Gantt Chart
Gantt Chart
Gantt Chart
Mode T W T F S S
1 Pre inspection of current workshop layout 1 day Tue 12/4/18 Tue 12/4/18
2 Purchasing and order processing 2 days Wed 12/5/18 Thu 12/6/18 1
3 Order follow up 3 days Fri 12/7/18 Tue 12/11/18 2
4 Shipment receiving 1 day Wed 12/12/18 Wed 12/12/18 3
5 Installation of parts 1 day Thu 12/13/18 Thu 12/13/18 4
6 Trial cut 1 day Fri 12/14/18 Fri 12/14/18 5
7 Setting up DNC 1 day Mon 12/17/18 Mon 12/17/18 6
8 Software Installation 1 day Tue 12/18/18 Tue 12/18/18 7
9 Issuing Proposal 1 day Wed 12/5/18 Wed 12/5/18 1
10 Accepting and Finalizing Proposal 1 day Thu 12/6/18 Thu 12/6/18 9
11 Finalizing contractor 1 day Fri 12/7/18 Fri 12/7/18 10
12 Final quality inspection 1 day Wed 12/19/18 Wed 12/19/18 11,8
13 Testing and performance review 1 day Thu 12/20/18 Thu 12/20/18 12
14 Final testing and Initiation of production 1 day Fri 12/21/18 Fri 12/21/18 13
15 Project Success Meet 1 day Mon 12/24/18 Mon 12/24/18 14