Karwar To Gajendragad RFP PDF
Karwar To Gajendragad RFP PDF
Karwar To Gajendragad RFP PDF
-1-
Ministry of Road Transport & Highways
Government of India
Consultancy Services for FS/DPR of following Projects
Sl. Name of work / NH No. Section State Tentative Packag
No. Length e No.
(in Km)
1 “Consultancy Services for Feasibility Study, cum DPR, Survey Karwar-Kaiga- Karnataka. 318.00 1
and Preparation of Land plan for Upgradation of State Mundgod-
Highway to National Highway by Adopting LiDAR or similar Savanur-
Gadag-
technology for widening to Two lane with paved Shoulders
Gajendragad.
from Karwar-Kaiga-Mundgod-Savanur-Gadag-
Gajendragad. for an approximate length of 318.00 Kms
(including Bypass or Flyover Wherever necessary in
Town/City limits) in the State of Karnataka”.
-2-
INDEX
Sl.
Content Page No.
No.
1 Notice Inviting Tender (NIT)
2 Letter of Invitation
3 Annex -I : List of Projects along with Package Nos.
Annex-II : Procedure of Assessment of Least Cost to
4 Executive Engineer, National Highway Division, Karwar.
under special circumstances
5 Data Sheet
6 Appendix - I : Terms of Reference
7 Supplement -I: Additional Requirements for Hill Roads
8 Supplement - II: Additional Requirements for Bridges
9 Supplement – III : Additional requirement for safety audit
10 Enclosure - I : Manning Schedule
11 Enclosure - II : Qualification Requirements of Key Personnel
12 Enclosure - III: Schedule for Submission of Reports and Documents
13 Appendix – II : Formats for Eligibility
14 Appendix - III : Formats for Technical Proposals
15 Appendix - IV: Formats for Financial Proposals
16 Appendix - V: Detailed Evaluation Criteria
17 Appendix - VI: Draft Contract Agreement
-3-
Ministry of Road Transport & Highways
Government of India
NOTICE INVITING TENDER (NIT)
1. Executive Engineer, N.H. Division, Karwar has been assigned with the entrustment of the work of (as
per Annexure I ).
Tentative
Sl. Package
Name of work / NH No. Section State Length (in
No. No.
Km)
1 “Consultancy Services for Feasibility Study, cum DPR, Karwar- Karnataka. 318.00 1
Survey and Preparation of Land plan for Upgradation of Kaiga-
State Highway to National Highway by Adopting LiDAR Mundgod-
or similar technology for widening to Two lane with paved Savanur-
Gadag-
Shoulders from Karwar-Kaiga-Mundgod-Savanur-
Gajendragad
Gadag-Gajendragad. for an approximate length of 318.00 .
Kms (including Bypass or Flyover Wherever necessary in
Town/City limits) in the State of Karnataka”.
2. Proposals are hereby invited from eligible Consultants for preparation of Detailed
Project Report of “ Above mentioned works” The Letter of Invitation (LOI) and Terms of
Reference (ToR) including Request for Proposal (RFP) is available online on e-tender portal of
MORT&H https://morth.eproc.in.The document can also be downloaded from <Agency Website>.
Cost of the Document in MORT&H the form of a Non- refundable document fee of Rs. 5,000
(Rupees Five Thousand only) in the form of Demand Draft favouring Executive Engineer, N.H.
Division, Karwar and payable at <Karwar> must be furnished in a separate envelop while
submitting the proposal.
-4-
3.The RFP has also been uploaded on “INFRACON” (www.infracon.nic.in). As such before
submitting the proposal the Consultant shall mandatorily register and enlist themselves (the firm
and all key personnel), on the MoRTH portal “INFRACON” and furnish registration details along
with its RFP. A copy of Infracon Operation Procedure is also enclosed for bidder’s reference.
4.All the bidders registered on Infracon shall form a Team on Infracon and which would be
assigned unique Infracon Team ID. Bidders while submitting the proposal shall quote the
Infracon Team ID.
Yours sincerely,
Executive Engineer,
National Highway Division,
Karwar.
-5-
Tel:08382-225283 Fax:08382-225981
E-mail:[email protected] Website:https://morth.e-proc.in
Dear Sir,
1.Introduction
1.1.The Executive Engineer, National Highway Division, Karwar has been entrusted with
the assignment o f as per . as per Annexure-I Executive Engineer, National Highway Division,
Karwar now invites proposal from Technical consultants for carrying out detailed project
report as per details given in Annexure-1.
1.2A brief description of the assignment and its objectives are given in the Appendix-I,
“Terms of Reference”.
1.3.The Executive Engineer, National Highway Division, Karwar. invites Proposals (the
“Proposals”) through e-tender (on-line bid submission) for selection of Technical Consultant
(the “Consultant”) who shall prepare DPR. A Consultant with “a Particular Team” may
submit proposals for more than one package. However, a Consultant is not allowed to bid for
a package with more than one team. For the sake of clarity, it is mentioned that one consultant
can not submit two proposals/ bids for the same package. A consultant (either as sole or as in
JV/Association) can be awarded only upto 2 packages. Consultants are hereby invited to
submit proposals in the manner as prescribed in the RFP. A Consultant with “a Particular
Team” may submit
only one “proof of eligibility (Part 1)” and “Technical Proposal (Part II)” for any number
of packages applied for by them. However, the packages for which a Consultant with “a
Particular Team” applies should be clearly mentioned. Financial proposal for each
package are to be submitted separately. Financial proposal are only to be submitted online
and no hard copy of the financial proposal should be submitted. The most preferred bidder
(H-1) for each package would be determined on the basis of Quality and Cost as
mentioned in the RFP. Award of work to a Consultant with “a Particular Team” either as
sole or as in JV/Association shall be limited to one package only. In case, a Consultant
with “a Particular Team” turns out to be the most preferred bidder (H-1) in more than one
package, the package which is to be awarded to this Consultant with “a Particular Team”
shall be determined on the basis of least cost to Executive Engineer, National Highway
Division, Karwar. considering the financial quote of H-1 bidder and H-2 bidder limited to
those packages, which shall be worked out as per the procedure given in the RFP. The
consultants are hereby invited to submit proposals in the manner prescribed in the RFP.
-6-
1.4The consultants shall submit proposals either in sole capacity or in JV or in
Association. Joint Venture/Association shall not have more than two firms. Any entity
which has been barred by the Ministry of Road Transport and Highways (MORTH) or its
implementing agencies for the works of Expressways, National Highways, ISC and EI
Works and the bar subsists as on the date of application, would not be eligible to submit
the bid, either individually or as a member of a Joint Venture.
1.5 To obtain first hand information on the assignment and on the local conditions, the
consultants are encouraged to pay a visit to the client, local State PWDs and the project
site before submitting a proposal and attend a pre-proposal conference. They must fully
inform themselves of local and site conditions and take them into account in preparing the
proposal.
1.6.Financial Proposals will be opened only for the firms found to be eligible and scoring
qualifying marks in accordance with Para 5 hereof. The consultancy services will be
awarded to the highest ranking consultant on the basis of Quality and Cost.
1.7.Please note that (i) costs of preparing the proposal and of negotiating the contract,
including visits to the Client, etc., are not reimbursable as a direct cost of the assignment;
and (ii) Client is not bound to accept any of the proposals submitted and reserve the right
to reject any or all proposals without assigning any reasons.
-7-
Delineation of duties/ responsibilities and scope of work to be undertaken by each
firm along with resources committed by each partner of the JV/Association for the
proposed services
An undertaking that the JV firms are jointly and severally liable to the Employer
for the performance of the services
The authorized representative of the joint venture/Association
The Association firm shall give a Letter of Association, MOU as in i) to vi above except v,
letter of Authorization, copies of GPA/SPA for the person signing the documents and a
certificate of incorporation.
1.8.3.In case of Joint venture, one of the firms which preferably have relatively higher
experience, will act as the lead firm representing the Joint Venture. The duties,
responsibilities and powers of such lead firm shall be specifically included in the MOU
/agreement. It is expected that the lead partner would be authorized to incur liabilities and
to receive instructions and payments for and on behalf of the Joint Venture. Payment to be
made to the JV can also be made to the account of the JV. For a JV to be eligible for
bidding, the experience of lead partner and other partner should be as indicated in data
sheet.
1.8.4.A firm can bid for a project either as a sole consultant or in the form of joint venture
with other consultant or in association with any other consultant. However, alternative
proposals i.e. one as sole or in JV with other consultant and another in association / JV
with any other consultant for the same package will be summarily rejected. In such cases,
all the involved proposals shall be rejected.
1.9.Pre-proposal conference shall be held on the date, time and venue given in Data Sheet.
1.10.1.The applicant shall furnish as part of its Proposal, a Bid Security of Rs 2,00,000 (
Rupees two lakhs only) in the form of a Bank Guarantee issued by one of the
Nationalized/Scheduled Banks in India in favour of the Executive Engineer, National
Highway Division, Karwar payable at Executive Engineer, National Highway Division,
Karwar. (the “Bid Security”) valid for a minimum period of 150 days (i.e.30 days
beyond the validity of the bid) from the last date of submission of proposals. This Bid
Security is returnable not later than 30 (thirty) days from the date of Opening of the
Financial proposals except in case of the two highest ranked Applicants. Bid Security of
the Selected Applicant and the Second ranked Team shall be returned, upon the Selected
Applicant signing the Agreement.
1.10.2.Any Bid not accompanied by the Bid Security of the required value and minimum
required validity shall be rejected by the Authority as non-responsive.
1.10.3.The Executive Engineer, National Highway Division, Karwar shall not be liable to
pay any interest on the Bid Security and the same shall be interest free.
-8-
1.10.4.The Applicant, by submitting its Application pursuant to this RFP, shall be deemed to
have acknowledged that without prejudice to the Executive Engineer, National Highway
Division, Karwar. any other right or remedy hereunder or in law or otherwise, the Bid
Security shall be forfeited and appropriated by the Authority as the mutually agreed pre-
estimated compensation and damage payable to the Authority for, inter alia the time, cost
and effort of the Executive Engineer, National Highway Division, Karwar. in regard to
RFP including the consideration and evaluation of the Proposal under the following
conditions:
a)If an Applicant withdraws its Proposal during the period of its validity as
specified in this RFP and as extended by the Applicant from time to time
b)In the case of the Selected Applicant, if the Applicant fails to reconfirm its
commitments during negotiations as required vide Para 6
c)In the case of a Selected Applicant, if the Applicant fails to sign the Agreement
2 Documents
2.1.To enable you to prepare a proposal, please find and use the attached documents listed
in the Data Sheet.
2.3.At any time before the submission of proposals, the Client may, for any reason,
whether at its own initiative or in response to a clarification requested by a Consulting
firm, modify the Documents by amendment or corrigendum. The amendment will be
uploaded on Executive Engineer, National Highway Division, Karwar. website. The
Client may at its discretion extend the deadline for the submission of proposals and the
same shall also be uploaded on Executive Engineer, National Highway Division, Karwar
website.
3.Preparation of Proposal
The proposal must be prepared in three parts viz., Part 1: Proof of eligibility
Part 2: Technical Proposal Part 3: Financial Proposal
3.1.1.The minimum essential requirement in respect of eligibility has been indicated in the
Data Sheet. The proposal found deficient in any respect of these requirements will not be
considered for further evaluation. The following documents must be furnished in support
of proof of eligibility as per Formats given in Appendix-II:
-9-
i)Forwarding letter for Proof of Eligibility in the Form-E1.
ii)Firm’s relevant experience and performance for the last 7 years: Project
sheets in support of relevant experience as per Form-E2/T3 supported by the
experience certificates from clients in support of experience as specified in data
sheet for the project size preferably in terrain of similar nature as that of proposed
project shall be submitted. Certificate should indicate clearly the firms
Design/DPR experience, in 2/4-/6- laning of highway, structures like bridges,
Viaducts, tunnels, hill slope stabilization, rock bolting, ground improvement, etc.
Scope of services rendered by the firm should be clearly indicated in the certificate
obtained from the client. The information given in Form E2/T3 shall also be
considered as part of Technical Proposal and shall be evaluated accordingly. The
Consultants are therefore advised to see carefully the evaluation criteria for
Technical Proposal and submit the Project Sheets accordingly.
iii)Document fee: The fee for the document amounting to Rs. 5,000 (Rupees Five
Thousand only) in the form of Demand Draft favoring Executive Engineer,
National Highway Division, Karwar. payable at <Location> must be furnished in a
separate envelope while submitting the proposal.
v)Bid Security: Bank Guarantee in support of bid security for an amount specified
in Data Sheet and having validity for a minimum period of 150 days (i.e.30 days
beyond the validity of the bid), from the last date of submission of proposals in the
Form E4.
3.1.2.The minimum essential requirement in respect of eligibility has been indicated in the
data sheet, the proposal found deficient in any respect of these requirements will not be
considered for further evaluation.
3.2.Technical Proposal
3.2.1.You are expected to examine all terms and instructions included in the Documents.
Failure to provide all requested information will be at your own risk and may result in
rejection of your proposal.
-10-
3.2.2.During preparation of the technical proposal, you must give particular attention to
the following:
3.2.3.The technical proposal shall be submitted strictly in the Formats given in Appendix-
III And shall comprise of following documents:
i.Forwarding letter for Technical proposal duly signed by the authorized person on
behalf of the bidder, as in Form-T-1
ii. Details of projects for which Technical and Financial Proposals have been
submitted by a Consultant with a particular Team as in Form-T-2
iii. Firm’s references - Relevant Services carried out in the last seven years as per
Form-E2/T-3. This information submitted as part of Proof of Eligibility shall be
evaluated and need not be submitted again as a part of the Technical proposal
iv. Site Appreciation: limited to four A4 size pages in 1.5 space and 12 font including
photographs, if any (Form-T-4).
v. Comments on Terms of Reference: limited to two A4 size pages in 1.5 space and 12
font (Form-T-5).
vii. Proposed methodology for the execution of the services illustrated with bar charts
of activities, including any change proposed in the methodology of services indicated
in the TOR, and procedure for quality assurance: Maximum 4 pages (Form-T-7)
viii. The proposal should clearly identify and mention the details of Material Testing
lab facilities to be used by the Consultants for the project (Form-T-8). In this
connection, the proposals of the Consultants to use in-house lab facilities up to a
distance of maximum 400 km from the project site being feasible would be accepted.
For all other cases suitable nearby material Testing Laboratory shall be proposed
before Contract Agreement is executed.
ix. The proposal shall indicate as to whether the firm is having the facilities for
carrying out the following field activities or these are proposed to be outsourced to
specialized agencies in the Form- T-9
-11-
a)Pavement Investigation
b)Geo-technical Investigation
In case the consultant envisages outsourcing any or all of the above services to
the expert agencies, the details of the same indicating the arrangement made
with the agencies need to be furnished. These agencies would however, be
subject to approval of the client to ensure quality input by such agencies during
technical negotiation before award of the work. For out-sourced services,
proposed firms/consultants should have such experience on similar projects
i. The CVs of the key personnel in the format as per Form T-11 is to be furnished. It may
please be ensured that the format is strictly followed and the information furnished therein
is true and correct. The CV must indicate the work in hand and the duration till which the
person will be required to be engaged in that assignment. Experience certificates shall also
be submitted. If any information is found incorrect, at any stage, action including
termination and debarment from future Executive Engineer, National Highway Division,
Karwar. projects upto 2 years may be taken by Executive Engineer, National Highway
Division, Karwar. on the personnel and the Firm.
ii. . No alternative to key personnel may be proposed and only one CV may be submitted
for each position. The minimum requirements of Qualification and Experience of all key
personnel are listed in Enclosure-II of TOR. CV of a person who does not meet the
minimum experience requirement as given at enclosure-II of TOR shall be evaluated
and the marks obtained shall be taken into consideration during evaluation of
Technical Proposal (except Team leader). However if a firm with such key personnel is
declared the “most preferred bidder” for a particular package , such key personnel
should be replaced at the time of Contract Negotiations with a person meeting
requirements of Qualification and Experience as given at enclosure-II of TOR and
whose CV secures 75 % marks and above. If a proposed key personnel does not possess
the minimum (essential) educational qualification as given at enclosure-II of TOR, Zero
marks shall be assigned to such CV and such CV shall not be evaluated further. The
CV of the proposed Team Leader should score at least 75 % marks otherwise the
entire proposal shall be considered to have failed in the evaluation of Technical
Proposals and shall not be considered for opening of Financial Proposal
iii. Team Leader, Highway cum Pavement Engineer, Bridge Engineer, Geo-
technical cum material engineer and Senior Survey Engineer should be available from
beginning of the project. 3 Key Personnel namely Environmental Specialist, Quantity
Surveyor / Documentation expert and Traffic and safety expert are allowed to be
deployed/proposed in 2 teams at a time. If same CV is submitted by two or more firms,
zero marks shall be given for such CV for all the firms.
iv. the availability of key personnel must be ensured for the duration of the
project as per proposed work programme. If a firm claims that a key personnel proposed by
them is a permanent employee of the firm ( the personnel should have worked in the firm
continuously for a period of at least 1 year) , a certificate to the effect along with pay slips
are required to be submitted.
-12-
v.The age limit for key personnel is 70years as on the date of bid submission
except for Senior survey engineer in which case the age limit is 65 years. The proof of age
and qualification of the key personnel must be furnished in the technical proposal.
vi.An undertaking from the key personnel must be furnished that he/she will be
available for entire duration of the project assignment and will not engage himself/herself
in any other assignment during the currency of his/her assignment on the project. After the
award of work, in case of non-availability of key personnel in spite of his/her declaration,
he/she shall be debarred for a period of two years for all projects of Executive Engineer,
National Highway Division, Karwar.
vii.Age limit for supporting staff to be deployed on project is 65 years as on the date
of bid submission.
vii.A good working knowledge of English Language is essential for key professional
staff on this assignment. Study reports must be in English Language.
ix. Photo, contact address and phone/mobile number of key personnel should be
furnished in the CV.
xi. It may please be noted that in case the requirement of the ‘Experience’ of the
firm/consortium as mentioned in the “Proof of Eligibility’ is met by any foreign company, their
real involvement for the intended project shall be mandatory. This can be achieved either by
including certain man-months input of key experts belonging to the parent foreign company, or
by submitting at least the draft feasibility report and draft DPR duly reviewed by the parent
firm and their paying visit to the
site and interacting with Executive Engineer, National Highway Division, Karwar. In case
of key personnel proposed by the foreign company, they should be on its pay roll for at
least last six months (from the date of submission).
xii.In case a firm is proposing key personnel from educational/research
institutions, a
-13-
‘No Objection Certificate’ from the concerned institution should be enclosed with the
CV of the proposed key personnel committing his services for the instant project.
i. Financial Proposal
3.3.1.The Financial proposal should include the costs associated with the assignment.
These shall normally cover: remuneration for staff (foreign and local, in the field, office
etc), accommodation, transportation, equipment, printing of documents, surveys,
geotechnical investigations etc. This cost should be broken down into foreign and local
costs. Your financial proposal should be prepared strictly using, the formats attached in
Appendix – IV. Your financial proposal should clearly indicate the amount asked for by
you without any assumptions of conditions attached to such amounts. Conditional offer or
the proposal not furnished in the format attached in Appendix-IV shall be considered non-
responsive and is liable to be rejected.
3.3.2.The financial proposal shall take into account all types of the tax liabilities and cost
of insurance specified in the Data Sheet.
4 Submission of Proposals
4.1.The Applicants shall submit the proposal (Proof of Eligibility and Technical Proposal) in
hard bound form with all pages numbered serially and by giving and index of submissions.
Applications submitted in other forms like spiral bound form; loose form etc shall be rejected.
Copies of Applications shall not be submitted and considered. A Consultant with
“a Particular Team” may submit only one hard copy (in original) of “proof of eligibility
(Part 1)” and “Technical Proposal (Part II)” to Executive Engineer, National Highway
Division, Karwar. for all the packages applied by them with a particular team on or before
the deadline of submission of bids. A consultant can apply for a particular package with
one team only. The packages for which a
-14-
Consultant with “a Particular Team” applies should be clearly mentioned in their
proposal. However, Consultants are required to submit a copy of Proof of Eligibility and
Technical Proposal online separately for each package. Financial proposal for each
package are to be submitted separately. Financial proposal are only to be submitted online
and no hard copy of the financial proposal should be submitted.
4.2 You must submit original proposal as indicated in the Data Sheet. “Proof of
Eligibility” in original and hard bound should be enclosed in an envelope which should be
marked as “Part-I – Proof of Eligibility”. Similarly, “Technical Proposal” in original and
hard bound should be enclosed in an envelope which should be marked as “Part-II –
Technical Proposal” The proposal will be sealed in an outer envelope which will bear
the address and information indicated in the Data Sheet and shall be submitted to
Executive Engineer, National Highway Division, Karwar. on or before the deadline for
submission of bids. The envelope must be clearly marked:
4.2.1.This outer envelope will contain three separate envelopes. The first envelope
containing
“Proof of Eligibility” (which should be clearly marked), the second envelope containing
“Technical Proposal” (which should be clearly marked) and the third envelope containing a
demand draft of Rs. 5,000/- (cost of RFP), Bid Security of required amount and validity as
mentioned in the RFP and Proof of Payment of application processing fees amounting to
Rs. 1295/- to M/s. C-1 India Pvt. Ltd. Only one bid security and one DD of Rs 5000/ (as cost
of Document) may be submitted by a consultant applying with a particular team for a number
of packages. However for consultants applying with 2 teams, 2 nos of Bid Security of
Rs 2 lakhs each and 2 no’s of DD of Rs 5000/ each as mentioned in RFP have to be
submitted.
4.2.2The proposal must be prepared in indelible ink and must be signed by the authorized
representative of the consultants. The letter of authorization must be confirmed by a written
power of attorney accompanying the proposals. All pages of the Proof of Eligibility and
Technical Proposal must be initialed by the person or persons signing the proposal.
4.4Your completed Proof of eligibility and Technical proposal (in hard copy) must be
delivered on or before the time and date at the address stated in Data Sheet. Proof of
Eligibility, Technical Proposal and Financial Proposal for each package shall have to be
submitted online also on or before the time and date at the address stated in Data Sheet
4.5.Your proposal must be valid for the number of days stated in the Data Sheet from the
closing date of submission of proposal.
-15-
5. Proposal Evaluation
In case answers to any of the above items is ‘No’ the bid shall be declared as
non-responsive and shall not be evaluated further.
A Consultant satisfying the minimum Eligibility Criteria as mentioned in the Data sheet
and who had submitted the above mentioned documents shall be declared “pass” in Proof
of Eligibility and the Technical Proposals of only those consultants shall be opened and
evaluated further.
5.2.In the second stage the Technical proposal shall be evaluated as per the detailed
evaluation criteria given in Data Sheet.
A proposal securing 75 points shall be declared pass in the evaluation of Technical Proposal
.The technical proposal should score at least 75 points out of 100 to be considered for
financial evaluation. The CV of the proposed Team Leader should score at least
75 % marks otherwise the entire proposal shall be considered to have failed in the
evaluation of Technical Proposals and shall not be considered for opening of Financial
Proposals.
