2-3 Site Condition

Download as pdf or txt
Download as pdf or txt
You are on page 1of 43

Statement Showing Earth Work Quantities from KM 2.000 to KM 3.

000
ALL SOILS F&F HARD ROCK
Distance
SL No. Chainage Mean Mean
in mts Area in Area in Area in Mean Area in HR Qty in
Area in Qty in Cum Area in Qty in Cum
Sq.mts Sq.mts Sq.mts Sq.mts Cum
Sq.mts Sq.mts
1 2.000 3.443 2.146 30.116
25 3.678 91.944 4.922 123.044 27.868 696.690
2 2.025 3.913 7.697 25.619
25 3.841 96.025 7.912 197.800 27.731 693.267
3 2.050 3.769 8.127 29.842
25 3.686 92.142 6.476 161.912 29.570 739.250
4 2.075 3.602 4.826 29.298
25 3.807 95.167 4.826 120.650 29.374 734.350
5 2.100 4.011 4.826 29.450
25 3.681 92.032 3.667 91.675 30.761 769.025
6 2.125 3.352 2.508 32.072
25 2.949 73.720 3.287 82.175 31.502 787.550
7 2.150 2.546 4.066 30.932
25 3.733 93.325 4.653 116.325 31.246 781.150
8 2.175 4.920 5.240 31.560
25 5.325 133.130 5.052 126.300 30.885 772.125
9 2.200 5.730 4.864 30.210
25 3.732 93.298 5.692 142.306 30.535 763.387
10 2.225 1.733 6.521 30.861
25 2.037 50.930 6.946 173.644 30.456 761.400
11 2.250 2.341 7.371 30.051
25 2.898 72.437 8.566 214.144 28.856 721.406
12 2.275 3.454 9.760 27.662
25 3.810 95.238 8.013 200.319 26.308 657.706
13 2.300 4.165 6.265 24.955
25 3.285 82.113 4.348 108.712 28.894 722.337
14 2.325 2.404 2.432 32.832
25 2.578 64.450 2.312 57.812 34.601 865.017
15 2.350 2.752 2.193 36.369
25 2.809 70.237 4.279 106.963 34.912 872.792
16 2.375 2.867 6.364 33.454
25 2.783 69.575 4.379 109.475 33.090 827.245
17 2.400 2.699 2.394 32.726
25 2.914 72.837 4.358 108.938 31.314 782.847
18 2.425 3.128 6.321 29.902
25 3.477 86.937 4.945 123.625 31.781 794.532
19 2.450 3.827 3.569 33.660
25 3.543 88.580 4.236 105.888 32.719 817.967
20 2.475 3.259 4.902 31.777
25 5.156 128.893 4.042 101.050 32.340 808.507
ALL SOILS F&F HARD ROCK
Distance
SL No. Chainage Mean Mean
in mts Area in Area in Area in Mean Area in HR Qty in
Area in Qty in Cum Area in Qty in Cum
Sq.mts Sq.mts Sq.mts Sq.mts Cum
Sq.mts Sq.mts
21 2.500 7.052 3.182 32.904
25 5.091 127.280 4.085 102.125 33.639 840.972
22 2.525 3.130 4.988 34.374
25 2.761 69.015 6.020 150.500 33.304 832.587
23 2.550 2.391 7.052 32.233
25 3.788 94.708 6.235 155.875 32.646 816.140
24 2.575 5.186 5.418 33.058
25 5.139 128.473 6.357 158.925 31.121 778.030
25 2.600 5.092 7.296 29.184
Cross bund from km 2.600 to km 2.625
25 2.600 5.092 7.296 29.184
25 5.161 129.013 6.980 174.512 27.801 695.029
26 2.625 5.229 6.665 28.483
25 5.071 126.787 8.372 209.312 27.988 699.705
27 2.650 4.914 10.080 27.493
25 4.489 112.237 11.597 289.937 25.735 643.375
28 2.675 4.065 13.115 23.977
25 4.140 103.488 9.245 231.125 27.572 689.290
29 2.700 4.214 5.375 31.166
25 4.670 116.745 7.912 197.800 28.204 705.093
30 2.725 5.126 10.449 25.241
25 4.717 117.935 7.681 192.037 28.581 714.512
31 2.750 4.309 4.914 31.920
Structure gap from km 2.750 to 2.850
35 2.850 2.835 3.800 24.837
25 3.226 80.655 5.187 129.675 23.248 581.210
36 2.875 3.618 6.574 21.660
25 4.231 105.768 5.150 128.750 25.009 625.226
37 2.900 4.844 3.726 28.358
25 5.101 127.522 3.592 89.800 28.798 719.941
38 2.925 5.358 3.458 29.237
25 4.898 122.455 4.427 110.675 27.854 696.350
39 2.950 4.438 5.396 26.471
25 4.950 123.742 4.353 108.837 28.690 717.240
40 2.975 5.461 3.311 30.908
25 3.629 90.725 4.472 111.800 30.595 764.862
41 3.000 1.797 5.633 30.281
Total 3519.559 5114.444 26888.119

Total Earth work Execution Cum 35522


CROSS SECTION @ Km 2.000
L/S R/S
8.10 Avg spoil bank level
269.628 SPOIL BANK
soils
4.408 269.203

F&F 268.938

1.

1
HR

5:
5:

1.
1
CBL 264.728 265.220
9.400 8.100
BED WIDTH 18.000
HYDRAULIC PARTICULARS
OLD NEW
Bed Width 9.4 18 m Cutting Levels
Distance from Bank 8.4 (9m for
n value 0.03 0.03 Edge (m)
0.0 3.0 6.0
ground level)
Average

CBL 264.728 264.728 m Ground Level 269.850 269.795 269.680 269.185 269.628

prism 1.5:1 1.5:1 Top of F&F Levels 269.190 269.210 269.200 269.210 269.203

Extension in width= 8.1 m Top of HR Levels 268.920 268.950 268.960 268.920 268.938

Excavated Level 265.200 265.230 265.150 265.300 265.220

Excavated Areas of canal Classification Levels Classification Depths


top width Bottom area in Sq.m=
soil depth ( c) 269.628 m Depth of soils
(a) width (b) 1/2*(a+b)*c Top of Soils Level 0.425 m
In all
8.10 8.10 0.425 3.443
F&F top level
269.203 m Depth of F&F 0.265 m
soils=
In F&F= 8.10 8.10 0.265 2.146 HR Top Level 268.938 m Depth of HR 3.718 m
In HR= 8.10 8.10 3.718 30.116 HR Bottom level 265.220 m Total Depth 4.408 m

Contractor Asst Executive Engineer Deputy Executive Engineer Executive Engineer


HNSS Sub Division HNSS Sub Division HNSS Division no-1
Nandikotkur Nandikotkur Nandikotkur
CROSS SECTION @ Km 2.025
L/S R/S
8.60 Avg spoil bank level
269.554 SPOIL BANK
soils
4.329 269.099

F&F 268.204

1.

1
HR

5:
5:

1.
1
CBL 264.724 265.225
9.400 8.600
BED WIDTH 18.000
HYDRAULIC PARTICULARS
OLD NEW
Bed Width 9.4 18 m Cutting Levels
Distance from Bank 8.4 (9m for
n value 0.03 0.03 Edge (m)
0.0 3.0 6.0
ground level)
Average

CBL 264.724 264.724 m Ground Level 269.725 269.605 269.585 269.300 269.554

prism 1.5:1 1.5:1 Top of F&F Levels 269.100 269.250 269.020 269.025 269.099

Extension in width= 8.6 m Top of HR Levels 268.200 268.225 268.235 268.195 268.204

Excavated Level 265.200 265.230 265.250 265.220 265.225

Excavated Areas of canal Classification Levels Classification Depths


top width Bottom area in Sq.m=
soil depth ( c) 269.554 m Depth of soils
(a) width (b) 1/2*(a+b)*c Top of Soils Level 0.455 m
In all
8.60 8.60 0.455 3.913 269.099 m
soils= F&F top level Depth of F&F 0.895 m
In F&F= 8.60 8.60 0.895 7.697 HR Top Level 268.204 m Depth of HR 2.979 m
In HR= 8.60 8.60 2.979 25.619 HR Bottom level 265.225 m Total Depth 4.329 m

Contractor Asst Executive Engineer Deputy Executive Engineer Executive Engineer


HNSS Sub Division HNSS Sub Division HNSS Division no-1
Nandikotkur Nandikotkur Nandikotkur
CROSS SECTION @ Km 2.050
L/S R/S
8.60 Avg spoil bank level
269.644 SPOIL BANK
soils
4.864 269.195

F&F 268.250

1.

