharges any surge, the capacitor gets charged before the gap spark over. later
the gap spark over and the surge are now bypassed to ground through this .the charged capacitor
then discharged through the electro-mechanical counter which counts the discharged .
2.5 RATINGS OF L.A:-
LD class 3
(AIET/DOEE/2018-19/PTS/018)
CHAPTER 3
3.1 TRANSMISSION LINES
In the category of EHV line viz. Extra high voltage line of 400 kv , 220 kv & 132 kv are
considered/are used for voltage from one grid substation to other grid sub -station through
various types of conductors.
3.2 THE CONDUCTORS USED FOR:-
1. For 400 kv line : tarantulla and marculla conductor
2. For 220 kv line : zebra conductor is used composite of aluminum strands and steel wires
3. For 132 kv line : panther conductor is used composite of aluminum strands and steel wires
(AIET/DOEE/2018-19/PTS/020)
CHAPTER 4
4.1 SWITCHING SCHEME BUS BAR ARRANGEMENT:-
4.1.1 SINGLE BUS BAR ARRANGEMENT:-
The switching-scheme is a life line of GSS in fact a Gss is considered in technical as extension of
generating unit i.e. there is infinite source of power behind the grid .So the Gss must have all
feature to efficiently, effectively and selectively control &monitor parameters of each network
element in straight forward terms, we may say that the Gss must have highest degree of stabilized
,selectivity &safety in insulation co-ordination with the highest B.I.L IS that of the bus bar
arrangement be done judiciously keeping all related requirement and codes of standard practical in
consideration various types of switching –schemes, generally in operation are being discussed in
following paragraphs.
This is operation simplest type of bus bar arrangement and is the cheapest one .Every feeder has
got its own terminal equipment‟s and hence in case of outage of any element of the terminal
equipment the feeder will remain off although each feeder has its own protection circuit failure of
the faulty feeder in isolating its faulty element may lead to collapse of the complete Gss due to its
simplest and cheapest one this form of bus bar arrangement is common at sub –transmission level
of 33 kv &11 kv and LT distribution system in rural area.
(AIET/DOEE/2018-19/PTS/023)
The marshalling box is a weather proof steel box mounted on the side of x-mer tank, the
marshalling box is Provided with heater for the prevention of moisture condensation, beside this
the inside of box is provided with anti condensation point.The following equipment is mounted
inside the marshaling box:-
The X-mer is in the yard has many tapping on ways every one about 5 Tapping. when the load on
x-mer increase due to regulation of the voltage 90 Down to increase the voltage on the secondary
side by the changing their tapping to higher position. For changing tap simply we have to close the
supply and taken change the tap by mechanically means. In champura G.S.S. there are on load tap
changer and it is totally remote control. There is one panels at control room for X-mer and by
pushing button, once we increase or decrease which we can see the number of tap on meter at the
panels.
The on load tap changer design is a part of X-mer unit wdg (e.g. as line and connection & switch )
The on load tap changer consist load divider(diverter switch) and a selector switch ,the desire wdg
is first select current legs by as low switching selector switch then flow the charge over by mean of
load diverter connection ,the natural point has even and odd number selector and contact plates
alternatively .This adjustment scheme shows a symmetrically design and mod of operation of the
tapping center.
power transformers are installed with various fittings and devices which are necessary for their
proper function and protection. some of the fitting which are normally provide depending upon
the size of transformer are as:
1. Magnetic type /simple oil level indicator(MOG)
2. Pressure relief vent(PRV)
3. Buchholz relay
4. Tap changer gear(OLTC)
5. Oil filling, drain valves and plugs like butter fly valve, circular type valve.
6. Oil filters valves/Terminal kiosk/ Earthing terminal, name plate, radiators, rollers,etc.
(AIET/DOEE/2018-19/PTS/024)
5.3 CONSTRUCTIONAL PART:-
The main elements of the construction are:
MAGNETIC CKT : comprising limbs ,yokes and clamping structure.