5.3. Evaluation of Financial Proposal
5.3.1.In case for a particular package, only one firm is eligible for opening of Financial
Proposals, the Financial Proposal shall not be opened, the bids for that package shall be
cancelled and Executive Engineer, National Highway Division, , Karwar. shall invite
fresh bids for this package. For financial evaluation,
-16-
total cost of financial proposal excluding Service Tax shall be considered. Service Tax
shall be payable extra.
5.3.2 The evaluation committee will determine whether the financial proposals are complete
(i.e. whether they have included cost of all items of the corresponding proposals ; if not,
then their cost will be considered as NIL but the consultant shall however be required to
carry out such obligations without any compensation. In case, if client feels that the work
cannot be carried out within overall cost of financial proposal, the proposal can be
rejected. The client shall correct any computational errors and correct prices in various
currencies to the single currency specified in Data Sheet. The evaluation shall exclude
those taxes, duties, fees, levies and other charges imposed under the applicable law
applied to foreign components/ resident consultants.
5.3.3For a package, the procedure as mentioned at Clauses 5.3.4, 5.4 and, 5.5 as mentioned
below shall be followed for determining the “most preferred bidder (H-1 bidder)” for this
package.
5.3.4The lowest financial proposal (FM) will be given a financial score (SF) of 100
points. The financial scores of other proposals will be computed as follows:
SF = 100xFM/F
(SF = Financial Score, FM= Amount of lowest bid, F= Amount of financial proposal
converted in the common currency)
T and f are values of weightage for technical and financial proposals respectively as given
in the Data Sheet.
5.5.For a particular package, a Consultant with a “particular Team” having the maximum
Combined score (S) shall be declared as the most preferred bidder (H-1).
5.6.In case work has to be awarded for multiple packages, award of work to a Consultant
with “a Particular Team” either as sole or as in JV/Association shall be limited to one
package only. At first, Consultants who become H-1 in one package each shall be
assigned the respective package. Then packages in which a Consultant with “a Particular
Team” turns out to be the most preferred bidder (H-1) in more than one package shall be
considered. In
-17-
case, a Consultant with “a Particular Team” turns out to be the most preferred bidder (H-1) in
more than one package, the package which is to be awarded to this team of a consultant shall
be determined on the basis of least cost to Executive Engineer, National Highway Division, ,
Karwar. considering the Financial Quote of H-1 bidder and H-2 Bidder limited to those
packages. Procedure to be followed for awarding work based on QCBS including assessment
of least cost to Executive Engineer, National Highway Division, , Karwar. under special
circumstances i.e. When a Consultant with “a Particular Team” turns out to be the most
preferred bidder (H-1) in more than one package is given at given at Annex-II.
6. Negotiations
6.1. Prior to the expiration period of proposal validity, the Client will notify the most
preferred Consultant/Bidder i.e. the highest ranking consultant in writing by registered
letter, e-mail, or facsimile and invite him to negotiate the Contract.
6.2. Before the start of negotiations, the most preferred Consultant/Bidder (H-1) shall
be asked to give justification for the cost quoted by them to the full satisfaction of
Executive Engineer, National Highway Division, Karwar. Each key personnel of the
preferred consultant shall be called for interview at the time of negotiation at the cost of
consultant before the award of work.
6.3. Negotiations normally take two to three days. The aim is to reach agreement on all
points and initial a draft contract by the conclusion of Negotiations.
6.4. Negotiations will commence with discussion on technical proposal, the proposed
methodology (work plan), staffing and any suggestions made to improve the TOR, the
staffing and bar charts, which will indicate activities, periods in the field and in the home
office, staff months, logistics and reporting. The financial proposal is subject to
rationalization. Special attention will be paid to optimize the required outputs from the
Consultants within the available budget and to define clearly the inputs required from the
Client to ensure satisfactory implementation of the Assignment.
6.5. Changes agreed upon will then be reflected in the financial proposal using proposed unit
rates.
6.6. Having selected Consultants, among other things, on the basis of an evaluation of
proposed key professional staff, the Client expects to negotiate, within the proposal
validity period, a contract on the basis of the staff named in the proposal and, prior to
contract negotiations, will require assurances that the staff will be actually available. The
Client may ask to give a replacement for the key professional who has scored less
than 75% marks by a person of at least 75% score. No reduction in remuneration
would be made on account of above change.
6.7. The Client will not consider substitutions during contract negotiations except in cases of
incapacity of key personnel for reasons of health. Similarly, after award of contract the Client
expects all of the proposed key personnel to be available during implementation of the
contract. The client will not consider substitutions during contract negotiations/ contract
-18-
6.8. implementation except under exceptional circumstances. For the reason other than
death/ extreme medical ground, where replacement is proposed by the Consultant due to
non availability of the originally proposed key personnel or in cases where replacement
has become necessary as a key personnel proposed by the Consultant has been found to
be unsuitable for the project by Executive Engineer, National Highway Division,
Karwar. during contract negotiations / contract implementation , the following shall
apply (i) for total replacement upto 33% of key personnel, remuneration shall be reduced
by 5% (ii) for total replacement between 33% to 50%, remuneration shall be reduced by
10% (iii) for total replacement beyond 50% and 66% remuneration shall be reduced by
15% (iv) for total replacement beyond 66% of the total key personnel, the Client may
initiate action for debarment of such consultant for future projects of Executive
Engineer, National Highway Division, Karwar. for a period of 6 months to 24 months.
If for any reason beyond the reasonable control of the consultants, it becomes
necessary to replace any of the personnel, the consultants shall forthwith provide as
a replacement a person of equivalent or better qualification and experience.
6.9. The negotiations will be concluded with a review of the draft Contract Agreement
attached at Appendix-V. The Client and the Consultants will finalize the contract to
conclude negotiations.
6.10. If a Consultant fails to conclude the negotiations with Executive Engineer, National
Highway Division, Karwar. or in case a consultant withdraws without starting /
completing the negotiations with Executive Engineer, National Highway Division,
Karwar., it shall attract penalty – encashment of Bid Security submitted by the
Consultant
7.Performance Security
The consultant will furnish within 15 days of the issue of Letter of Acceptance (LOA),
an unconditional Bank Guarantee from a Nationalised Bank, IDBI or ICICI/ICICI
Bank/Foreign Bank/EXIM Bank / Any Scheduled Commercial Bank approved by RBI
having a net worth of not less than 500 crore as per latest Annual Report of the Bank. In
the case of a Foreign Bank (issued by a Branch in India) the net worth in respect of
Indian operations shall only be taken into account. In case of Foreign Bank, the BG
issued by Foreign Bank should be counter guaranteed by any Nationalised Bank in India.
In case of JV, the BG shall be furnished on behalf of the JV or by the lead member of
the JVs for an amount equivalent to 10 % of the total contract value to be received by
him towards Performance Security valid for a period of three years beyond the date of
completion of services, or end of civil works contract, whichever earlier. The Bank
Guarantee will be released by Executive Engineer, National Highway Division,
Karwar. upon expiry of 3 years beyond the date of completion of services, or end of
civil works contract, whichever earlier, provided rectification of errors if any,
found during implementation of the contract for civil work and satisfactory report
by Executive Engineer, National Highway Division, Karwar. in this regard is
issued. If a Consultant fails to submit the Performance Security (as specified above), it
shall attract penalty – encashment of Bid Security submitted by the Consultant
8.Penalty
The consultant will indemnify for any direct loss or damage that accrue due to
deficiency in services in carrying out Detailed Project Report. Penalty shall be imposed
on the consultants for poor performance/deficiency in service as expected from the
consultant
-19-
and as stated in General Conditions of Contract.
9.Award of Contract
After successful Negotiations with the selected Consultant the Client shall issue letter of
award and ask the Consultant to provide Performance Security as in Para 7 above. If
negotiations (as per para 6 above) fail or the selected Consultant fail to provide
performance security within the prescribed time or the Consultant fail to sign the
nd
Contract Agreement within prescribed time the Client may invite the 2 highest ranking
bidder Consultant for Contract negotiations and follow the procedure outlined in Para 6,
9 and 10 of this Letter of Invitation.
10.Signing of Contract Agreement
After having received the performance security and verified it, the Client shall invite the
selected bidder for signing of Contract Agreement on a date and time convenient to both
parties within 15 days of receipt of valid Performance Security.
11. The Client shall keep the bidders informed during the entire bidding process and shall
host the following information on its website:
i. Notice Inviting Tender (NIT)
ii. Request For Proposal (RFP)
iii. Replies to pre-bid queries, if any
iv. Amendments / corrigendum to RFP
v. List of bidders who submitted the bids up to the deadline of submission
vi. List of bidders who did not pass the eligibility requirements, stating the broad
deficiencies
vii. List of bidders who did not pass the Technical Evaluation stating the reasons.
viii. List of bidders along with the technical score, who qualified for opening the
financial bid
ix. Final Score of qualified bidders
x. Name of the bidders who is awarded the Contract
12.Confirmation
Thanking you.
Yours sincerely,
Executive Engineer,
National Highway Division,
Karwar.
Encl. as above
-20-
Annex-1
Tentative Package
Sl. No. NH No. Section State
Length (in km) No.
1 2 3 4 5 6
1 “Consultancy Services for Feasibility Study, Karwar- Karnataka Km. 318.00 1
cum DPR, Survey and Preparation of Land plan Kaiga-
for Upgradation of State Highway to National Mundgod-
Highway by Adopting LiDAR or similar Savanur-
Gadag-
technology for widening to Two lane with Gajendragad
paved Shoulders from Karwar-Kaiga-
Mundgod-Savanur-Gadag-Gajendragad. for
an approximate length of 318.00 Kms
(including Bypass or Flyover Wherever
necessary in Town/City limits) in the State of
Karnataka”.
Annex-II
1. At first, Consultants who become H-1 in one package each shall be assigned the
respective package. Then packages in which a Consultant with “a Particular Team” turns out
to be the most preferred bidder (H-1) in more than one package shall be considered. In case, a
Consultant with “a Particular Team” turns out to be the most preferred bidder (H-1) in more
than one package, the package which is to be awarded to this team of a consultant shall be
determined on the basis of least cost to Executive Engineer, National Highway Division,
Karwar. considering the Financial Quote of H-1 bidder and H-2 Bidder limited to those
packages which shall be worked out as per procedure illustrated with an example as mentioned
below.
2. Suppose there are 8 packages namely Package-1, Package-2, Package -3, Package-4, Package -
5, package -6, package-7 and Package-8 respectively. It is also assumed that 10 consultants
namely P, Q, R, S, T, U, V, W, X and Y has applied for these packages. It is also assumed that
three Consultants namely P, R and U has applied with two Teams and the remaining
Consultants have applied with only one team. It is also assumed that the following is the
position of various firms after opening of the Financial proposals (and after arithmetic
corrections if any of the Financial bids) of the packages and after applying QCBS
H-1 H-2 H-3 H-4 H-5 H-6
Package no. Name of Consultants and Financial Quotes (Rs in lakhs)
Package-1 P (team-1) Q W X T Y
230 lakhs 200 lakhs 240 lakhs 220 lakhs 200 lakhs 230 lakhs
Package-2 V U(team-1) X P (team-2) T Y
240 lakhs 210 lakhs 240 lakhs 220 lakhs 200 lakhs 230 lakhs
Package-3 V P(team-1) U(team-1) R (team-2) X Y
200 lakhs 230 lakhs 250 lakhs 230 lakhs 220 lakhs 200 lakhs
Package-4 R (team-1) T U (team-2) P (team-2) Y X
250 lakhs 220 lakhs 250 lakhs 260 lakhs 220 lakhs 245 lakhs
Package-5 R (team-1) V S U(team-2) W T
220 lakhs 240 lakhs 260 lakhs 250 lakhs 220 lakhs 240 lakhs
Package-6 Q T S P (team-2) W U (team-2)
210 lakhs 240 lakhs 250 lakhs 220 lakhs 200 lakhs 230 lakhs
Package-7 R (team-1) U (team-1) Q S W Y
200 lakhs 220 lakhs 240 lakhs 255 lakhs 230 lakhs 240 lakhs
Package-8 V R(team-1) W S P (team-1) Y
190 lakhs 250 lakhs 220 lakhs 240 lakhs 255 lakhs 240 lakhs
-21-
The different packages shall be awarded to consultants as mentioned below
2.1 Step-1 :
In this case, Consultants P (team-1) and Q are the H-1 in only one package each namely package-1
and package-6 respectively. Consultant V is H-1 in 3 packages namely Package-2, Package-3 and
Package-8 respectively. Consultant R (team-1) is H-1 in 3 packages namely Package-4, Package-5
and Package-7 respectively. Since Consultant P (team-1) is H-1 in Package-1 only and Consultant
Qis H-1 in Package-6 only, Consultant P (team-1) shall be awarded Package-1 and Consultant Q
shall be awarded Package-6.
2.2 Step-2:
After Consultant P (team-1) is awarded Package-1 and Consultant Qis awarded Package-6, the
scenario for the remaining 6 packages is as given below .P (team-1) and Q occurring anywhere
else stands deleted as they have already been awarded one work each
Consultant V s h a l l be awarded only one package out of the 3 packages for which it is H-1
namely Package-2, Package-3 and Package-8 respectively. Similarly Consultant R (team-1) Shall
be awarded only one package out of the 3 packages for which it is H-1 namelyPackage-4, Package-
5 and Package-7 respectively. The determination of package to be awarded to Consultant V and
Consultant R (team-1) shall be worked out in a single step (i.e. one at a time) .New H-1 for the
remaining packages (4 packages) shall be worked out only after determination of packages to be
awarded to the H-1 bidders at this stage [ i.e. Consultant V and R (Team-1) in the instant case ] in
one step . Determination of Package to be awarded to each of Consultant V and Consultant R
(team-1) shall be worked out as follows
(i) After the award of Package-1 to Consultant –P (team-1) and Package -6 to Consultant
–Q and also considering that a Consultant with a particular team can be awarded only one work ,
the details of H-1 and H-2 / New H-2 in the remaining 6 packages are as mentioned below
.Since V is H-1 in more than one package and shall be awarded one of these packages, V has
been deleted from all other packages .Similarly, since R(Team-1) in more than one
-22-
package and shall be awarded one of these packages, R (Team-1) has been deleted from all
other packages
<
H-1 H-2 / New Remarks
H-2
Package-2 V U(team-1)
240 lakhs 210 lakhs
Package-3 V U(team-1) Since Consultant P( Team-1) is awarded
200 lakhs 250 lakhs Package-1, Consultant U(team-1) becomes
the new H-2
Package-4 R (team-1) T
250 lakhs 220 lakhs
Package-5 R (team-1) S
220 lakhs 260 lakhs
Package-7 R (team-1) U (team-1)
200 lakhs 220 lakhs
Package-8 V W Consultant-R(team-1) has not been considered
190 lakhs 220 lakhs as H-2 since Consultant –C (team-1) is to be
awarded one package out of the packages 4,5 and
7 in which it is H-1. Hence Consultant – W is
the new H-2
(ii) Package to be awarded to Consultant –V who is H-1 in three packages namely Package - 2, 3
and 8 respectively shall be determined on the basis of least cost to Executive Engineer, National
Highway Division, Karwar. considering the Financial Quote of H-1 bidder and H-2 Bidder limited
to those packages The situation for least cost to Executive Engineer, National Highway Division,
Karwar. shall be when the firm with Consultant –G is awarded the package for which Financial
Bid of second ranked team (H-2) minus Financial Bid of the first ranked team (H-1) is
maximum. The same is illustrated as given below
H-1 H-2 / New Financial Bid of H-2/ Remarks
H-2 NewH-2minus
Financial Bid of H-1
Package-2 V U(team-1) 210-240 = (-) 30 lakhs
240 lakhs 210 lakhs
Package-3 V U(team-1) 250 – 200 = (+) 50 H-2 minus H-1 is
200 lakhs 250 lakhs lakhs Maximum. Hence
Consultant V shall be
awarded Package-3
Package-8 V W 220 – 190 = (+) 30
lakhs
-23-
In a similar way, Package to be awarded to Consultant – R (team-1) who is H-1 in three
packages namely Package -4, 5 and 7 respectively shall be determined as illustrated below:
2.3 Step-3
(i) After the award of the above mentioned 4 packages namely, Package-1 to Consultant–P
(team-1), Package -6 to Consultant –Q, Package -3 to Consultant –V, Package -5 to Consultant
–R (team-1) and also considering that a Consultant with a particular team can be awarded only
one work, the details of new H-1 and New H-2 in the remaining 4 packages are as mentioned
below
H-1 (New H-2 (New Remarks
H-1) H-2)
Package-2 U(team-1) X Since Consultant V is awarded Package-3 ,
210 lakhs 240 lakhs Consultant U (team-1) becomes the new H-1
and Consultant X becomes the new H-2
Package-4 T U (team-2) Since Consultant -R(team-1) is awarded
220 lakhs 240 lakhs Package-5 , Consultant T becomes the new H-
1 and Consultant U (team-2) becomes the new
H-2
Package-7 U (team-1) S Since Consultant R(team-1) is awarded
220 lakhs 255 lakhs Package-5 , Consultant U (team-1) becomes the
new H-1 and Consultant S becomes the new H-2
-24-
2.4 Step-4:
Consultant U (team-1) is the new H-1 for package- 2 and Package-7 respectively and
Consultant U (team-1) shall be awarded only one package out of this 2 packages. Package to be
awarded to Consultant –U (team-1) shall be determined as illustrated below
H-1 H-2 / New Financial Bid of H-2/ Remarks
H-2 NewH-2minus
Financial Bid of H-1
Package-2 U(team-1) X 240-210 = (+) 30
210 lakhs 240 lakhs lakhs
Package-7 U (team-1) S 255 – 220 = (+) 35 H-2 minus H-1 is
220 lakhs 255 lakhs lakhs Maximum. Hence
Consultant – U (team-
1) shall be awarded
Package- 7
2.5 Step-5 :
(i) After the award of the above mentioned 7 packages namely, Package-1 to Consultant
–P (team-1) , Package -6 to Consultant –Q, Package -3 to Consultant –V , Package -5 to
Consultant –R (team-1), Package-4 to Consultant -T, Package -8 to Consultant-W, package
-7 to Consultant –U (team-1) team and also considering that a Consultant with a particular team
can be awarded only one work , the details of new H-1 and / New H-2 in the remaining
package i.e. package -2 is as mentioned below
(ii) Consultant X is the new H-1 for only one package namely Package-2. Accordingly,
Package -2 shall be awarded to Consultant –X.
-25-
3. Thus as per the above mentioned procedure the 8 packages are awarded to the following
Consultant at the Financial Quoted (after arithmetic Corrections) by them for the
respective packages
Package No. Name of Consultants awarded packages
Package-1 Consultant- P (team-1)
Package-2 Consultant- X
Package-3 Consultant- V
Package-4 Consultant- T
Package-5 Consultant- R (team-1)
Package-6 Consultant- Q
Package-7 Consultant- U (team-1)
Package-8 Consultant- W
-26-
DATA SHEET
(The Name of project and Package No. should be indicated in the format given in the
technical proposal)
Date, Time and Venue of Pre-Proposal Conference Date: 11.00 Hours Dated 28-12-2016
(Place: office of the Executive Engineer, National Highway Division, Karwar.)
(Ref. Para 1.9)
(i). The Consultants and their personnel shall pay all taxes (including service tax),
custom duties, fees, levies and other impositions levied under the laws prevailing
seven days before the last date of submission of the bids. The effects of any
increase / decrease of any type of taxes levied by the Government shall be borne
by the Client / Consultant, as appropriate.
-27-
(ii). Limitations of the Consultant’s Liability towards the Client shall be as per Clause3.4 of
Draft Contract Agreement
(iii). The risk and coverage shall be as per Clause 3.5 of Draft Contract Agreement.
The number of copies of the proposal required to be submitted: 1 no. (ref. para 4.1)
Executive Engineer,
National Highway Division, Karwar
Original Proposal;
Documents in proof of eligibility and technical proposal as appropriate; and,
Do not open, except in presence of the evaluation committee on the outer envelope.
Consultancy Package No. :----------
Project Name: ------------
Name and Address of Consultant
Date 28-12-2016
-28-
Table-1: Minimum Eligibility Requirements
Sl.No. Minimum experience and performance of Annual average turnover
Preparation of DPR of Highways / Bridges in
the last 7 years(NH/SH/Equivalent) (for past
performance attach undertaking for any
litigation history/ and arbitration).
1 A Firm applying for a package should have Annual average turnover for
Experience of preparation of Detailed Project last 3 years of the firm should be
Report of two/four/six lane / Feasibility of Two/ equal to or more than
four/ six lane projects of aggregate length equal to Rs.5.00 Crores.
the indicative length of the package (i.e. 100km if
the indicative length of the package is 100 km).
Firm should have also prepared DPR for at least one
project of 2/4/6laning of minimum 40% of the
indicative length of the package (i.e. 40 km if the
indicative length of the package is 100 km )or
Feasibility Study of two/four/six laning of
minimum 60% of the indicative length of the
package (i.e. 60 km if the indicative length of the
package is 100 km )
i) The sole applicant shall fulfill all the requirements given in Table-1.
(ii) In case of JV, the Lead Partner should fulfill at least 75% of all eligibility requirements and
the other partner shall fulfill at least 50% of all eligibility requirements.
(iii) If the applicant firm has / have prepared the DPR/FS projects solely on its own,
100%weightage shall be given. If the applicant firm has prepared the DPR/FS projects as a
lead partner in a JV, 75% weightage shall be given. If the applicant firm have prepared the
DPR projects as the other partner (not lead partner) in a JV 50% weightage shall be given. If
the applicant firm have prepared the DPR/FS projects as an associate,
25% weightage shall be given.
-29-
Second stage technical evaluation (Refer 5.2)
Maximum Sub-
Sl.No Description Points
Points
1.1.1 More than the indicative Length of the package applied 5.5
For
1.1.2 More than 2 times the indicative length of the package 6.5
applied for
1.1.3 More than 3 times the indicative length of the package 7.5
applied for
1.2 DPR for 2/4/6 laning projects each equal to or more 7.5
than 40 % of indicative length of a package applied
for (or Feasibility Study for 2/4/6 laning projects
each equal to or more than 60 % of indicative length
of a package applied for)
-30-
Maximum Sub-
Sl.No Description
Points Points
2.1 1 bridge 2
2.2 2 bridges 3
2.3 3 bridges 4
For special projects such as special bridges, tunnels and expressways that require specialized
capabilities and skill sets, the following is the break-up:
-31-
Sl.No Description Maximum Sub-
Points Points
1.2.1 1 project 4
1.2.2 2 projects 5
2.1 1 bridge 1
2.2 2 bridges 2
2.3 3 bridges 3
4.1.1 1 project 1
4.1.2 2 projects 2
-32-
Sl.No Description Maximum Sub-
Points Points
4.1.3 3 projects 3
4.1.4 4 projects 4
Note: In case feasibility study is a part of DPR services the experience shall be counted in DPR
only. In case bridge is included as part of DPR of highway the experience will be (1) and (2)
B. Adequacy of approach and methodology
1 Site appreciation 2
2 Comments on TOR 1
3 Team composition and task assignment 1
4 Methodology 1
Total 5
C. Material testing, survey and investigation, equipment and software proposed to be
used
1.1 Available 2
1.2 Outsourced 1
-33-
Sl.No Description Maximum Sub-
Points Points
2.1 Available 3
3.1 Available 3
4.1 1 project 1
4.2 2 projects 2
4.3 3 projects 3
5.1 1 project 1
5.2 2 projects 2
5.3 3 projects 3
-34-
Sl.No Description Maximum Sub-
Points Points
6.1 1 project 1
6.2 2 projects 2
6.3 3 projects 3
The number of points assigned during the evaluation of qualification and competence of key
staff are as given below:
1 General Qualification 25
-35-
Sl.No Description Maximum Sub-
Points Points
12.3 Detailed evaluation criteria which is to be used for evaluation of technical bids is as
indicated at Appendix-V.
