Groupwide Master Service Agreement (Msa) For Integrated Turnaround Main Mechanical & Maintenance Mechanical Static (Ta4Ms)
Groupwide Master Service Agreement (Msa) For Integrated Turnaround Main Mechanical & Maintenance Mechanical Static (Ta4Ms)
Groupwide Master Service Agreement (Msa) For Integrated Turnaround Main Mechanical & Maintenance Mechanical Static (Ta4Ms)
REVISION NO: 00
DISMILLAR MATERIAL DATE REVISION 1st August 2019
SCIENCE TECH SOLUTION SDN BHD
Project:
Document Title:
1/6
SPECIFIC REPAIR PROCEDURES DOCUMENTNO: STS/QAC/SRP/02
REVISION NO: 00
DISMILLAR MATERIAL DATE REVISION 1st August 2019
SCIENCE TECH SOLUTION SDN BHD
Controlled document: No part of this document may be printed or reproduced for external purposes without
the written permission of the management appointee of Science-Tech Solutions Sdn Bhd.
1. SCOPE
a) This procedure provides guideline for replace the joint carbon steel type connection And the stainless steel plate
leaked activities in accordance with
e) ASME Section IX
f) ASME V
2/6
SPECIFIC REPAIR PROCEDURES DOCUMENTNO: STS/QAC/SRP/02
REVISION NO: 00
DISMILLAR MATERIAL DATE REVISION 1st August 2019
SCIENCE TECH SOLUTION SDN BHD
a) STS/WPS/01/104-1 (GTAW)
b) STS/WPS/01/104-2 (GTAW)
4. MATERIAL
NOTE: Visual inspection and evaluation shall be as UW-42 or UW-38 (ASME Section VIII, Div.
Dye Penetration Testing or Magnetic Particle Testing as per Appendix 6 or Appendix 8. (ASME Section VIII, Div.)
5. PREPARATION
a) All weld seams and defective area should be power brushed or solvent to remove any rust, dirt, grease, oil etc.
b) Part need to be securely anchored because heat generated from the weld can loosen clamps and cause bad weld or
injure the welder
c) Grinding Disc / wire brush must be a suitable type to the material of equipment repair. ( segregation on storage of
stainless steel wire brush and disc )
d) All sharp edges shall be carefully ground to remove sharp edges. Extra care should be given not to damage the
nearby area.
e) The pipe should be cut to 111mm length and 1piece stainless steel plate diameter 60mm
f) Welding repair process shall be strictly complying accordingly with the following documents (refer attachments)
which are relevant and approved by an authorized party before work started
6. WELDING EQUIPMENT
3/6
SPECIFIC REPAIR PROCEDURES DOCUMENTNO: STS/QAC/SRP/02
REVISION NO: 00
DISMILLAR MATERIAL DATE REVISION 1st August 2019
SCIENCE TECH SOLUTION SDN BHD
a) All welding power source used in the performance of production welding to this specification shall be of DC constant
current type and shall be of DC current type and shall be capable of maintaining a uniform output throughout their
entire operation range.
7. WORKFLOW
4/6
SPECIFIC REPAIR PROCEDURES DOCUMENTNO: STS/QAC/SRP/02
REVISION NO: 00
DISMILLAR MATERIAL DATE REVISION 1st August 2019
SCIENCE TECH SOLUTION SDN BHD
8. PIC OF INSPECTION
5/6
SPECIFIC REPAIR PROCEDURES DOCUMENTNO: STS/QAC/SRP/02
REVISION NO: 00
DISMILLAR MATERIAL DATE REVISION 1st August 2019
SCIENCE TECH SOLUTION SDN BHD
TAG NO:4200-P-001-D
9. SKETCH
7/6
SPECIFIC REPAIR PROCEDURES DOCUMENTNO: STS/QAC/SRP/02
REVISION NO: 00
DISMILLAR MATERIAL DATE REVISION 1st August 2019
SCIENCE TECH SOLUTION SDN BHD
111mm
Joint Detail
Joint 1 - Single V
NDT Method
DPI required
8/6
SPECIFIC REPAIR PROCEDURES DOCUMENTNO: STS/QAC/SRP/02
REVISION NO: 00
DISMILLAR MATERIAL DATE REVISION 1st August 2019
SCIENCE TECH SOLUTION SDN BHD
9/6