ELECTRICAL CKT: the primary, secondary and (if any) tertiary winding, transformers
insulation and bracing devices.
TERMINALS: tapping switches, tapping, terminal insulator and leads.
TANK: oil, cooling device conservators, dryers and auxiliary apparatus
(AIET/DOEE/2018-19/PTS/025)
FIG 5.5:- Block Diagram Of Transformer
5.6 WINDING
Classification of winding may be done as:
1. Circular or rectangular
2. Concentric or sandwiched
5.7 INSULATION:-
The insulation between the H.V and L.V winding and between L.V. winding and core compresses
Bakelite paper cylinders or elephantine wrap.
The insulation of conductors may be of paper, cotton or glass tape being used for air insulated
transformers. The paper is wrapped round the conductors in a suitable machine, preferably
without overlap of adjacent turns. In the power transformers, owing to strain on the insulation
between turns the line end of the high voltage wdg about 5 percent of the turns are reinforced with
the extra insulation material.
5.8 LEADS AND MATERIAL:-
The connections to the winding are copper rod or bars, insulation wholly or in part and taken to
the bus bars directly in the case of oil cooled transformers .The shape and size of the conductors
important in Very high voltage systems, not on account of the current carrying capacity, because
dielectric stresses, corona, etc. at sharp bends corners with such voltages.
(AIET/DOEE/2018-19/PTS/026)
5.9 BUSHINGS:-
Up to voltages of 33 kv, ordinary porcelain insulators can be used. Above this voltage the use of
conductor and oil filled terminal bushings, or for certain cases, a combination of the two has to be
considered. Of course, any conductor can be effectively insulated by air provided that it is a
sufficient distance from other conducting bodies and sufficiently proportioned to prevent corona
phenomena .such conditions are naturally UN-obtainable with transformers where the conductor
has to be taken through the cover of the containing tank, although common enough with overhear
transmission lines. The oil filled bushing consists of a hollow porcelain cylinder of special shape
with a conductor (usually a hollow tube) through its center at champapura GSS this type bushing
used in HV Side.
The capacitor type bushing is constructed of thick layers of Bakelite paper alternating with thin
graded layers of then foil .the result is a series of capacitors formed by the conductors and the first
tin foil layer, the first and second tin foil layers so on. The capacitance of the capacitors is
controlled by their length and the radial separation of their tin foil plates. The oil immersed ends
of HV bushing maybe reentrant from, reducing the immersed length and permitting as more
uniforms distribution of the axial and radial electric stress components.
5.10 CONSERVATOR:-
Conservator is required to take up the expansion and contraction of the oil to come in contact with
the air, from which it is liable to take up moisture. The conservator may consist of an airtight
cylindrical metal drum supported on the transformer lid or a neighboring wall, or of a flexible flat
corrugated dies drum. The tank is filled when cold and the expansion is taken up in the
conservator. A Air cell made by the leather material is provided in to conservator with air filled
and connected to silica gel breather, so no any air or moisture can come to contact with oil of
conservator. when it is fully airtight then the level in pressure matic glass of conservator will be
show full if there is any air leak then it will not fully inflated and level will become down.
Oil in transformers construction serves the double purpose of cooling and insulating in the choice
of oil for transformers use the following characteristics have to be considered. Viscosity,
insulating property, flash point, fire point, purity, slugging audity.
(AIET/DOEE/2018-19/PTS/027)
5.12 SYNTHETIC TRANSFORMERS OIL:-
These have been developed to avoid the risk of fire and explosion, present always with normal
mineral oils. Chlorinated biphenyl, a synthetic oil suitable for transformers is chemically stable,
nonoxidizing, rather voltage, and heavier than water. Its dielectric strength is higher than that of
mineral oil, and moisture has a smaller tendency to migrate through it .The permittivity is 4.5,
compared with an about 2.5.