Financial Proposals of all Qualified Consultants in accordance with clause 5.2 and 5.3 of
Letter of Invitation shall be opened.
The consultancy services will be awarded to the consultant scoring highest marks in combined
evaluation of Technical and Financial proposals in accordance with clause 1.3 and 5.4 hereof.
The Factors are:
The weight given to Technical Proposal (T) = 0.80
The weight given to Financial Proposal (f) = 0.20
13. The common currency is “Indian Rupee”. (Ref. Para 3.3.3)
Consultant have to quote in Rupees both for domestic Consultant as well as Foreign
Consultants
-36-
Commencement of Assignment (Date, Location): The Consultants shall commence the
Services within fifteen days of the date of effectiveness of the contract at locations as
required for the project stretch stated in TOR. (Ref. Para 1.2 of LOI and 2.3 of GCC/SC)
-37-
APPENDIX I
-38-
Terms of Reference for Consultancy Services (TOR)
1. General
1.1 The Executive Engineer, National Highway Division, Karwar. has been entrusted
with the assignment of as per Annexure I Executive Engineer, National Highway
Division, Karwar. now invites proposal from Technical consultants for carrying out
detailed project report as per details given in Annexure-1
1.2. Executive Engineer, National Highway Division, Karwar. will be the employer and
executing agency for the consultancy services and the standards of output required from
the appointed consultants are of international level both in terms of quality and adherence
to the agreed time schedule.
1.3Ministry has recently awarded works of consultancy services for construction of ROBs
for replacing level crossings in various states. In case a level crossing exists in a project
reach, consultant is required to co-ordinate with those consultants and finalise the
alignment & configuration of road accordingly. However, if the same is not covered in the
above assignment of DPR/feasibility study awarded by Ministry, the consultant under this
assignment shall be responsible for preparing DPR for such level crossings.
2.Objective
2.1The main objective of the consultancy service is to establish the technical, economical,
and financial viability of the project and prepare detailed project reports for rehabilitation
and upgrading of the existing road to <lane> configuration.
2.2The viability of the project shall be established taking into account the requirements
with regard to rehabilitation, upgrading and improvement based on highway design,
pavement design, provision of service roads wherever necessary, type of intersections,
rehabilitation and widening of existing and/or construction of new bridges and structures,
road safety features, quantities of various items of works and cost estimates and economic
analysis.
2.3The Detailed Project Report would inter-alia include detailed highway design, design of
pavement and overlay with options for flexible or rigid pavements, design of bridges and
cross drainage structures and grade separated structures, design of service roads, quantities
of various items, detailed working drawings, detailed cost estimates, economic and
financial viability analyses, environmental and social feasibility, social and environmental
action plans as appropriate and documents required for tendering the project on
commercial basis for international / local competitive bidding.
2.4The DPR consultant should ensure detailed project preparation incorporating aspects of
value engineering, quality audit and safety audit requirement in design and implementation.
-39-
2.5The consultant should, along with Feasibility Report, clearly bring out through
financial analysis the preferred mode of implementation on which the Civil Works for the
stretches are to be taken up. The consultant should also give cost estimates along with
feasibility report/ detailed Project Report.
2.6If at feasibility stage, employer desire to terminate the contract, the contract will be
terminated after payment up to that stage.
3.Scope of Services
3.1As far as possible, the widening/improvement work to <lane> shall be within the existing
right of way avoiding land acquisition, except for locations having inadequate width and
where provisions of short bypasses, service roads, alignment corrections, improvement of
intersections are considered necessary and practicable and cost effective. However
bypasses proposals should also be considered, wherever in urban areas, improvement to
<lane> of the existing road is not possible. The Consultant shall furnish land acquisition
details as per revenue records/maps for further processing of land acquisition. Consultant
shall also submit 3a, 3A and 3D draft notification for acquisition of land.
3.2 The Consultant shall study the possible locations and design of toll plaza, if applicable
to the project. Wayside amenities required on tolled highway shall also be planned. The
local and slow traffic may need segregation from the main traffic and provision of service
roads and fencing may be considered, wherever necessary to improve efficiency and safety.
3.3The general scope of services is given in the sections that follow. However, the entire
scope of services would, inter-alia, include the items mentioned in the Letter of Invitation and
the TOR. The Consultant will also make suitable proposals for widening/improvement of the
existing road and strengthening of the carriageways, as required at the appropriate time to
maintain the level of service over the design period. The Consultants shall prepare documents
for EPC/PPP contracts for each DPR assignment
3.6Wherever required, consultant will liaise with concerned authorities and arrange all
clarifications. Approval of all drawings including GAD and detail engineering drawings will
be got done by the consultant from the Railways. However, if Railways require proof
checking of the drawings prepared by the consultants, the same will be got done by Executive
Engineer, National Highway Division, Karwar. and payment to the proof consultant shall be
made by Executive Engineer, National Highway Division, Karwar. directly. Consultant will
also obtain final approval from Ministry of Environment and Forest for all
-40-
applicable clearances. Consultant will also obtain approval for estimates for shifting of
utilities of all types from the concerned authorities and competent authority within
MoRTH and its implementation agencies, as applicable. Consultant is also required to
prepare all Land Acquisition papers (i.e. all necessary schedule and draft 3a, 3A, and 3D,
3G notification as per L.A. act) for acquisition of land either under NH Act or State Act.
3.7The DPR consultant may be required to prepare the Bid Documents, based on the
feasibility report, due to exigency of the project for execution if desired by Executive
Engineer, National Highway Division, Karwar.
3.8Consultant shall obtain all types of necessary clearances required for implementation
of the project on the ground from the concerned agencies. The client shall provide the
necessary supporting letters and any official fees as per the demand note issued by such
concerned agencies from whom the clearances are being sought to enable implementation.
3.9The consultant shall prepare separate documents for BoT as well as EPC contracts at
Feasibility stage / DPR stage. The studies for financing options like BoT, Annuity, EPC
will be undertaken in feasibility study stage.
3.10The consultant shall be guided in its assignment by the Model Concession/ Contract
Agreements for PPP/ EPC projects, as applicable and the Manual of Specifications and
Standards for two/ four/ six laning of highways published by IRC (IRC:SP:73 or
IRC:SP:84 or IRC:SP:87, as applicable) (the "Manual") along with relevant IRC codes
for design of long bridges.
3.11The consultant shall prepare the bid documents including required schedules (as
mentioned above) as per EPC/ PPP documents. For that it is suggested that consultant
should also go through the EPC/PPP documents of ministry before bidding the project.
The Consultant shall assist the Executive Engineer, National Highway Division,
Karwar. and it's Financial Consultant and the Legal Adviser by furnishing clarifications
as required for the financial appraisal and legal scrutiny of the Project Highway and Bid
Documents.
3.12Consultant shall be responsible for sharing the findings from the preparation stages
during the bid process. During the bid process for a project, the consultant shall support
the authority in responding to all technical queries, and shall ensure participation of
senior team members of the consultant during all interaction with potential bidders
including pre-bid conference, meetings, site visits etc. In addition, the consultant shall
also support preparation of detailed responses to the written queries raised by the bidders.
4.General
4.1Primary Tasks
General Scope of Services shall cover but be not limited to the following major tasks
(additional requirements for Preparation of Detailed Project Report for Hill Roads and
Major Bridges are given in Supplement I and II respectively):
-41-
i. review of all available reports and published information about the project road
and the project influence area;
ii. Environmental and social impact assessment, including such as related to cultural
properties, natural habitants, involuntary resettlement etc.
ii (a). Public consultation, including consultation with Communities located along the
road, NGOs working in the area, other stake-holders and relevant Government
departments at all the different stages of assignment (such as inception stage,
feasibility stage, preliminary design stage and once final designs are concretized).
v. traffic studies including traffic surveys and Axle load survey and demand
forecasting for next thirty years;
vii. Inventory and condition surveys for bridges, cross-drainage structures, other
Structures, river Bank training/Protection works and drainage provisions;
viii. Detailed topographic survey using mobile/ aerial LiDAR or equivalent technology
-42-
xiii. Identification of the type and the design of intersections;
xiv. Design of complete drainage system and disposal point for storm water
xviii. Strip plan indicating the scheme for carriageway widening, location of all existing utility
services (both over- and underground) and the scheme for their relocation, trees to be felled,
transplanted and planted and land acquisition requirements including schedule for LA:
reports documents and drawings arrangement of estimates for cutting/ transplanting of trees
and shifting of utilities from the concerned department;
xix. To find out financial viability of project for implementation and suggest the preferred
mode on which the project is to be taken up.
xx. Preparation of detailed project report, cost estimate, approved for construction Drawings,
rate analysis, detailed bill of quantities, bid documents for execution of civil works
through budgeting resources.
xxi. Design of toll plaza and identification of their numbers and location and office cum
residential complex including working drawings
xxv. Preparation of social plans for the project affected people as per policy of the lending
agencies/ Govt. of India R & R Policy.
4.2 While carrying out the field studies, investigations and design, the development
plans being implemented or proposed for future implementation by the local
bodies, should be taken into account. Such aspect should be clearly brought out in
the reports and drawings.
-43-
4.3 The consultant shall study the possible locations and design of toll plaza, wayside
amenities required and arboriculture along the highway shall also be planned.
4.4 The local and slow traffic may need segregation from the main traffic and provision of
service roads and physical barrier including fencing may be considered, wherever
necessary to improve efficiency and safety.
4.8.Social Analysis
The social analysis study shall be carried out in accordance with the MORT&H/World
Bank/ADB Guidelines. The social analysis report will, among other things, provide a
socio-economic profile of the project area and address in particular, indigenous people,
communicable disease particularly HIV/AIDS poverty alleviation, gender, local
population, industry, agriculture, employment, health, education, health, child labor, land
acquisition and resettlement .
4.9Traffic Surveys
All traffic surveys and studies will be completed in feasibility studies.
-45-
2.The number of survey locations indicated in the table above are indicative only.
The Consultants shall, immediately upon award of the work, submit to Executive
Engineer, National Highway Division, Karwar. proposals regarding the total number as
well as the locations of the traffic survey stations as put of inception report. Suitable
maps and charts should accompany the proposals clearly indicating the rationale for
selecting the location of survey Station
3.The methodology of collection and analysis of data, number and location of traffic
survey stations shall be finalized in consultation with Executive Engineer,
National Highway Division, Karwar.
1. 4.9.2Classified Traffic Volume Count Survey
2. Consultant shall use ATCC systems that can meet the following accuracy levels
after validation/ correction:
c) Before validation and correction, the ATCC system shall meet the
following accuracy levels:
5. All results shall be presented in tabular and graphical form. The survey data shall
be analysed to bring out the hourly and daily variations. The traffic volume count per day
shall be averaged to show a weekly average daily traffic (ADT) by vehicle type. The
annual average daily traffic (AADT) shall be worked out by applying seasonal factors.
6. The consultant shall compile the relevant traffic volume data from secondary
sources also. The salient features of traffic volume characteristics shall be brought out and
variations if any, from the traffic census carried out by the State PWD shall be suitably
explained.
1. The consultants shall carry out 1-day (24 hour, both directions) O-D and commodity
movement surveys at locations finalized in consultation with Executive Engineer,
National Highway Division, Karwar. These will be essentially required around
congested towns to delineate through traffic. The road side interviews shall be on
random sample basis and cover all four-wheeled vehicles. The location of the O-D
survey and commodity movement surveys shall normally be same as for the classified
traffic count.
2. The location of origin and destination zones shall be determined in relation to each
individual station and the possibility of traffic diversion to the Project Road
from/to other road routes including bypasses.
3. The trip matrices shall be worked out for each vehicle type information on weight
for trucks should be summed up by commodity type and the results tabulated,
giving total weight and average weight per truck for the various commodity types.
The sample size for each vehicle type shall be indicated on the table and also in
the graphical representations.
4. The data derived from surveys shall also be analysed to bring out the lead and
load characteristics and desire line diagrams. The data analysis should also bring
out the requirement for the construction of bypasses.
-47-
5. The distribution of lead and load obtained from the surveys should be compared
The axle load surveys shall normally be done using axle load pads or other
sophisticated instruments. The location(s) of count station(s) and the survey with
those derived from the axle load studies.
6. The commodity movement data should be duly taken into consideration while
making the traffic demand estimates.
4.9.4..Turning Movement Surveys
1. The turning movement surveys for estimation of peak hour traffic for the
design of major and minor intersections shall be carried out for the Study. The
details regarding composition and directional movement of traffic shall be
furnished by the Consultant.
2. The methodology for the surveys shall be as per IRC: SP: 41-1994. The details
including location and duration of surveys shall be finalized in consultation
with Executive Engineer, National Highway Division, Karwar. officials. The
proposal in response to this TOR shall clearly indicate the number of locations
that the Consultants wish to conduct turning movement surveys and the
rationale for the same.
3. The data derived from the survey should be analyzed to identify requirements
of suitable remedial measures, such as construction of underpasses, fly-overs,
interchanges, grade-separated intersections along the project road alignment.
Intersections with high traffic volume requiring special treatments either
presently or in future shall be identified.
The Consultants shall carry out appropriate field studies such as moving car survey to
determine running speed and journey speed. The data should be analyzed to identify
sections with typical traffic flow problems and congestion. The objective of the survey
would be to recommend suitable measures for segregation of local traffic, smooth flow of
through traffic and traffic safety. These measures would include the provision of bypasses,
under-passes, fly-overs, interchanges, grade-separated intersections and service roads.
The data derived from the O-D, speed-delay, other surveys and also supplementary surveys
should be analysed to assess requirements for present and future development of truck
terminals at suitable locations en route.
1. The consultants shall make traffic demand estimates and establish possible traffic
growth rates in respect of all categories of vehicles, taking into account the past trends,
annual population and real per capita growth rate, elasticity of transport demand in
relation to income and estimated annual production increase. The other aspects
including socio-economic development plans and the land use patterns of the region
having impact on the traffic growth, the projections of vehicle manufacturing industry
in the country, development plans for the other modes of transport, O-D and
commodity movement behaviour should also be taken into account while working out
the traffic demand estimates.
2. The values of elasticity of transport demand shall be based on the prevailing practices
i n the country. The Consultants shall give complete background including
references for selecting the value of transport demand elasticity.
-49-
3. country. The Consultants shall give complete background including references for
selecting the value of transport demand elasticity.
4. It is envisaged that the project road sections covered under this TOR would be completed
and opened to traffic after 3 years. The traffic demand estimates shall be done for a
further period of 30 years from completion of two/four lane. The demand estimates shall
be done assuming three scenarios, namely, optimistic, pessimistic and most likely traffic
growth. The growth factors shall be worked out for five-yearly intervals.
5. Traffic projections should be based on sound and proven forecasting techniques. In case
traffic demand estimated is to be made on the basis of a model, the application of the
model in the similar situation with the validation of the results should be established. The
traffic projections should also bring out the possible impact of implementation of any
competing facility in the near future. The demand estimates should also take into account
the freight and passenger traffic along the major corridors that may interconnect with the
project. Impact of toll charges on the traffic estimates should be estimated.
6. The methodology for traffic demand estimates described in the preceding paragraphs is
for normal traffic only. In addition to the estimates for normal traffic, the Consultants
shall also work out the estimates for generated, induced and diverted traffic.
7. The traffic forecasts shall also be made for both diverted and generated traffic.
8. Overall traffic forecast thus made shall form the basis for the design of each pavement
type and other facilities/ancillary works.
-50-
iv. realignment requirements including the provision of bypasses, ROBs /
Flyovers and via-duct for pedestrian crossings with possible alignment
alternatives;
v. preliminary identification of improvement requirements including treatments
and measures needed for the cross-roads;
vi. traffic pattern and preliminary identification of traffic homogenous links;
vii. sections through congested areas;
viii. inventory of major aspects including land width, terrain, pavement type,
carriageway type, bridges and structures (type, size and location),
intersections(type, cross-road category, location) urban areas (location,
extent), geologically sensitive areas, environmental features:
ix. critical areas requiring detailed investigations; and,
x. Requirements for carrying out supplementary investigations.
xi. soil (textural classifications) and drainage conditions
xii. Type and extent of existing utility services along the alignment (within ROW).
xiii. Typical physical features along the approach roads
xiv. Possible bridge locations, land acquisition problems, nature of crossings,
likely length of approaches and bridge, firmness of banks, suitability of
alignment of approach roads.
3.The data derived from the reconnaissance surveys are normally utilized
for
planning and programming the detailed surveys and investigations. All field
studies including the traffic surveys should be taken up on the basis of information
derived from the reconnaissance surveys.
4. The data and information obtained from the reconnaissance surveys should be
documented. The data analysis and the recommendations concerning alignment
and the field studies should be included in the Inception Report. The data obtained
from the reconnaissance surveys should form the core of the database which
would be supplemented and augmented using the data obtained from detailed field
studies and investigations.
5.The data obtained from the reconnaissance surveys should be compiled in the
tabular as well as graphical (chart) form indicating the major physical features and
the proposed widening scheme for Executive Engineer, National Highway
Division, Karwar. comments. The data and the charts should also accompany the
rationale for the selection of traffic survey stations.
4.11.2.Topographic Surveys
1. The basic objective of the topographic survey would be to capture the essential
ground features along the alignment in order to consider improvements and for working
out improvements, rehabilitation and upgrading costs. The detailed
topographic surveys should normally be taken up after the completion of reconnaissance
surveys.
-51-
2. The carrying out of topographic surveys will be one of the most important and crucial
field tasks under the project. Technologies which can meet the following accuracy levels
shall be adopted. For land based surveys (a) Fundamental horizontal accuracy of 2 cm or
better (b) Fundamental vertical accuracy of 2 cm or better (c) More than 50 points shall be
measured per sq. m and for aerial based surveys (a) Fundamental horizontal accuracy of 5
cm or better (b) Fundamental vertical accuracy of 5 cm or better (c) More than 10 points
shall be measured per sq. m. To establish accuracy, a check point survey using DGPS (for
horizontal accuracy) and Auto Level (for vertical accuracy) shall be carried out to
establish the fundamental horizontal and vertical accuracy. A minimum of 25 check
points, or check points once every 4 km should be established, and these should be strictly
different from any geo-referencing or control network points.
3. The following are the set of deliverables which should be submitted after completion of
survey: (a) Raw DGPS data for the entire highway length and adjoining areas of interest
(b) Point cloud data/ Data of points captured for the entire highway length and adjoining
areas of interest (c) Topographic map of scale 1:1000 of the entire highway length and
adjoining areas of interest (d) Contour map of 50 cm of entire highway length and
adjoining areas of interest (e) Cross section of the highway at every 1 m in *.dwg format.
4. For land based surveys, Mobile LiDAR (Light Detection and Ranging) or equivalent
technology that can meet above requirements shall be adopted. For aerial based surveys,
Aerial Mobile LiDAR (Light Detection and Ranging) or equivalent technology that can meet
above requirements shall be adopted. In shadow areas such as invert levels below culverts,
where LiDAR or equivalent technologies cannot survey accurately, traditional methods of
Total Station/ Auto Level shall be used to complete the study.
5. In case of mobile LiDAR or equivalent technology, 360 degree panoramic images of the
entire highway length and adjoining areas of interest shall be submitted. In case of aerial
LiDAR or equivalent technology, ortho-images of the entire highway length and
adjoining areas of interest shall be submitted.
6. The detailed field surveys would essentially include the following activities:
i. Topographic Surveys along the Existing Right of Way (ROW):
Carrying out topographic survey using LiDAR or equivalent
technology along the existing road and realignments, wherever
required and properly referencing the same with reference pillars
fixed on either side of the centre-line at safe places within the
ROW
ii. The detailed field surveys would essentially include the
topographic surveys along the proposed location of bridge and
alignment of approach road.
iii. The detailed topographic surveys should be carried out along the
approach roads alignment and location of bridge approved by
Executive Engineer, National Highway Division, Karwar.
-52-
iv. Collection/ Extraction of details for all features such as structures
(bridges, culverts etc.) utilities, existing roads, electric and
telephone installations (both O/H as well as underground), huts,
buildings, fencing and trees (with girth greater than 0.3metre) oil
and gas lines etc. falling within the extent of survey.
ii. In case the reconnaissance survey reveals the need for bypassing the
congested locations, the traverse lines would be run along the possible
alignments in order to identify and select the most suitable alignment for
the bypass. The detailed topographic surveys should be carried out along
the bypass alignment approved by Executive Engineer, National Highway
Division, Karwar. At locations where grade separated intersections could
be the obvious choice, the survey area will be suitably increased. Field
notes of the survey should be maintained which would also provide
information about traffic, soil, drainage etc.
iii. The width of the surveyed corridor will be widened appropriately where
developments and / or encroachments have resulted in a requirement for
adjustment in the alignment, or where it is felt that the existing alignment
can be improved upon through minor adjustments.
iv. iv Where existing roads cross the alignments, the survey will extend a
minimum of100 m either side of the road centre line and will be of
sufficient width to allow improvements, including at grade intersection to
be designed.
iii. Longitudinal section for cross roads for length adequate for design and
quantity estimation purposes.
iv. Longitudinal and cross sections for major and minor streams shall cover
Cross section of the channel at the site of proposed crossing and few cross
sections at suitable distance both upstream and downstream, bed level upto
top of banks and ground levels to a sufficient distance beyond the edges of
channel, nature of existing surface soil in bed, banks & approaches,
longitudinal section of channel showing site of bridge etc. These shall be as
per recommendations contained in IRC Special Publication No. 13
(Guidelines for the Design of Small Bridges and Culverts) and provisions of
IRC:5 (“Standard Specifications & Code of Practice for Road Bridges,
Section 1 – General Features of Design”).
3.The information collected during reconnaissance and field surveys shall be shown
on a strip plan so that the proposed improvements can be appreciated and the extent of
land acquisition with L.A schedule, utility removals of each type etc. assessed and
suitable actions can be initiated. Separate strip plan for each of the services involved
shall be prepared for submission to the concerned agency.