1
HR

5:
5:

1.
1
CBL 264.720 264.780
9.400 8.600
BED WIDTH 18.000
HYDRAULIC PARTICULARS
OLD NEW
Bed Width 9.4 18 m Cutting Levels
Distance from Bank 8.4 (9m for
n value 0.03 0.03 Edge (m)
0.0 3.0 6.0
ground level)
Average

CBL 264.720 264.720 m Ground Level 269.840 269.805 269.795 269.135 269.644

prism 1.5:1 1.5:1 Top of F&F Levels 269.190 269.220 269.200 269.170 269.195

Extension in width= 8.6 m Top of HR Levels 268.225 268.270 268.250 268.255 268.250

Excavated Level 264.770 264.795 264.730 264.825 264.780

Excavated Areas of canal Classification Levels Classification Depths


top width Bottom area in Sq.m=
soil depth ( c) 269.644 m Depth of soils
(a) width (b) 1/2*(a+b)*c Top of Soils Level 0.449 m
In all
8.60 8.60 0.449 3.769 269.195 m
soils= F&F top level Depth of F&F 0.945 m
In F&F= 8.60 8.60 0.945 8.127 HR Top Level 268.250 m Depth of HR 3.470 m
In HR= 8.60 8.60 3.470 29.842 HR Bottom level 264.780 m Total Depth 4.864 m

Contractor Asst Executive Engineer Deputy Executive Engineer Executive Engineer


HNSS Sub Division HNSS Sub Division HNSS Division no-1
Nandikotkur Nandikotkur Nandikotkur
CROSS SECTION @ Km 2.075
L/S R/S
7.60 Avg spoil bank level
269.680 SPOIL BANK
soils
4.964 269.206

F&F 268.571

1.

:1
HR

5:

5
1.
1
CBL 264.716 264.716
9.400 7.600
BED WIDTH 18.000
HYDRAULIC PARTICULARS
OLD NEW
Bed Width 9.4 18 m Cutting Levels
Distance from Bank 8.4 (9m for
n value 0.03 0.03 Edge (m)
0.0 3.0 6.0
ground level)
Average

CBL 264.716 264.716 m Ground Level 269.720 269.775 269.705 269.520 269.680

prism 1.5:1 1.5:1 Top of F&F Levels 269.195 269.220 269.200 269.210 269.206

Extension in width= 7.6 m Top of HR Levels 268.565 268.580 268.590 268.550 268.571

Excavated Level 264.705 264.725 264.740 264.695 264.716

Excavated Areas of canal Classification Levels Classification Depths


top width Bottom area in Sq.m=
soil depth ( c)
Top of Soils Level
269.680 m Depth of soils
0.474 m
(a) width (b) 1/2*(a+b)*c
In all
7.60 7.60 0.474 3.602
F&F top level
269.206 m Depth of F&F 0.635 m
soils=
In F&F= 7.60 7.60 0.635 4.826 HR Top Level 268.571 m Depth of HR 3.855 m
In HR= 7.60 7.60 3.855 29.298 HR Bottom level 264.716 m Total Depth 4.964 m

Contractor Asst Executive Engineer Deputy Executive Engineer Executive Engineer


HNSS Sub Division HNSS Sub Division HNSS Division no-1
Nandikotkur Nandikotkur Nandikotkur
CROSS SECTION @ Km 2.100
L/S R/S
7.60 Avg spoil bank level
269.701 SPOIL BANK
soils
4.988 269.223

F&F 268.588

1.

:1
HR

5:

5
1.
1
CBL 264.713 264.713
9.400 7.600
BED WIDTH 18.000
HYDRAULIC PARTICULARS
OLD NEW
Bed Width 9.4 18 m Cutting Levels
Distance from Bank 8.4 (9m for
n value 0.03 0.03 Edge (m)
0.0 3.0 6.0
ground level)
Average

CBL 264.713 264.713 m Ground Level 269.895 269.805 269.715 269.390 269.701

prism 1.5:1 1.5:1 Top of F&F Levels 269.220 269.240 269.210 269.220 269.223

Extension in width= 7.6 m Top of HR Levels 268.585 268.575 268.600 268.590 268.588

Excavated Level 264.710 264.730 264.710 264.700 264.713

Excavated Areas of canal Classification Levels Classification Depths


top width Bottom area in Sq.m=
soil depth ( c) 269.701 m Depth of soils
(a) width (b) 1/2*(a+b)*c Top of Soils Level 0.478 m
In all
7.60 7.60 0.478 4.011 F&F top level 269.223 m Depth of F&F 0.635 m
soils=
In F&F= 7.60 7.60 0.635 4.826 HR Top Level 268.588 m Depth of HR 3.875 m
In HR= 7.60 7.60 3.875 29.450 HR Bottom level 264.713 m Total Depth 4.988 m

Contractor Asst Executive Engineer Deputy Executive Engineer Executive Engineer


HNSS Sub Division HNSS Sub Division HNSS Division no-1
Nandikotkur Nandikotkur Nandikotkur
CROSS SECTION @ Km 2.125
L/S R/S
7.60 Avg spoil bank level
269.700 SPOIL BANK
soils
4.991 269.259

F&F 268.929

1.

:1
HR

5:

5
1.
1
CBL 264.709 264.709
9.400 7.600
BED WIDTH 18.000
HYDRAULIC PARTICULARS
OLD NEW
Bed Width 9.4 18 m Cutting Levels
Distance from Bank 8.4 (9m for
n value 0.03 0.03 Edge (m)
0.0 3.0 6.0
ground level)
Average

CBL 264.709 264.709 m Ground Level 269.805 269.845 269.605 269.545 269.700

prism 1.5:1 1.5:1 Top of F&F Levels 269.250 269.265 269.275 269.245 269.259

Extension in width= 7.6 m Top of HR Levels 268.910 268.935 268.950 268.920 268.929

Excavated Level 264.700 264.690 264.670 264.775 264.709

Excavated Areas of canal Classification Levels Classification Depths


top width Bottom area in Sq.m=
soil depth ( c)
Top of Soils Level
269.700 m Depth of soils
0.441 m
(a) width (b) 1/2*(a+b)*c
In all
7.60 7.60 0.441 3.352 269.259 m
soils= F&F top level Depth of F&F 0.330 m
In F&F= 7.60 7.60 0.330 2.508 HR Top Level 268.929 m Depth of HR 4.220 m
In HR= 7.60 7.60 4.220 32.072 HR Bottom level 264.709 m Total Depth 4.991 m

Contractor Asst Executive Engineer Deputy Executive Engineer Executive Engineer


HNSS Sub Division HNSS Sub Division HNSS Division no-1
Nandikotkur Nandikotkur Nandikotkur
CROSS SECTION @ Km 2.150
L/S R/S
7.60 Avg spoil bank level
269.645 SPOIL BANK
soils
4.940 269.310

F&F 268.775

1.

:1
HR

5:

5
1.
1
CBL 264.705 264.705
9.400 7.600
BED WIDTH 18.000
HYDRAULIC PARTICULARS
OLD NEW
Bed Width 9.4 18 m Cutting Levels
Distance from Bank 8.4 (9m for
n value 0.03 0.03 Edge (m)
0.0 3.0 6.0
ground level)
Average

CBL 264.705 264.705 m Ground Level 269.725 269.695 269.650 269.510 269.645

prism 1.5:1 1.5:1 Top of F&F Levels 269.290 269.305 269.320 269.325 269.310

Extension in width= 7.6 m Top of HR Levels 268.770 268.790 268.805 268.735 268.775

Excavated Level 264.700 264.690 264.720 264.710 264.705

Excavated Areas of canal Classification Levels Classification Depths


top width Bottom area in Sq.m=
soil depth ( c)
Top of Soils Level
269.645 m Depth of soils
0.335 m
(a) width (b) 1/2*(a+b)*c
In all
7.60 7.60 0.335 2.546 F&F top level 269.310 m Depth of F&F 0.535 m
soils=
In F&F= 7.60 7.60 0.535 4.066 HR Top Level 268.775 m Depth of HR 4.070 m
In HR= 7.60 7.60 4.070 30.932 HR Bottom level 264.705 m Total Depth 4.940 m

Contractor Asst Executive Engineer Deputy Executive Engineer Executive Engineer


HNSS Sub Division HNSS Sub Division HNSS Division no-1
Nandikotkur Nandikotkur Nandikotkur
CROSS SECTION @ Km 2.175
L/S R/S
8.00 Avg spoil bank level
269.916 SPOIL BANK
soils
5.215 269.301

F&F 268.646

1.

1
HR

5:
5:

1.
1
CBL 264.701 264.701
9.400 8.000
BED WIDTH 18.000
HYDRAULIC PARTICULARS
OLD NEW
Bed Width 9.4 18 m Cutting Levels
Distance from Bank 8.4 (9m for
n value 0.03 0.03 Edge (m)
0.0 3.0 6.0
ground level)
Average

CBL 264.701 264.701 m Ground Level 270.140 270.005 269.805 269.715 269.916

prism 1.5:1 1.5:1 Top of F&F Levels 269.290 269.310 269.325 269.280 269.301

Extension in width= 8 m Top of HR Levels 268.640 268.655 268.630 268.660 268.646

Excavated Level 264.690 264.710 264.725 264.680 264.701

Excavated Areas of canal Classification Levels Classification Depths


top width Bottom area in Sq.m=
soil depth ( c) 269.916 m Depth of soils
(a) width (b) 1/2*(a+b)*c Top of Soils Level 0.615 m
In all
8.00 8.00 0.615 4.920 269.301 m
soils= F&F top level Depth of F&F 0.655 m
In F&F= 8.00 8.00 0.655 5.240 HR Top Level 268.646 m Depth of HR 3.945 m
In HR= 8.00 8.00 3.945 31.560 HR Bottom level 264.701 m Total Depth 5.215 m

Contractor Asst Executive Engineer Deputy Executive Engineer Executive Engineer


HNSS Sub Division HNSS Sub Division HNSS Division no-1
Nandikotkur Nandikotkur Nandikotkur
CROSS SECTION @ Km 2.200
L/S R/S
7.60 Avg spoil bank level
270.066 SPOIL BANK
soils
5.369 269.312

F&F 268.672

1.

