: 09
Monthly Report for Quality Surveillance Month:-
September 2019
RINA-Surveyors
Name : Mr. Sanjay kumar Bhola
Date of issue : 03.10.2019
Page 1 of 13
Report No.: 09
Monthly Report for Quality Surveillance Month:-
September 2019
Executive Summary
GAIL (India) Limited had assigned RINA INDIA PVT. LTD. to provide the Third Party Inspection for
Quality Surveillance for GAIL’s for hiring of third party inspection agency for quality surveillance and
conformity assessment of GAIL’s various Pipeline Projects & LMC Pipeline Projects. As per
RINA India Pvt. Ltd. scope of inspection services includes, but is not limited to, inspection during
manufacturing & Coating of Line Pipe, Pipeline construction related activities viz. Welding, NDT and E
& I, Mechanical & Civil jobs at stations on routs as well as at compressor stations.
REPORTING
PMC Construction
In-charge
Page 2 of 13
Report No.: 09
Monthly Report for Quality Surveillance Month:-
September 2019
1 - Reference
Project : LAYING & CONSTRUCTION OF STEEL GAS PIPELINEALONG WITH ASSOCIATED
FACILITIES FOR DHAMRA ANGUL PIPELINE OF JAGDISHPUR-HALDIA -BOKARO-
DHAMRA PIPELINE PROJECT (JHBDPL) PH-II ,SEC-2A.
2 - Documents
Page 3 of 13
Report No.: 09
Monthly Report for Quality Surveillance Month:-
September 2019
(List of procedure / specification carried out at the time of inspection, Reference codes, standard
and specifications carried out at the time of inspection :)
3 - Quality highlights
It was observed that during the month workers are using proper PPE whenever work is in progress.
Successfully mainline welding construction work started.
4 - Areas of concern:-
NIL
Page 4 of 13
Report No.: 09
Monthly Report for Quality Surveillance Month:-
September 2019
5 -The availability of the machinery, unit or plant and reasons for fallback in availability.
13 JCB Nos. 2
14 Vehicle Nos. 4
15 Tractor Nos. 3
16 Welding Rectifiers Nos. 6
17 Boring machine (Auger Boring) Nos. 3
18 Hydra Nos. 6
19 Truck Nos. 0
20 Miller welding M/c Nos. 1
21 HDD Rig Nos. 0
Page 5 of 13
Report No.: 09
Monthly Report for Quality Surveillance Month:-
September 2019
6 - Site-wise trends
Achieved at site
Sr. No. Description Remarks
(%)
1 Repair Rate No any work is in progress due to
30.28%
financial crisis of M/S PLL
2 Rejection Rate 0% Nil
3 Recycling Rate 0% Nil
4 Plant availability
5 Laying Rate Slow progress due to shortage of
0.1248%
manpower of M/S PLL
7 - Trend-graphs
20.00%
18.00%
16.00%
14.00%
Progress in Percentage
12.00%
10.00%
18.89%
8.00%
6.00%
4.00%
2.00% 4.14%
2.12%
0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
Page 6 of 13
Report No.: 09
Monthly Report for Quality Surveillance Month:-
September 2019
Month-
8 - Status of inspection
Completed
Sr. Total Completed
Description Unit upto last Balance
No. scope this month
month
1 Handing Over of ROU Mtr 206595 166257 2761 37577
2 ROU Clearing & Grading Mtr 206595 56441 0 150154
3 Line Pipe Received at Site Mtr 206595 58114 0 148481
3.1 API 5L X70(PSL-2) 36ӯx 15.9mmWt Mtr 140241 40401 0 99840
,3LPE COATED.