-55-
xi. Land width i.e. ROW
xii. Culverts, bridges and other structures (type, size, span arrangement and
location)
xiii. Roadside arboriculture
xiv. Existing utility services on either side within ROW.
xv. General drainage conditions
xvi. Design speed of existing road
The data should be collected in sufficient detail. The data should be compiled and
presented in tabular as well as graphical form. The inventory data would be stored
in computer files using simple utility packages, such as EXCEL.
4.11.3.2Pavement Investigation
1.Pavement Composition
i.The data concerning the pavement composition may be already available
with the PWD. However, the consultants shall make trial pits to ascertain
the pavement composition. The test pit interval will be as per Para 4
below.
ii.For each test pit, the following information shall be recorded:
test pit reference (Identification number, location):
pavement composition (material type and thickness); and
subgrade type (textural classification) and condition (dry, wet)
2.Road and Pavement Condition Surveys
i)Detailed field studies shall be carried out to collect road and pavement
surface conditions. The data should generally cover:
pavement condition (surface distress type and extent); shoulder
condition;
embankment condition; and drainage condition
Pavement Condition
cracking (narrow and wide cracking), % of pavement area
affected;
raveling, % of pavement area affected;
potholing, % of pavement area affected;
edge break, length (m); and, rut depth, mm
Shoulder Condition
Paved: Same as for pavement
Unpaved: material loss, rut depth and corrugation, Edge drop,
mm.
-56-
Embankment Condition
general condition; and extent of slope erosion
ii. The objective of the road and pavement condition surveys shall be to
identify defects and sections with similar characteristics. All defects shall be
systematically referenced, recorded and quantified for the purpose of
determining the mode of rehabilitation.
iii. The pavement condition surveys shall be carried out using visual means.
Supplemented by actual measurements and in accordance with the widely
accepted methodology (AASHTO, IRC, OECD, TRL and World Bank
Publications) adapted to meet the study requirements. The measurement of
rut depth would be made using standard straight edges.
vi. Middle 200m could be considered as representative sample for each one
km. of road and incase all other things are considered similar.
Drainage Condition
General condition
Connectivity of drainage turnouts into the natural topography
Condition in cut sections
Condition at high embankments
The data obtained from the condition surveys should be analysed and the road
segments of more or less equal performance may be identified using the criteria
given in IRC: 81-1997.
3.Pavement Roughness
i. The roughness surveys shall be carried out using Bump Integrator or similar
instrument. The methodology for the surveys shall be as per the widely used
standard practices. The calibration of the instrument shall be done as per the
procedure given in the World Bank’s Technical Publications and duly got
authenticated by established laboratory/institution acceptable to the client
ii. The surveys shall be carried out along the outer wheel paths. The surveys shall cover
a minimum of two runs along the wheel paths for each
-57-
.iii.The results of the survey shall be expressed in terms of BI and IRI and shall be presented
in tabular and graphical forms. The processed data shall be analysed using the cumulative
difference approach to identify road segments homogenous with respect to surface roughness.
vi. In case, the Consultants wish to use any acceptable method(s) other than
Benkelman Beam deflection technique for the evaluation of pavement
1. strength, viz. Falling weight deflectometer method etc.
details of such methods or innovative features for deflection
testing using Benkelman Beam technique along with the
methodology for data analysis, interpretation and the use of
such data for pavement overlay design purposes using IRC
or any other widely used practices, such as AASHTO
guidelines, should be got approved by Executive Engineer,
National Highway Division, Karwar. The sources of such
methods should be properly referenced.
-58-
1. 4.11.3.3.Subgrade Characteristics and Strength
1. Based on the data derived from condition (surface condition, roughness) and structural
strength surveys, the project road section should be divided into segments homogenous with
respect to pavement condition and strength. The delineation of segments homogenous with
respect to roughness and strength should be done using the cumulative difference approach
(AASHTO, 1993).
2. The data on soil classification and mechanical characteristics for soils along the existing
alignments may already be available with the PWD. The testing scheme is, therefore, proposed as
given under:
i. For the widening (2/- Laning) of existing road within the ROW, the
Consultants shall test at least three sub-grade soil samples for each
homogenous road segment or three samples for each soil type
encountered, whichever is more.
ii. For the roads along new alignments, the test pits for sub grade soil shall
be @5km or for each soil type, whichever is more. A minimum of three
samples should be tested corresponding to each homogenous segment.
3 The testing for subgrade soil shall include:
iii.in-situ density and moisture content at each test pit
iv. Field CBR using DCP at each test pit
v. Characterization (grain size and Atterberg limits) at each test pit and,
vi. Laboratory moisture-density characteristics (modified AASHTO
compaction);
vii. Laboratory CBR (unsoaked and 4-day soak compacted at three energy
levels) and swell.
4For problematic soils, the testing shall be more rigorous. The characteristics with
regard to permeability and consolidation shall also be determined for these soils. The
frequency of sampling and testing of these soils shall be finalised in consultation with
the Executive Engineer, National Highway Division, karwar. officers after the
problematic soil types are identified along the road sections.
5The laboratory for testing of material should be got approved from Executive
Engineer, National Highway Division, Karwar. before start of work.
-60-
2. For the bridges identified to be in a distressed condition based
upon the visual condition survey, supplementary testing shall be carried
out as per IRC-SP:35 and IRC-SP:40. Selection of tests may be made
based on the specific requirement of the structure.
3. The assessment of the load carrying capacity or rating of existing
bridges shall be carried out under one or more of the following scenarios:
when the design live load is less than that of the statutory commercial
vehicle plying or likely to ply on bridge;
if during the condition assessment survey and supplementary testing the
bridge is found to indicate distress of serious nature leading to doubt
about structural and / or functional adequacy, and
Design live load is not known nor are the records and drawings available
.
4.The evaluation of the load carrying capacity of the bridge shall be carried out
as per IRC-SP:37 (“Guidelines for Evaluation of Load Carrying Capacity of
Bridges”). The analytical and correlation method shall be used for the evaluation
of the load carrying capacity as far as possible. When it is not possible to
determine the load carrying capacity of the bridge using analytical and
correlation method, the same shall be carried out using load testing. The
consultant has to exhaust all other methods of evaluation of strength of bridges
before recommending to take up load testing of bridges. Road closure for testing
if unavoidable shall be arranged by Executive Engineer, National Highway
Division, Karwar. for limited duration say 12 hours or so.
5.Consultant shall carryout necessary surveys and investigations to establish the
remaining service life of each retainable bridge or structure with and without the
proposed strengthening and rehabilitation according to acceptable international
practice in this regard.
Geo-technical Investigations and Sub-Soil Exploration
4.11.4.4
The Consultants shall carry out geo-technical investigations and sub-surface
explorations for the proposed Bridges / Road over bridges/ tunnels/ viaducts/
interchanges etc., along high embankments and any other location as necessary
for proper design of the works and conduct all relevant laboratory and field tests
on soil and rock samples. The minimum scope of geo-technical investigations for
bridge and structures shall be as under:
-61-
S.No. Description Location of Boring
1 Overall length = 6 – 30 m One abutment location and One abutment
location and at least one intermediate location
between abutments for structures having more
than one span
2 Overall length = 30 – 60 m One abutment location and at least one
intermediate location between abutments for
structures having more than one span.
3 Overall length >60 m Each abutment and each pier locations.
1. The deviation(s), if any, by the Consultants from the scheme presented above
should be approved by Executive Engineer, National Highway Division, Karwar.
2. However, where a study of geo-technical reports and information available from
adjacent crossings over the same waterway (existing highway and railway bridges)
indicates that subsurface variability is such that boring at the suggested spacing
will be insufficient to adequately define the conditions for design purposes, the
Consultants shall review and finalise the bore hole locations in consultation with
the Executive Engineer, National Highway Division, Karwar. officers.
3. Geotechnical Investigations and Sub soil Explorations hall be carried out to
determine the nature and properties of existing strata in bed, banks and approaches
with trial pits and bore hole sections showing the levels, nature and properties of
various strata to a sufficient depth below the level suitable for foundations, safe
intensity of pressure on the foundation strata, proneness of site to artesian
conditions, seismic disturbance and other engineering properties of soil etc.
Geotechnical investigation and Sub-soil Exploration will be done as per IRC 78.
4. The scheme for the borings locations and the depth of boring shall be prepared by
the Consultants and submitted to Executive Engineer, National Highway
Division, Karwar. for approval. These may be finalised in consultation with
Executive Engineer, National Highway Division, Karwar.
5. The sub-soil exploration and testing should be carried out through the Geotechnical
Consultants empanelled by MORT&H The soil testing reports shall be in the
format prescribed in relevant IRC Codes.
6. For the approach road pavement, bore holes at each major change in pavement
condition or in deflection readings or at 2 km intervals whichever is less shall be
carried out to a depth of at least 2 m below embankment base or to rock level and
are to be fully logged. Appropriate tests to be carried out on samples collected
from these bore holes to determine the suitability of various materials for use in
widening of embankments or in parts of new pavement structure.
-62-
4.11.5.Material Investigations
1. The Consultants shall identify sources (including use of fly-ash/ slag), quarry sites
and borrow areas, undertake field and laboratory testing of the materials to
determine their suitability for various components of the work and establish
quality and quantity of various construction materials and recommend their use on
the basis of techno-economic principles. The Consultants shall prepare mass haul
diagram for haulage purposes giving quarry charts indicating the location of
selected borrow areas, quarries and the respective estimated quantities.
“Environment friendly materials”
th
“As per MORTH circular No. RW /NH-33044/53/2013-S&R(R) dated 20
November, 2013, alternative pavement materials and technologies for road
construction shall be assessed and compared in the design stage. The
alternative resulting in substantial reduction in GHG emission and with least
life cycle cost shall be recommended for implementation.
1. 4.12.2.Design Standards
1. The Consultants shall evolve Design Standards and material
specifications for the Study primarily based on IRC publications,
MORT&H Circulars and relevant recommendations of the
international standards for approval by Executive Engineer,
National Highway Division, Karwar.
2. The Design Standards evolved for the project shall cover all aspects
of detailed design including the design of geometric elements,
pavement design, bridges and structures, traffic safety and materials.
2. 4.12.3.Geometric Design
1. The design of geometric elements shall, therefore, take into account the essential
requirements of such facilities.
2. Based on the data collected from reconnaissance and topographic surveys, the
sections with geometric deficiencies, if any, should be identified and suitable measures for
improvement should be suggested for implementation.
3. The data on accident statistics should be compiled and reported showing accident
type and frequency so that black spots are identified along the project road section. The possible
causes (such as poor geometric features, pavement condition etc.) of accidents should be
investigated into and suitable cost-effective remedial measures suggested for implementation.
-64-
4. The detailed design for geometric elements shall cover, but not be limited to the
following major aspects:
i. horizontal alignment;
ii. longitudinal profile;
iii. cross-sectional elements, including refuge lane (50m)
at every 2kms.
iv. junctions, intersections and interchanges;
v. bypasses; and,
vi. service roads as and when require i.e built up area..
1. The alignment design shall be verified for available sight distances as per the
standard norms. The provision of appropriate markings and signs shall be made
wherever the existing site conditions do not permit the adherence to the sight
distance requirements as per the standard norms.
2. The consultants shall make detailed analysis of traffic flow and level of service
for the existing road and workout the traffic flow capacity for the improved
project road. The analysis should clearly establish the widening requirements with
respect to the different horizon periods taking into account special problems such
as road segments with isolated steep gradients.
3. In the case of closely spaced cross roads the Consultant shall examine different
options such as, providing grade separated structure for some of them with a view
to reduce number of at-grade crossings, services roads connecting the cross-roads
and closing access from some of the intersections and prepare and furnish
appropriate proposals for this purpose keeping in view the cost of improvement,
impact on traffic movement and accessibility to cross roads. The detailed drawings
and cost estimate should include the provisions for realignments of the existing
cross roads to allow such arrangements.
4. The Consultant shall also prepare design of grade separated pedestrian crossings
(viaducts) for large cross traffic of pedestrians and / or animals.
5. The Consultant shall also prepare details for at-grade junctions, which may be
adopted as alternative to the grade separated structures. The geometric design of
interchanges shall take into account the site conditions, turning movement
characteristics, level of service, overall economy and operational safety.
6. The Consultants shall prepare design and other details in respect of the parallel
service roads in urbanized locations and other locations to cater to the local traffic,
their effect of the viability of the project on commercial basis if service roads are
constructed as part of the project and the implications of not providing the service
roads.
7. The consultant shall prepare complete road and pavement design including
drainage for new bypass option identified around congested town en-route.
4.12.4.Pavement Design
1.The detailed design of pavement shall involve:
-65-
i. strengthening of existing road pavement and design of the new pavement if
any, if the findings of the traffic studies and life-cycle costing analysis
confirm the requirement for widening of the road beyond 2lane undivided
carriageway standard;;
1.1.1 pavement design for bypasses; and,
1.1.2 design of shoulders.
1. The design of pavement shall primarily be based on IRC publications.
2. The design of pavement shall be rigorous and shall make use of the latest
Indian and International practices. The design alternatives shall include
both rigid and flexible design options. The most appropriate design,
option shall be established on life-cycle costing and techno-economic
consideration.
3. For the design of pavement, each set of design input shall be decided on
the basis of rigorous testing and evaluation of its suitability and relevance
in respect of in-service performance of the pavement. The design
methodology shall accompany the design proposals and shall clearly bring
out the basic assumptions, values of the various design inputs, rationale
behind the selection of the design inputs and the criteria for checking and
control during the implementation of works. In other words, the design of
pavement structure should take due account of the type, characteristics of
materials used in the respective courses, variability of their properties and
also the reliability of traffic predictions. Furthermore, the methodology
adopted for the design of pavement shall be complete with flowcharts
indicating the various steps in the design process, their interaction with one
another and the input parameter required at each step.
4. For the design of overlays for the existing 2-lane pavement, the
strengthening requirement shall duly take into account the strength of the
existing pavement vis-à-vis the remaining life. The overlay thickness
requirements shall be worked out for each road segment homogenous with
respect to condition, strength and sub-grade characteristics. The
rehabilitation provisions should also include the provision of regulating
layer. For existing pavement with acceptable levels of cracking, provision
of a crack inhibiting layer should also be included.
5. Latest techniques of pavement strengthening like provision of geo-
synthetics and cold/hot pavement recycling should be duly considered by
the consultant for achieving economy.
6. The paved shoulders shall be designed as integral part of the pavement for
the main carriageway. The design requirements for the carriageway
pavement shall, therefore, be applicable for the design of shoulder
pavements. The design of granular shoulder should take into account the
drainage considerations besides the structural requirements.
7. The pavement design task shall also cover working out the maintenance
and strengthening requirements and periodicity and timing of such
treatments.
-66-
2 4.12.5.Design of Embankments
2.1 1.The embankments design should provide for maximum utilization of locally available
materials consistent with economy. Use of fly ash wherever available with in economical
leads must be considered. In accordance with Government instructions, use of fly ash
within 100 km from Thermal Power Stations is mandatory.
2.1.1 2.The Consultants shall carry out detailed analysis and design for all embankments
of height greater that 6 m based on relevant IRC publications.
2.2 3.The design of embankments should include the requirements for protection
works and traffic safety features.
-67-
2.The Consultant shall prepare General Arrangement Drawing (GAD) and Alignment
Plan showing the salient features of the bridges and structures proposed to be constructed
/ reconstructed along the road sections covered under the Study. These salient features
such as alignment, overall length, span arrangement, cross section, deck level, founding
level, type of bridge components (superstructure, substructure, foundations, bearings,
expansion joint, return walls etc.) shall be finalized based upon hydraulic and geo-
technical studies, cost effectiveness and ease of construction. The GAD shall be
supplemented by Preliminary designs. In respect of span arrangement and type of bridge a
few alternatives with cost-benefit implications should be submitted to enable Executive
Engineer, National Highway Division, Karwar. to approve the best alternative. After
approval of alignment and GAD the Consultant shall prepare detailed design as per IRC
codes /guidelines and working drawings for all components of bridges and structures.
1. .The location of all at-grade level crossings shall be identified falling across the
existing level crossings for providing ROB at these locations. The Consultants shall
prepare preliminary GAD for necessary construction separately to the Client. The
Consultant shall pursue the Indian Railways Authorities or/and any statutory authority of
State/Central Government for approval of the GAD from concerned Authorities.
2. GAD for bridges/structures across irrigation/water way channels shall be got approved
from the concerned Irrigation/Water way Authorities. Subsequent to
a. approval of GAD and alignment plan by Executive Engineer, National Highway
Division, Karwar. the Consultants shall prepare detailed design as per IRC
codes/guidelines for all components of the bridges and structures.
3. Subsequent to the approval of the GAD and Alignment Plan by Executive Engineer,
National Highway Division, Karwar. and Railways, the Consultant shall prepare detailed
design as per IRC and Railways guidelines and working drawings for all components of
the bridges and structures. The Consultant shall furnish the design and working drawings
for suitable protection works and/or river training works wherever required.
4. Dismantling/ reconstruction of existing structures shall be avoided as far as possible
except where considered essential in view of their poor structural conditions/ inadequacy
of the provisions etc.
5. The existing structures having inadequate carriageway width shall be
widened/reconstructed in pat or fully as per the latest MORT&H guidelines. The
Consultant shall furnish the detailed design and working drawings for carrying out the
above improvements.
6. Suitable repair / rehabilitation measures shall be suggested in respect of the existing
structures as per IRC-SP:40 along with their specifications, drawings and cost estimate in
the form of a report. The rehabilitation or reconstruction of the structures shall be
suggested based on broad guidelines for rehabilitation and strengthening of existing
bridges contained in IRC-SP:35 and IRC-SP:40.
7. Subsequent to the approval of the GAD and the alignment plan by Executive Engineer,
National Highway Division, Karwar., detailed design shall also be carried out for the
proposed underpasses, overpasses and interchanges.
8. The Consultants shall also carry out the design and make suitable recommendations for
protection works for bridges and drainage structures.
-68-
9. In case land available is not adequate for embankment slope, suitable design for RCC
retaining wall shall be furnished. However, RES wall may also be considered depending
upon techno-economic suitability to be approved by Executive Engineer, National
Highway Division, Karwar.
4 4.12.7.drainage System
1. The requirement of roadside drainage system and the integration of the same with
proposed cross-drainage system shall be worked out for the entire length of the
project road section.
2. In addition to the roadside drainage system, the Consultants shall design the
special drainage provisions for sections with super-elevated carriageways, high
i. embankments and for road segments passing through cuts. The drainage
provisions shall also be worked out for road segments passing through
urban areas.
3. The designed drainage system should show locations of turnouts/outfall points
with details of outfall structures fitting into natural contours. A separate drawing
sheet covering every 5 km. stretch of road shall be prepared.
7 4.12.10.Toll Plaza
7.1 The Consultants shall identify the possible toll plaza location(s) based on the data and
information derived from the traffic studies and a study of the existing physical
features including the availability of land. The location of the plaza should keep in
view that the project road is to be developed as a partially access controlled highway
facility and it is required to collect toll on rational basis from as much of the vehicular
traffic as possible consistent with economy of collection and operations. The location
of the toll plaza should be finalised in consultation with Executive Engineer,
National Highway Division, Karwar.
7.2 Toll Plaza shall be designed as per IRC 84.
-69-
8 4.12.11.Weighing Station, Parking Areas and Rest Areas
The consultant shall select suitable sites for weighing stations, parking areas and rest
areas and prepare suitable separate designs in this regard. The common facilities like
petrol pump, first-aid medical facilities, police office, restaurant, vehicle parking etc.
should be included in the general layout for planning. For petrol pump, the guidelines
issued by OISD of Ministry of Petroleum shall be followed. The
facilities should be planned to be at approximately 50 km interval. Atleast
each facility (1 no.) is foreseen to be provided for this project stretch. Weighing stations can be
located near toll plazas so that overloaded vehicles can be easily identified and suitably penalized
and unloaded before being allowed to proceed further. The type of weighing system suitable for
the project shall be brought out in the report giving merits of each type of the state-of-the art and
basis of recommendations for the chosen system.
9 4.12.12Office-cum-Residential Complex for PIU-Deleted
10 Miscellaneous Works
1. The Consultants shall make suitable designs and layout for miscellaneous
works including rest areas, bus bays, vehicle parking areas,
telecommunication facilities etc. wherever appropriate.
2. The Consultants shall prepare the detailed scheme and lay out plan for the
works mentioned in Para 1.
3. The Consultants shall prepare detailed plan for the traffic management and
safety during the construction period.
12.6 10.The consultant shall identify and plan for plantation and Transplantation of the
suitable trees along the existing highway in accordance with IRC guidelines.
12.7 11.The consultant shall assist in providing appropriate input in preparation of
relevant environment and social sections of BPIP.
4.13.2.Social Assessment
a. The consultant would conduct base line socio-economic and census survey to
assess the impacts on the people, properties and loss of livelihood. The
socioeconomic survey will establish the benchmark for monitoring of R&R
activities. A social assessment is conducted for the entire project to identify
mechanisms to improve project designs to meet the needs of different
stakeholders. A summary of stakeholder discussions, issue raised and how the
project design was developed to meet stakeholders need would be prepared.
b. The consultant shall prepare Land Acquisition Plan and assist Executive
Engineer, National Highway Division, Karwar. in acquisition of land under
various Acts.
4.13.2.3.The consultant would prepare Resettlement and Rehabilitation Plan and
assess feasibility and effectiveness of income restoration strategies and
suitability and availability to relocation sites. The resettlement plan which
-71-
accounts for land acquisition and resettlement impacts would be based on a 25%
socio-economic survey and 100 % census survey of project affected people
which provides the complete assessment of the number of affected households
and persons, including common property resources. All untitled occupants are
recorded at the initial stages and identify cards will be issued to ensure there is
no further influx of peoplen to the project area. All consultations with affected
persons (to include list of participants) should be fully documented and records
made available to Executive Engineer, National Highway Division, Karwar.
Assessment on the impact of the project on the poor and vulnerable groups
along the project road corridor.
Based on the identified impacts, developing entitlement matrix for the
project affected people.
Assessment on social issues such as indigenous people, gender,
HIV/AIDS, labourers including child labour.
Implementation budgets, sources and timing of funding and schedule of
tasks.
Responsibility of tasks, institutional arrangements and personnel for
delivering entitlement and plans to build institutional capacity.
Internal and external monitoring plans, key monitoring indicators and
grievance redress mechanism.
Incorporating any other suggestions of the Executive Engineer, National
Highway Division, Karwar., till the acceptance of the reports by the
Executive Engineer, National Highway Division, Karwar.
-72-
Incorporating any other as per the suggestions of the ADB/ World
Bank / MORT&H/ Executive Engineer, National Highway
Division, Karwarr., till the acceptance of the reports by the ADB/
World Bank / MORT&H/ Executive Engineer, National Highway
Division, Karwar. , as applicable.
EMP Reports for Contract Package based on uniform methodology
and processes. The consultant will also ensure that the EMP has all
the elements for it to be a legal document. The EMP reports would
include the following:
Brief description of the project, purpose of the EMP, commitments on incorporating
environmental considerations in the design, construction and operations phases of the
project and institutional arrangements for implementing the EMP.