1
HR

5:
5:

1.
1
CBL 264.697 264.697
9.400 7.600
BED WIDTH 18.000
HYDRAULIC PARTICULARS
OLD NEW
Bed Width 9.4 18 m Cutting Levels
Distance from Bank 8.4 (9m for
n value 0.03 0.03 Edge (m)
0.0 3.0 6.0
ground level)
Average

CBL 264.697 264.697 m Ground Level 270.205 270.100 269.880 270.080 270.066

prism 1.5:1 1.5:1 Top of F&F Levels 269.300 269.320 269.315 269.315 269.312

Extension in width= 7.6 m Top of HR Levels 268.660 268.690 268.705 268.635 268.672

Excavated Level 264.680 264.700 264.720 264.690 264.697

Excavated Areas of canal Classification Levels Classification Depths


top width Bottom area in Sq.m=
soil depth ( c)
Top of Soils Level
270.066 m Depth of soils
0.754 m
(a) width (b) 1/2*(a+b)*c
In all
7.60 7.60 0.754 5.730 269.312 m
soils= F&F top level Depth of F&F 0.640 m
In F&F= 7.60 7.60 0.640 4.864 HR Top Level 268.672 m Depth of HR 3.975 m
In HR= 7.60 7.60 3.975 30.210 HR Bottom level 264.697 m Total Depth 5.369 m

Contractor Asst Executive Engineer Deputy Executive Engineer Executive Engineer


HNSS Sub Division HNSS Sub Division HNSS Division no-1
Nandikotkur Nandikotkur Nandikotkur
CROSS SECTION @ Km 2.225
L/S R/S
8.10 Avg spoil bank level
269.522 SPOIL BANK
soils
4.829 269.308

F&F 268.503

1.

1
HR

5:
5:

1.
1
CBL 264.693 264.693
9.400 8.100
BED WIDTH 18.000
HYDRAULIC PARTICULARS
OLD NEW
Bed Width 9.4 18 m Cutting Levels
Distance from Bank 8.4 (9m for
n value 0.03 0.03 Edge (m)
0.0 3.0 6.0
ground level)
Average

CBL 264.693 264.693 m Ground Level 269.610 269.585 269.535 269.360 269.522

prism 1.5:1 1.5:1 Top of F&F Levels 269.300 269.320 269.290 269.320 269.308

Extension in width= 8.1 m Top of HR Levels 268.550 268.490 268.470 268.500 268.503

Excavated Level 264.680 264.700 264.710 264.680 264.693

Excavated Areas of canal Classification Levels Classification Depths


top width Bottom area in Sq.m=
soil depth ( c) 269.522 m Depth of soils
(a) width (b) 1/2*(a+b)*c Top of Soils Level 0.214 m
In all
8.10 8.10 0.214 1.733 269.308 m
soils= F&F top level Depth of F&F 0.805 m
In F&F= 8.10 8.10 0.805 6.521 HR Top Level 268.503 m Depth of HR 3.810 m
In HR= 8.10 8.10 3.810 30.861 HR Bottom level 264.693 m Total Depth 4.829 m

Contractor Asst Executive Engineer Deputy Executive Engineer Executive Engineer


HNSS Sub Division HNSS Sub Division HNSS Division no-1
Nandikotkur Nandikotkur Nandikotkur
CROSS SECTION @ Km 2.250
L/S R/S
8.10 Avg spoil bank level
269.588 SPOIL BANK
soils
4.899 269.309

F&F 268.399

1.

1
HR

5:
5:

1.
1
CBL 264.689 264.689
9.400 8.100
BED WIDTH 18.000
HYDRAULIC PARTICULARS
OLD NEW
Bed Width 9.4 18 m Cutting Levels
Distance from Bank 8.4 (9m for
n value 0.03 0.03 Edge (m)
0.0 3.0 6.0
ground level)
Average

CBL 264.689 264.689 m Ground Level 269.635 269.605 269.550 269.560 269.588

prism 1.5:1 1.5:1 Top of F&F Levels 269.300 269.320 269.310 269.305 269.309

Extension in width= 8.1 m Top of HR Levels 268.390 268.410 268.430 268.365 268.399

Excavated Level 264.680 264.695 264.700 264.680 264.689

Excavated Areas of canal Classification Levels Classification Depths


top width Bottom area in Sq.m=
soil depth ( c) 269.588 m Depth of soils
(a) width (b) 1/2*(a+b)*c Top of Soils Level 0.279 m
In all
8.10 8.10 0.279 2.341 269.309 m
soils= F&F top level Depth of F&F 0.910 m
In F&F= 8.10 8.10 0.910 7.371 HR Top Level 268.399 m Depth of HR 3.710 m
In HR= 8.10 8.10 3.710 30.051 HR Bottom level 264.689 m Total Depth 4.899 m

Contractor Asst Executive Engineer Deputy Executive Engineer Executive Engineer


HNSS Sub Division HNSS Sub Division HNSS Division no-1
Nandikotkur Nandikotkur Nandikotkur
CROSS SECTION @ Km 2.275
L/S R/S
8.10 Avg spoil bank level
269.717 SPOIL BANK
soils
5.031 269.306

F&F 268.101

1.

1
5:
5:

1.
1
CBL 264.686 264.686
9.400 8.100
BED WIDTH 18.000
HYDRAULIC PARTICULARS
OLD NEW
Bed Width 9.4 18 m Cutting Levels
Distance from Bank 8.4 (9m for
n value 0.03 0.03 Edge (m)
0.0 3.0 6.0
ground level)
Average

CBL 264.686 264.686 m Ground Level 269.805 269.755 269.705 269.605 269.717

prism 1.5:1 1.5:1 Top of F&F Levels 269.320 269.320 269.350 269.235 269.306

Extension in width= 8.1 m Top of HR Levels 268.090 268.150 268.005 268.160 268.101

Excavated Level 264.680 264.700 264.690 264.675 264.686

Excavated Areas of canal Classification Levels Classification Depths


top width Bottom area in Sq.m=
soil depth ( c)
Top of Soils Level
269.717 m Depth of soils
0.411 m
(a) width (b) 1/2*(a+b)*c
In all
8.10 8.10 0.411 3.454 269.306 m
soils= F&F top level Depth of F&F 1.205 m
In F&F= 8.10 8.10 1.205 9.760 HR Top Level 268.101 m Depth of HR 3.415 m
In HR= 8.10 8.10 3.415 27.662 HR Bottom level 264.686 m Total Depth 5.031 m

Contractor Asst Executive Engineer Deputy Executive Engineer Executive Engineer


HNSS Sub Division HNSS Sub Division HNSS Division no-1
Nandikotkur Nandikotkur Nandikotkur
CROSS SECTION @ Km 2.300
L/S R/S
7.00 Avg spoil bank level
269.737 SPOIL BANK
soils
5.055 269.142

F&F 268.247

1.

1
5:
5:

1.
1
CBL 264.682 264.682
9.400 7.000
BED WIDTH 18.000
HYDRAULIC PARTICULARS
OLD NEW
Bed Width 9.4 18 m Cutting Levels
Distance from Bank 8.4 (9m for
n value 0.03 0.03 Edge (m)
0.0 3.0 6.0
ground level)
Average

CBL 264.682 264.682 m Ground Level 269.815 269.785 269.705 269.645 269.737

prism 1.5:1 1.5:1 Top of F&F Levels 269.140 269.160 269.130 269.140 269.142

Extension in width= 7 m Top of HR Levels 268.240 268.270 268.285 268.195 268.247

Excavated Level 264.670 264.690 264.665 264.705 264.682

Excavated Areas of canal Classification Levels Classification Depths


top width Bottom area in Sq.m=
soil depth ( c) 269.737 m Depth of soils
(a) width (b) 1/2*(a+b)*c
Top of Soils Level 0.595 m
In all
7.00 7.00 0.595 4.165 269.142 m
soils= F&F top level Depth of F&F 0.895 m
In F&F= 7.00 7.00 0.895 6.265 HR Top Level 268.247 m Depth of HR 3.565 m
In HR= 7.00 7.00 3.565 24.955 HR Bottom level 264.682 m Total Depth 5.055 m

Contractor Asst Executive Engineer Deputy Executive Engineer Executive Engineer


HNSS Sub Division HNSS Sub Division HNSS Division no-1
Nandikotkur Nandikotkur Nandikotkur
CROSS SECTION @ Km 2.325
L/S R/S
7.60 Avg spoil bank level
269.604 SPOIL BANK
soils
4.926 269.318

F&F 268.998

1.