(AIET/DOEE/2018-19/PTS/029)
CHAPTER 6
INSTRUMENT TRANSFORMERS
Precision measurement and metering has assumed increasing importance as of the growth of the
supply and particularly where energy interchanging between different power systems is concerned
with large quantities of energy transferred of the financial effect of measuring error assume
considerable importance. It is also importance and required that small fraction of the rated primary
current should be measured with adequate accuracy some of the meters beyond rated current is
also necessary to make consideration of the normal system overload. The instrument transformers
is therefore, required to maintain the accuracy class within says 50%to 120%of the rated current
and small measuring errors with the ranges evident.
The transformer winding high-voltage connection points are typically labeled as H1, H2
(sometimes H0 if it is internally grounded) and X1, X2 and sometimes an X3 tap may be present.
Sometimes a second isolated winding (Y1, Y2, Y3) may also be available on the same voltage
transformer. The high side (primary) may be connected phase to ground or phase to phase. The
low side (secondary) is usually phase to ground.
The terminal identifications (H1, X1, Y1, etc.) are often referred to as polarity. This applies to
current transformers as well. At any instant terminals with the same suffix numeral have the same
polarity and phase. Correct identification of terminals and wiring is essential for proper operation
of metering and protective relays.
Some meters operate directly on the secondary voltages at or below 600 V. VTs are typically used
for higher voltages (for example, 132/220/400/765 kV for power transmission)
(AIET/DOEE/2018-19/PTS/030)
There are primarily three types of voltage transformers (VT): electromagnetic, capacitor, and
optical. The electromagnetic voltage transformer is a wire-wound transformer. The capacitive
voltage transformer uses a capacitance potential divider and is primarily used at higher voltages
due to a lower cost than a electromagnetic VT. An optical voltage transformer exploits the
electrical properties of optical materials.
6.1.1 WORKING:-
The potential transformer works on the same principle of other transformers. It converts voltages
from high to low. It will take the thousands of volts behind power transmission systems and step
the voltage down to something that meters can handle. These transformers work for single and
three phase systems and attached at a point where it is convenient to measure the voltage.
(AIET/DOEE/2018-19/PTS/031)
(a) Bar type : a current transformers in which the primary winding consist of a bar suitable size
and material form an integral part of transformers.
(b) wound type : a current transformer having a primary winding of more than one full turn
wound on core.
The rated current of the apparatus and the rated burden required determines the use of one of the
other.
6.3 SELECTION OF C.T.
The following points need to be considered while selecting a CT.
1. Type
2. Number of secondary
3. Accuracy class of each secondary
4. Rated burden
5. Accuracy limited factor rating
6. Short time current raring
7. Insulation values e.g. power frequency dry and wet withstand values, impulse withstand values.
(AIET/DOEE/2018-19/PTS/032)
6.5 RATING OF C.T.:-
It has got low inherent reactance as such is subjected to severe short circuit condition since
primary and secondary side uses same winding there is always possibility of in position of higher
voltage on secondary in case of fault both the winding make use of common neutral, as such
neutral is required to be earthed or isolator on both side, Provision of additional insulation on
secondary side and increased frame size when adjustable tap are provided erodes the initial
advantage of low cost.
(AIET/DOEE/2018-19/PTS/033)
CHAPTER 7
CAPACTIVE VOLTAGE TRANSFROMER (CVT)
7.1 INTRODUCTION
Capacitive voltage transformer is used for line voltage metering, synchroscops, protective relays,
tariff meter, etc. The performance of CVT is inferior to that of electromagnetic PT. Its
performance is affected by the supply frequency,
Switching transient, magnitude of connected burden, etc. The CVT is more economical than PT
when the nominal system voltage increases above 66KV. The carrier current equipment can be
connected via the capacitor of the CVT. So there is no need of separate coupling capacitors.
CVT is used for voltage 66KV and more. At such voltage the cost of PT is high. The capacitor is
connected in series act like potential divider provides the current taken by his burden is negligible
compared with the current passing through the series connected capacitor. However the burden
current becomes relatively larger & ratio error and also phase error is introduced. Compensation is carried out
by tuning. The reactor is connected in series with the burden is adjusted to such a value that at
supply frequency is resonates with the sum of two capacitor. This is eliminating the error.
