2 Case Study of An Energy Efficient Commercial Building
2 Case Study of An Energy Efficient Commercial Building
2 Case Study of An Energy Efficient Commercial Building
35
improving day lighting, energy efficient lighting and
cooling systems and integration of renewable energy.
Following EEMs were agreed upon and implemented
during construction stage. The EEMs include:
Roof insulation (Figure 6): Roof of this building is
insulated with 40 mm polyurethane foam (PUF)
resulting a U-value of 0.6 W/m2.K. Also, light
coloured terrazzo tiles at top was incorporated to
have high reflectivity.
36
Energy efficient cooling system: A centralised
high efficiency water-cooled chiller (COP: 5.8)
was implemented for air-conditioning the
building. Given the water scarcity in Jaipur, a
sewage treatment plant (capacity: 15 m3/d) was
installed and treated waste water is used for the
cooling towers.
Solar photovoltaic (SPV) system: A 45kWp grid-
connected roof-top SPV system (Figure 9) with net
metering is installed to meet part of the building
energy requirement. It should be noted that the
contribution of solar PV system has not been
included in the EPI calculations during energy
simulations. Figure 11: Reduction in EPI size with EEMs (SPV
contribution not included)
ENERGY MONITORING
Energy monitoring of the building was done to
understand the actual energy performance of the
building and to compare it with the estimated energy
performance through energy simulation. As the building
does not have an EIS, the methodology for energy
monitoring involved.
Figure 9: SPV system at the rooftop Collection of Electricity Bill
The energy simulation of the building was carried out
Monthly electricity bills for a period of one year (May
using DesignBuilder software to quantify the benefits
2015 to April 2016) were collected. Using this data
of the integration of EEMs. The key results of the
monthly and annual EPI of the building was calculated.
energy simulation were:
The billing data was also cross-checked with the data
Reduction in cooling system size: The cooling from the log book maintained by the building operation
system size was reduced from 230 TR (before the team on the hours of usage of HVAC system and
design workshop) to 165 TR (after the integration periodic readings of the electricity meter.
of EEMs), which is a 28% reduction in the cooling Seasonal Energy Monitoring
system size (Figure 10).
The objective of the detailed seasonal energy
monitoring was (1) to get break-up of energy
consumption for different end-uses (e.g. HVAC,
lighting, equipment, etc.), and (2) to identify further
energy saving opportunities by measuring the
performance of different systems (e.g. chillers, pumps,
fans, lighting fixtures etc.).
Detailed energy monitoring for two weeks in winter and
two weeks in summer was done. Winter monitoring was
done for a duration of two weeks in January 2016.
During this period, the HVAC system was not
operational. Except HVAC system data, all
Figure 10: Reduction in cooling system size with EEMs measurements were done. In addition, data on building
usage such as number of people, occupancy schedule,
Reduction in energy consumption: The energy
schedule of operation for lighting and other systems was
performance index (EPI) was reduced from 77
gathered. Summer monitoring was for a duration of two
kWh/m2.y to 53 kWh/m2.y (31% reduction) after
considering EEMs in energy simulation (Figure weeks in May 2016. During summer, all the
11). This does not include the energy generated
from SPV system.
37
measurements were done as the HVAC system was Level 3: Data collection (from hourly panel reading,
fully operational. through records or through interaction): Energy
generated from SPV system, from DG set was collected
Prior to actual energy monitoring, a detailed monitoring to get energy supply from these systems.
plan was prepared. Architectural drawings, HVAC
schematic and electrical schematic was studied in detail
to prepare a draft monitoring plan (Figure 12). A visit to
the building was done to exactly identify the different
measurement points, instruments needed, measurement
frequency and other details to be collected.
