Gantt Chart

Download as pdf or txt
Download as pdf or txt
You are on page 1of 2

ID Task Task Name Duration Start November Finish Predecessors

Mode T W T F S S
1 Pre inspection of current workshop layout 1 day Tue 12/4/18 Tue 12/4/18
2 Purchasing and order processing 2 days Wed 12/5/18 Thu 12/6/18 1
3 Order follow up 3 days Fri 12/7/18 Tue 12/11/18 2
4 Shipment receiving 1 day Wed 12/12/18 Wed 12/12/18 3
5 Installation of parts 1 day Thu 12/13/18 Thu 12/13/18 4
6 Trial cut 1 day Fri 12/14/18 Fri 12/14/18 5
7 Setting up DNC 1 day Mon 12/17/18 Mon 12/17/18 6
8 Software Installation 1 day Tue 12/18/18 Tue 12/18/18 7
9 Issuing Proposal 1 day Wed 12/5/18 Wed 12/5/18 1
10 Accepting and Finalizing Proposal 1 day Thu 12/6/18 Thu 12/6/18 9
11 Finalizing contractor 1 day Fri 12/7/18 Fri 12/7/18 10
12 Final quality inspection 1 day Wed 12/19/18 Wed 12/19/18 11,8
13 Testing and performance review 1 day Thu 12/20/18 Thu 12/20/18 12
14 Final testing and Initiation of production 1 day Fri 12/21/18 Fri 12/21/18 13
15 Project Success Meet 1 day Mon 12/24/18 Mon 12/24/18 14

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: gantt chart
Summary Manual Summary Rollup Progress
Date: Wed 11/14/18
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 1
December
S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: gantt chart
Summary Manual Summary Rollup Progress
Date: Wed 11/14/18
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 2

You might also like