Job Safety Analysis Worksheet

The document is a job safety analysis worksheet that identifies potential hazards and required safety controls for various construction tasks. It lists tasks such as excavation, wall setup, dismantling formwork, and piping work. For each task, potential hazards are identified such as falling, tripping, sharp edges, and noise. Controls like using protective equipment, maintaining clean work areas, and having railings on excavations are described. The analysis aims to make jobsites safer by planning for hazards in advance.

Uploaded by

SAHIL SHARMA
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
242 views4 pages

Job Safety Analysis Worksheet

The document is a job safety analysis worksheet that identifies potential hazards and required safety controls for various construction tasks. It lists tasks such as excavation, wall setup, dismantling formwork, and piping work. For each task, potential hazards are identified such as falling, tripping, sharp edges, and noise. Controls like using protective equipment, maintaining clean work areas, and having railings on excavations are described. The analysis aims to make jobsites safer by planning for hazards in advance.

Uploaded by

SAHIL SHARMA
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 4

JOB SAFETY ANALYSIS WORKSHEET

Ref No: CU/NES/MAN/JSA/001 Date :-

NAME OF MASTER EMPLYOER:

Project:

Location:

The type of work, nature of work:

The tools and machineries used:

The training and skill required for the job: Safety induction training, Safe practices and JSA Briefing before starting
the erection work.

Personal Protective Equipment Required: Safety Shoes, Hard hat, Hi vis. reflective Jacket, Safety goggles, Hand
gloves, mouth mask, Safety harness

Prepared By:

Reviewed by:

Approved by:

Job Step Hazards Identified Controls Required Training PPEs Needs Action By/Record

Work place set up &  Slip and trip  Engage trained/inducted workforce for
pit area dismantling of person the task Site Engg./ Sup
with breakers.  Poor house  Stack the material in arranged manner.
keeping  Maintain good housekeeping.
 High noise  Use ear plug
area

Boring in R.W.H pit  Slip and trip  Maintain good housekeeping at work
hazard. place. Site Engg./ Sup.
 Fall of  Carry the load according to personal
material and capacity if the load is more than 25 kg
fall of person.
then seek the help of other workers.
 High noise
area  Wear job specific personal protective
equipment (hand gloves, safety shoes,
ear plug,hardhat, gumboot etc.)
 All material should be stack in proper
place.
 All stacking material should be
barricaded.
Excavation of pit  Fall of side  Wear job specific and excavation with
area with help of soil in pit slop Site Engg./ Sup.
Jcb. & manually.  Carry the load according to personal
.
capacity if the load is more than 25 kg
 Fall of person
then seek the help of other workers.
from height
 High noise  Use full body safety belt if height is
area. more then two meter.
 Working area should be hard
barricaded.
 Don’t stack lose material on height.
 Use stair with railing both sides enter
the pit.

 Dressing  Slip and trip  Use stair with railing both sides enter
 Layout of person the pit. Site Engg./ Sup.
 Bar binding  Poor house  Engage trained/inducted workforce for
 Pcc work keeping the task
 Fall of person  Stack the material in arranged manner.
from height
 Maintain good housekeeping.
 Area should be barricaded and display
warning signage’s.
 Wear job specific personal protective
equipment (hand gloves, safety
shoes,,hardhat, etc.)
 Use full body safety belt if height is
more then two meter.

steel cutting &  Flying chips,  Use job specific PPEs ( like hand
wooden cutting for material gloves, safety shoes, safety Site Engg./ Sup.
wall setup.  Fire and goggles,face shield.ear plug etc. )
explosion  Use fire cylinder cutting steel or
hazards wooden area.
 Electrical
 Use Every electrical equipments should
hazards&
be inspected.
Noise
 Only trained person perform task jobs.
.

Wall setup inside pit .


 Slip and trip
of person
• Use stair with railing both sides enter
Site Engg./ Sup.

 Poor house the pit.


keeping • Stack the material in arranged manner.
 Cut with Maintain good housekeeping
sharp edges
• Use iron cap in sharp steel edges.
Wall casting  Slip trip  Clean area and use pies casting wall
hazards work Site Engg./ Sup.
 Noise  Use ear plug when machine running.
hazards

Dismantling  fall of material  dismantling of shuttering use proper


shuttering  sharp edges tools and clean area. Site Engg./ Sup.
cut  Material should we properly arranged
in storage area.

Refilling of soil out  Slip trip & fall  Area should be barricaded and display
side the tank  Poor warning signage’s . Site Engg./ Sup.
housekeeping  .Refill the soil outside the tank properly
clean and dressed.
 Use properly ppe’s ear plug hard
helmet, safety shoes ,dust mask, etc.

oil trap chamber  Slip trip fall  Set up ground level


layout & pcc  Cut with  Bar binding working use iron cap on Site Engg./ Sup.
manually. sharp edges steel
• Do not lift the weight more than 25 kg.

• Use ppe’s gloves, goggles, hard helmet,


etc.

shuttering of tank  Fall from  Use full body safety belt and life line
slab & bar binding. person for while fixing hard pole. Site Engg./ Sup.
height  No lose item should be place on height.
 Cut with
 Display warning signage.
sharp edges.
 Area should be barricaded.
 Use cap in steel edges.

dismantling road  High Noise  Use ear plug breaker works.


main chamber to oil Area  Area barricaded Site Engg./ Sup.
trap chamber with  Slip trip fall  Housekeeping maintain.
breaker & remove
soil oil trap chamber
.
ss pipe setup oil trap  Slip tip  Area should be barricaded and display
chamber to main hazards warning signage’s. Site Engg./ Sup.
chamber &   Use ppe’s safety shoes hard helmet
etc.

shuttering bar  fall of material  Every material should be properly lifted


binding main drain  Cut with  Area should be barricaded and display Site Engg./ Sup.
chamber sharp edges warning signage’s.
l
 Use proper ppe’s
casting tank slab /oil  Fall of object.  Area should be barricaded and display
trap chamber/main  Slip trip warning signage’s . Site Engg./ Sup.
drain chamber hazards  Must use of tool kit.
 Poor  No lose item should be place on height.
housekeeping
 Casting with rmc vehicles and install
the pipe line to connect with pump.
 Rmc vehicles properly guarding
 Clean all working area