S.T.D IS-3156/9348
8.2 OPERATION:-
The operation of isolator may be manual (i.e. by hand without using any other supply or storage
of energy meter) or power operated isolators.
During the cause of operation utilize energy which is not supplied by the operator. The energy
may be electrical, pneumatic or the energy previously stored in spring or counter weight.
8.3 CONTROL:-
In case power operated(motorized) isolator are purchased for any installation it may be worthwhile
to examine further weather control should be local in switch yard or remote in the control room
the extra cost enrolled in the isolated is quite substantial particularly at voltage 132 kv and below
it should therefore considered in detail weather any installation really in stifles the procurement of
remote operate isolators keeping in view the fast frequency of operation of isolator is rather low.
8.4 RATING OF ISOLATOR:- TABLE NO. 8.4
MAKE EXCEL ASSOCIATE PVT. LTD
Rated voltage 145kv
Rated current 800amp
Auxiliary switch 6 no.+6 nc
10 amp 110 v
(AIET/DOEE/2018-19/PTS/036)
CHAPTER 9
CIRCUIT BREAKER
9.1 INTRODUCTION:-
A circuit breaker is equipment which can open or close circuit under all condition viz. No load,
full loads or fault conditions. It so designed that it can be operated manually under normal
conditions and automatically under fault conditions, for the later operation, relay circuit is used.
Circuit breaker can be defined as an electrical device, which protects the system from short
circuits or over load with the help of relays. In case, circuit breaker is not of adequate capacity, its
failure may result into interruption of power, shut downs, injury to personals and damage to
property. Installation of over rated circuit breakers or extra sensitive and costly protective devices
will mean un-wanted expenditure. It is therefore necessary that calculations in respect of short
circuit currents for the concerned system be made before correctly rated circuit breakers are
selected or steps are taken to improve the existing system.
9.2 OPREATING PRINCIPLE: -
A circuit breaker consists of fixed and moving contacts under normal operating conditions these
contacts remains closed. In this condition, the emf in the secondary winding of currents
transformer (C.T) in sufficient to operate the trip coil of the breaker but the contacts can be
opened by manual or automatic control.
When fault occurs on any part of the system the resulting over current in the primary winding
increases the secondary winding emf and hence the current flow through relay operating coils. The
relay contacts are closed and the trip coil (tripping coil) of the breaker is energized. The moving
contacts are pulled apart by some mechanism thus operating the circuit breaker.
When the contacts of the circuit breaker are separated under fault conditions, arc is produced
between them (male and female contacts). The current is thus able to continue until the arc ceases.
This arc generates enormous heat, which may cause damage to the system or to the breaker itself.
Therefore, the main problem in a circuit breaker is to extinguish the arc within the shortest 6 time
so that heat generates by it may not reach a dangerous value.
9.3 CLASSIFICATION OF CIRCUIT BREAKERS FOR VARIOUS
VOLTAGES:
1. Bulk oil circuit breaker.
(AIET/DOEE/2018-19/PTS/037)
2. SF-6 circuit breaker.
3. Air blast circuit breaker.
4. Minimum oil circuit breaker.
5. Vacuums circuit breaker
(AIET/DOEE/2018-19/PTS/038)
The heat transferability of gas is 2-5times that of air at the same temperature & pressure SF6has
low arc time constant. The time constant of medium is defined as the “medium time between
current t zero and the instant the conductance of contract space reaches zero value.” Due to the
electro negativity of SF6dielectric strength is high.
9.7 APPLICATIONS:-
A typical SF6 circuit breaker consists of interrupter units each capable of dealing with currents up
to 60 ka and voltages in the range of 50-80kv. A number of units are connected in series according
to the system voltage.SF6 circuit breaker have been developed for voltages 115kv to 230kv,
power ratings 10MVA to 20MVA and interrupting time less than 3 cycles.