1
5:
5:

1.
1
CBL 264.678 264.678
9.400 7.600
BED WIDTH 18.000
HYDRAULIC PARTICULARS
OLD NEW
Bed Width 9.4 18 m Cutting Levels
Distance from Bank 8.4 (9m for
n value 0.03 0.03 Edge (m)
0.0 3.0 6.0
ground level)
Average

CBL 264.678 264.678 m Ground Level 269.720 269.695 269.645 269.355 269.604

prism 1.5:1 1.5:1 Top of F&F Levels 269.310 269.290 269.325 269.345 269.318

Extension in width= 7.6 m Top of HR Levels 268.900 269.005 269.150 268.935 268.998

Excavated Level 264.670 264.690 264.660 264.690 264.678

Excavated Areas of canal Classification Levels Classification Depths


top width Bottom area in Sq.m=
soil depth ( c) 269.604 m Depth of soils
(a) width (b) 1/2*(a+b)*c Top of Soils Level 0.286 m
In all
7.60 7.60 0.286 2.404 269.318 m
soils= F&F top level Depth of F&F 0.320 m
In F&F= 7.60 7.60 0.320 2.432 HR Top Level 268.998 m Depth of HR 4.320 m
In HR= 7.60 7.60 4.320 32.832 HR Bottom level 264.678 m Total Depth 4.926 m

Contractor Asst Executive Engineer Deputy Executive Engineer Executive Engineer


HNSS Sub Division HNSS Sub Division HNSS Division no-1
Nandikotkur Nandikotkur Nandikotkur
CROSS SECTION @ Km 2.350
L/S R/S
8.60 Avg spoil bank level
269.534 SPOIL BANK
soils
4.804 269.214

F&F 268.959

1.

1
5:
5:

1.
1
CBL 264.674 264.730
9.400 8.600
BED WIDTH 18.000
HYDRAULIC PARTICULARS
OLD NEW
Bed Width 9.4 18 m Cutting Levels
Distance from Bank 8.4 (9m for
n value 0.03 0.03 Edge (m)
0.0 3.0 6.0
ground level)
Average

CBL 264.674 264.674 m Ground Level 269.680 269.625 269.585 269.245 269.534

prism 1.5:1 1.5:1 Top of F&F Levels 269.205 269.250 269.210 269.190 269.214

Extension in width= 8.6 m Top of HR Levels 268.940 268.975 268.970 268.950 268.959

Excavated Level 264.670 264.690 264.705 264.855 264.730

Excavated Areas of canal Classification Levels Classification Depths


top width Bottom area in Sq.m=
soil depth ( c) 269.534 m Depth of soils
(a) width (b) 1/2*(a+b)*c Top of Soils Level 0.320 m
In all
8.60 8.60 0.320 2.752 269.214 m
soils= F&F top level Depth of F&F 0.255 m
In F&F= 8.60 8.60 0.255 2.193 HR Top Level 268.959 m Depth of HR 4.229 m
In HR= 8.60 8.60 4.229 36.369 HR Bottom level 264.730 m Total Depth 4.804 m

Contractor Asst Executive Engineer Deputy Executive Engineer Executive Engineer


HNSS Sub Division HNSS Sub Division HNSS Division no-1
Nandikotkur Nandikotkur Nandikotkur
CROSS SECTION @ Km 2.375
L/S R/S
8.60 Avg spoil bank level
269.701 SPOIL BANK
soils
4.971 269.360

F&F 268.620

1.

1
HR

5:
5:

1.
1
CBL 264.670 264.730
9.400 8.600
BED WIDTH 18.000
HYDRAULIC PARTICULARS
OLD NEW
Bed Width 9.4 18 m Cutting Levels
Distance from Bank 8.4 (9m for
n value 0.03 0.03 Edge (m)
0.0 3.0 6.0
ground level)
Average

CBL 264.670 264.670 m Ground Level 269.795 269.735 269.675 269.600 269.701

prism 1.5:1 1.5:1 Top of F&F Levels 269.355 269.370 269.375 269.340 269.360

Extension in width= 8.6 m Top of HR Levels 268.610 268.595 268.630 268.645 268.620

Excavated Level 264.660 264.685 264.695 264.880 264.730

Excavated Areas of canal Classification Levels Classification Depths


top width Bottom area in Sq.m=
soil depth ( c) 269.701 m Depth of soils
(a) width (b) 1/2*(a+b)*c Top of Soils Level 0.341 m
In all
8.60 8.60 0.341 2.867 269.360 m
soils= F&F top level Depth of F&F 0.740 m
In F&F= 8.60 8.60 0.740 6.364 HR Top Level 268.620 m Depth of HR 3.890 m
In HR= 8.60 8.60 3.890 33.454 HR Bottom level 264.730 m Total Depth 4.971 m

Contractor Asst Executive Engineer Deputy Executive Engineer Executive Engineer


HNSS Sub Division HNSS Sub Division HNSS Division no-1
Nandikotkur Nandikotkur Nandikotkur
CROSS SECTION @ Km 2.400
L/S R/S
7.60 Avg spoil bank level
269.662 SPOIL BANK
soils
4.942 269.341

F&F 269.026

1.

1
HR

5:
5:

1.
1
CBL 264.666 264.720
9.400 7.600
BED WIDTH 18.000
HYDRAULIC PARTICULARS
OLD NEW
Bed Width 9.4 18 m Cutting Levels
Distance from Bank 8.4 (9m for
n value 0.03 0.03 Edge (m)
0.0 3.0 6.0
ground level)
Average

CBL 264.666 264.666 m Ground Level 269.715 269.685 269.605 269.645 269.662

prism 1.5:1 1.5:1 Top of F&F Levels 269.320 269.350 269.385 269.310 269.341

Extension in width= 7.6 m Top of HR Levels 269.010 269.035 269.055 269.005 269.026

Excavated Level 264.625 264.645 264.670 264.725 264.720

Excavated Areas of canal Classification Levels Classification Depths


top width Bottom area in Sq.m=
soil depth ( c) 269.662 m Depth of soils
(a) width (b) 1/2*(a+b)*c Top of Soils Level 0.321 m
In all
7.60 7.60 0.321 2.699 269.341 m
soils= F&F top level Depth of F&F 0.315 m
In F&F= 7.60 7.60 0.315 2.394 HR Top Level 269.026 m Depth of HR 4.306 m
In HR= 7.60 7.60 4.306 32.726 HR Bottom level 264.720 m Total Depth 4.942 m

Contractor Asst Executive Engineer Deputy Executive Engineer Executive Engineer


HNSS Sub Division HNSS Sub Division HNSS Division no-1
Nandikotkur Nandikotkur Nandikotkur
CROSS SECTION @ Km 2.425
L/S R/S
8.60 Avg spoil bank level
269.696 SPOIL BANK
soils
4.576 269.332

F&F 268.597

1.

1
HR

5:
5:

1.
1
CBL 264.662 265.120
9.400 8.600
BED WIDTH 18.000
HYDRAULIC PARTICULARS
OLD NEW
Bed Width 9.4 18 m Cutting Levels
Distance from Bank 8.6 (9m for
n value 0.03 0.03 Edge (m)
0.0 3.0 6.0
ground level)
Average

CBL 264.662 264.662 m Ground Level 269.810 269.735 269.675 269.565 269.696

prism 1.5:1 1.5:1 Top of F&F Levels 269.310 269.355 269.330 269.335 269.332

Extension in width= 8.6 m Top of HR Levels 268.580 268.610 268.630 268.570 268.597

Excavated Level 265.100 265.150 265.130 265.100 265.120

Excavated Areas of canal Classification Levels Classification Depths


top width Bottom area in Sq.m=
soil depth ( c) 269.696 m Depth of soils
(a) width (b) 1/2*(a+b)*c Top of Soils Level 0.364 m
In all
8.60 8.60 0.364 3.128 269.332 m
soils= F&F top level Depth of F&F 0.735 m
In F&F= 8.60 8.60 0.735 6.321 HR Top Level 268.597 m Depth of HR 3.477 m
In HR= 8.60 8.60 3.477 29.902 HR Bottom level 265.120 m Total Depth 4.576 m

Contractor Asst Executive Engineer Deputy Executive Engineer Executive Engineer


HNSS Sub Division HNSS Sub Division HNSS Division no-1
Nandikotkur Nandikotkur Nandikotkur
CROSS SECTION @ Km 2.450
L/S R/S
8.60 Avg spoil bank level
269.769 SPOIL BANK
soils
4.774 269.324

F&F 268.909

1.

1
HR

5:
5:

1.
1
CBL 264.659 264.995
9.400 8.600
BED WIDTH 18.000
HYDRAULIC PARTICULARS
OLD NEW
Bed Width 9.4 18 m Cutting Levels
Distance from Bank 8.4 (9m for
n value 0.03 0.03 Edge (m)
0.0 3.0 6.0
ground level)
Average

CBL 264.659 264.659 m Ground Level 269.805 269.825 269.715 269.730 269.769

prism 1.5:1 1.5:1 Top of F&F Levels 269.300 269.330 269.350 269.315 269.324

Extension in width= 8.6 m Top of HR Levels 268.895 268.920 268.905 268.915 268.909

Excavated Level 264.990 264.980 265.000 265.010 264.995

Excavated Areas of canal Classification Levels Classification Depths


top width Bottom area in Sq.m=
soil depth ( c) 269.769 m Depth of soils
(a) width (b) 1/2*(a+b)*c Top of Soils Level 0.445 m
In all
8.60 8.60 0.445 3.827 269.324 m
soils= F&F top level Depth of F&F 0.415 m
In F&F= 8.60 8.60 0.415 3.569 HR Top Level 268.909 m Depth of HR 3.914 m
In HR= 8.60 8.60 3.914 33.660 HR Bottom level 264.995 m Total Depth 4.774 m

Contractor Asst Executive Engineer Deputy Executive Engineer Executive Engineer


HNSS Sub Division HNSS Sub Division HNSS Division no-1
Nandikotkur Nandikotkur Nandikotkur
CROSS SECTION @ Km 2.475
L/S R/S
8.60 Avg spoil bank level
269.759 SPOIL BANK
soils
4.644 269.380

F&F 268.810

1.