A detailed EMP for construction and operational phases with
recourse to the mitigation measures for all adverse impacts.
o Detailed plans for highway-side tree
plantation (as part
o of the compensatory aforestation component).
Environmental enhancement measure would be incorporated.
Enhancement measures would include items described in the scope
of work and shall be complete with plans, designs, BOQ and technical specifications.
Environmental monitoring plans during and after construction
including scaling and measurement techniques for the performance indicators selected for
monitoring.
The EMP should be amendable to be included in the contract
documents for the works.
Incorporating any other as per the suggestions of the ADB/ World
Bank/ Executive Engineer, National Highway Division, Karwar., till the
acceptance of the reports by the ADB/ World Bank / Executive Engineer,
National Highway Division, Karwar. as applicable.
Executive summary
Description of project
Objectives of the project.
The need for Resettlement in the Project and evaluation of
measures to minimize resettlement.
Description and results of public consultation and plans for
continued participation of PAPs.
Definition of PAPs and the eligibility criteria.
Census and survey results-number affected, how are they affected
and what impacts will they experience.
-73-
Legal and entitlement policy framework-support principles for
different categories of impact.
Arrangements for monitoring and evaluation (internal and external)
Implementation schedule for resettlement which is linked to the civil
works contract
A matrix of scheduled activities linked to land acquisition
procedures to indicate clearly what steps and actions will be taken
at different stages and the time frame
The payment of compensation and resettlement during the
acquisition process
An itemized budget (replacement value for all assets) and unit costs
for different assets
-74-
4. The economic and commercial analyses should bring out the priority of the
different homogenous links in terms of project implementation.
6.1.Economic Analysis
1. The Consultants shall carry out economic analysis for the project. The analysis
should be for each of the sections covered under this TOR. The benefit and cost
streams should be worked out for the project using HDM-IV or other
internationally recognized life-cycle costing model.
2. The economic analysis shall cover but be not limited to be following aspects:
2. assess the capacity of existing roads and the effects of capacity constraints
-75-
1. on vehicle operating costs (VOC);
2. calculate VOCs for the existing road situation and those for the project;
3. quantify all economic benefits, including those from reduced congestion,
travel distance, road maintenance cost savings and reduced incidence of road
accidents; and,
4. estimate the economic internal rate of return (EIRR) for the project over a
30-year period. In calculating the EIRRs, identify the tradable and non-tradable
components of projects costs and the border price value of the tradable
components.
5. Saving in time value.
3.Economic Internal Rate of Return (EIRR) and Net Present Value (NPV), “with “and “without
time and accident savings” should be worked out based on these cost-benefit stream.
Furthermore, sensitivity of EIRR and NPV worked out forth different scenarios as given under:
Scenario – I Base Costs and Base Benefits
Scenario - II Base Costs plus 15% and Base Benefits
Scenario - III Base Costs and Base Benefits minus 15%
Scenario - IV Base Costs plus 15% and Base Benefits minus 15%
The sensitivity scenarios given above are only indicative. The Consultants shall
select the sensitivity scenarios taking into account possible construction delays,
construction costs overrun, traffic volume, revenue shortfalls, operating costs,
exchange rate variations, convertibility of foreign exchange, interest rate volatility,
non-compliance or default by contractors, political risks and force majeure.
12.8 4.The economic analysis shall take into account all on-going and future road and
transport infrastructure projects and future development plans in the project area.
6.2.Financial Analysis
a. It is envisaged that the project stretch should be implemented on EPC/BOT basis,
therefore, the Consultant shall study the financial viability of the project under a
commercial format and under different user fee scenarios and funding options.
The Consultants shall submit and finalize in consultation with the Executive
Engineer, National Highway Division, Karwar. officers the format for the
analysis and the primary parameters and scenarios that should be taken into
account while carrying out the commercial analysis. The financial model so
developed shall be the property of Executive Engineer, National Highway
Division, Karwar.
b. The Financial analysis for the project should cover financial internal rate of return,
projected income statements, balance sheets and fund flow statements and should
bring out all relevant assumptions. The sensitivity analysis should be carried out
for a number of probabilistic scenarios.
c. The financial analysis should cover identification, assessment, and mitigating
measures for all risks associated with the project. The analysis shall cover, but be not
limited to, risks related to construction delays, construction costs overrun, traffic
volume, revenue shortfalls, operating costs, exchange rate variations, convertibility of
foreign exchange, interest rate volatility, non-compliance or default by
-76-
i. contractors, political risks and force majeure.
d. The consultant shall suggest positive ways of enhancing the project Viability and
furnish different financial models for implementing on BOT format.
7.Time period for the service
12.9 1.Time period envisaged for the study of the project is indicated in Annex-I to
LOI. The final reports, drawings and documentation shall be completed within
this time schedule.
2. Executive Engineer, National Highway Division, Karwar. shall arrange to give approval
on all sketches, drawings, reports and recommendations and other matters and proposals
submitted for decision by the Consultant in such reasonable time so as not to delay
or disrupt the performance of the Consultant’s services.
-77-
i. The Consultant shall maintain an Attendance Register to be signed by each
individual key personnel at site as well as at Head Office. The Consultant
shall furnish certificate that all the key personnel as envisaged in the
Contract
ii. Agreement have been actually deployed in the Projects at the time of
submission of their bills to the Executive Engineer, National Highway
Division, Karwar. from time to time.
Preliminary design work should commence without waiting for feasibility study to be
completed. Stage 3, 5 and 6 shall run in parallel with Stage 2 and 4
Stage 1: Inception Report
9.3.Consultant shall be required to complete, to the satisfaction of the client, all the different
stages of study within the time frame indicated in the schedule of submission in para 10
pertaining to Reports and Documents for becoming eligible for payment for any part of
the next stage.
-78-
2.The time schedule for various submissions prescribed at s.l.no.1 above shall be strictly
adhered to. No time-over-run in respect of these submissions will normally be permitted.
Consultant is advised to go through the entire terms of reference carefully and plan his work
method in such a manner that various activities followed
-79-
iv. Work programme;
v. Proforma for data collection;
vi. Design standards and proposed cross-sections;
-80-
vii. Key plan and Linear Plan;
viii. Development plans being implemented and / or proposed for implementation
in the near future by the local bodies and the possible impact of such
development plans on the overall scheme for field work and design for the
study;
ix. Quality Assurance Plan (QAP) finalised in consultation with Executive
Engineer, N.H. Division, Karwar;
x. Draft design standards; and
2.The requirements, if any, for the construction of bypasses should be identified on
the basis of data derived from reconnaissance and traffic studies. The available
alignment options should be worked out on the basis of available maps. The most
appropriate alignment option for bypasses should be identified on the basis of site
conditions and techno-economic considerations. Inception Report should include the
details regarding these aspects concerning the construction of bypasses for approval
by Executive Engineer, National Highway Division, Karwar.
STAGE 2:
10.3.Feasibility Report
1. The consultant shall commence the Feasibility Study of the project in accordance
with the accepted IR and the report shall contain the following:
i. Executive summary
ii. Overview of Executive Engineer, National Highway Division,
Karwar. organization and activities, and project financing and cost
recovery mechanisms
iii. Project description including possible alternative
alignments/bypasses and technical/engineering alternatives
iv. Methodology adopted for the feasibility study
v. Socioeconomic profile of the project areas
vi. Indicative design standards, methodologies and specifications
vii. Traffic surveys and analysis
viii. Environmental screening and preliminary environmental assessment
ix. Initial social assessment and preliminary land
acquisition/resettlement plan
x. Cost estimates based on preliminary rate analysis and bill of
quantities
xi. Economic and financial analysis
xii. Conclusions and recommendations
2.In view of para 1 above the consultant has to submit the following documents in six sets:
iii. Cost Estimates: This volume will present the each item of work as well as a
summary of total cost.
iv. Bill of Quantities: This volume shall contain the detailed Bill of Quantities for all
items of works
3. The basic data obtained from the field studies and investigations shall be submitted in a separate
volume as an Appendix to Feasibility Report.
4. The Final Feasibility Study Report incorporating comments, revisions and modifications
suggested by Executive Engineer, National Highway Division, Karwar. shall be submitted within
15 days of comments from Executive Engineer, National Highway Division, Karwar. on draft
feasibility study report.
STAGE 3:
STAGE: 4
10.7 Draft Detailed Project Report (DPR)
1. The draft DPR Submission shall consist of construction package-wise Main Report,
Design Report, Materials Report, Engineering Report, Drainage Design Report,
Economic and Financial Analysis Report, Environmental Assessment Report including
Resettlement Action Plan (RAP), Package-wise bid Documents and Drawings.
2. The Report volumes shall be submitted as tabulated in para 10 above.
3.The Documents and Drawings shall be submitted for the Package and shall be in the
following format:
-83-
I. Reports
i. Volume-I, Main Report: This report will present the project background, social
analysis of the project, details of surveys and investigations carried out, analysis and
interpretation of survey and investigation data, traffic studies and demand forecasts
designs, cost estimation, environmental aspects, economic and commercial analyses and
conclusions. The report shall include Executive Summary giving brief accounts of the
findings of the study and recommendations.
The Report shall also include maps, charts and diagrams showing locations and details of
existing features and the essential features of improvement and upgrading. The
Environmental Impact Assessment (EIA) Report for contract package shall be submitted as a
part of the main report.
The basic data obtained from the field studies and investigations and input data used for
the preliminary design shall be submitted in a separate volume as an Appendix to Main
Report.
ii. Volume - II, Design Report: This volume shall contain design calculations, supported
by computer printout of calculations wherever applicable. The Report shall clearly bring out
the various features of design standards adopted for the study. The design report will be in
two parts. Part-I shall primarily deal with the design of road features and pavement
composition while Part-II shall deal with the design of bridges, tunnels and cross-drainage
structures. The sub-soil exploration report including the complete details of boring done,
analyses and interpretation of data and the selection of design parameters shall be included
as an Appendix to the Design Report.
The detailed design for all features should be carried out as per the requirements of the
Design Standards for the project. However, there may be situations wherein it has not
been possible to strictly adhere to the design standards due to the existing site conditions,
restrictions and other considerations. The report should clearly bring out the details of
these aspect and the standards adopted.
iii. Volume - III, Materials Report: The Materials Report shall contain details
concerning the proposed borrow areas and quarries for construction materials and
possible sources of water for construction purposes. The report shall include details on
locations of borrow areas and quarries shown on maps and charts and also the estimated
quantities with mass haul diagram including possible end use with leads involved, the
details of sampling and testing carried out and results in the form of important index
values with possible end use thereof.
The materials Report shall also include details of sampling, testing and test
results obtained in respect physical properties of subgrade soils. The information shall be
presented in tabular as well as in graphical
-84-
representations and schematic diagrams. The Report shall present soil profiles along
the alignment.
The material Report should also clearly indicate the locations of areas with
problematic soils. Recommendations concerning the improvement of such soils for use
in the proposed construction works, such as stabilization (cement, lime, mechanical)
should be included in the Report.
vi. Volume - VI, Rate Analysis: This volume will present the analysis of rates for all
items of works. The details of unit rate of materials at source, carriage charges, any
other applicable charges, labour rates, machine charges as considered in arriving at
unit rates will be included in this volume.
vii. Volume - VII, Cost Estimates: This volume will present the contract package wise
cost of each item of work as well as a summary of total cost.
viii. Volume - VIII, Bill of Quantities: This volume shall contain the package-wise
detailed Bill of Quantities for all items of works.
ix. Volume - IX, Drawing Volume: All drawings forming part of this volume shall be
‘good for construction’ drawings. All plan and profile drawings will be prepared in
scale 1:250V and 1:2500H scale to cover one km in one sheet. In addition this volume
will contain ‘good for construction’ drawings for the following:
Horizontal Alignment and Longitudinal Profile.
Cross-section @ 50m interval along the alignment within ROW
Typical Cross-Sections with details of pavement structure.
Detailed Working Drawings for individual Culverts and Cross Drainage Structures.
Detailed Working Drawings for individual Bridges, tunnels and Structures.
Detailed Drawings for Improvement of At-Grade and Grade-
-85-
Separated
Intersections and Interchanges.
Drawings for Road Sign, Markings, Toll Plazas, and other Facilities.
Schematic Diagrams (linear chart) indicating but be not limited to be following:
o Widening scheme;
o Locations of median openings, intersections, interchanges, underpasses,
overpasses, bypasses;
o Locations of service roads;
o Location of traffic signals, traffic signs, road markings, safety features; and,
o Locations of toll plaza, parking areas, weighing stations, bus bays, rest areas, if
any.
Drawings for toll plaza, Bus Bays, Parking areas, Rest areas, weighing
stations etc. All drawings will be prepared in A2 size sheets. The format for
plan, cross section and profile drawings shall be finalised in consultation
with the concerned Executive Engineer, National Highway Division,
Karwar. officers. The drawings shall also include details of all BM and
reference pillars, HIP and VIP. The co-ordinates of all points should be
referenced to a common datum, preferably GTS referencing system. The
drawings shall also include the locations of all traffic safety features
including traffic signals, signs, markings, crash barriers, delineators and rest
areas, busbays, parking areas etc.
The typical cross-section drawings should indicate the scheme for future
widening of the carriageway. The proposed cross-sections of road
segment passing through urban areas should indicate the provisions for
pedestrian movements and suitable measures for surface and sub-surface
drainage and lighting, as required.
1. The Final package-wise DPR consisting of Main Report, Design Report, Drainage
Design Report and Materials Report, incorporating all revisions deemed relevant
following receipt of the comments from Executive Engineer, National Highway
Division, Karwar. on the draft DPR shall be submitted as per the schedule given
in Enclosure-III.
STAGE: 5
10.9 Technical Schedules
1.Civil Work Contract Agreement: A civil works contract agreement shall be submitted
-86-
STAGE: 6
10.10 LA & Clearances II Report
2. All the necessary project related clearances such as environment, forest and wildlife
clearance from MOEF, Railways in respect of ROB/ RUBs, Irrigation Deptt and any
other concerned agencies shall be obtained by the consultant. The final approvals
shall be obtained and submitted to Executive Engineer, National Highway
Division, Karwar. so that project implementation can straight away proceed without
any hold up. For utility clearances, consultant shall prepare draft utility shifting
estimates using the latest Schedule of Rates and obtain final approval from utility
agency and Executive Engineer, National Highway Division, Karwar.
1. During entire period of services, the Consultant shall interact continuously with Executive
Engineer, National Highway Division, Karwar. and provide any clarification as regards
methods being followed and carryout modification as suggested by Executive Engineer,
National Highway Division, Karwar. A programme of various activities shall be provided to
Executive Engineer, National Highway Division, Karwar. and prior intimation shall be
given to Executive Engineer, National Highway Division, Karwar. regarding start of key
activities such as boring, survey etc. so that inspections of Executive Engineer, National
Highway Division, Karwar. officials could be arranged in time.
2. The Executive Engineer, National Highway Division, Karwar. officers and other
Government officers may visit the site at any time, individually or collectively to acquaint/
supervise the field investigation and survey works. Executive Engineer, National Highway
Division, Karwar. may also appoint a Proof Consultant to supervise the work of the DPR
consultant including inter-alia field investigation, survey work, Design work and
preconstruction activities
3. The consultant shall be required to send 3 copies of concise monthly Progress Report by the 5th
day of the following month to the designated officer at his Head Quarter so that progress could
be monitored by the Executive Engineer, National Highway Division, Karwar. These reports
will indicate the dates of induction and de-induction of various key personnel and the activities
performed by them. Frequent meetings with the consultant at site office or in Delhi are foreseen
during the currency of project preparation.
4. All equipment, software and books etc. required for satisfactory services for this project
shall be obtained by the Consultant at their own cost and shall be their property.
1. The Consultant will be paid consultancy fee as a percentage of the contract values as per the
schedule given in the Draft Contract Agreement.
-87-
13. Data and Software
1. The floppy diskettes/CD’s containing all basic as well as the processed data from all field
studies and investigations, report, appendices, annexure, documents and drawings shall be
submitted to Executive Engineer, National Highway Division, Karwar. at the time of the
submission of the Final Report. The data can be classified as follows:
II. Topographic Surveys and Drawings: All topographic data would be supplied in (x, y,
z) format along with complete reference so that the data could be imported into any
standard highway design software. The drawing files would be submitted in dxf or
dwg format.
III. Rate Analysis: The Consultant shall submit the rate analysis for various works items
including the data developed on computer in this relation so that it could be used by
the Authority later for the purpose of updating the cost of the project.
2. Software: The Consultant shall also hand-over to Executive Engineer, National Highway
Division, Karwar. floppies/CD’s containing any general software including the financial
model which has been specifically developed for the project.
3. The floppy diskettes/CD’s should be properly indexed and a catalogue giving contents of all
floppies/CD’s and print-outs of the contents (data from field studies topographic data and
drawings) should be handed over to Executive Engineer, National Highway Division,
Karwar. at the time of submission of the Final Report.
4. Consultant shall include editable soft copies of the final versions of all documents, including but
not limited to the strip plan, plan & profile drawings, cross sections of right of way and details
of structures as well as any cost workings.
-88-
UPPLEMENT I
5. 4.5 (1) All activities related to field studies, design and documentation shall be
done as per the latest guidelines/circulars of MORT&H and relevant
publications of the Indian Roads Congress (IRC)/Bureau of Indian Standards
(BIS) for hill roads. For aspects not covered by IRC and BIS, international
standard practices, such as, British and American Standards may be adopted.
89-
protection works, slope stabilization measures, snow drift control
measures, avalanche protection measures
f) Existing land slide and snow clearance facilities
g)Geological details of rock strata in the area in case of tunnels
7. 4.11(1) The Consultant should make an in depth study of available geological and
meteorological maps of the area.
8. 4.11 (2) The primary tasks to be accomplished during the reconnaissance survey
shall also include:
a) details of terrain (steep or mountainous ), cliffs and gorges, general
elevation of the road including maximum heights negotiated by main
ascents and descents, total number of ascents and descents, hair pin bends,
vegetation etc.
b) Climatic conditions i.e. temperature, rain fall data, snow fall data, fog
conditions, unusual weather conditions etc.
c) Realignment requirements including provision of tunnels, if required.
d) Inventory of tunnels and geologically sensitive areas like slip prone
areas, areas subject to landslides, rock fall, snow drifts, erosion, avalanche
activity etc.
9. 4.11.2.1 (ii) Cross sections shall be taken at every 25 m. in case of hill roads and at
points of appreciable changes in soil conditions. While taking cross
sections, soil conditions shall also be recorded.
10. 4.11.3.1 (1) The inventory data shall also include:
a) General elevation of road indicating maximum & minimum heights
negotiated by main ascents & descents and total no. of ascents &descents.
b) Details of road gradients, lengths of gentle & steep slopes, lengths &
location of stretches in unstable areas, areas with cliffs, areas with loose
rocks, land slide prone areas, snow drift prone areas, no. & location of
hairpin bends etc.
c) Details of tunnels
d) Details & types of protective structures, erosion & land slide
control/protection measures, snow drift control measures, avalanche
protection/control measures etc.
13 4.11.3.2 (2) Pavement:
-90-
12. -- Condition Surveys & Investigation for Slope Stabilization, Erosion Control, Landslide
Correction/Protection & Avalanche Protection Measures:
-91-
for the Study primarily based on IRC publications, MORT&H Circulars
and relevant recommendations of the international standards for hill roads for
4.12.2 (2) approval by Executive Engineer, National Highway Division, Karwar.
The Design Standards evolved for the project shall cover all aspects of
detailed design including the design of geometric elements, pavement design,
bridges and structures, tunnels if required, traffic safety and materials.
16. 4.12.3 Wherever practicable/feasible hairpin bends and steep gradients shall be
avoided by realignments, provision of structures or any other suitable
provisions.
17. 4.12.4 While designing pavement for hill roads specific aspects relevant to hill
regions like terrain & topographic conditions, weather conditions, altitude
effects etc. shall be duly considered and suitably incorporated in design so
that pavement is able to perform well for the design traffic and service life.
Effects of factors like heavy rainfall, frost action, intensive snow and
avalanche activity, thermal stresses due to temperature difference in day
and night, damage by tracked vehicles during snow clearance operations
etc. must also be considered along with traffic intensity, its growth, axle
loads and design life.
18. 4.12.5(3) The design of embankments should include the requirements for protection
works and traffic safety features including features specific to hill roads.
19. -- Design and Drawing of Tunnels:
The Consultant shall prepare design and drawings for tunnels, if required
as per the results of feasibility study, as per the relevant specifications of
IRC:SP:91/MORT&H and other international specifications.
20. 4.12.7 a) Topography of hills generates numerous water courses and this coupled
with continuous gradients of roads in hills and high intensity of rainfall
calls for effective drainage of roads. The drainage system shall be
designed to ensure that the water flowing towards the road surface may
be diverted and guided to follow a definite path by suitable provision of
road side drains, catch water drains, interceptors etc. and flow on valley
side is controlled so that stability is not affected.
b) Further, adequate provision shall be made for sub-surface/subgrade
drainage to take care of seepage through the adjacent hill face of the
road & underground water flows.
21. 4.12.8 The Consultant shall design suitable traffic safety features and road
furniture including traffic signals, signs, markings, overhead sign boards,
crash barriers ,delineators etc. including any feature specific to hill roads.
The locations of these features shall be given in the reports and also shown
in the drawings.
22. 4.12.3 (1) The Consultant shall make suitable designs and layout for miscellaneous
-92-
works including rest areas, bus bays, vehicle parking areas,
telecommunication facilities, scenic overlooks, watering points etc.
wherever appropriate.
23. 10.6 (1) Volume II: Design Report :
a) Inventory of protection measures and other structures
b) Inventory of tunnels, if required.
c) Proposed preliminary designs for tunnels, if required.
Volume III: Drawings
a) Drawings for protection/control measures and other structures
b) Drawings for tunnels, if required.
24. 10.7 (3) Volume II: Design Report (Part II)
Part II of Design Report shall also deal with design of tunnels, if required
and design of other protection/control structures.
Volume IX: Drawing Volume
This shall also include :
a) Detailed working drawings for tunnels, if required.
b) Detailed working drawings for protection/control structures
-93-
SUPPLEMENT II
3.Scope of Work
3.1Physical Model study
Physical modeling with appropriate model scale for Hydraulic and
Hydrologic Investigations to :
i. Finalize span arrangement causing uniformity in flow
distribution, and work out the alignment and
orientation of river training works and bridge axis.
ii. Provide information on estimated/observed maximum
depth of scour.
iii. Provide information on required river training works
for proposed bridge
iv. Provide hydraulic design for the bridge and the
required river training works.
v. Quantify the general direction of river course through
bridge, afflux, extent and magnitude of flood, effect of
backwater, if any, aggradation/degradation of bed,
evidence of scour etc. shall be used to augment the
available hydrological data. The presence of flood
control/irrigation structures, if affecting the hydraulic
characteristics like causing obliquity, concentration of
-94-
flow, scour, silting of bed, change in flow levels, bed
levels etc. shall be studied and considered in Hydraulic
design of proposed bridge. The details of any planned
work in the immediate future that may affect the river
hydraulics shall be studied and considered
3.2 Mathematical Model study
Mathematical modeling for detailed Hydraulic / Hydrologic
investigations regarding the proposed new bridge to:
i) Finalize the site/location of the proposed new bridge based on
mathematical modeling.
ii) Provide information on estimated/observed maximum depth of
scour..
iii) Provide information on required river training works for proposed
bridge
iv) Provide hydraulic design for the bridge and the required river
training works.
v) Quantify the general direction of river course through bridge, afflux,
extent and magnitude of flood, effect of backwater, if any,
aggradation/degradation of bed, evidence of scour etc. shall be used to
augment the available hydrological data. The presence of flood
control/irrigation structures, if affecting the hydraulic characteristics
like causing obliquity, concentration of flow, scour, silting of bed,
change in flow levels, bed levels etc. shall be studied and considered in
Hydraulic design of proposed bridge. The details of any planned work
in the immediate future that may affect the river hydraulics shall be
studied and considered.