9.8.1 PRINCIPLE :-
When the contacts of the breaker are opened in vacuum (10 -7 to 10 -5 torr), an arc is
produced between the contacts by the ionization of metal vapours of contacts. The arc is quickly
extinguished because the metallic vapours, electrons and ions produced during arc condense
quickly on the surfaces of the circuit breaker contacts, resulting in quick recovery of dielectric
strength. As soon as the arc is produced in vacuum, it is quickly extinguished due to the fast rate
of recovery of dielectric strength in vacuum.
(AIET/DOEE/2018-19/PTS/040)
9.8.2 WORKING:-
When the breaker operates the moving contacts separates from the fixed contacts and an arc is
struck between the contacts. The production of arc is due to the ionization of metal ions and
depends very much upon the material of contacts. The arc is quickly extinguished because the
metallic vapours, electrons and ions produced during arc are diffused in short time and seized by
the surfaces of moving and fixed members and shields. Since vacuum has very fast rate of
(AIET/DOEE/2018-19/PTS/041)
recovery of dielectric strength, the arc extinction in a vacuum breaker occurs with a short contact
separation.
9.8.3 ADVANTAGES:
a. They are compact, reliable and have longer life.
b. There are no fire hazards.
c. There is no generation of gas during and after operation.
d. They can interrupt any fault current. The outstanding feature of a VCB is that it can break any
heavy fault current perfectly just before the contacts reach the definite open position.
e. They require little maintenance and are quiet in operation.
f. Can withstand lightning surges.
g. Low arc energy.
h. Low inertia and hence require smaller power for control mechanism.
9.8.4 APPLICATIONS:
For outdoor applications ranging from 22 kV to 66 kV. Suitable for majority of applications in
rural area.
9.9 RATINGS OF CIRCIT BREAKER:
Type 120-SEM-32B
Make Crompton greaves limited (CGL)
Sr. NO. 31240C
Rated voltage 145 KV
Rated current 1600A
Rated gas pressure 7 kg/cm-g
Malary capacity 1000KAP
Motor voltage 230v
Rated operating duty 0-0.3 sec-Co-3 min-CO
No. of breaks per pole 1
Operation- tripping Pneumatic
Closing Charged Spring
The carrier current uses for PLCC have to be prevented from entering the power equipments
such as attenuation or even complete loss of communication signals.
For this purpose wave trap or line trap are used between transmission line and sub- station equip
ment to –
1. Avoid carrier power dissipation in power plant
2. Reduced cross talks with other PLCC CKT
connected to the same power station.
(AIET/DOEE/2018-19/PTS/043)
CHAPTER 11
EARTHING OF G.S.S.
11.1 INTRODUCTION
Earthing of electric installation play an important role as regards the behavior of the network and
personal safety .The purpose of earthing is electric are protection of the installation, improvement
in the quality of service and safety of personnel. Earth is inherently a rather poor conductor whose
resistivity is around 1 billion times that of copper. An 8 feet*20 MM diameter ground rod driven
into earth might very likely represent a 25 ohm connected to earth. This resistance may be
imagined to be made up of the collective resistance of a series of equal thickness cylindrical shells
of earth. The inner shell will of course represent the largest incremental value of resistance, since
the resistance is inversely proportional to the shell diameter. Thus the central small diameter shell
of earth constitute of the bulk earthing terminal resistance.
11.2 REQUIREMENT OF EARTHING:-
Provision of adequate earthing in substation is extremely important for the safety of the operating
personnel as well as proper system operation. The primary requirements of a good earthing
system in a substation are:
1. The impedance of ground should be low as possible.
2. The touch potential and step should in safe limits.
3. Equipment framework and other nun-current carrying parts.
(AIET/DOEE/2018-19/PTS/044)
CHAPTER 12
CAPACITOR BANK
(AIET/DOEE/2018-19/PTS/045)
CHAPTER 13
PROTECTIVE RELAYS
13.1 BASIC EQUIPMENT OR REQUIREMENT OF PROTECTIVE RELAYS:-
Basic equipment or requirements of protective relays are as follows:-
13.1.1 SPEED:-
Protective relaying should do connect a faulty element as quickly as possible.