3.2 API 5L X70(PSL-2) 36 ӯx19.1mmWt Mtr 63860 17713 0 46147
,3LPE COATED
3.3 API 5L X70(PSL-2) 36 ӯ x 23.1mmWt Mtr 2494 0 0 2494
3LPE COATED
4 Stringing Mtr 206595 45973 0 160622
5 Pipe Bending fabrication(Cold Field Nos 620 90 0 530
Bend)
Cold field bend Installation Nos 620 10 0 610
6 Mainline Welding, Nos 17147 3157 67 13923
Mtr 206595 38603.68 662.58 167328.74
7 Free Tie / Tie-in Welding Free Tie Nos 6 0
in
Tie-In Nos 4 0
Length Mtr
8 Total Welding Mtr 206595 37450.3 1153.38 167991.32
Nos 17147 3169 55 13923
9 Radiography Nos 17147
9.1 Taken Nos 17147 2951 112 14084
9.2 Reviewed Nos 17147 2772 258 14117
9.3 First Accepted Nos 17147 1848 63 15236
9.4 Repair Nos 248 18
9.5 Repair Accepted Nos 184 0
9.6 RT/RS/GRS Nos 493 5
9.7 Reshoot, Retake, DRS Accepted Nos 217 0
9.8 Repair Percentage % 13.41 28.57
Page 7 of 13
Report No.: 09
Monthly Report for Quality Surveillance Month:-
September 2019
Completed
Sr. Total Completed
Description Unit upto last Balance
No. scope this month
month
15 Cased Crossings (NH ,SH) Nos 26 2 0 24
16 Asphalted Roads / RCC / Metaled Nos 52 2 0 50
Road
17 Unlined / Left main / distributary / Nos 120 0 0 0
Minor lined / Field Canal Crossing
18 HDD Crossing Nos 23 3 0 20
Pre/Post Hydrostatic Testing Nos 0 0 0 0
19 Pipeline Crossing Nos 0
20 Backfilling Mtr 206595 13265 450 192880
21 Cleaning & Gauging Mtr 206595 0 0 0
22 Hydro testing Mtr 206595 0 0 0
23 CP Work
23.1 Soil Resistivity Mtr 206595 0 0 0
23.2 Mg. Anode-2.5 Kg Installation Nos 0 0 0
23.3 Mg. Anode-10 Kg Installation Nos 0 0 0
23.4 Zn. Anode-20 Kg Installation Nos 0 0 0
23.5 Thermite Welding Nos 0 0 0
23.6 TLP Installation Nos 0 0 0
23.7 TCP Commissioning Mtr 206595 0 0 0
24 Marker Installation
24.1 Direction Marker Nos 580 0 0 0
24.2 Pipeline Warning Signs Nos 160 0 0 0
24.3 Kilo Meter Posts Nos 207 0 0 0
24.4 Aerial Marker Nos 42 0 0 0
24.5 Navigable Waterway Marker Nos 10 0 0 0
24.6 ROU Boundary Marker Nos 1650 0 0 0
24.7 OFC Distance Markers Nos 0 0 0
25 Clean up &Restoration Mtr 206595 0 0 206595
26 Nitrogen (N2) Pursing Mtr. 206595 0 0 206595
27 Pre-Commissioning & Mtr. 206595 0 0 206595
Commissioning
28 Cathodic Protection Mtr. 206595 0 0 206595
29 ANY OTHER ACTIVITY
9 - Bottlenecks of Project:
Page 8 of 13
Report No.: 09
Monthly Report for Quality Surveillance Month:-
September 2019
10 - Quality Index
Page 9 of 13
Report No.: 09
Monthly Report for Quality Surveillance Month:-
September 2019
11.2Observations:
Page 10 of 13
Report No.: 09
Monthly Report for Quality Surveillance Month:-
September 2019
12 - Photographs
Page 11 of 13
Report No.: 09
Monthly Report for Quality Surveillance Month:-
September 2019
Page 12 of 13
Report No.: 09
Monthly Report for Quality Surveillance Month:-
September 2019
REPORT REVIEWED BY
Name: SharalSasidharan
Signature:
Date:
Page 13 of 13