4. Information /Documents /Data required for Physical
/Mathematical Model study
i) Plan layouts showing the locations of the proposed bridge as
well as the existing bridges / barrages etc., in the vicinity of
the proposed bridge with the chainages with respect to a
standard reference marked on it.
ii) High flood discharges and corresponding flood levels at the
locations of the existing bridges in the vicinity of the
proposed bridge.
iii) General arrangement drawing (GAD) of the existing bridges
showing number of spans, pier and well dimensions, founding levels,
maximum scour level, the
95
design discharge and the HFL, guide bund details. On
this, the plan form of the river course with the bridge
alignment may also be shown as far as possible.
vii) The longitudinal profile of the river along the length of the
proposed alignment.
viii) Size distribution of the river bed material and the bore log data
at different locations at the site of the proposed bridge.
iv)The series of annual peak flood of the river for at least 15 years
period.
-96-
SUPPLEMENT-III
S
ADDITIONAL REQUIREMENT FOR SAFETY AUDIT
U
The use of checklists is highly recommended as they provide a useful “aide memoire” for the
audit team to check that no important safety aspects are being overlooked. They also give to the
project manager and the design engineer a sense of understanding of the place of safety audit in
the design process. The following lists have been drawn up based on the experience of
undertaking systematic safety audit procedures overseas. This experience indicates that extensive
lists of technical details has encouraged their use as “tick” sheets without sufficient thought being
given to the processes behind the actions. Accordingly, the checklists provide guidelines on the
principal issues that need to be examined during the course of the safety audits.
CONTENTS ITEMS
A1 : General Departures from standards
Cross-sectional variation
Drainage
Climatic conditions
Landscaping
Services apparatus
Lay-byes
Footpath
Pedestrian crossings
Access (minimize number of private accesses)
-97-
Emergency vehicles
Public Transport
Future widening
Staging of contracts
Adjacent development
A2 : Local Alignment Visibility
New/Existing road interface
Safety Aids on steep hills
A3 : Junctions Minimise potential conflicts
Layout
Visibility
A4 : Non-Motorised Adjacent land
road users Provision Pedestrians
Cyclists
Non-motorised vehicles
A5 : Signs and Lighting Lighting
Signs/Markings
A6 : Construction and Buildability
Operation Operational
Network Management
1. The audit team should review the proposed check the following aspects design from a road
safety perspective and check the following aspects
CONTENTS ITEMS
-98-
E. Safety implications of the scheme beyond its physical limits
i.e. how the scheme fits into its environs and road hierarchy
B1 : General Departures from standards
Cross-sectional variation
Drainage
Climatic conditions
Landscaping
Services apparatus
Lay-byes
Footpaths
Pedestrian crossings
Access (minimize number of private accesses)
Emergency vehicles
Public Transport
Future widening
Staging of contracts
Adjacent development
B2 : Local Alignment Visibility
New/Existing road interface
Safety Aids on steep hills
B3 : Junctions Minimise potential conflicts
Layout
Visibility
B4 : Non-Motorised road Adjacent land
users Provision Pedestrians
Cyclists
Non-motorised vehicles
B5 : Signs and Lighting Lighting
Signs/Markings
B6: Construction and Buildability
Operation Operational
Network Management
-99-
Stage 2 – Completion of Detailed Design
14 The audit team should satisfy itself that all issues raised at Stage 1 have been resolved. Items may
require further consideration where significant design changes have occurred.
15 If a scheme has not been subject to a stage 1 audit, the items listed in Checklists B1 to B6 should
be considered together with the items listed below.
CONTENTS ITEMS
-100-
Non-motorised vehicles
C5 : Signs and Lighting Advanced direction signs
Local traffic signs
Variable message signs
Other traffic signs
Lighting
C6 : Construction and Buildability
Operation Operational
Network Management
101-
Enclosure-I
MANNING SCHEDULE
<Details of packages>
1. Consultants have to provide a certificate that all the key personnel as envisaged in the Contract
Agreement have been actually deployed in the projects. They have to furnish the certificate at
the time of submission of their bills to Executive Engineer, National Highway Division,
Karwar. from time to time.
2. In case Tunnels are to be constructed, necessary input of Tunnel Experts shall be provided in
addition to above mentioned Manpower requirement.
-102-
Enclosure-II
-103-
Enclosure-II(contd.)
104
Enclosure-II(contd.)
Sr Bridge Engineer
i) Educational Qualification
-105-
Enclosure-II(contd.)
-106-
Enclosure-II(contd.)
-107-
Enclosure-II(contd.)
-108-
Enclosure-II(contd.)
Environmental Specialist
i) Educational Qualification
-109-
Enclosure-II(contd.)
110-
Enclosure-III
3 F.S. REPORT
i) Draft Feasibility Study 4 75
Report including option
study report
ii) Comments of client 1 90
4 LA & Clearances I
Report
-111-
5 Detailed Project Report
i) Draft DPR 4 165
6 Technical
Schedules
i) Draft
Technical 4 135
Schedules
7 LA & Clearances II 6
Report
-112-
APPENDIX-II
Proof of Eligibility
Form-E1
Letter of Proposal (On Applicant’s letter head)
(Date and Reference) To, **********
*********
*********
With reference to your RFP Document dated ………, I/we i.e M/s-------------------------------------
--------------------------------------(Name of Bidder) h a v i n g examined all relevant documents and
understood their contents, hereby submit our Proposal for selection as Consultant. The proposal is
unconditional and unqualified.
1. All information provided in the Proposal and in the Appendices is true and correct and all
documents accompanying such Proposal are true copies of their respective originals.
2. This statement is made for the express purpose of appointment as the Consultant for the
aforesaid Project.
3. I/We shall make available to the Authority any additional information it may deem necessary
or require for supplementing or authenticating the Proposal.
4. I/We acknowledge the right of the authority to reject our application without assigning any
reason or otherwise and hereby waive our right to challenge the same on any account
whatsoever.
5. I/We certify that in the last three years, we or any of our Associates have neither failed to
perform on any contract, as evidenced by imposition of a penalty by an arbitral or judicial
authority or a judicial pronouncement or arbitration award against the Applicant, nor been
expelled from any project or contract by any public authority nor have had any contract
terminated by any public authority for breach on our part.
-113-
6. I/We understand that you may cancel the Selection Process at any time and that you are
neither bound to accept any Proposal that you may receive nor to select the Consultant,
without incurring any liability to the Applicants in accordance with Clause 1.7 of the RFP
document.
7. I/We declare that we/any member of the consortium, are/is not a Member of any other
Consortium applying for Selection as a Consultant.
8. I/We certify that in regard to matters other that security and integrity of the country, we or
any of our Associates have not been convicted by a Court of Law or indicted or adverse
orders passed by a regulatory authority which would cast a doubt on our ability to undertake
the Consultancy for the Project or which relates to a grave offence that outrages the moral
sense of the community.
9. I/We further certify that in regard to matters relating to security and integrity of the country,
we have not been charge-sheeted by any agency of the Government or convicted by a Court
of Law for any offence committed by us or by any of our Associates.
10. I/We further certify that no investigation by a regulatory authority is pending either against us
or against our Associates or against our CEO or any of our Directors/Managers/employees.
11. I/We hereby irrevocably waive any right or remedy which we may have at any stage at law or
howsoever otherwise arising to challenge or question any decision taken by the Authority
[and/ or the Government of India] in connection with the selection of Consultant or in
connection with the Selection Process itself in respect of the above mentioned Project.
12. The Bid Security of Rs. ***** (Rupees *****) in the form of a Bank Guarantee is attached,
in accordance with the RFP document.
13. I/We agree and understand that the proposal is subject to the provisions of the RFP document. In
no case, shall I/we have any claim or right of whatsoever nature if the Consultancy for the Project
is not awarded to me/us or our proposal is not opened or rejected.
14. I/We agree to keep this valid for 120 (One hundred and twenty) days from the Proposal Due
Date specified in the RFP.
15. A Power of Attorney in favour of the authorized signatory to sign and submit this Proposal
and documents is attached herewith.
-114-
16 In the event of my/our firm/consortium being selected as the Consultant, I/we agree to enter
into any Agreement in accordance with the form Appendix V of the RFP. We agree not to
seek any changes in the aforesaid form and agree to abide by the same.
17 I/We have studied RFP and all other documents carefully and also surveyed the Project site.
We understand that except to the extent as expressly set forth in the Agreement, we shall
have no claim, right or title arising out of and documents or information provided to us by
the Authority or in respect of any matter arising out of or concerning or relating to the
Selection Process including the award of Consultancy.
18 The Proof of Eligibility and Technical proposal are being submitted in separate covers in
hard copy and they are being submitted online also. Financial Proposal is being submitted
online only. This Proof of Eligibility read with Technical Proposal and Financial Proposal
shall constitute the Application which shall be binding on us.
19 I/We agree and undertake to abide by all the terms and conditions of the RFP Document. In
witness thereof, I/we submit this Proposal under and in accordance with the terms of the
RFP Document.
Yours faithfully,
(Signature, name and designation of the authorized signatory)
(Name and seal of the Applicant/Lead Member)
-115-
Appendix- II
Form-E2/T3
FIRM’S REFERENCES
Relevant Services Carried out in the Last Seven Years (2008-09 onwards)
Which Best Illustrate Qualifications
The following information should be provided in the format below for each reference assignment
for which your firm, either individually as a corporate entity or as one of the major companies
within a consortium, was legally contracted by the client:
-116-
APPENDIX-II
Form- E3
Name of Applicant:
$
Certificate from the Statutory Auditor
This is to certify that --------------(name of the Applicant) has received the payments
shown above against the respective years on account of Consultancy Services.
$
In case he Applicant does not have a statutory auditor, it shall provide the
certificate from its chartered accountant that ordinarily audits the annual account of the
Applicant.
Note:
-117-
APPENDIX-II
Form- E4
WHEREAS, ____________ (Name of Bidder) ____(hereinafter called "the bidder") has submitted his
bid dated ____________ (date) for the Tender No. _________, dated _______ (hereinafter called "the
Bid". KNOW ALL MEN by these presents that We, ______________ [Name of Bank] of
____________ [Name of Country] having our registered office at ________ (hereinafter called "the
Bank") are bound unto ___________ [name of employer] (hereinafter called "the Employer") in the
sum of Rs. ______ (Rupees ______Lakhs only) for which payment will and truly to be made to the
said employer the bank binds himself, his successors and assigns by these presents. SEALED with the
Common Seal of the said Bank this _____ day of ____ 201_.
-118-
Appendix III
(Form-T1)
TECHNICAL PROPOSAL
FROM: TO:
Sir:
I/We (name of
Bidder) Consultant/ Consultancy firm herewith enclose Technical Proposal for selection of
my/our firm/organization as Consultant for .
Yours faithfully,
Signature
Full Name
Designation
Address
(Authorized Representative)
-119-
(Form-T-2)
Details of projects for which Technical and Financial Proposals have been submitted
1
2
3
4
-120-
Form-E2/T3
FIRM’S REFERENCES
Relevant Services Carried out in the Last Seven Years
Which Best Illustrate Qualifications
The following information should be provided in the format below for eachreference assignment
for which your firm, either individually as a corporate entity oras one of the major companies
within a consortium, was legally contracted by the client:
-121-
Form- T4
SITE APPRECIATION
Shall give details of site as per actual site visit and data provided in RFP and collected from
site supported by photographs to demonstrate that responsible personnel of the Consultant
have actually visited the site and familiarized with the salient details/complexities and scope
of services.
-122-
Form- T5
1.
2.
3.
4.
5.
….
….
-123-
Form- T6
20 Technical/Managerial Staff
1.
2.
3.
4.
….
….
….
21 Support Staff
1.
2.
3.
4.
….
….
….
-124-
Form- T7
The approach and methodology will be detailed precisely under the following topics.
1) Composition of the team [not more than 1 page]
2) Methodology for services, surveying, data collection [not more than 2 pages]
and analysis
3) Quality Assurance system for consultancy assignment [not more than 1 page]
-125-
Form- T8
1 . State whether the Applicant has in-house Material Testing Facility Available / Outsourced / Not
Available
2. In case answer to 1 is Available, attach a list of Lab equipment and facility for testing of
materials and location of laboratory
4. In case laboratory is located at a distance of more than 400 km from the project site, state
arrangements made/proposed to be made for testing of materials
-126-
Form- T9
Facility for Field investigation and Testing
2.In case answer to 1 is Avail able a list of field investigation and testing equipments available in-
house
4. For experience in LiDAR or equivalent technology for topographic survey, GPR and Induction
Locator or equivalent technologies for detection of sub-surface utilities and digitization of
cadastral maps for land acquisition, references need to be provided in following format:
REFERENCES
Relevant Services Carried
Which Best Illustrate Qualifications
The following information should be provided in the format below for each reference assignment
for which your firm, either individually as a corporate entity or as one of the major companies
within a consortium, was legally contracted by the client:
-127-
Assignment Name: Country:
Location within Country : Professional Staff Provided
by your firm:
Name of Client : No. of Staff :
Address : No. of Staff Months :
Technology Used:
Start Date Completion Date Approx. Value of
(Month / (Month / Year) Services : (in INR/current USD) :
Year)
Name of JV/Association Firm(s) if any : No. of Months of Professional
Staff provided by Associated Firm(s)
Status of your Company in the Assignment i.e., Sole/Lead Member/Other Member/Associate
Narrative Description of Project :
Description of Actual Services Provided by your Company:
-128-
Form- T10
Office Equipment and software
129-
Form- T11
Photo
1. Proposed Position:
2. Name of Staff:
4. Nationality:
5. Educational Qualification:
(Summarize college/university and other specialized education of staff
member, giving names of schools, dates attended and degrees obtained). (Please
furnish proof of qualification)
-130-
9. Summary of the CV
(Furnish a summary of the above CV. The information in the summary shall be
precise and accurate. The information in the summary will have bearing on the
evaluation of the CV).
A) Education:
i) Field of graduation and year
ii) Field of post-graduation and year
iii) Any other specific qualification
B) Experience
(i) Total experience in highways: ___ Yrs.
(ii) Responsibilities held: a) ___Yrs.
i. b)___Yrs.
ii. c)___ Yrs.
(iii)Relevant experience: ___ Yrs.
C)Permanent Employment with the firm: ___Yrs. If yes, how many years:
If no, what is the employment: Arrangement with the firm?
Certification:
1. I am willing to work on the project and I will be available for entire duration of the project
assignment and I will not engage myself in any other assignment during the currency of this
assignment on the project
2. I, the undersigned, certify that to the best of my knowledge and belief, this biodata correctly
describes myself my qualification and my experience.
Place
Date
Note: Each page of the CV shall be signed in ink by both the staff member and the Authorized
representative of the firm. Photocopies will not be considered for evaluation.
-131-
UNDERTAKING FROM THE PROFESSIONAL
I, …………………. (Name and Address) have not left any assignment with the consultants
engaged by MORT&H/ contracting firm (firm to be supervised now) for any continuing works of
MORT&H without completing my assignment. I will be available for the entire duration of the current
project (named…………..). If I leave this assignment in the middle of the completion of the work, I
may be debarred for an appropriate period to be decided by Executive Engineer, National Highway
Division, Karwar. I have also no objection if my services are extended by Executive Engineer,
National Highway Division, Karwar. for this work in future.
-132-
Appendix IV
(Form-I)
FINANCIAL PROPOSALS
FROM: TO:
Sir:
I/We Consultant/consultancy firm herewith enclose *Price Proposal for selection of my/our
Yours faithfully,
Signature
Full Name
Designation
Address
(Authorized Representative)
*The Financial proposal is to be filled strictly as per the format given in RFP.
-133-
(Form-II)
Format of Financial Proposal
Summary of Cost in Local Currency
A Topographical Survey
B Investigations
-134-
(Form-III)
Rate
S.No. Position Name SM Amt.(INR)
(INR)
Professional Staff
1 Team Leader cum Senior 7
Highway Engineer
2 Senior Bridge Engineer 3
3 Highway cum Pavement 3.5
Engineer
4 Material-cum-Geotechnical 5
Engineer- Geologist
5 Senior Survey Engineer 5
6 Traffic and Safety Expert 3.5
7 Environmental Specialist 2.5
8 Quantity Surveyor/ 4.5
Documentation Expert
Sub-Total:
Sub-Professional Staff (To be assessed by Consultant as per requirement
of assignment)
1
2
3
4
5
6
7
Sub-Total:
TOTAL
-135-
II. Support Staff
2 Typist
3 Office Boy
4 Night Watchman
Total :
Total
-136-
VI. Office Supplies, Utilities and Communication (Fixed Costs)
2 Supplies Computer
3 Running Costs
TOTAL :---------------------------
-137-
VIII. Reports and Document Printing
Total
-138-
IX. Survey and Investigation
A. Topographical Survey (Fixed Rate)
Rate per Amount
No. Item Kms Km (INR)
(INR)
1 Topographic Survey including hire
charges for equipment and supply of
survey teams comprising of project
survey filed staff etc. inclusive of cost
of materials, labourer
2 Detailed topographic surveys using
mobile/ aerial LiDAR or equivalent
technology
-140-
(Form-IV)
Total :
Total
-141-
TENTATIVE QUANTITIES FOR SUB-SOIL INVESTIGATIONS (BORING)
(Form –V)
S. Stretch NH Approxi Package State Cumulative Tentative
No Proposed for DPR No. mate No. Quantities ( in m )
Length In Soils In hard
(in Km.) other than rock
hard rock
1 For projects of length < 110 As per As per List As per As per 1500 200
km As per ANNUXURE -I List at at Annex-1 List at List at
Annex- Annex-1 Annex-
1 1
2 For projects of length > 110 As per As per List As per As per 2000 300
km - As per ANNUXURE I List at at Annex-1 List at List at
Annex- Annex-1 Annex-
1 1
-142-
Appendix-V
(a) & (b) Firm should have experience of preparation of DPR/Feasibility of 4/6 lane of
aggregate length as given below. The firm should have also prepared DPR/Feasibility of at least
one project of 4/6 laning of minimum length as indicated below in the last 7 years (i.e. from
2008-09 onwards)
S. Package No. Tentative Minimum Minimum length of a Eligible Project (4/6
No. Length Aggregate Length lane)
required
DPR/ Feasibility = DPR = 0.4 x Feasibility = 0.6 x
Tentative Length Tentative Length Tentative Length
1 2 3 4 5 6
(c) Annual Average Turn Over for the last 3 years {In cases where, Audited/Certified copy of Balance Sheet
for the FY 2014-15 is available, last three years shall be counted from 2012-13 to 2014-15. However, where
audited/certified copy of the Balance Sheet for the FY 2014-15 is not available (as certified by the Statutory
auditor) then in such cases last three years shall be considered from 2011-12 to 2013-14} of the firm from
Consultancy services should be equal to more than Rs 5 crore.
-143-
Eligibility criteria for Lead Partner/Other Partner in case of JV.
In case of JV, the Lead Partner should fulfill at least 75% of all eligibility requirements and the other
partner shall fulfill at least 50% of all eligibility requirements as given at 1.1 above. Thus a Firm applying
as Lead Partner/Other Partner in case of JV/Associate should satisfy the following
(a) & (b) Firm should have experience of preparation of DPR/Feasibility of 4/6 lane of aggregate length as
given below. The firm should have also prepared DPR/Feasibility of at least one project of 4/6 laning of
minimum length as indicated below in the last 7 years (i.e. from
2008-09 onwards
S. Package No. Minimum Aggregate Minimum length of a Eligible Project (4/ 6 lane)
No. Length required of
DPR/ Feasibility km)
DPR Feasibility
-144-
c) Minimum Annual Average Turn Over for the last 5 years {In cases where,
Audited/Certified copy of Balance Sheet for the FY 2014-15 is available, last five years shall be
counted from 2010-11 to 2014-15. However, where audited/certified copy of the Balance Sheet for
the FY 2014-15 is not available (as certified by the Statutory auditor) then in such cases last five years
shall be considered from 201-11 to 2013-14} of a firm applying as Lead
Partner/Other Partner in case of JV from Consultancy services should be as given below:
No. Mode of Submission by a firm Annual Average Turn Over for the last 5 years
Note: (i) Weightage to be given when experience by a Firm as Sole Firm/Lead Partner in a JV/Other
Partner in a JV/As Associate
(ii) The experience of a firm in preparation of DPR for a private Concessionaire/contractor shall not
be considered
1.1.1 More than the indicative Length of the package applied 5.5
for
1.1.2 More than 2 times the indicative length of the package 6.5
-145-
S.No Description Maximum Sub-
Points Points
applied for
1.1.3 More than 3 times the indicative length of the package 7.5
applied for
1.2 DPR for 2/4/6 laning projects each equal to or more 7.5
than 40 % of indicative length of a package applied
for (or Feasibility Study for 2/4/6 laning projects
each equal to or more than 60 % of indicative length
of a package applied for)
2.1 1 bridge 2
2.2 2 bridges 3
2.3 3 bridges 4
-146-
For special projects such as special bridges, tunnels and expressways that require specialized capabilities and
skill sets, the following is the break-up:
1.2.1 1 project 4
1.2.2 2 projects 5
2.1 1 bridge 1
2.2 2 bridges 2
2.3 3 bridges 3
-147-
S.No Description Maximum Sub-
Points Points
4.1.1 1 project 1
4.1.2 2 projects 2
4.1.3 3 projects 3
4.1.4 4 projects 4
Note: In case feasibility study is a part of DPR services the experience shall be counted in DPR only.
In case bridge is included as part of DPR of highway the experience will be (1) and (2)
-148-
Note: (i) Weightage to be given when experience by a Firm as Sole Firm/Lead Partner in a JV/Other
Partner in a JV/As Associate
3 Other partner in a JV 50 %
4 As Associate 25%
(ii) The experience of a firm in preparation of DPR for a private Concessionaire/contractor shall not be
considered.