13.1.2 SELECTIVITY:-
The ability of the protective relay to determine the point of which have the fault occurs and select
the nearest circuit breaker tripping of which will lead the clearing of fault with min-or so damage
to the system.
13.1.3 SENSITIVITY:-
It is the capacity of the relaying to operate relay under the actual condition that produces the last
operating condition tendency.
Depending upon the method of element connected primary relay (series element connect directly
on the circuit protective element) and secondary relay (sensing element connected through a
current and voltage transformer) which are depending upon the time action and depending upon
the kind of contacts.These are called normally opened normally closed in GSS control room there
in panel in which the relays are set and there are many type of relays.
a. Over current relay
b. I.D.M.T.fault Relay
c. Impendence Relay
d. Earth Fault Relay
e. Buncheloz`s Relay
f. Differential Relay
g. Auxiliary Relay
h. Distance protection Relay
i. Under frequency Relay(UFR)
j. .Over voltage Relay
k. Under voltage Relay
l. Neutral Displacement Relay (NDR)
(AIET/DOEE/2018-19/PTS/046)
CHAPTER 14
DC SUPPLY SYSTEM OF G.S.S.
14.1 DC SYSTEM HAS THREE MAIN PARTS AT G.S.S.:-
1. Rectifier
2. battery set
3. dc distributor board (DCDB)
Rectifier have two parts:-
1. Float charger
2. boost charger
Battery set have two types:-
1. Liquid type
2. Dry type like VRLA type
Dc distribution board have mainaly Earth fault relay and low voltage alarm.
(AIET/DOEE/2018-19/PTS/047)
14.2 BATTER SET:-
There is a battery set (2.25V) of 54 batteries which are all of 110 volts. At some GSS two DC
system provided So in emergency or during shut down for maintenance work DC supply can be
maintain for the GSS maintenance is carried out on daily, monthly and yearly basis ,but during
now days most of GSS have VRLA type DC batteries which are almost maintenance free due to
dry type. The technical data of battery set is maintained by every GSS through measuring the
each cell voltage on monthly basis so that if any cell voltage may going towards downward may
be out of circuit or may give to boost etc. for safety of other cell’s as well as battery set. Because
the DC System is heart for the every GSS and it is very important part of GSS equipment’s.
Boost 2.30VPC
Current 20 to 40 amp
(AIET/DOEE/2018-19/PTS/048)
CHAPTER 15
INSPECTION AND MAINTENANCE SCHEDULE:
15.1 POWER TRANSFORMERS:
In addition to the log sheet, which is maintained by the shift staff, each transformer should have
its own maintenance record register, with history card affixed to it. In RVPN these are maintained
as per IS : 2008 as the RVPNL is ISO:2008 certified company.
TABLE 15.1 ROUTINE INSPECTION SCHEDULE
(POWERTRANSFORMERS)
(AIET/DOEE/2018-19/PTS/049)
(a) Fans and motors Each shift
(b) Bearing (Lubrication) (as per recommendations of)
(c) Heat exchanger Annually
(POWER TRANSFORMERS)
SCHEDULE
1. Leakage of oil Half yearly
equipment if installed
8. Tightening of the contacts Half yearly
(AIET/DOEE/2018-19/PTS/050)
15.3 MAINTENANCE TESTS (POWER TRANSFORMERS)
voltage or winding
4. Polarization Index Yearly 8 or less
(AIET/DOEE/2018-19/PTS/051)
CHAPTER16
ANNUNCIATOR AND METER SECTION
16.1 ANNUNCIATOR
In the control room the annunciate‟ is most control box as when the fault across and relay
trip by which we mean that the fault is occurred.
In this there is a box type thing in which probable fault at different feeder and different zone have
written and in front of them there are bulb/LED provided in each window of annunciator panel.
There is also an alarm system.
