Check List For Installation of Earthing System: Contractor: Sub-Contractor

Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 4

CHECK LIST FOR INSTALLATION OF EARTHING SYSTEM

Contractor : Form No:


Rev No:
Sub-Contractor : Page: 1 of

SECTION OF WORK: LOCATION:

LEVEL:

Checked by Checked by
Stage Item

Check against approved electrical shop


drawings.

Pre-installation Check if the sleeve level and thickness of


the pipes are as per approved shop
drawings. Seal all sleeves as per
specification.
Check if sizes of the earthing wires are as
per the approved shop drawing.
Check cable trays, trunking, and equipment
Equipotentially bonded as per project
specification.
Check if locations and sizes of earth bar are
as specification and approved shop
drawings.
Check if that earthing wire(s) is connected
Earthing System to equipment as per shop drawing in proper
Installation way.

Check the level & location of earth pit as


per approved shop drawings.

Check if earth pit fixing is as specification


and approved shop drawings.

Check the connection(s) of earthing wire to


earthing rod electrode.

Check if earthing resistance reading is less


than 1 Ohm and submit earth resistance
Testing report.
Check Earth Continuity test for all metal
parts and equipment of building.

Sub. Cont. Date: Contractor Date: Consultant

Name: Sign: Name: Sign: Name: