Carter1996 PDF
Carter1996 PDF
To cite this article: M. Carter CEng, BSc, MSc, MICE (1996) Methods Used to Reduce
Settlements and Shorten Construction Time at Macau International Airport, HKIE Transactions, 3:1,
1-8
Article views: 14
Background
Macau is situated on the western side of the Pearl River T erminat area
estuary, about 60km west of Hong Kong, and comprises the
peninsular of Macau itself and the islands of Taipa and Sea dyke and wall
Coloane. Since the total land area of Macau is only about
16km', the new Macau International Airport (MIA) had to be
built on reclaimed land. Also, to minimise noise and air traffic -!-
,
problems, the runway and associated taxiways and safety
areas, which formed the majority of the reclamation, were
constructed as an artificial island located between the islands
ofTaipa and Coloane (see Figure 1). Runway
-20
-Cl
<) -30
~
-E
..
c -40
-
0
~
>
~
w -50
-70
-80 Note: mean sea level is 1.8m above Macau Chart Datum (MCD)
P",,,pel woll
s,.t"ty "''''''
II RLlrlW"Y s .....ty ""~".
'.....
. -- ...... " ,'.-
. -,'. . - - '.-,'-
- - -
.'... -.'
-
: - :".
-,
-. .. _
- ..
., '->.-:....L.~••.:.
--:. ~.
:.',:, ..:-.;..:.,. .
.._......
..::;.:t.
-. ..
-- - - - -- -- - ~ ~
- ~
-
~
Figure 3 - Section A-A. typical section for northern part of the artificial island
.
concentrated on settlement measurement, since this was of location Spacing No
more concern, and was considered to be a critical factor for Shore • 2 surface settlement blocks every 100m, 150
successful operation of the runway_ Settlement of the sand fill protection during construction
(runway, taxiway and safety areas) was measured mainly dyke • 1 surface settlement point on sea parapet 75-
through settlement plates which comprised 1m-square metal wall after cO,nstruction
• 6 inclinometers in sand fill behind wall at 6
plates or 3m-square frames, attached to a vertical tube. For the locations agreed between CAM's designer
sea dyke, temporary settlement points, consisting of O.Sm' and specialist advisers
concrete blocks, were used initially, to be replaced by points
Runway • settlement plates along the centreline every 115
set in the concrete sea wall once this was cast. and 100m and along the edges every 200m
Special instrumented sections were located at either end taxiway • temporary surface monitoring points on 400
of the artificial Island, which were the first areas to be completed pavement, 3 points every 40m
constructed, and at other areas of special concern. In these • permanent surface monitoring points on 55
areas, the normal settlement plate monitoring was pavement shoulders, 2 points every 200m
supplemented by settlement gauges, piezometers and Safety areas • settlement plates every 200m 45
inclinometers. Typical layout of these instruments is shown in Special • piezometers located at 7 sections of special 22
Figure 3. instrumented interest
Settlement gauges were the magnetic probe type, sections • settlement gauges (extensometers) located 28
comprising magnetic rings inserted at various depths in a at 7 sections of special interest
borehole, with a plastic tube through the centre. A torpedo- Table 2 - Spacing and Numbers of Instruments
type probe inserted down the tube gave readouts of each
plate location. Up to 8 plates were inserted down each
major influence on construction methods and programming of
borehole so that the compression of individual layers of soil
the work. Several measures were taken to speed up the
could be measured. Piezometers were of the pneumatic type,
settlement process and thus reduce the amount of settlement
inserted in boreholes to measure pore water pressures in the
remaining on completion of construction. Vertical drains were
marine mud and upper clay layer. Inclinometers were the
inserted through the marine mud and upper clay layer, as
keyed tube type, inserted into boreholes. The spacings and
indicated in Figure 3, and runway and taxiway areas were
numbers of instruments used are indicated in Table 2.
surcharged using sand fill which was subsequently spread over
the safety areas. Deep densification of the sand fill was
Constraints of the Project specified beneath the runway and taxiways.
The island was formed by dredging the recent marine mud For the runways and taxiways, the aim of these ground
beneath the sea dyke, runway and taxiways, and replacing it improvement measures was to limit settlements after
with sand fill. In the less-critical safety areas, only the upper 1- completion of the pavement so that the surface profile would
2m of mud was dredged. This is illustrated in the typical cross remain within ICAO (1990) guidelines. The long~term
section shown in Figure 3. settlement profile of the runway was of particular concern
For a project of its size and compleXity, the construction since the choice of a concrete pavement will limit the scope for
period was extremely short; initial dredging for the island regulation of the surface at a later date. The limiting factor, for
began in February 1992, and flight trials were conducted, on compliance with ICAO guidelines, is curvature of the
schedule, in June 1995. This short time-scale, coupled with the longitudinal profile, especially combinations of adjacent sag
need to minimise settlements of the completed runway, had a and hump curves, so that it was not possible to set simple limits
.1
L -
rates. The main problems were due to the drain coming back
up with the mandrel as it was withdrawn or tearing of the
drain inside the mandrel. Both were affected by the size and
•
••
••
•
• .. . stiffness of shoe used for insertion. Shoes, small rectangular
• ..
plates with handles for attaching the vertical drain, block off
the bottom of the mandrel during insertion and then anchor
-_. ._-----_._---- ._._.- .__ ...- ..
TIm.
---_..- -- •.. _._.- the drain in the ground during withdrawal. The use of water
I" to flush the mandrel during insertion was particulariy effective
0 in curing these problems and was eventually adopted by most
, ---
"
lO"'_~"=~_-= (Oacl~~ __ _ "
1.___._ subcontractors, sometimes after initial resistance owing to the
added complication of providing the necessary pumps and
! hoses.
~
• Drains beneath the runway and taxiway areas were
installed to between 325m and 3S.Sm depth but, because the
._._-_._-- ,... mud in these areas had been replaced by sand fill, it was not
- -_._----- --_ .. .. _ _---_.~-
Acknowledgements
The author thanks CAM Sociedade do Aeroporto Internacional
de Macau and SPP Concorcio Internacional for permission to
publish this paper. Grateful thanks are also due to Adelina
Kong Santos, whose help and ideas during both the
development of the settlement analysis system and the
preparation of this paper were invaluable, and to colleagues
David Coffey and Denis McDowell for checking the drafts and
for their helpful suggestions.
References
ICAO (1990). International Standards And Recommended Practices.
Aerodromes: Annex 74 to the Convention on International Civil
Aviation, Vol. I, Aerodrome design and operations, International Civil
Aviation Organization.