When same fault is occurred the relay is trip and is given two signal one for two circuit breaker
and second to annunciator auxiliary relays. This relays first signal trip the C.B and signal when
goes to relay i.e.auxilary type trip, that relay this relay i.e. seeds the signal to annunciator which
given alarm and the bulb is lighting in the front of the type of the fault, which is occurred. The
shift engineer can receives this signal and sees the annunciator at which feeder at which zone and
which type of fault is occurred.
Penal at which the C.B is open it trip again to see that weather it is instantaneous fault (like
monkey made short CKT or bird made a short CKT) the closes the circuits breaker and reset the
relay is trip or not. It is not other the system coil leak as much as it again announce that the CKT
is still faulty then as we know that suppose fault is at RPS Feeder zone earth fault send a
maintenance party to rectify the fault.
16.2 METER SECTION:
The energy meter is the meter, which measures the energy consumed by the particular feeder.
These are filled to different feeders and we note hourly reading how much amount we are
importing/exporting (KWH). These meters read in MWH/KWH. at champapura GSS two type
energy meters are provided one of them is multifunctional meter of various company make like
AE Ltd. on panel and other is also on panel but provided by the Protection wing of RVPN for
correct metering purpose with high accuracy company make like Genus ltd.
(AIET/DOEE/2018-19/PTS/052)
CHAPTER 17
SAP ERP MODULE
17.1 INTRODUCTION
The RVPNL now is moving toward digital technology and adopt a online software namely SAP
ERP which is the abbreviation for “Systems Applications and Products in Data processing.it is
used by RVPNL on very vast level and maximum data related to employees like attendance,
payroll activity ,loan requirement ,transfer-posting, all type of billing payment, tender’s, etc.as
well as technical data related to the Gss like stock balance, progress of old /new project of RVPN
etc. .log sheet data, will be available on real time basis for use in any further project/Scheme of
RVPN .The higher authority up to Top management of RVPN may check or analysis these data at
any time. In this system each GSS has a unique ID namely cost center /plant code/purchase grip.
profit center etc.as well as every account unit also have unique ID‟s. Similarly a unique ID also
given to the every employee of RVPN namely Employee Identification number by using this ID
every employee can see all over self- history in RVPN at any time.
In SAP ERP Module various module created for the various technical and Non- technical work of
GSS. one of them is important namely PM Module like as :-
17.2 PLANT MAINTENANCE (PM MODULE) –
It is a combination of all technical, administrative and management tasks carried out during the
life cycle of a technical object to keep it operational or to return it to this condition so it can work
as intended.
1. Getting Started
LOG ON:
Select SAP Log in Icon
On PC Desktop & press enter key or double click Or follow the menu path as shown in following
screen
(AIET/DOEE/2018-19/PTS/053)
Select the QAS System
and Click on Logon
2. Logging onto the SAP system
You need to enter your USER NAME, PASSWORD to log-in to the system.
SAP easy access is the standard entry screen displayed after the logon You navigate through
the system using the tree structure.
(AIET/DOEE/2018-19/PTS/054)
4. Selecting Functions:
(AIET/DOEE/2018-19/PTS/055)
You can call functions in the SAP as follows:
Menu Option
Favorites
Entry in the SAP easy access Menu
/n -- ends the current session
/i -- delete the current session
/o<T-code> opens a new session and branches out to the transaction specified
<with reqd. T-code>
Command Field: Use command field to go to applications directly by entering the transaction
code.
Standard Tool Bar: the push buttons in the standard tool bar are found on every screen in an
SAP system. Any push buttons that cannot be used in a particular application are grayed out. If
you place your cursor on a push button for a while the system displays a quick info text that
explains the push button function.
The Application Tool bar: shows which functions are available in the current application.
A Tab page: provides a clearer overview of several information screens
Status bar: the status bar displays information on the current system status, for example.
Warning or error messages
Menu bar: the menus shown here depend on which application you are working in.
Title bar: the title bar displays the functions that are available for the user.
Checkboxes: checkboxes enable you to select several options simultaneously within a group.
Radio Buttons: allow you to choose exactly one item from a selection.