Monitoring plan for building included three levels of Sr. Name of Make Measurement
data monitoring and collection No Instruments
1 Single CT MECO Snap shot power
Level 1: Continuous data logging with an interval of power meter measurement
15 min. or less: Energy loggers were installed at 2 Three CT power ORACLE Power Data Logging
analyzer
electricity distribution panel to continuous log the 3 Three CT power Krykard Power Data Logging
HVAC and non-HVAC loads. In addition, data logging analyzer
was done for HVAC system components which 4 Swing JRM DBT & WBT
Psychrometer
included power for each operational chillers, condenser 5 Lux meter TES 1332 A Illumination levels
water flow, condenser water in and out temperature, 6 Surface contact Libratherm Measurement of
power for air handling units, ambient air temperature type temperature surface temperature on
and relative humidity. This data was used to calculate sensor condenser water
header
the HVAC energy break-up in AHU and Chiller plant
7 Head mount Libratherm Measurement of water
and to calculate the chiller coefficient of performance temperature temperature through
(COP). sensor thermowell
8 8 Channel Libratherm Logging of water
Level 2: Spot measurement of parameters (2 times Temperature temperature readings
per day: 1100-1230 hrs, 1430-1630 hrs): The key aim Logger
of this task was to find an approximate energy break-up 9 8 Channel Libratherm Logging of Ambient
Temperature Temperature + water
of non-HVAC loads which included lighting (office Logger + %RH temperature + %RH
spaces, corridor & exterior), office equipment, STP & logger
miscellaneous (lift, water pump, basement ventilation 10 Ambient Libratherm Ambient Temperature
temperature + + %RH
fan, etc.). Measurement points on multiple electricity %RH sensor
distribution panel were identified for the same. Ultrasonic Data logging of Water
11 Water Flow Essiflo flow through main
Spot measurements of electrical power was done for meter header of condenser
primary chilled water pump, secondary chilled water Infrared Measurement of
12 temperature gun Testo Envelope temperature
pump, condenser pump and cooling tower fan to get
further break-up of chiller plant energy consumption.
Calibrated Energy Simulation Model
Spot measurements were also made for indoor lighting
levels and artificial lighting power to understand the Based on the information gathered, detailed
daylight penetration in spaces and lighting energy. specification of equipment and performance
measurement of systems; an energy simulation model
38
(using VisualDOE) was prepared. Calibration of
simulation model was done:
Against the monthly energy bills to match the
monthly energy consumption
Against the energy consumption of different end-
uses (lighting, equipment, HVAC, etc.) for the
detailed monitoring period i.e. two weeks of
January and two weeks of May
The objective of this model was: (1) to calculate the
break-up of energy consumption for different end-uses
round the year as the detailed monitoring was done only
Figure 14: Simulated and actual monthly EPI
for a total of four weeks duration and (2) to calculate the
energy saving through the additional measures
Key reasons for these differences are:
identified during the monitoring period.
ECBC Compliance The simulation was done using the ISHRAE
weather data file which gives the hourly data for a
‘Whole building performance method’ was followed for year with long term measured data. Weather
ECBC compliance check. This requires preparation of conditions for the monitoring period may have
energy simulation model for two cases differences as compared to the data considered in
(1) ECBC Prescriptive and (2) As Designed. All the the energy simulation.
simulation inputs, (e.g. wall U-value, roof U-value, During monitoring it was observed that the HVAC
fenestration SHGC, VLT & U-value, lighting power remained OFF during the period November - Mid
density, HVAC system COP, etc.) for ‘ECBC March, while in simulation, the HVAC system was
considered operational during this period.
Prescriptive’ case, were taken as defined in ECBC. For
the ‘As Designed’ case, all the simulation inputs were The artificial lighting energy consumed in winter
(Nov-Feb) was also less than that estimated in the
taken as designed capacity and design specification.
charrette due to better use of daylight.
Inputs on building operation (e.g. thermostat setpoints,
During the simulation, only weekends (Saturday &
schedules, internal gains, occupant loads, etc.) were
Sunday) were considered as holidays, whereas in
kept same for both cases. In addition, all the mandatory actual there were 20-30 additional holidays.
requirements were checked for ECBC compliance.
All the findings of energy monitoring (actual schedule
Actual energy performance of building may not match to for occupancy, lighting, equipment, HVAC system
the ‘As Designed’ case due difference in user behaviour performance) were used to prepare a ‘calibrated energy
and difference in actual performance of various simulation model’ as explained in subsequent sections.
Energy supply and consumption
systems.
Figure 15 gives the break-up of energy supply from grid
RESULTS AND DISCUSSIONS & SPV system. DG set was hardly used during this
period and thus does not feature here. SPV system of 25
Comparison of energy performance (Simulation vs
actual) kWp capacity was installed in October-2015 and
subsequently the installed capacity was increased to 45
The simulated EPI during the charrette (December kWp in January-2016 and later net metering was done in
2012) was 53 kWh/m2.y as compared to the actual EPI April-2016. Therefore, during May-15 to April-2016,
(monitored data for May-15 to Apr-16) of 43 kWh/m2.y. only ~6% of energy was supplied through SPV system
Figure 14 shows the comparison of monthly EPI for and ~94% was drawn through the grid. However, is it
these two cases. estimated that contribution of energy from SPV system
would increase to ~20% (considering the present energy
consumption and energy generation from 45 kWp
system for a year).