1
HR

5:
5:

1.
1
CBL 264.655 265.115
9.400 8.600
BED WIDTH 18.000
HYDRAULIC PARTICULARS
OLD NEW
Bed Width 9.4 18 m Cutting Levels
Distance from Bank 8.4 (9m for
n value 0.03 0.03 Edge (m)
0.0 3.0 6.0
ground level)
Average

CBL 264.655 264.655 m Ground Level 269.835 269.795 269.685 269.720 269.759

prism 1.5:1 1.5:1 Top of F&F Levels 269.370 269.405 269.420 269.325 269.380

Extension in width= 8.6 m Top of HR Levels 268.805 268.825 268.840 268.770 268.810

Excavated Level 265.100 265.230 265.150 264.980 265.115

Excavated Areas of canal Classification Levels Classification Depths


top width Bottom area in Sq.m=
soil depth ( c) 269.759 m Depth of soils
(a) width (b) 1/2*(a+b)*c Top of Soils Level 0.379 m
In all
8.60 8.60 0.379 3.259 269.380 m
soils= F&F top level Depth of F&F 0.570 m
In F&F= 8.60 8.60 0.570 4.902 HR Top Level 268.810 m Depth of HR 3.695 m
In HR= 8.60 8.60 3.695 31.777 HR Bottom level 265.115 m Total Depth 4.644 m

Contractor Asst Executive Engineer Deputy Executive Engineer Executive Engineer


HNSS Sub Division HNSS Sub Division HNSS Division no-1
Nandikotkur Nandikotkur Nandikotkur
CROSS SECTION @ Km 2.500
L/S R/S
8.60 Avg spoil bank level
270.191 SPOIL BANK
soils
5.016 269.371

F&F 269.001

1.

1
HR

5:
5:

1.
1
CBL 264.651 265.175
9.400 8.600
BED WIDTH 18.000
HYDRAULIC PARTICULARS
OLD NEW
Bed Width 9.4 18 m Cutting Levels
Distance from Bank 8.4 (9m for
n value 0.03 0.03 Edge (m)
0.0 3.0 6.0
ground level)
Average

CBL 264.651 264.651 m Ground Level 270.325 270.210 270.175 270.055 270.191

prism 1.5:1 1.5:1 Top of F&F Levels 269.365 269.380 269.425 269.315 269.371

Extension in width= 8.6 m Top of HR Levels 269.100 268.990 268.975 268.940 269.001

Excavated Level 265.100 265.130 265.150 265.320 265.175

Excavated Areas of canal Classification Levels Classification Depths


top width Bottom area in Sq.m=
soil depth ( c) 270.191 m Depth of soils
(a) width (b) 1/2*(a+b)*c Top of Soils Level 0.820 m
In all
8.60 8.60 0.820 7.052 269.371 m
soils= F&F top level Depth of F&F 0.370 m
In F&F= 8.60 8.60 0.370 3.182 HR Top Level 269.001 m Depth of HR 3.826 m
In HR= 8.60 8.60 3.826 32.904 HR Bottom level 265.175 m Total Depth 5.016 m

Contractor Asst Executive Engineer Deputy Executive Engineer Executive Engineer


HNSS Sub Division HNSS Sub Division HNSS Division no-1
Nandikotkur Nandikotkur Nandikotkur
CROSS SECTION @ Km 2.525
L/S R/S
8.60 Avg spoil bank level
269.751 SPOIL BANK
soils
4.941 269.387

F&F 268.807

1.

1
HR

5:
5:

1.
1
CBL 264.647 264.810
9.400 8.600
BED WIDTH 18.000
HYDRAULIC PARTICULARS
OLD NEW
Bed Width 9.4 18 m Cutting Levels
Distance from Bank 8.4 (9m for
n value 0.03 0.03 Edge (m)
0.0 3.0 6.0
ground level)
Average

CBL 264.647 264.647 m Ground Level 269.805 269.775 269.730 269.695 269.751

prism 1.5:1 1.5:1 Top of F&F Levels 269.370 269.400 269.385 269.395 269.387

Extension in width= 8.6 m Top of HR Levels 268.800 268.790 268.820 268.820 268.807

Excavated Level 264.630 264.650 264.640 265.320 264.810

Excavated Areas of canal Classification Levels Classification Depths


top width Bottom area in Sq.m=
soil depth ( c) 269.751 m Depth of soils
(a) width (b) 1/2*(a+b)*c
Top of Soils Level 0.364 m
In all
8.60 8.60 0.364 3.130 269.387 m
soils= F&F top level Depth of F&F 0.580 m
In F&F= 8.60 8.60 0.580 4.988 HR Top Level 268.807 m Depth of HR 3.997 m
In HR= 8.60 8.60 3.997 34.374 HR Bottom level 264.810 m Total Depth 4.941 m

Contractor Asst Executive Engineer Deputy Executive Engineer Executive Engineer


HNSS Sub Division HNSS Sub Division HNSS Division no-1
Nandikotkur Nandikotkur Nandikotkur
CROSS SECTION @ Km 2.550
L/S R/S
8.60 Avg spoil bank level
269.576 SPOIL BANK
soils
4.846 269.298

F&F 268.478

1.

1
HR

5:
5:

1.
1
CBL 264.643 264.730
9.400 8.600
BED WIDTH 18.000
HYDRAULIC PARTICULARS
OLD NEW
Bed Width 9.4 18 m Cutting Levels
Distance from Bank 8.4 (9m for
n value 0.03 0.03 Edge (m)
0.0 3.0 6.0
ground level)
Average

CBL 264.643 264.643 m Ground Level 269.620 269.585 269.505 269.595 269.576

prism 1.5:1 1.5:1 Top of F&F Levels 269.280 269.305 269.315 269.290 269.298

Extension in width= 8.6 m Top of HR Levels 268.470 268.495 268.510 268.435 268.478

Excavated Level 264.630 264.655 264.660 264.975 264.730

Excavated Areas of canal Classification Levels Classification Depths


top width Bottom area in Sq.m=
soil depth ( c) 269.576 m Depth of soils
(a) width (b) 1/2*(a+b)*c Top of Soils Level 0.278 m
In all
8.60 8.60 0.278 2.391 269.298 m
soils= F&F top level Depth of F&F 0.820 m
In F&F= 8.60 8.60 0.820 7.052 HR Top Level 268.478 m Depth of HR 3.748 m
In HR= 8.60 8.60 3.748 32.233 HR Bottom level 264.730 m Total Depth 4.846 m

Contractor Asst Executive Engineer Deputy Executive Engineer Executive Engineer


HNSS Sub Division HNSS Sub Division HNSS Division no-1
Nandikotkur Nandikotkur Nandikotkur
CROSS SECTION @ Km 2.575
L/S R/S
8.60 Avg spoil bank level
269.912 SPOIL BANK
soils
5.077 269.309

F&F 268.679

1.

1
HR

5:
5:

1.
1
CBL 264.639 264.835
9.400 8.600
BED WIDTH 18.000
HYDRAULIC PARTICULARS
OLD NEW
Bed Width 9.4 18 m Cutting Levels
Distance from Bank 8.4 (9m for
n value 0.03 0.03 Edge (m)
0.0 3.0 6.0
ground level)
Average

CBL 264.639 264.639 m Ground Level 269.995 269.950 269.905 269.800 269.912

prism 1.5:1 1.5:1 Top of F&F Levels 269.300 269.325 269.290 269.320 269.309

Extension in width= 8.6 m Top of HR Levels 268.670 268.690 268.710 268.645 268.679

Excavated Level 264.625 264.640 264.660 265.415 264.835

Excavated Areas of canal Classification Levels Classification Depths


top width Bottom area in Sq.m=
soil depth ( c) 269.912 m Depth of soils
(a) width (b) 1/2*(a+b)*c Top of Soils Level 0.603 m
In all
8.60 8.60 0.603 5.186 269.309 m
soils= F&F top level Depth of F&F 0.630 m
In F&F= 8.60 8.60 0.630 5.418 HR Top Level 268.679 m Depth of HR 3.844 m
In HR= 8.60 8.60 3.844 33.058 HR Bottom level 264.835 m Total Depth 5.077 m

Contractor Asst Executive Engineer Deputy Executive Engineer Executive Engineer


HNSS Sub Division HNSS Sub Division HNSS Division no-1
Nandikotkur Nandikotkur Nandikotkur
CROSS SECTION @ Km 2.600
L/S R/S
7.60 Avg spoil bank level
270.105 SPOIL BANK
soils
5.470 269.435

F&F 268.475

1.

1
HR

5:
5:

1.
1
CBL 264.635 264.635
9.400 7.600
BED WIDTH 18.000
HYDRAULIC PARTICULARS
OLD NEW
Bed Width 9.4 18 m Cutting Levels
Distance from Bank 8.4 (9m for
n value 0.03 0.03 Edge (m)
0.0 3.0 6.0
ground level)
Average

CBL 264.635 264.635 m Ground Level 270.225 270.185 270.095 269.915 270.105

prism 1.5:1 1.5:1 Top of F&F Levels 269.425 269.445 269.460 269.410 269.435

Extension in width= 7.6 m Top of HR Levels 268.470 268.495 268.510 268.425 268.475

Excavated Level 264.620 264.640 264.670 264.610 264.635

Excavated Areas of canal Classification Levels Classification Depths


top width Bottom area in Sq.m=
soil depth ( c) 270.105 m Depth of soils
(a) width (b) 1/2*(a+b)*c
Top of Soils Level 0.670 m
In all
7.60 7.60 0.670 5.092 269.435 m
soils= F&F top level Depth of F&F 0.960 m
In F&F= 7.60 7.60 0.960 7.296 HR Top Level 268.475 m Depth of HR 3.840 m
In HR= 7.60 7.60 3.840 29.184 HR Bottom level 264.635 m Total Depth 5.470 m

Contractor Asst Executive Engineer Deputy Executive Engineer Executive Engineer


HNSS Sub Division HNSS Sub Division HNSS Division no-1
Nandikotkur Nandikotkur Nandikotkur
CROSS SECTION @ Km 2.625
L/S R/S
8.60 Avg spoil bank level
270.095 SPOIL BANK
soils
4.710 269.472

F&F 268.697

1.

1
HR

5:
5:

1.
1
CBL 264.632 265.385
9.400 8.600
BED WIDTH 18.000
HYDRAULIC PARTICULARS
OLD NEW
Bed Width 9.4 18 m Cutting Levels
Distance from Bank 8.4 (9m for
n value 0.03 0.03 Edge (m)
0.0 3.0 6.0
ground level)
Average

CBL 264.632 264.632 m Ground Level 270.245 270.185 270.055 269.895 270.095

prism 1.5:1 1.5:1 Top of F&F Levels 269.470 269.490 269.450 269.480 269.472

Extension in width= 8.6 m Top of HR Levels 268.680 268.710 268.725 268.675 268.697

Excavated Level 265.300 265.380 265.450 265.410 265.385

Excavated Areas of canal Classification Levels Classification Depths


top width Bottom area in Sq.m=
soil depth ( c) 270.095 m Depth of soils
(a) width (b) 1/2*(a+b)*c Top of Soils Level 0.623 m
In all
8.60 8.60 0.623 5.229
F&F top level
269.472 m Depth of F&F 0.775 m
soils=
In F&F= 8.60 8.60 0.775 6.665 HR Top Level 268.697 m Depth of HR 3.312 m
In HR= 8.60 8.60 3.312 28.483 HR Bottom level 265.385 m Total Depth 4.710 m

Contractor Asst Executive Engineer Deputy Executive Engineer Executive Engineer


HNSS Sub Division HNSS Sub Division HNSS Division no-1
Nandikotkur Nandikotkur Nandikotkur
CROSS SECTION @ Km 2.650
L/S R/S
8.40 Avg spoil bank level
270.083 SPOIL BANK
soils
5.058 269.498

F&F 268.298

1.

1
HR

5:
5:

1.
1
CBL 264.628 265.025
9.400 8.400
BED WIDTH 18.000
HYDRAULIC PARTICULARS
OLD NEW
Bed Width 9.4 18 m Cutting Levels
Distance from Bank 8.4 (9m for
n value 0.03 0.03 Edge (m)
0.0 3.0 6.0
ground level)
Average

CBL 264.628 264.628 m Ground Level 270.205 270.165 270.055 269.905 270.083

prism 1.5:1 1.5:1 Top of F&F Levels 269.485 269.510 269.480 269.515 269.498

Extension in width= 8.4 m Top of HR Levels 268.280 268.305 268.320 268.285 268.298

Excavated Level 265.000 265.100 265.080 264.920 265.025

Excavated Areas of canal Classification Levels Classification Depths


top width Bottom area in Sq.m=
soil depth ( c) 270.083 m Depth of soils
(a) width (b) 1/2*(a+b)*c Top of Soils Level 0.585 m
In all
8.40 8.40 0.585 4.914 269.498 m
soils= F&F top level Depth of F&F 1.200 m
In F&F= 8.40 8.40 1.200 10.080 HR Top Level 268.298 m Depth of HR 3.273 m
In HR= 8.40 8.40 3.273 27.493 HR Bottom level 265.025 m Total Depth 5.058 m

Contractor Asst Executive Engineer Deputy Executive Engineer Executive Engineer


HNSS Sub Division HNSS Sub Division HNSS Division no-1
Nandikotkur Nandikotkur Nandikotkur
CROSS SECTION @ Km 2.675
L/S R/S
8.60 Avg spoil bank level
269.992 SPOIL BANK
soils
4.797 269.508

F&F 267.983

1.

1
HR

5:
5:

1.
1
CBL 264.608 265.195
9.400 8.600
BED WIDTH 18.000
HYDRAULIC PARTICULARS
OLD NEW
Bed Width 9.4 18 m Cutting Levels
Distance from Bank 8.4 (9m for
n value 0.03 0.03 Edge (m)
0.0 3.0 6.0
ground level)
Average

CBL 264.608 264.608 m Ground Level 270.105 269.985 269.910 269.970 269.992

prism 1.5:1 1.5:1 Top of F&F Levels 269.500 269.485 269.515 269.530 269.508

Extension in width= 8.6 m Top of HR Levels 267.970 267.990 268.000 267.970 267.983

Excavated Level 265.100 265.200 265.150 265.330 265.195

Excavated Areas of canal Classification Levels Classification Depths


top width Bottom area in Sq.m=
soil depth ( c) 269.992 m Depth of soils
(a) width (b) 1/2*(a+b)*c
Top of Soils Level 0.484 m
In all
8.60 8.60 0.484 4.065 269.508 m
soils= F&F top level Depth of F&F 1.525 m
In F&F= 8.60 8.60 1.525 13.115 HR Top Level 267.983 m Depth of HR 2.788 m
In HR= 8.60 8.60 2.788 23.977 HR Bottom level 265.195 m Total Depth 4.797 m

Contractor Asst Executive Engineer Deputy Executive Engineer Executive Engineer


HNSS Sub Division HNSS Sub Division HNSS Division no-1
Nandikotkur Nandikotkur Nandikotkur
CROSS SECTION @ Km 2.700
L/S R/S
8.60 Avg spoil bank level
270.014 SPOIL BANK
soils
4.739 269.524

F&F 268.899

1.

1
HR

5:
5:

1.
1
CBL 264.604 265.275
9.400 8.600
BED WIDTH 18.000
HYDRAULIC PARTICULARS
OLD NEW
Bed Width 9.4 18 m Cutting Levels
Distance from Bank 8.6 (9m for
n value 0.03 0.03 Edge (m)
0.0 3.0 6.0
ground level)
Average

CBL 264.604 264.604 m Ground Level 270.320 270.285 270.005 269.445 270.014

prism 1.5:1 1.5:1 Top of F&F Levels 269.510 269.535 269.560 269.490 269.524

Extension in width= 8.6 m Top of HR Levels 268.870 268.910 268.890 268.925 268.899

Excavated Level 265.200 265.280 265.300 265.320 265.275

Excavated Areas of canal Classification Levels Classification Depths


top width Bottom area in Sq.m=
soil depth ( c) 270.014 m Depth of soils
(a) width (b) 1/2*(a+b)*c Top of Soils Level 0.490 m
In all
8.60 8.60 0.490 4.214 269.524 m
soils= F&F top level Depth of F&F 0.625 m
In F&F= 8.60 8.60 0.625 5.375 HR Top Level 268.899 m Depth of HR 3.624 m
In HR= 8.60 8.60 3.624 31.166 HR Bottom level 265.275 m Total Depth 4.739 m

Contractor Asst Executive Engineer Deputy Executive Engineer Executive Engineer


HNSS Sub Division HNSS Sub Division HNSS Division no-1
Nandikotkur Nandikotkur Nandikotkur
CROSS SECTION @ Km 2.725
L/S R/S
8.60 Avg spoil bank level
269.801 SPOIL BANK
soils
4.746 269.205

F&F 267.990

1.

1
HR

5:
5:

1.
1
CBL 264.600 265.055
9.400 8.600
BED WIDTH 18.000
HYDRAULIC PARTICULARS
OLD NEW
Bed Width 9.4 18 m Cutting Levels
Distance from Bank 8.4 (9m for
n value 0.03 0.03 Edge (m)
0.0 3.0 6.0
ground level)
Average

CBL 264.600 264.600 m Ground Level 270.000 269.910 269.840 269.455 269.801

prism 1.5:1 1.5:1 Top of F&F Levels 269.200 269.185 269.200 269.235 269.205

Extension in width= 8.6 m Top of HR Levels 267.980 268.000 268.050 267.930 267.990

Excavated Level 265.000 265.080 265.040 265.100 265.055

Excavated Areas of canal Classification Levels Classification Depths


top width Bottom area in Sq.m=
soil depth ( c) 269.801 m Depth of soils
(a) width (b) 1/2*(a+b)*c Top of Soils Level 0.596 m
In all
8.60 8.60 0.596 5.126 269.205 m
soils= F&F top level Depth of F&F 1.215 m
In F&F= 8.60 8.60 1.215 10.449 HR Top Level 267.990 m Depth of HR 2.935 m
In HR= 8.60 8.60 2.935 25.241 HR Bottom level 265.055 m Total Depth 4.746 m

Contractor Asst Executive Engineer Deputy Executive Engineer Executive Engineer


HNSS Sub Division HNSS Sub Division HNSS Division no-1
Nandikotkur Nandikotkur Nandikotkur
CROSS SECTION @ Km 2.750
L/S R/S
8.40 Avg spoil bank level
269.993 SPOIL BANK
soils
4.898 269.480

F&F 268.895

1.