Adequacy of the proposed work plan and methodology in responding to the TOR
(iv) Methodology 1
Total Points 5
-149-
Material testing, Survey and investigation equipment and software proposed to be used
1.1 Available 2
1.2 Outsourced 1
2.1 Available 3
3.1 Available 3
4.1 1 project 1
4.2 2 projects 2
4.3 3 projects 3
-150-
S.No Description Maximum Sub-
Points Points
5.1 1 project 1
5.2 2 projects 2
5.3 3 projects 3
6.1 1 project 1
6.2 2 projects 2
6.3 3 projects 3
-151-
Qualification and Competence of the Key Staff for adequacy of the Assignment. (Para 12.2
of Data Sheet and Enclosure II of TOR)
<80km 0
80km-150km 14
>150km-250km 17
>250km 19
(ii) In Design/ Pavement Design of Highway Projects (2/4/6 laning of NH/SH/ 9
Expressways) in Similar Capacity – Number of Projects
2 projects 7
3- 5 projects 8
More than 5 projects 9
III Employment with Firm 10
-153-
SENIOR BRIDGE ENGINEER
-154-
TRAFFIC AND SAFETY EXPERT
-155-
MATERIAL ENGINEER cum GEOTECHNICAL ENGINEER cum GEOLOGIST
-156-
2.4.6 SENIOR SURVEY ENGINEER
-157-
2.4.7 ENVIRONMENTAL SPECIALIST
-158-
QUANTITY SURVEYOR/DOCUMENTATION EXPERT
159-
Assumptions to be made regarding Similar Capacity for various positions
and above
Design Engineer
Engineer/Pavement Engineer.
Technical Engineer
-160-
5. Traffic and Safety Expert
Expert
i) On behalf of Consultant:
Senior Survey Engineer/ Survey Engineer/
Senior Surveyor
Senior Surveyor
7. Environmental Specialist
-161-
Appendix VI
DRAFT CONTRACT
AGREEMENT
Between
Executive Engineer
National Highway Division,
Karwar
and
162-
CONTENTS
1. General Provisions
1.1 Definitions
1.2 Relation between the Parties
1.3 Law Governing the Contract
1.4 Language
1.5 Headings
1.6 Notices
1.7 Location
1.8 Authority of Member in Charge
1.9 Authorized Representatives
1.10 Taxes and Duties
-163-
3.2.1 Consultants not to Benefit from Commissions, discounts etc.
3.2.2 Consultants and Affiliates not to be otherwise interested in
Project
3.2.3 Prohibition of Conflicting Activities
3.3 Confidentiality
3.4 Liability of the Consultants
3.5 Insurance to be taken out by the Consultants
3.6 Accounting, Inspection and Auditing
3.7 Consultants’ Actions requiring Client’s prior Approval
3.8 Reporting Obligations
3.9 Documents prepared by the Consultants to be the Property of the
Client
3.10 Equipment and Materials furnished by the Client
4. Consultants’Personnel
General
Description of Personnel
Approval of Personnel
Working Hours, Overtime, Leave etc.
Removal and/or Replacement of Personnel
Resident Project Manager
9. SETTLEMENT OF DISPUTES
Amicable Settlement
Dispute Settlement
-164-
III. SPECIAL CONDITIONS OF CONTRACT
IV. APPENDICES
-165-
DRAFT CONTRACT FOR CONSULTANT’S SERVICES
-166-
INDIA
day of the month of -----------------2015 , between, on the one hand, Executive Engineer,
National Highway Division, Karwar.(hereinafter called the “Client”)
and,
on the other hand,M/s ------------------------------------------
in JV with ----------------------------------
and in Association with ……………………………………………. (hereinafter called the
“Consultants”).
WHEREAS
(A) the Client has requested the Consultants to provide certain consulting services as defined in the General
Conditions attached to this Contract (hereinafter called the “Services”);
(B)the Consultants, having represented to the Client that they have the required professional skills,
personnel and technical resources, have agreed to provide the Services on the terms and conditions set
forth in this Contract;
NOW THEREFORE the parties hereto hereby agree as follows:
1 The following documents attached hereto shall be deemed to form an integral part of this Contract:
Appendix A: Terms of reference containing, inter-alia, the Description of the Services and
Reporting Requirements
Appendix B: Consultants’ Sub consultants, Key Personnel and Sub Professional Personnel,
Task assignment, work programme, manning schedule, qualification
requirements of key personnel, and schedule for submission of various report.
-167-
Appendix H: Copy of letter of acceptance
2. The mutual rights and obligations of the Client and the Consultants shall be as set forth in the
Contract; in particular:
(a) The Consultants shall carry out the Services in accordance with the provisions of the
Contract; and
(b) Client shall make payments to the Consultants in accordance with the provisions of the
Contract.
IN WITNESS WHEREOF, the Parties hereto have caused this Contract to be signed in their
respective names as of the day and year first above written.
1. Signature
Name
Address
By
Authorised Representative 2. Signature
Name
Address
-168-
GENERAL CONDITIONS OF CONTRACT
-169-
GENERAL CONDITIONS OF CONTRACT
1. GENERAL PROVISIONS
1.1 Definitions
Unless the context otherwise requires, the following terms whenever used in this Contract
have the following meanings:
a) “Applicable Law means the laws and any other instruments having the force of lawin
the Government’s country as they may be issued and in force from time to time;
b) “Contract” means the Contract signed by the Parties, to which these General
Conditions of Contract are attached, together with all the documents listed in Clause
i) of such signed Contract;
c) “Effective Date” means the date on which this Contract comes into force and effect
pursuant to Clause GC 2.1;
d) “foreign currency” means any currency other than the currency of the Government;
h) “Member”, in case the Consultants consist of a joint venture or consortium of more than one
entity, means any of these entities, and “Members” means all of these entities;
j) “Party” means the Client or the Consultants, as the case may be, and Parties means both of
them;
k) “Services” means the work to be performed by the Consultants pursuant to this Contract for the
purposes of the Project, as described in Appendix A hereto;
l) “SC” means the Special Conditions of Contract by which these General Conditions of
Contract may be amended or supplemented;
m) “Sub consultant” means any entity to which the Consultants subcontract any part of the
Services in accordance with the provisions of Clause GC 3.7; and
n) “Third Party” means any person or entity other than the Government, the Client, the
Consultants or a Sub consultant.
-170-
1.2 Relation between the Parties
Nothing contained herein shall be construed as establishing a relation of master and servant or
of agent and principal as between the Client and the Consultants. The Consultants, subject to
this Contract, have complete charge of Personnel performing the Services and shall be fully
responsible for the Services performed by them or on their behalf hereunder.
1.4 Language
This Contract has been executed in the language specified in the SC, which shall be the binding and
controlling language for all matters relating to the meaning or interpretation of this Contract.
1.6 Notices
1.6.1 Any notice, request or consent required or permitted to be given or made pursuant to this
Contract shall be in writing. Any such notice, request or consent shall be deemed to have
been given or made when delivered in person to an authorized representative of the Party to
whom the communication is addressed, or when sent by registered mail, facsimile or e-mail
to such Party at the address specified in the SC.
Location
-171-
Authorized Representatives
Any action required or permitted to be taken, and any document required or permitted to be
executed, under this Contract by the Client or the Consultants may be taken or executed by the
officials specified in the SC.
Effectiveness of Contract
This Contract shall come into force and effect on the date of the Client’s notice to the Consultants
instructing the Consultants to begin carrying out the Services. This notice shall confirm that the
effectiveness conditions, if any, listed in the SC have been met.
Modification
Modification of the terms and conditions of this Contract, including any modification of the
scope of the Services, may only be made by written agreement between the Parties. Pursuant to
Clause GC 7.2 hereof, however, each party shall give due consideration to any proposals for
modification made by the other Party.
Force Majeure
-172-
2.7.1 Definition
a) For the purposes of this Contract, “Force Majeure” means an event which is beyond the reasonable
control of a Party, and which makes a Party’s performance of its obligations hereunder impossible
or so impractical as reasonably to be considered impossible in the circumstances, and includes, but
is not limited to, war, riots, civil disorder, earthquake, fire, explosion, storm, flood or other adverse
weather conditions, strikes, lockouts or other industrial action (except where such strikes, lockouts
or other industrial action are within the power of the Party invoking Force Majeure to prevent),
confiscation or any other action by government agencies.
b) Force Majeure shall not include (i) any event which is caused by the negligence or intentional
action of a Party or such Party’s Sub consultants or agents or employees, nor (ii) any event which a
diligent Party could reasonably have been expected to both (A) take into account at the time of the
conclusion of this Contract and (B) avoid or overcome in the carrying out of its obligations
hereunder.
c) Force Majeure shall not include insufficiency of funds or failure to make any payment required
hereunder.
b) A party affected by an event of Force Majuere shall notify the other Party of such event as soon as
possible, and in any event not later than fourteen (14) days following the occurrence of such event,
providing evidence of the nature and cause of such event, and shall similarly give notice of the
restoration of normal conditions as soon as possible.
c) The Parties shall take all reasonable measures to minimize the consequences of any event of Force
Majeure.
2.7.5 Payments
During the period of their inability to perform the Services as a result of an event of Force Majeure,
the Consultants shall be entitled to be reimbursed for additional costs reasonably and necessarily
incurred by them during such period for the purposes of the Services and in reactivating the
Services after the end of such period.
-173-
2.7.3 Consultation
Not later than thirty (30) days after the Consultants, as the result of an event of Force Majeure,
have become unable to perform a material portion of the Services, the Parties shall consult with
each other with a view to agreeing on appropriate measures to be taken in the circumstances.
2.8 Suspension
The Client may, by written notice of suspension to the Consultants, suspend all payments to the
Consultants hereunder if the Consultants fail to perform any of their obligations under this Contract,
including the carrying out of the Services, provided that such notice of suspension (i) shall specify the
nature of the failure, and (ii) shall request the Consultants to remedy such failure within a period not
exceeding thirty (30) days after receipt by the Consultants of such notice of suspension.
2.9 Termination
2.9.1 By the Client
The Client may, by not less than thirty (30) days’ written notice of termination to the Consultants
(except in the event listed in paragraph (f) below, for which there shall be a written notice of not
less than sixty (60) days), such notice to be given after the occurrence of any of the events specified
in paragraphs (a) through (f) of this Clause2.9.1, terminate this Contract:
a) if the Consultants fail to remedy a failure in the performance of their obligations are under, as
specified in a notice of suspension pursuant to Clause 2.8 hereinabove, within thirty (30) days of
receipt of such notice of suspension or within such further period as the Client may have
subsequently approved in writing;
b) if the Consultants become (or, if the Consultants consist of more than one entity, if any of their
Members becomes) insolvent or bankrupt or enter into any agreements with their creditors for
relief of debt or take advantage of any law for the benefit of debtors or go into liquidation or
receivership whether compulsory or voluntary;
c) if the Consultants fail to comply with any final decision reached as a result of arbitration
proceedings pursuant to Clause 8 hereof;
d) if the Consultants submit to the Client a statement which has a material effect on the rights,
obligations or interests of the Client and which the Consultants know to be false;
e) if, as the result of Force Majeure, the Consultants are unable to perform a material portion of the
Services for a period of not less than sixty (60) days; or
f) if the Client, in its sole discretion and for any reason whatsoever, decides to terminate this
Contract.
-174-
2.9.2 By the Consultants
The Consultants may, by not less than thirty (30) day’s written notice to the Client, such
notice to be given after the occurrence of any of the events specified in paragraphs (a) through
(d) of this Clause 2.9.2, terminate this Contract:
a) if the Client fails to pay any money due to the Consultants pursuant to this contract and not
subject to dispute pursuant to Clause 8 hereof within forty-five(45) days after receiving
written notice from the Consultants that such payment is overdue;
b) if the Client is in material breach of its obligations pursuant to this Contract and has not
remedied the same within forty-five (45) days (or such longer period as the Consultants may
have subsequently approved in writing) following the receipt by the Client of the Consultants’
notice specifying such breach;
c) if, as the result of Force Majeure, the Consultant are unable to perform a material portion of
the Services for a period of not less than sixty (60) days; or
d) if the Client fails to comply with any final decision reached as a result of arbitration pursuant
to Clause 8 hereof.
i) remuneration pursuant to Clause 6 hereof for Services satisfactorily performed prior to the
effective date of termination.
ii) reimbursable expenditures pursuant to Clause 6 hereof for expenditures
actually incurred prior to the effective date of termination; and
iii) except in the case of termination pursuant to paragraphs (a) through (d) of Clause 2.9.1
hereof, reimbursement of any reasonable cost incident to the prompt and orderly
termination of the Contract including the cost of the return travel of the Consultants’
personnel and their eligible dependents.
-175-
2.9.6 Disputes about Events of Termination
If either Party disputes whether an event specified in paragraphs (a) through (e) of Clause
2.9.1 or in Clause 2.9.2 hereof has occurred, such Party may, within forty-five(45) days after
receipt of notice of termination from the other Party, refer the matter to arbitration pursuant to
Clause 8 hereof, and this Contract shall not be terminated on account of such event except in
accordance with the terms of any resulting arbitral award.
3.1 General
The Consultants shall perform the Services in accordance with the Applicable Law and shall
take all practicable steps to ensure that any Sub consultants, as well as the Personnel and
agents of the Consultants and any Sub consultants, comply with the Applicable Law. The
Client shall advise the Consultants in writing of relevant local customs and the Consultants
shall, after such notifications, respect such customs.
The remuneration of the Consultants pursuant to Clause 6 hereof shall constitute the Consultants' sole
remuneration in connection with this Contract or the Services and the Consultants shall not accept for
their own benefit any trade commission, discount or similar payment in connection with activities
pursuant to this Contract or to the Services or in the Discharge of their obligations hereunder, and the
Consultants shall use their best efforts to ensure that any Sub consultants, as well as the Personnel and
agents of either of them, similarly shall not receive any such additional remuneration.
The Consultants agree that, during the term of this Contract and after its termination, the Consultants and
any entity affiliated with the Consultants, as well as any Sub consultant and any entity affiliated with such
Sub consultant, shall be disqualified from providing goods, works or services (other than the Services and
any continuation thereof) for any project resulting from or closely related to the Services.
-176-
3.2.3 Prohibition of Conflicting Activities
Neither the Consultants nor their Sub consultants nor the Personnel of either of them shall engage,
either directly or indirectly, in any of the following activities:
a) during the term of this Contract, any business or professional activities in the Government's
country which would conflict with the activities assigned to them under this Contract; or
b) after the termination of this Contract, such other activities as may be specified in the SC.
3.3 Confidentiality
The Consultants, their Sub consultants and the Personnel of either of them shall not, either
during the term or within two (2) years after the expiration of this Contract, disclose any
proprietary or confidential information relation to the Project, the Services, this Contract or
the Client's business or operations without the prior written consent of the Client.
Subject to additional provisions, if any, set forth in the SC, the Consultants' liability under this
Contract shall be as provided by the Applicable Law.
The Consultants (i) shall take out and maintain, and shall cause any Sub consultants to take
out and maintain, at their (or the Sub consultants', as the case may be) own cost but on terms
and conditions approved by the Client, insurance against the risks, and for the coverage, as
shall be specified in the Special Conditions (SC), and (ii) at the Client's request, shall provide
evidence to the Client showing that such insurance has been taken out and maintained and that
the current premiums therefore have been paid.
The Consultants (i) shall keep accurate and systematic accounts and records in respect of the
Services hereunder, in accordance with internationally accepted accounting principles and in
such form and detail as will clearly identify all relevant time charges and cost, and the bases
thereof (including the bases of the Consultants' costs and charges), and (ii) shall permit the
Client or its designated representative periodically, and up to one year from the expiration or
termination of this Contact, to inspect the same and make copies thereof as well as to have
them audited by auditors appointed by the Client.
The Consultants shall obtain the Client's prior approval in writing before taking any of the
following actions:
-177-
b) entering into a subcontract for the performance of any part of the Services, it being understood
(i)that the selection of the Sub-consultant and the terms and conditions of the subcontract shall
have been approved in writing by the Client prior to the execution of the subcontract, and (ii)
that the Consultants shall remain fully liable for the performance of the Services by the Sub-
consultant and its Personnel pursuant to this Contract;
c) any other action that may be specified in the SC.
The Consultants shall submit to the Client the reports and documents specified in Appendix A/E here
to, in the form, in the numbers and within the time periods set forth in the said Appendix.
All plans, drawings, specifications, designs, reports and other documents prepared by the
Consultants in performing the Services shall become and remain the property of the Client, and the
Consultants shall, not later than upon termination or expiration of this Contract, deliver all such
documents to the Client, together with a detailed inventory thereof. The Consultants may retain a copy
of such documents. Restrictions about the future use of these documents, shall be as specified in the
SC.
Equipment and materials made available to the Consultants by the Client, or purchased by the
Consultants with funds provided by the Client, shall be the property of the Client and shall be marked
accordingly. Upon termination or expiration of this Contract, the Consultants shall make available to
the Client an inventory of such equipment and materials and shall dispose of such equipment and
materials in accordance with the Client's I instructions. While in possession of such equipment and
materials, the Consultants, unless otherwise instructed by the Client in writing, shall insure them in an
amount equal to their full replacement value.
4. CONSULTANTS' PERSONNEL
4.1 General
The Consultants shall employ and provide such qualified and experienced Personnel as are required to
carry out the Services.
a) The titles, agreed job descriptions, minimum qualification and estimated periods of
engagement in the carrying out of the Services of each of the Consultants' Key Professional /
Sub Professional Personnel are described in Appendix B.
b) If required to comply with the provisions of Clause 3.1.1 of this Contract, adjustments with
respect to the estimated periods of engagement of Key Professional / Sub Professional
Personnel set forth in Appendix B may be made by the Consultants by written notice to the
Client, provided
(i)that such adjustments shall not alter the originally estimated period of engagement of any
-178-
individual by more than 10% or one week, whichever is larger, and
(ii) that the aggregate of such adjustments shall not cause payments under this Contract to
exceed the ceilings set forth in Clause 6.1 (b) of this Contract. Any other such adjustments
shall only be made with the Client's written approval.
(c) If additional work is required beyond the scope of the Services specified in Appendix A, the
estimated periods of engagement of Key Personnel set forth in Appendix B may be increased
by agreement in writing between the Client and the Consultants.
4.3 Approval of Personnel
The Key Personnel and Sub consultants listed by title as well as by name in Appendix B are
hereby approved by the Client. In respect of other Key Personnel which the Consultants
propose to use in the carrying out of the Services, the Consultants shall submit to the Client
for review and approval a copy of their biographical data. If the Client does not object in
writing (stating the reasons for the objection) within twenty-one (21) calendar days from the
date of receipt of such biographical data, such Key Personnel shall be deemed to have been
approved by the Client.
(a) Working hours and holidays for Key Professional / Sub Professional Personnel are set forth in
Appendix C hereto. To account for travel time, foreign Personnel carrying out Services inside
the Government's country shall be deemed to have commenced (or finished) work in respect
of the Services such number of days before their arrival in (or after their departure from) the
Government's country as
is specified in Appendix C hereto.
(b) The Key Professional / Sub Professional Personnel shall not be entitled to be paid for
overtime nor to take paid sick leave or vacation leave except as specified in Appendix C hereto,
and except as specified in such Appendix, the Consultants' remuneration shall be deemed to
cover these items. All leave to be allowed to the Personnel is included in the staff- months of
service set for in Appendix B. Any taking of leave by Personnel shall be subject to the prior
approval of the Client by the Consultants, who shall ensure that absence for leave purposes
will not delay the progress and adequate supervision of the Services.
4.5.1 In case notice to commence services pursuant to Clause 2.1 of this Contract is not ordered by
Client within 120 days of negotiations the key personnel can excuse themselves on valid
grounds, e.g., selection on some other assignment, health problem developed after contract
negotiation, etc. In such a case no penalty shall be levied on the Firm or on the person
concerned. The firm shall however be asked to give a replacement by an equal or better
scoring person, whenever mobilization is ordered.
4.5.2 In case notice to commence services is given within 120 days of negotiations the
replacement shall be as below:
-179-
a) Replacement up to 33%: Replacement shall be by an equal or better scoring person.
Reduction in remunerations for the balance period shall be @ 5% of the monthly rate.
b) Replacement of more than 33% and up to 50%: Replacement shall be by an equal or
better scoring person. Reduction in remunerations for the balance period shall be @ 10%
of the monthly rate.
c) Replacement beyond 50% and upto 66% . Replacement shall be by an equal or better
scoring person. Reduction in remunerations for the balance period shall be @ 15% of the
monthly rate.
d) Replacement beyond 66 %shall normally not be considered. However in exceptional
circumstances, where it becomes absolutely essential the remunerations of the substitute
shall be reduced by 50 % of the original person replaced. Replacement shall be by an
equal or better scoring person, The Department may initiate action for
termination/debarment of such consultant for future projects of Executive Engineer,
National Highway Division, Karwar. for a period of 6 months to 24 months depending
upon the severity of case.
4.5.3 Replacement after original contract period is over:
There shall be no limit on the replacements and no reduction in remunerations shall be
made. The replacement shall however be of equal or better score.
4.5.4 If the Employer (i) finds that any of the Personnel has committed serious misconduct or has
been charged with having committed a criminal action or (ii) has reasonable ground to be
dissatisfied with the performance of any of the Personnel, then the consultant shall, at the
Employer’s written request specifying the grounds therefore, forthwith provide a replacement
with qualifications and experience acceptable to him.
4.5.5 If the team leader or any other key personnel/ specialist considered pivotal to the project is
replaced, the substitute may be interviewed by Executive Engineer, National Highway
Division, Karwar. to assess their merit and suitability.
4.5.6 If any member of the approved team of a consultant engaged by Executive Engineer,
National Highway Division, Karwar. leaves that consultant before completion of the job, he
shall be barred for a period of 6 months to 24 months from being engaged as a team member of
any other consultant working (or to be appointed) for any other Executive Engineer, National
Highway Division, Karwar. projects.
4.5.7 In exceptional situations where the replacement with equivalent or better qualification is not
available, replacement with lower qualifications than the originally approved may be accepted
with reduction in remuneration as per the procedure prescribed below. This kind of relaxation
shall however, be limited to replacement of 2 key personnel only in one consultancy contract
package.
i) The new proposed personnel as a replacement has to be evaluated as per the criteria fixed at
the time of evaluation of original proposal and marks/rating and then:
-If the original personnel (included in the original proposal based on which the contract was
awarded) is to be replaced at the instruction of Executive Engineer, National Highway
Division, Karwar. and the new proposed personnel is having less qualification/ experience i.e
marks/rating (but fulfilling the minimum requirement as per TOR), his remuneration would be
reduced by 15% over and above the stipulated
-180-
conditions in the contract because of less qualified personnel
-If the original personnel (included in Contract Agreement) is to be replaced by the Consulting
firm and the new proposed personnel is having less qualification/ experience (marks/rating),
then his remuneration would be decreased proportionally in comparison to the marks of the
original personnel. This will also take into account the contract condition and if the proposed
reduction is less than that stipulated in contract condition, it would be as per the
contract provision.