39
Seasonal energy break-up
40
Figure 23: Sample spaces for daylight measurement
Figure 20: Measured chiller performance Out of these 9 spaces, 3 spaces (marked as ‘X’) had
average daylight of ~30 lux and required artificial
Figure 21 shows the COP of overall HVAC plant
lighting. This was mainly due shading by adjacent
(including chiller, pumps & cooling tower) for the
staircase block. Other 6 spaces had average daylight of
monitoring period. It varied from 3.6 to 4.6 during the
~300 lux and did not require any artificial lighting.
monitoring period and the average COP was calculated
Further Energy Saving Opportunities
as 4.1.
Energy monitoring identified few additional measures
which can further help in energy saving. The saving
potential of these additional measures is estimated
through energy simulation (by adding these measures in
the ‘calibrated energy simulation model’). These
measures are:
Reduction of contract demand from 500 kVA to
400 kVA as the recorded demand did not exceed
300 kVA.
Improve condenser approach for under-
performing chiller by cleaning the condenser tubes
Figure 21: HVAC plant performance and maintaining water quality.
Improve cooling tower efficiency.
Replace condenser water pumps & primary chilled
water pump with revised capacity (pressure &
flow).
Energy savings through these additional measures is
estimated to be ~10,000 kWh/y.
ECBC Compliance Analysis Results
41
Figure 24: Energy consumption results for ECBC compliance
BEE also has a star rating programme for existing two-weeks detailed energy monitoring twice a year, in
buildings based on one energy consumption (EPI) data winter and summer season; (ii) analysis of monthly
for a complete year. For day-use office building in energy bills for a year; and (iii) a calibrated energy
composite climate (e.g. Jaipur), a building with an EPI simulation model. Results show 53% of electricity is
< 90 kWh/m2.y, gets a five-star (maximum) rating. used for HVAC annually, while 31% of electricity is
With an EPI of 43 kWh/m2.y, The building easily used for office equipment and 6% for artificial
qualifies for five-star rating under BEE’s star rating lighting. The difference in simulated performance
programme. (EPI: 53 kWh/m2.y) and measured performance (EPI:
Cost Benefit Analysis 43 kWh/m2.y) is explained.
Cost of construction before design workshop was The case study shows that for building without an
estimated to be Rs 300 million, while the actual cost EIS, using a customised energy monitoring
of construction after implementing all EEMs (except methodology, one can get quite good understanding
SPV system) was Rs 306 million. The increase in of energy performance of building, break-up of
energy for end- uses and performance of systems;
capital cost was only 2% while energy saving
also identify possibilities of further improvement in
estimated to be 44%; thereby resulting in a payback
energy performance.
period of 2.5-3.0 years.
There is a need to have many such case studies. This
would help in motivating builders / developers and
CONCLUSION
other building sector professional to adopt energy
Good quality case studies based on monitored energy efficiency measures in their projects, having more
performance are needed for mainstreaming ECBC in ECBC compliant buildings.
the country. The paper presents case study of an office
building at Jaipur and cover: ACKNOWLEDGEMENT
a) Energy efficiency measures adopted in the The authors of this paper would like to thank Indo-
building. Swiss Building Energy Efficiency Project (BEEP)
b) Results of the building energy simulation under which the technical support was provided to
during the building design. Aranya Bhawan project team for design &
c) Methodology and results of the performance implementation of energy efficiency measures as
monitoring of the fully functional building for well as funding was provided to carry out the energy
one-year period. monitoring work. The authors would also like to
d) Results of checking compliance with ECBC thank Energetic Consulting Pvt. Ltd. for conducting
the energy monitoring; Rajasthan State Road
Energy efficiency measures (EEMs) for this building
Development Cooperation (RSRDC) for
includes use of insulation in external walls & roof,
implementing the EEMs and Forest Department of
optimized window-to-wall ratio, efficient glazing,
Rajasthan to support as building owner.
high efficiency water cooled screw chiller, T5 & LED
lighting and rooftop solar photovoltaic system. Since
the building does not have an EIS, a monitoring
methodology was developed. This consisted of (i)
42
REFERENCES
Energy Statistics, 2017. Central Statistics Office,
Ministry of Statistics and Programme
Implementation, Government of India
India Energy Security Scenario (IESS), 2015. NITI
Aayog
Liu F, Meyer A S, Hogan J F, 2010. Mainstreaming
Building Energy Codes in Developing Countries.
World Bank Working Paper No. 204.
43