1
HR

5:
5:

1.
1
CBL 264.595 265.095
9.400 8.400
BED WIDTH 18.000
HYDRAULIC PARTICULARS
OLD NEW
Bed Width 9.4 18 m Cutting Levels
Distance from Bank 8.4 (9m for
n value 0.03 0.03 Edge (m)
0.0 3.0 6.0
ground level)
Average

CBL 264.595 264.595 m Ground Level 270.190 270.085 269.975 269.720 269.993

prism 1.5:1 1.5:1 Top of F&F Levels 269.470 269.495 269.505 269.450 269.480

Extension in width= 8.4 m Top of HR Levels 268.890 268.905 268.915 268.870 268.895

Excavated Level 265.000 265.080 265.100 265.200 265.095

Excavated Areas of canal Classification Levels Classification Depths


top width Bottom area in Sq.m=
soil depth ( c) 269.993 m Depth of soils
(a) width (b) 1/2*(a+b)*c Top of Soils Level 0.513 m
In all
8.40 8.40 0.513 4.309 269.480 m
soils= F&F top level Depth of F&F 0.585 m
In F&F= 8.40 8.40 0.585 4.914 HR Top Level 268.895 m Depth of HR 3.800 m
In HR= 8.40 8.40 3.800 31.920 HR Bottom level 265.095 m Total Depth 4.898 m

Contractor Asst Executive Engineer Deputy Executive Engineer Executive Engineer


HNSS Sub Division HNSS Sub Division HNSS Division no-1
Nandikotkur Nandikotkur Nandikotkur
CROSS SECTION @ Km 2.775
L/S R/S
8.60 Avg spoil bank level
269.323 SPOIL BANK
soils
4.560 269.043

F&F 268.148

1.

1
HR

5:
5:

1.
1
CBL 264.763 264.763
9.400 8.600
BED WIDTH 18.000
HYDRAULIC PARTICULARS
OLD NEW
Bed Width 9.4 18 m Cutting Levels
Distance from Bank 8.6 (9m for
n value 0.03 0.03 Edge (m)
0.0 3.0 6.0
ground level)
Average

CBL 264.763 264.763 m Ground Level 269.323

prism 1.5:1 1.5:1 Top of F&F Levels 269.043

Extension in width= 8.6 m Top of HR Levels 268.148

Excavated Level 264.763

Excavated Areas of canal Classification Levels Classification Depths


top width Bottom area in Sq.m=
soil depth ( c) Top of Soils Level 269.323 m Depth of soils 0.280 m
(a) width (b) 1/2*(a+b)*c
In all
8.60 8.60 0.280 2.408 F&F top level 269.043 m Depth of F&F 0.895 m
soils=
In F&F= 8.60 8.60 0.895 7.697 HR Top Level 268.148 m Depth of HR 3.385 m
In HR= 8.60 8.60 3.385 29.111 HR Bottom level 264.763 m Total Depth 4.560 m

Contractor Asst Executive Engineer Deputy Executive Engineer Executive Engineer


HNSS Sub Division HNSS Sub Division HNSS Division no-1
Nandikotkur Nandikotkur Nandikotkur
CROSS SECTION @ Km 2.800
L/S R/S
8.60 Avg spoil bank level
269.429 SPOIL BANK
soils
4.670 269.029

F&F 267.959

1.

1
HR

5:
5:

1.
1
CBL 264.759 264.759
9.400 8.600
BED WIDTH 18.000
HYDRAULIC PARTICULARS
OLD NEW
Bed Width 9.4 18 m Cutting Levels
Distance from Bank 8.6 (9m for
n value 0.03 0.03 Edge (m)
0.0 3.0 6.0
ground level)
Average

CBL 264.759 264.759 m Ground Level 269.429

prism 1.5:1 1.5:1 Top of F&F Levels 269.029

Extension in width= 8.6 m Top of HR Levels 267.959

Excavated Level 264.759

Excavated Areas of canal Classification Levels Classification Depths


top width Bottom area in Sq.m=
soil depth ( c) Top of Soils Level 269.429 m Depth of soils 0.400 m
(a) width (b) 1/2*(a+b)*c
In all
8.60 8.60 0.400 3.440 F&F top level 269.029 m Depth of F&F 1.070 m
soils=
In F&F= 8.60 8.60 1.070 9.202 HR Top Level 267.959 m Depth of HR 3.200 m
In HR= 8.60 8.60 3.200 27.520 HR Bottom level 264.759 m Total Depth 4.670 m

Contractor Asst Executive Engineer Deputy Executive Engineer Executive Engineer


HNSS Sub Division HNSS Sub Division HNSS Division no-1
Nandikotkur Nandikotkur Nandikotkur
CROSS SECTION @ Km 2.825
L/S R/S
8.60 Avg spoil bank level
269.421 SPOIL BANK
soils
4.666 269.155

F&F 268.260

1.

1
HR

5:
5:

1.
1
CBL 264.755 264.755
9.400 8.600
BED WIDTH 18.000
HYDRAULIC PARTICULARS
OLD NEW
Bed Width 9.4 18 m Cutting Levels
Distance from Bank 8.6 (9m for
n value 0.03 0.03 Edge (m)
0.0 3.0 6.0
ground level)
Average

CBL 264.755 264.755 m Ground Level 269.421

prism 1.5:1 1.5:1 Top of F&F Levels 269.155

Extension in width= 8.6 m Top of HR Levels 268.260

Excavated Level 264.755

Excavated Areas of canal Classification Levels Classification Depths


top width Bottom area in Sq.m=
soil depth ( c) Top of Soils Level 269.421 m Depth of soils 0.266 m
(a) width (b) 1/2*(a+b)*c
In all
8.60 8.60 0.266 2.288 F&F top level 269.155 m Depth of F&F 0.895 m
soils=
In F&F= 8.60 8.60 0.895 7.697 HR Top Level 268.260 m Depth of HR 3.505 m
In HR= 8.60 8.60 3.505 30.143 HR Bottom level 264.755 m Total Depth 4.666 m

Contractor Asst Executive Engineer Deputy Executive Engineer Executive Engineer


HNSS Sub Division HNSS Sub Division HNSS Division no-1
Nandikotkur Nandikotkur Nandikotkur
CROSS SECTION @ Km 2.850
L/S R/S
7.60 Avg spoil bank level
269.441 SPOIL BANK
soils
4.141 269.068

F&F 268.568

1.

1
HR

5:
5:

1.
1
CBL 264.568 265.300
9.400 7.600
BED WIDTH 18.000
HYDRAULIC PARTICULARS
OLD NEW
Bed Width 9.4 18 m Cutting Levels
Distance from Bank 8.4 (9m for
n value 0.03 0.03 Edge (m)
0.0 3.0 6.0
ground level)
Average

CBL 264.568 264.568 m Ground Level 269.595 269.525 269.480 269.165 269.441

prism 1.5:1 1.5:1 Top of F&F Levels 269.060 269.085 269.100 269.025 269.068

Extension in width= 7.6 m Top of HR Levels 268.550 268.580 268.595 268.545 268.568

Excavated Level 265.200 265.280 265.320 265.400 265.300

Excavated Areas of canal Classification Levels Classification Depths


top width Bottom area in Sq.m=
soil depth ( c)
Top of Soils Level
269.441 m Depth of soils
0.373 m
(a) width (b) 1/2*(a+b)*c
In all
7.60 7.60 0.373 2.835 269.068 m
soils= F&F top level Depth of F&F 0.500 m
In F&F= 7.60 7.60 0.500 3.800 HR Top Level 268.568 m Depth of HR 3.268 m
In HR= 7.60 7.60 3.268 24.837 HR Bottom level 265.300 m Total Depth 4.141 m

Contractor Asst Executive Engineer Deputy Executive Engineer Executive Engineer


HNSS Sub Division HNSS Sub Division HNSS Division no-1
Nandikotkur Nandikotkur Nandikotkur
CROSS SECTION @ Km 2.875
L/S R/S
7.60 Avg spoil bank level
269.491 SPOIL BANK
soils
4.191 269.015

F&F 268.150

1.