It will be ensured that the new proposed personnel should score at least 75% of the marks of
the originally approved key personnel. Both the Consulting firm and the proposed personnel
should give the undertaking in the format available in Form VII of Appendix II along with the
replacement CV.
ii) The CV should be signed by personnel and the consulting firm in every page. If the CV is
found incorrect at later date, the personnel accepted would be removed from the assignment
and debarred from further Executive Engineer, National Highway Division, Karwar. works
for an appropriate period to be decided by Executive Engineer, National Highway Division,
Karwar. and the new proposed personnel in place of removed personnel would be paid 15%
less salary than the original personnel. 15% reduction in the salary will be imposed as penalty
for submitting the incorrect information. This penalty will be imposed only once. If the same
consulting firm submits incorrect information again second time, necessary action will be taken
by Executive Engineer, National Highway Division, Karwar. to blacklist the firm.
If required by the SC, the Consultants shall ensure that at all times during the Consultants'
performance of the Services in the Government's country a resident project manager,
acceptable to the Client, shall take charge of the performance of such Services.
-181-
(b) assist for the Personnel and, if appropriate, their eligible dependents to be provided promptly
with all supporting papers for necessary entry and exit visas, residence permits, exchange permits
and any other documents required for their stay in India;
(c) facilitate prompt clearance through customs of any property required for the Services;
(d) issue to officials, agents and representatives of the Government all such instructions as may be
necessary or appropriate for the prompt and effective implementation of the Services;
Access to Land
The Client warrants that the Consultants shall have, free of charge, unimpeded access to all land in
the Government’s country in respect of which access is required for the performance of the
Services. The Client will be responsible for any damage to such land or any property thereon
resulting from such access and will indemnify the Consultants and each of the Personnel in respect
of liability for any such damage, unless such damage is caused by the default or negligence of the
Consultants or any Sub consultants or the Personnel of either of them.
-182-
Change in the Applicable Law
If, after the date of this Contract, there is any change in the Applicable Law with respect to
taxes and duties which increases or decreases the cost or reimbursable expenses incurred by
the Consultants in performing the Services, then the remuneration and reimbursable expenses
otherwise payable to the Consultants under this Contract shall be increased or decreased
accordingly by agreement between the Parties hereto, and corresponding adjustments shall be
made to the ceiling amounts specified in Clause
6.1(b),
The client shall make available to the Consultants and the Personnel, for the purposes of the
Services and free of any charge, the services, facilities and property described in Appendix D
at the times and in the manner specified in said Appendix D, provided that if such services,
facilities and property shall not be made available to the Consultants as and when so specified,
the Parties shall agree on (i) any time extension that may be appropriate to grant to the
Consultants for the performance of the Services, (ii) the manner in which the Consultants shall
procure any such services, facilities and property from other sources, and (iii) the additional
payments, if any, to be made to the Consultants as a result thereof pursuant to Clause 6.1(c)
hereinafter.
Payment
In consideration of the Services performed by the Consultants under this Contract, the Client
shall make to the Consultants such payments and in such manner as is provided by Clause 6 of
this Contract.
a) An abstract of the cost of the Services payable in local currency (Indian Rupees) is set forth
in Appendix E.
b) Except as may be otherwise agreed under Clause 2.6 and subject to Clause 6.1(c), the
payments under this Contract shall not exceed the ceiling specified in the SC. The Consultants
shall notify the Client as soon as cumulative charges incurred for the Services have reached
80% of the ceiling.
c) Notwithstanding Clause 6.1(b) hereof, if pursuant to Clauses 5.4 hereof, the Parties shall agree
that additional payments shall be made to the Consultants in order to cover any necessary
additional expenditures not envisaged in the cost estimates referred to in Clause 6.1(a) above,
the ceiling set forth in Clause 6.1(b) above shall be increased by the amount or amounts, as the
case may be, of any such additional payments.
-183-
Currency of Payment
(a) The Client shall cause to be paid to the Consultants an advance payment as specified in the SC, and
as otherwise set forth below. The advance payment will be due after provision by the Consultants to
the Client of a bank guarantee by a bank acceptable to the Client in an amount (or amounts) and in a
currency (or currencies) specified in the SC, such bank guarantee (i) to remain effective until the
advance payment has been fully set off as provided in the SC, and ii) in such form as the Client
shall have approved in writing.
Payment as %
S.No Item of contract
value
1 Submission of final Inception Report 15%
2 Submission of final Alignment Report 10%
3 Submission of final Feasibility Report 5%
Submission of final Land Acquisition
4 10%
Report
5 Submission of clearance proposals 5%
6 Submission of Draft DPR 10%
7 Approval of Final DPR 10%
8 Approval of Technical Schedules 5%
9 3D publication 10%
10 Clearance – Stage I Approval 5%
11 Clearance – Stage II/Final Approval 5%
12 Retention to be released after 3 years 10%
Total: 100%
Bonus on submission of draft 3A within 1
13 2.5% bonus
month of alignment finalization
Bonus on submission of draft clearance
14 proposals within 1 month of alignment 2.5% bonus
finalization
-184-
Note: Consultants have to provide a certificate that all key personnel as envisaged in the Contract
Agreement has been actually deployed in the project. They have to submit this certificate at the time
of submission of bills to Executive Engineer, National Highway Division, Karwar. from time to
time.
(c) No payment shall become eligible for the next stage till the consultant completes to the
satisfaction of the client the work pertaining to the preceding stage. The payment for the work
of sub-soil investigation (Boring)will be as per plan approved by the client and will be paid as
per actual at the rates quoted by the consultants .The payment for the quantity given by the
client for boring will be deemed to be included in the above mentioned payment schedule.
Any adjustment in the payment to the consultants will be made in the final payment only.
(d) The Client shall cause the payment of the Consultants in Para 6.4 (b) above as given in schedule
of payment within thirty (30) days after the receipt by the Client of bills. Interests at the rate
specified in the SC shall become payable as from the above due date on any amount due by,
but not paid on, such due date.
(c) The final payment under this Clause shall be made only after the final report and a final
statement, identified as such, shall have been submitted by the Consultants and approved as
satisfactory by the Client. The Services shall be deemed completed and finally accepted by the
Client and the final report and final statement shall be deemed approved by the Client as
satisfactory one hundred and eighty (180) calendar days after receipt of the final report and
final statement by the Client unless the Client, within ninety(90) day period, gives written
notice to the Consultants specifying in detailed deficiencies in the Services, the final report
or final statement. The Consultants shall thereupon promptly make any necessary
corrections, and upon completion of such corrections, the foregoing process shall be repeated.
Any amount which the Client has paid or caused to be paid in accordance with this Clause in
excess of the amounts actually payable in accordance with the provisions of this Contract shall
be reimbursed by the Consultants to the Client within thirty (30) days after receipt by the
Consultants of notice thereof. Any such claim by the Client for reimbursement must be made
within twelve (12) calendar months after receipt by the Client of a final report and a final
statement approved by the Client in accordance with the above.
(f) All payments under this Contract shall be made to the account of the Consultants specified in
the SC.
General
The Consultant shall be responsible for accuracy of the data collected, by him directly or procured
from other agencies/authorities, the designs, drawings, estimates and all other details prepared by him
as part of these services. He shall indemnify the Authority against any inaccuracy in the work which
might surface during implementation of the project. The Consultant will also be responsible for
correcting, at his own cost and risk, the drawings including any re-survey / investigations and
correcting layout etc. if required during the execution of the Services.
-185-
The Consultant shall be fully responsible for the accuracy of design and drawings of the bridges and
structures. All the designs and drawings for bridges and structures including all their components shall be
fully checked by a Senior Engineer after completion of the designs. All drawings for bridges and
structures shall be duly signed by the (a) Designer, (b) Senior Checking Engineer, and (c) Senior Bridge /
Structure Expert. The designs and drawings not signed by the three persons mentioned above shall not be
accepted. The Consultant shall indemnify the Client against any inaccuracy / deficiency in the designs and
drawings of the bridges and structures noticed during the construction and even thereafter and the Client
shall bear no responsibility for the accuracy of the designs and drawings submitted by the Consultants.
The survey control points established by the Consultant shall be protected by the Consultants till the
completion of the Consultancy Services.
Retention Money
An amount equivalent to 10% of the contract value shall be retained at the end of the contract for accuracy
of design and quantities submitted and the same will be released after the completion of civil contract
works or after 3 years from completion of consultancy services, whichever is earlier. The retention money
will however be released by the Client on substitution by Bank Guarantee of the same amount valid up to
the period as above.
Penalty
i) If variation in any of the main quantities of work like earth work including sub grade, GSB, WMM,
Bituminous works (BM/DBM/AC/BC),drains, total concrete quantities and reinforcing steel in bridge
works or overall project cost, found during execution is more than +/- 15%, the penalty equivalent to
5% of the contract value shall be imposed. For this purpose retention money equivalent to 5% of the
contract value will be forfeited. This shall exclude any additional/deletion of items/works ordered
during the execution
ii) For inaccuracies in survey/investigation/design work the penalties shall be imposed as per details
given in Table below:
-186-
Sl. Penalty (%age of
Item
No. contract value)
Topographic Surveys 0.5 to 1.0
a) The horizontal alignment does not match with ground
condition.
1
b) The cross sections do not match with existing ground.
c) The co-ordinates are defective as instruments of
desired accuracy not used.
Geotechnical Surveys 0.5 to 1.0
a) Incomplete surveys
2 b) Data not analysed properly
c) The substrata substantially different from the actual
strata found during construction.
Traffic data found to be varying by more than 25% on 0.2 to 0.5
3 resurvey at a later date, unless there are justifiable
reasons.
Axle load data found to be varying by more than 25% on 0.20 to 0.5
4 resurvey at a later date, unless there are justifiable
reasons.
Structural Designs found to be unsafe or grossly over 1.0 to 2.0
5
safe.
In case of delay in completion of services, a penalty equal to 0.05% of the contract price per day
subject to a maximum 5% of the contract value will be imposed and shall be recovered from
payments due/performance security. However in case of delay due to reasons beyond the control
of the consultant, suitable extension of time will be granted.
7.3.3 Total amount of recovery from all penalties shall be limited to 10% of the Consultancy Fee.
Consultant shall be liable to indemnify the client for any direct loss or damage accrued or likely
to accrue due to deficiency in service rendered by him.
In addition to the penalty as mentioned in para 7.3, warning may be issued to the erring
consultants for minor deficiencies. In the case of major deficiencies in the Detailed Project
Report involving time and cost overrun and adverse effect on reputation of Executive Engineer,
National Highway Division, Karwar., other penal action including debarring for certain period
may also be initiated as per policy of Executive Engineer, National Highway Division, Karwar.
-187-
8. FAIRNESS AND GOOD FAITH
The Parties undertake to act in good faith with respect to each other’s rights under this Contract
and to adopt all reasonable measures to ensure the realization of the objectives of this Contract.
The Parties recognize that it is impractical in this Contract to provide for every contingency which
may arise during the life of the Contract, and the Parties hereby agree that it is their intention that this
Contract shall operate fairly as between them, and without detriment to the interest of either of them,
and that, if during the term of this Contract either Party believes that this Contract is operating
unfairly, the Parties will use their best efforts to agree on such action as may be necessary to remove
the cause or causes of such unfairness, but no failure to agree on any action pursuant to this Clause
shall give rise to a dispute subject to arbitration in accordance with Clause 9 hereof.
9. SETTLEMENT OF DISPUTES
The Parties shall use their best efforts to settle amicably all disputes arising out of or in
connection with this Contract or the interpretation thereof.
9.2 Dispute Settlement
Any dispute between the Parties as to matters arising pursuant to this Contract which cannot be
settled amicably within thirty (30) days after receipt by one Party of the other Party’s request for
such amicable settlement may be submitted by either Party for settlement in accordance with the
provisions specified in the SC.
The change of Scope on account of variation of total length as well as 4 laned length of project
Highway from the indicative length as given at Annex-1 of Letter of Invitation of the RFP shall
be dealt as follows
ii) The Consultancy fee shall be revised on account of change of scope as below:
- In case the total length of project increase/ decrease up to more 10% of indicative length
given in the RFP : No change in Consultancy Fees
- In case the increase/ decrease in total length of project is more than 10 % of the
indicative length as given in the RFP:The consultancy fee shall be increased/
-188-
decreased in the same proportion in which the length of the project road is increased/
decreased beyond 10% .
- In case the length of 4 lane road is increased up to 10% of the length as indicated in the
RFP: No change in Consultancy Fees
- In case the length of 4 lane road is increased by more than 10% of the length as indicated
in the RFP : The consultancy fee shall be increased by 0.25 times the average quoted rate (
Rs per km ) for the increased length of 4 lane beyond 10%
iii) Length of Bypass / realignment shall not be treated as additionality to the existing length of
the highway for the purpose of change / variation in length. Increase/decrease in length on
account of bypasses shall not be considered as change of scope. However, the total length of
the project highway (including bypasses and realignment) along the finally approved
alignment shall be compared with the indicative length in the RFP for the purpose of
variation.
-189-
SPECIAL CONDITIONS OF CONTRACT
Number of
GC Clause
1.1(a) The words “in the Government’s country” are amended to read “in INDIA”
Attention :
Executive Engineer
National Highway Division,
Karwar
………. Ext.-…..; Fax: 011-………….
E-mail: [email protected]
For the Consultants:
Attention: Name
Designation
Address
Tel: Fax: E-mail address
1.8 Entity to Act as Member in charge (In case of Joint Venture of Consultants) with or without an
Associate:
- ………………………..
1.9 The Authorized Representatives are:
a) The contract has been approved by Executive Engineer, National Highway Division, Karwar.
b) The consultant will furnish within 15 days of the issue of letter of acceptance, an unconditional
Bank Guarantee from a Nationalised Bank, IDBI or ICICI/ICICI Bank/Foreign Bank/EXIM Bank /
Any Scheduled Commercial Bank approved by RBI having a networth of not less than 500 crore as
per latest Annual Report of the Bank. In the case of a Foreign Bank (issued by a Branch in India) the
networth in respect of Indian operations shall only be taken into account. In case of Foreign Bank,
the BG issued by Foreign Bank should be counter guaranteed by any Nationalised Bank in India. In
case of JV, the BG shall be furnished on behalf of the JV or lead partner of JV for an amount
equivalent to 10 %of the total contract value to be received by him towards Performance
Security valid for a period of
three years beyond the date of completion of services.
2.2 The time period shall be “fourmonths” or such other time period as the parties may agree in writing.
2.3 The time period shall be “fifteen days” or such other time period as the Parties may agree in writing.
2.4 The time period shall be ------ months or such other time period as the parties may agree in writing.
(a) Except in case of negligence or willful misconduct on the part of the Consultants or on the part of
any person or firm acting on behalf of the Consultants in carrying out the Services, the
Consultants, with respect to damage caused by the Consultants to the Client’s property, shall not
be liable to the Client:
Fees and Reimbursable Expenditure made or expected to be made to the Consultants hereunder,
or (B) the proceeds the Consultants may be entitled to receive from any insurance maintained by
the Consultants to cover such a liability, whichever of (A) or (B) is higher.
(b) This limitation of liability shall not affect the Consultants’ liability, if any, for damage to Third
Parties caused by the Consultants or any person or firm acting on behalf of the Consultants in
carrying out the Services.
-191-
(b) Third Party liability insurance with a minimum coverage, for Rs. 1.00 million for the period of
consultancy.
(c) (i) The Consultant shall provide to Executive Engineer, National Highway Division, Karwar.
Professional Liability Insurance (PLI) for a period of Five years beyond completion of
Consultancy services or as per Applicable Law, whichever is higher.
(ii) The Consultant will maintain at its expense PLI including coverage for errors and omissions
caused by Consultant’s negligence in the performance of its duties under this agreement, (A) For
the amount not exceeding total payments for Professional Fees and Reimbursable Expenditures
made or expected to be made to the Consultants hereunder OR (B) the proceeds, the
Consultants may be entitled to receive from any insurance maintained by the Consultants to cover
such a liability, whichever of (A) or (B) is higher.
iv) The policy should be issued only from an Insurance Company operating in India.
v) The policy must clearly indicate the limit of indemnity in terms of “Any One Accident” (AOA)
and “Aggregate limit on the policy” (AOP) and in no case should be for an amount less than
stated in the contract.
vi) If the Consultant enters into an agreement with Executive Engineer, National Highway Division,
Karwar. in a joint venture or ‘in association’, the policy must be procured and provided to
Executive Engineer, National Highway Division, Karwar. by the joint venture/in association
entity and not by the individual partners of the joint venture/ association.
vii) The contract may include a provision thereby the Consultant does not cancel the policy midterm
without the consent of NHAI. The insurance company may provide an undertaking in this
regard.
(d) Employer’s liability and workers’ compensation insurance in respect of the Personnel of the
Consultants and of any Sub consultant, in accordance with the relevant provisions of the
Applicable Law, as well as, with respect to such Personnel, any such life, health, accident, travel
or other insurance as may be appropriate; and all insurances and policies should start from the
date of commencement of services and remain effective as per relevant requirements of contract
agreement.
3.9 The Consultants shall not use these documents for purposes unrelated to this Contract without the
prior written approval of the Client.
4.6 The person designated as Team Leader cum Senior Highway Engineer in Appendix B shall serve in
that capacity, as specified in Clause 4.6.
Service Tax)
6.3 (a) No advance payment will be made. 6.3 (e) The interest rate is : @ 12% per annum 6.3 (f) The
account is :
-192-
Disputes shall be settled by arbitration in accordance with the following provisions:
Selection of Arbitrators
Each dispute submitted by a Party to arbitration shall be heard by a sole arbitrator or an
arbitration panel composed of three arbitrators, in accordance with the following provisions:
(a) Where the Parties agree that the dispute concerns a technical matter, they may agree to
appoint a sole arbitrator or, failing agreement on the identity of such sole arbitrator within
thirty (30) days after receipt by the other Party of the proposal of a name for such an
appointment by the Party who initiated the proceedings, either Party may apply to the President,
Indian Roads Congress, New Delhi, for a list of not fewer than five nominees and, on receipt of
such list, the Parties shall alternately strike names there from, and the last remaining nominee on
the list shall be the sole arbitrator for the matter in dispute. If the last remaining nominee has
not been determined in this manner within sixty (60) days of the date of the list, the president,
Indian Roads Congress, New Delhi, shall appoint, upon the request of either Party and from
such list or otherwise, a sole arbitrator for the matter in dispute.
(b) Where the Parties do not agree that the dispute concerns a technical matter, the Client and the
Consultants shall each appoint one arbitrator, and these two arbitrators shall jointly appoint a
third arbitrator, who shall chair the arbitration panel. If the arbitrators named by the Parties do
not succeed in appointing a third arbitrator within thirty (30) days after the later of the two
arbitrators named by the Parties has been appointed, the third arbitrator shall, at the request of
either Party, be appointed by Secretary, the Indian Council of Arbitration, New Delhi.
(c) If, in a dispute subject to Clause SC 9.2.1 (b), one Party fails to appoint its arbitrator within
thirty (30) days after the other Party has appointed its arbitrator, the Party which has named an
arbitrator may apply to the Secretary, Indian Council of Arbitration, New Delhi, to appoint a
sole arbitrator for the matter in dispute, and the arbitrator appointed pursuant to such application
shall be the sole arbitrator for that dispute.
Rules of Procedure
Arbitration proceedings shall be conducted in accordance with procedure of the Arbitration &
Conciliation Act 1996, of India unless the Consultant is a foreign national/firm, where
arbitration proceedings shall be conducted in accordance with the rules of procedure for
arbitration of the United Nations Commission on International Trade Law (UNCITRAL) as in
force on the date of this Contract.
Substitute Arbitrators
If for any reason an arbitrator is unable to perform his function, a substitute shall be appointed in
the same manner as the original arbitrator.
Qualifications of Arbitrators
The sole arbitrator or the third arbitrator appointed pursuant to paragraphs (a)through (c) of
Clause 8.2.1 hereof shall be an internationally recognized legal or technical expert with
extensive experience in relation to the matter in dispute.
-193-
9.2.5 Miscellaneous
b) the English language shall be the official language for all purposes; and
[Note: English language may be changed to any other Language, with the agreement of both the
Parties.]
c) the decision of the sole arbitrator or of a majority of the arbitrators (or of the third arbitrator if
there is no such majority) shall be final and binding and shall be enforceable in any court of
competent jurisdiction, and the Parties hereby waive any objections to or claims of immunity in
respect of such enforcement.
d) The maximum amount payable per Arbitrator in Arbitration clauses shall be as under
In exceptional cases, such as cases involving major legal implications/ wider ramifications/ higher
financial stakes etc., a special fee structure could be fixed in consultation with the Contractor/
Supervision Consultants and with the specific approval of the Executive Engineer, National Highway
Division, Karwar. before appointment of the Arbitrator,
-194-
Appendix A
-195-
Appendix B
-196-
Appendix C
The Consultant’s personnel shall normally work for 8 hours in a day and six days a week.
Normally Sundays shall be closed for working. In addition they shall also be allowed to avail
holidays as observed by the Client’s office in the relevant state without deduction of
remunerations. In case any person is required to work on Sunday or Holiday due to exigency of
work, he/she shall be given compensatory leave within the next 15 days.
-197-
Appendix D
-198-
Appendix E
Cost Estimate
-199-
Appendix F
200-
Appendix G: Copy of letter of invitation
-201-
Appendix H: Copy of letter of acceptance
-
202
Appendix - I
Format for Bank Guarantee for Performance Security (For individual work)
BANK GUARANTEE FOR PERFORMANCE SECURITY
To,
Executive Engineer,
National Highway Division,
Karwar
The Client shall have the fullest liberty without affecting in any way the liability of the Bank
under this Guarantee, from time to time to vary or to extend the time for performance of the
contract by the Consultant. The Client shall have the fullest liberty without affecting this
guarantee, to postpone from time to time the exercise of any powers vested in them or of any
right which they might have against the consultant and to exercise the same at any time in any
-203-
manner, and either to enforce or to forbear to enforce any covenants, contained or implied, in the
Contract between the Client and the Consultant any other course or remedy or security available
to the Client. The bank shall not be relieved of its obligations under these presents by any
exercise by the Client of its liberty with reference to the matters aforesaid or any of them or by
reason of any other act or forbearance or other acts of omission or commission on the part of the
Client or any other indulgence shown by the Client or by any other matter or thing whatsoever
which under law would but for this provision have the effect of relieving the Bank.
The Bank also agrees that the Client at its option shall be entitled to enforce this Guarantee
against the Bank as a principal debtor, in the first instance without proceeding against the
Consultant and notwithstanding any security or other guarantee that the Client may have in
relation to the Consultant’s liabilities.
c) We are liable to pay the guaranteed amount or any part thereof under this Bank Guarantee
only and only if you serve upon us a written claim or demand on or before
……………(date of expiry of Guarantee).
NOTE:
i) The bank guarantee(s) contains the name, designation and code number of the officer(s)
signing the guarantee(s).
ii) The address, telephone no. and other details of the Head Office of the Bank as well as of
issuing branch should be mentioned on the covering letter of issuing Branch.
iii) The bank guarantee for Rs. 10,000 and above is signed by at least two officials (or as per the
norms prescribed by the RBI in this regard).
204-
Appendix J : Reply to Queries of the Bidder
-205-