Multi Scheduling Heuristic

This document describes how to use the SAP_MULT_SCH heuristic in the PP/DS Planning board to schedule orders across multiple resources and sources of supply. The heuristic switches between modes and sources according to defined time blocks to keep receipts as close to required dates as possible. Key steps include activating the required business function, setting up the heuristic with alternative PDS/resources, including it in a heuristic profile, and running it on orders for a product with multiple available dates.

Uploaded by

pesimistix
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
320 views9 pages

Multi Scheduling Heuristic

This document describes how to use the SAP_MULT_SCH heuristic in the PP/DS Planning board to schedule orders across multiple resources and sources of supply. The heuristic switches between modes and sources according to defined time blocks to keep receipts as close to required dates as possible. Key steps include activating the required business function, setting up the heuristic with alternative PDS/resources, including it in a heuristic profile, and running it on orders for a product with multiple available dates.

Uploaded by

pesimistix
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 9

Scenario - Run Heuristic SAP_MULT_SCH in

PPDS Planning Board


Skip to end of metadata
 Created by Former Member, last modified on Jan 28, 2016
Go to start of metadata

Purpose
This page describes how to use heuristic SAP_MULT_SCH in PP/DS Planning board.

Overview
As of SCM Rel. 7.02, heuristic SAP_MULT_SCH (Function module /SAPAPO/HEU_MULTIRES_SCHED) is introduced to be
used in Process Industry scenarios. You can use this algorithm to switch modes and sources of supply according to defined
time blocks, so as to keep the receipts as close to the required date as possible.

Table of Contents
 Purpose
 Overview

 Requirements
 Example Creation
 Step 1: Check Customizing
 Step 2: Setup Heuristic
 Step 3: Include the heuristic in heuristic profile
 Step 4 Run the heuristic in PP/DS Planning board
 FAQ
 Related Content
 Related Documents
 Related Notes

Requirements
 Activate business function SCM_APO_PPDS_PI (SCM-APO-PPS, Continuous Production and Multi-Resource Scheduling).
 Location / Products / Resources.
 Sources of supply. e.g. PDS (Alternative PDS should have different resources).
 Multiple orders for the finished product on the same day.

Example Creation
 Product CY-01@Q65002
 Location PL0001@Q65002
 Resource WW-01_0001_001, WW-11_0001_001, WW-21_0001_001,
 PDS

PDS Test 1 is using resource WW-01_0001_001


PDS Test 2 is using resource WW-11_0001_001
PDS Test 3 is using resource WW-21_0001_001
 Multiple orders for the finished product on the same day:

Step 1: Check Customizing


In transaction SFW5, activate business function SCM-APO-PPS, Continuous Production and Multi-Resource Scheduling
(SCM_APO_PPDS_PI).
Step 2: Setup Heuristic
In transaction /SAPAPO/CDPSC11, copy heuristic SAP_MULT_SCH to be ZAP_MULT_SCH with the following settings:
Step 3: Include the heuristic in heuristic profile

Step 4 Run the heuristic in PP/DS Planning board


4.1 Goto transaction /SAPAPO/CDPS0, Select the overall profile SAP001 and planning version 000. Enter the resource,
location, and product in which the orders exist. Execute.
4.2 In "Profiles...", change to use heuristic profile SAP001 with Customizing ID MULT:
4.3 Select the product with the orders. Go to Functions -> Heuristic -> Multi-Resource Scheduling Heuristic and run the
heuristic.
4.4 The orders are scheduled in alternative modes, and different sources of supply are chosen after the switch over time.
FAQ
1. Does SAP_MULT_SCH heuristic works in MTO scenario?
Answer: Yes.
2. SAP_MULT_SCH needs alternative PDS/PPM, should they have exact same structure? (e.g. should they have same
operation number, only different resource in the mode?)
Answer: It can be different. However, it is good to have same structure as it checks alternatives.
3. Is it ok if the PDS have several operations, but only one operation uses different resource?
Answer: Yes, but selection of objects during scheduling has to be carefully selected and the results to be analyzed as it might
be complex to understand in such situations.
4. We define period in the heuristic. Should the period cover the whole order? That is, the length of the period should be
enough to cover order’s start and end date.
Answer: Yes.
5. The heuristic needs multiple orders for the finished product on the same available date. How about order available time? Do
they need to be on same available time?
Answer: In Case of bucket capacity, time would not be a concern on the same day. In case of Time continuous capacity yes.