1
HR

5:
5:

1.
1
CBL 264.565 265.300
9.400 7.600
BED WIDTH 18.000
HYDRAULIC PARTICULARS
OLD NEW
Bed Width 9.4 18 m Cutting Levels
Distance from Bank 8.4 (9m for
n value 0.03 0.03 Edge (m)
0.0 3.0 6.0
ground level)
Average

CBL 264.565 264.565 m Ground Level 269.610 269.535 269.475 269.345 269.491

prism 1.5:1 1.5:1 Top of F&F Levels 269.000 269.085 269.050 268.925 269.015

Extension in width= 7.6 m Top of HR Levels 268.140 268.175 268.190 268.095 268.150

Excavated Level 265.280 265.330 265.300 265.290 265.300

Excavated Areas of canal Classification Levels Classification Depths


top width Bottom area in Sq.m=
soil depth ( c) 269.491 m Depth of soils
(a) width (b) 1/2*(a+b)*c Top of Soils Level 0.476 m
In all
7.60 7.60 0.476 3.618 269.015 m
soils= F&F top level Depth of F&F 0.865 m
In F&F= 7.60 7.60 0.865 6.574 HR Top Level 268.150 m Depth of HR 2.850 m
In HR= 7.60 7.60 2.850 21.660 HR Bottom level 265.300 m Total Depth 4.191 m

Contractor Asst Executive Engineer Deputy Executive Engineer Executive Engineer


HNSS Sub Division HNSS Sub Division HNSS Division no-1
Nandikotkur Nandikotkur Nandikotkur
CROSS SECTION @ Km 2.900
L/S R/S
8.10 Avg spoil bank level
269.659 SPOIL BANK
soils
4.559 269.061

F&F 268.601

1.

1
HR

5:
5:

1.
1
CBL 264.561 265.100
9.400 8.100
BED WIDTH 18.000
HYDRAULIC PARTICULARS
OLD NEW
Bed Width 9.4 18 m Cutting Levels
Distance from Bank 8.4 (9m for
n value 0.03 0.03 Edge (m)
0.0 3.0 6.0
ground level)
Average

CBL 264.561 264.561 m Ground Level 269.720 269.690 269.620 269.605 269.659

prism 1.5:1 1.5:1 Top of F&F Levels 269.050 269.085 269.100 269.010 269.061

Extension in width= 8.1 m Top of HR Levels 268.595 268.625 268.640 268.545 268.601

Excavated Level 264.900 264.950 265.100 265.450 265.100

Excavated Areas of canal Classification Levels Classification Depths


top width Bottom area in Sq.m=
soil depth ( c) Top of Soils Level 269.659 m Depth of soils 0.598 m
(a) width (b) 1/2*(a+b)*c
In all
8.10 8.10 0.598 4.844 F&F top level 269.061 m Depth of F&F 0.460 m
soils=
In F&F= 8.10 8.10 0.460 3.726 HR Top Level 268.601 m Depth of HR 3.501 m
In HR= 8.10 8.10 3.501 28.358 HR Bottom level 265.100 m Total Depth 4.559 m

Contractor Asst Executive Engineer Deputy Executive Engineer Executive Engineer


HNSS Sub Division HNSS Sub Division HNSS Division no-1
Nandikotkur Nandikotkur Nandikotkur
CROSS SECTION @ Km 2.925
L/S R/S
7.60 Avg spoil bank level
269.707 SPOIL BANK
soils
5.007 269.002

F&F 268.547

1.

1
HR

5:
5:

1.
1
CBL 264.557 264.700
9.400 7.600
BED WIDTH 18.000
HYDRAULIC PARTICULARS
OLD NEW
Bed Width 9.4 18 m Cutting Levels
Distance from Bank 8.4 (9m for
n value 0.03 0.03 Edge (m)
0.0 3.0 6.0
ground level)
Average

CBL 264.557 264.557 m Ground Level 269.865 269.810 269.655 269.500 269.707

prism 1.5:1 1.5:1 Top of F&F Levels 269.100 269.045 268.900 268.965 269.002

Extension in width= 7.6 m Top of HR Levels 268.530 268.550 268.590 268.520 268.547

Excavated Level 264.600 264.680 264.750 264.770 264.700

Excavated Areas of canal Classification Levels Classification Depths


top width Bottom area in Sq.m=
soil depth ( c) 269.707 m Depth of soils
(a) width (b) 1/2*(a+b)*c Top of Soils Level 0.705 m
In all
7.60 7.60 0.705 5.358 269.002 m
soils= F&F top level Depth of F&F 0.455 m
In F&F= 7.60 7.60 0.455 3.458 HR Top Level 268.547 m Depth of HR 3.847 m
In HR= 7.60 7.60 3.847 29.237 HR Bottom level 264.700 m Total Depth 5.007 m

Contractor Asst Executive Engineer Deputy Executive Engineer Executive Engineer


HNSS Sub Division HNSS Sub Division HNSS Division no-1
Nandikotkur Nandikotkur Nandikotkur
CROSS SECTION @ Km 2.950
L/S R/S
7.60 Avg spoil bank level
269.442 SPOIL BANK
soils
4.777 268.858

F&F 268.148

1.

1
HR

5:
5:

1.
1
CBL 264.553 264.665
9.400 7.600
BED WIDTH 18.000
HYDRAULIC PARTICULARS
OLD NEW
Bed Width 9.4 18 m Cutting Levels
Distance from Bank 8.4 (9m for
n value 0.03 0.03 Edge (m)
0.0 3.0 6.0
ground level)
Average

CBL 264.553 264.553 m Ground Level 269.550 269.510 269.470 269.240 269.442

prism 1.5:1 1.5:1 Top of F&F Levels 268.840 268.860 268.890 268.840 268.858

Extension in width= 7.6 m Top of HR Levels 268.180 268.160 268.130 268.120 268.148

Excavated Level 264.540 264.560 264.590 264.970 264.665

Excavated Areas of canal Classification Levels Classification Depths


top width Bottom area in Sq.m=
soil depth ( c) 269.442 m Depth of soils
(a) width (b) 1/2*(a+b)*c Top of Soils Level 0.584 m
In all
7.60 7.60 0.584 4.438 268.858 m
soils= F&F top level Depth of F&F 0.710 m
In F&F= 7.60 7.60 0.710 5.396 HR Top Level 268.148 m Depth of HR 3.483 m
In HR= 7.60 7.60 3.483 26.471 HR Bottom level 264.665 m Total Depth 4.777 m

Contractor Asst Executive Engineer Deputy Executive Engineer Executive Engineer


HNSS Sub Division HNSS Sub Division HNSS Division no-1
Nandikotkur Nandikotkur Nandikotkur
CROSS SECTION @ Km 2.975
L/S R/S
8.60 Avg spoil bank level
269.359 SPOIL BANK
soils
4.614 268.724

F&F 268.339

1.

1
HR

5:
5:

1.
1
CBL 264.549 264.745
9.400 8.600
BED WIDTH 18.000
HYDRAULIC PARTICULARS
OLD NEW
Bed Width 9.4 18 m Cutting Levels
Distance from Bank 8.4 (9m for
n value 0.03 0.03 Edge (m)
0.0 3.0 6.0
ground level)
Average

CBL 264.549 264.549 m Ground Level 269.430 269.405 269.385 269.215 269.359

prism 1.5:1 1.5:1 Top of F&F Levels 268.750 268.730 268.720 268.695 268.724

Extension in width= 8.6 m Top of HR Levels 268.330 268.350 268.395 268.280 268.339

Excavated Level 264.700 264.790 264.750 264.740 264.745

Excavated Areas of canal Classification Levels Classification Depths


top width Bottom area in Sq.m=
soil depth ( c) 269.359 m Depth of soils
(a) width (b) 1/2*(a+b)*c Top of Soils Level 0.635 m
In all
8.60 8.60 0.635 5.461 268.724 m
soils= F&F top level Depth of F&F 0.385 m
In F&F= 8.60 8.60 0.385 3.311 HR Top Level 268.339 m Depth of HR 3.594 m
In HR= 8.60 8.60 3.594 30.908 HR Bottom level 264.745 m Total Depth 4.614 m

Contractor Asst Executive Engineer Deputy Executive Engineer Executive Engineer


HNSS Sub Division HNSS Sub Division HNSS Division no-1
Nandikotkur Nandikotkur Nandikotkur
CROSS SECTION @ Km 3.000
L/S R/S
8.60 Avg spoil bank level
268.995 SPOIL BANK
soils
4.390 268.781

F&F 268.126

1.
HR

1
5:
5:

1.
1
CBL 264.546 264.605
9.400 8.600
BED WIDTH 18.000
HYDRAULIC PARTICULARS
OLD NEW
Bed Width 9.4 18 m Cutting Levels
Distance from Bank 8.4 (9m for
n value 0.03 0.03 Edge (m)
0.0 3.0 6.0
ground level)
Average

CBL 264.546 264.546 m Ground Level 269.105 269.065 268.950 268.860 268.995

prism 1.5:1 1.5:1 Top of F&F Levels 268.770 268.795 268.810 268.750 268.781

Extension in width= 8.6 m Top of HR Levels 268.110 268.130 268.150 268.115 268.126

Excavated Level 264.530 264.550 264.540 264.800 264.605

Excavated Areas of canal Classification Levels Classification Depths


top width Bottom area in Sq.m=
soil depth ( c) 268.995 m Depth of soils
(a) width (b) 1/2*(a+b)*c Top of Soils Level 0.214 m
In all
8.60 8.60 0.214 1.797 268.781 m
soils= F&F top level Depth of F&F 0.655 m
In F&F= 8.60 8.60 0.655 5.633 HR Top Level 268.126 m Depth of HR 3.521 m
In HR= 8.60 8.60 3.521 30.281 HR Bottom level 264.605 m Total Depth 4.390 m

Contractor Asst Executive Engineer Deputy Executive Engineer Executive Engineer


HNSS Sub Division HNSS Sub Division HNSS Division no-1
Nandikotkur Nandikotkur Nandikotkur