PROJECT NAME: TEN STORIED EGL BUILDING AT GORAI, TANGAIL, HAMEEM GROUP

Revised Schedule for Mid Part Slab Casting (North side)

Sep, 15
Sep, 16
Sep, 17
Sep, 18
Sep, 19
Sep, 20
Sep, 21
Sep, 22
Sep, 23
Sep, 24
Sep, 25
Sep, 26
Sep, 27
Sep, 28
Sep, 29
Sep, 30
Work Duration
Description of Works Start dt. Finish dt.
(Days)
Shuttering Works Complete 17 18 6-Sep-19 23-Sep-19
Rebar Placement (Bottom layer) 12 13 12-Sep-19 24-Sep-19
Duct & Wire placement for Prestressing 10 11 15-Sep-19 25-Sep-19
Rebar Placement (Top layer) 8 20-Sep-19 27-Sep-19
Consultant Checking 2 27-Sep-19 28-Sep-19
Observation works 2 1 29-Sep-19 29-Sep-19
RCC Casting by RMC 1 30-Sep-19 30-Sep-19

Casting Volumn
6,500 Psi Concrete 62.00 Cum
5,500 Psi Concrete 645.00 Cum
Total Qty of RMC 707.00 Cum