(AIET/DOEE/2018-19/PTS/056)
menu
Command Field
Title bar
Standard tool bar
Application Tab
Status bar
(AIET/DOEE/2018-19/PTS/057)
7. SAP – Instructions:
Auto Log-Out
o The system logs you out automatically, if the screen is idle for 900 seconds (15 minutes). If
you are reading a screen or running a report please move your cursor to keep the screen
active.
Background Job
o All heavy reports should be run in the background. Reports tend to read a lot of data from the
database and hence can slow down the system. Background reports do not slow down the
system.
Sessions
o You can create up to 6 sessions with a single log-in. You may use this feature to increase
your productivity. However, be aware of the sessions you have created. You may actually be
locking yourself in one session, while you may be trying to edit an object in another session.
User Default
o You can set-up user parameters and defaults for your user name. However, only the
administrator is assigned this authorization. If you see decimal notation, date notation,
default printers and certain default organization units are not relevant to you, please get the
administrator to set them right.
Personalization
o You can personalize many screens. You may also use favorites. You can use the Options
feature to change some screen settings including the listing of keys along with the
description. Use these features carefully after you gain enough experience.
Password Protection
o Do not change your password if many people are using the same user name. If you are the
only one using it, change it once every month.
Excel Integration
o All your report outputs can be downloaded to excel to text files. Please use this feature if you
want to analyze certain reports. While you need to use SAP in real-time, you may choose to
work on some reports offline.
(AIET/DOEE/2018-19/PTS/058)
8. System Messages: System gives 4 types of error messages:
o I – Information
o W – Warning
o E – Error
o A – System Error
„I‟ will allow you to work without interruption. „W‟ will need you to press “enter”. “E”
means you have missed some input etc. It prompts the user to correct him and hence does not
allow you to go to next step without correction. Error type “A” is a serious error and is because
of some system issues. Bring it up to the system administrator immediately.
(AIET/DOEE/2018-19/PTS/059)
GSS LAYOUT
132 KV GSS CHAMPAPURA KALWAR ROAD ,JAIPUR
(AIET/DOEE/2018-19/PTS/060)
CONCLUSION
The power sector of the country has been set on a path of vigorous and sustainable growth
with self- reliance in all technological aspect. The country has aim at energy self-sufficient
the growth in power sector helped millions of people in the country to secure employment. It
is anticipated that a large part of nation‟s wealth would be in power sector.
A necessary and important aspect of engineering course is practical training. It gives an
engage to phase and tackle actual problems in the industries and field. The institute where the
students studies can‟t provide that practical knowledge on all learning. Until and unless the
student has been exposed to its practical aspects. The study of the subjects is incomplete. The
artificial studies built the engg. in him by providing him pool of knowledge where as practical
application makes him agile and complete. If theoretical knowledge teaches principal and
polices, the practical expose tells how to use those policies and principle atmosphear.during
training session the students learn to work human laboratory.
As the case of practical training there is a major difference between theoretical and practical
knowledge, hence practical training is taken at a company or industry to get
familiar with Engg. Organizational and technical practices implementation is just like a bird
with one fan.
So, I thought to take my practical training at 132kv G.S.S R.V.P.N.L. Kalwar Road,
Champapura, Jaipur. Also, this GSS has been won the Trophy& award of “Best Maintained
GSS for the FY 2012-13” in RVPN.I learnt there a lot of to know about CT and PT,
distribution system, various transformers, relays, circuit breakers, conductors, LA etc. DC
system, PLCC, SAP ERP online system with installation and maintenance procedures used by
RVPNL.
In Champapura G.S.S. every event added a lot of to my practical knowledge during my
training session. As during the practical session, maintenance period was going on thus it
made a right direction to understand and make a clear and absolute approach about various
equipment‟s and their fittings, testing‟s, maintenance work, and features installed there. This
made a perfect relation between theoretical and practical knowledge.
(AIET/DOEE/2018-19/PTS/061)
REFERENCES
(AIET/DOEE/2018-19/PTS/062)