GEO2019 Emad Farouz CBIS Drilled Shafts
GEO2019 Emad Farouz CBIS Drilled Shafts
GEO2019 Emad Farouz CBIS Drilled Shafts
February 8, 2019
www.jacobs.com | worldwide
Agenda
1. Project Background
2. Geology
3. Types of Bridge Foundations used in CBIS
4. Drilled Shafts for Bridge Foundation
5. Drilled Shafts Bearing in Rock and in Soil
6. Comparison of Drilled Shafts in Rock vs in Soil
7. Conclusions and Lesson’s Learned
1
13/02/2019
Project Background
• Modernization and
Rehabilitation of
approximately 18
miles of mainline
interstate (I-80, I-29,
and I-480)
Source: http://www.councilbluffsinterstate.iowadot.gov/projects/
3
Project Background
• 15 interchanges
• 59 bridges
Source: http://www.councilbluffsinterstate.iowadot.gov/projects/
2
13/02/2019
3
13/02/2019
7
Source: Iowa DOT Bridge Design Drawings – I-80WB over IA 192 (2016)
4
13/02/2019
In Rock In Soil
List of bridges List of bridges
Iowa DOT design guidelines Design guidelines
Design overview Design example
Load tests and results Load test and results
Production shafts installation Production shafts installation
10
Source: Iowa DOT Bridge Design Drawings – I-80WB over IA 192 (2016)
5
13/02/2019
11
12
6
13/02/2019
El. 928
Layer 3: Lean Clay
SPT N-Values 2 to 19 bpf; 9 bpf (Avg)
El. 894
Layer 4: Weathered Shale/Boulders
El. 890
Layer 5: Slightly weathered Shale and
Unweathered Limestone
13
7
13/02/2019
15
TS-1 TS-2
I-29 over Mosquito Creek US 275 over Mosquito Creek
16
8
13/02/2019
17 Excerpts from Report(s) on Drilled Shaft Load Testing by LoadTest, Aug and Sep 2014
18
Excerpts from Report(s) on Drilled Shaft Load Testing by LoadTest, Aug and Sep 2014
9
13/02/2019
19 Excerpts from Report(s) on Drilled Shaft Load Testing by LoadTest, Aug and Sep 2014
20 Excerpts from Report(s) on Drilled Shaft Load Testing by LoadTest, Aug and Sep 2014
10
13/02/2019
21 Excerpts from Report(s) on Drilled Shaft Load Testing by LoadTest, Aug and Sep 2014
11
13/02/2019
23
24
12
13/02/2019
In Rock In Soil
List of bridges List of bridges
Iowa DOT design guidelines Design guidelines
Design overview Design example
Load tests and results Load test and results
Production shafts installation Production shafts installation
25
Source: Iowa DOT Bridge Design Drawings – I-80WB over IA 192 (2016)
26
13
13/02/2019
27
• Pier
• Approx. 75 feet wide
• Approx. 20 feet high
• Foundation
• Four drilled shafts
• 60 inches diameter
• 90 feet long shafts
• C/C spacing 19 feet
• 5 feet thick pile cap
Source: Iowa DOT Bridge Design Drawings – I-80WB over IA 192 (2016)
28
14
13/02/2019
29
El. 954
Layer 3: Silty Sand and Poorly Graded Sand
Top of Bedrock
with Silt
SPT N-Values 8 to 41 bpf; 23 bpf (Avg) >140 feet bgs
El. 830
Layer 4: Slightly Weathered Limestone
Interbedded with Shale
30
15
13/02/2019
16
13/02/2019
33
34
17
13/02/2019
Excerpt from Report on Drilled Shaft Load Testing by LoadTest, Aug 2016
35
36
18
13/02/2019
37
Corresponding to the
depth at which the O-Cell
was installed
38
Excerpt from Report 1 of CSL Test Results – Test Shaft, by FTC, Aug 2016
19
13/02/2019
3
0.50
Displacement (inches)
Displacement (inches)
2
1.00 Upward Top of O-Cell
0
2.00
3.00
2,650 kips - 1.36 inches -2
0 500 1000 1500
Net Load (kips)
39
40 Excerpt from Report on Drilled Shaft Load Testing by LoadTest, Aug 2016
20
13/02/2019
Excerpt from Report on Drilled Shaft Load Testing by LoadTest, Aug 2016
41
960 970
950 960
Elevation (feet)
940 950
Elevation (feet)
930 940
920 930
910 920
900 910
Based on Design
890 900 Based on Design
Based on Load Test
880 Based on Load Test
890
0 500 1000 1500 2000 2500
Cummulative Nominal Side Resistance (kips) 880
42
21
13/02/2019
43
44
22
13/02/2019
45
46
23
13/02/2019
Questions?
47
24