Assignment 1 CTM2019

This document contains an assignment with 8 questions related to project scheduling and network diagrams. Question 1 involves drawing a bar chart and network diagram for a 10 event project plan. Question 2 asks to draw a network diagram based on specified predecessor relationships. Question 3 involves drawing a bar chart for a multi-activity project with specified durations and precedence relationships. It also asks for the expected completion date and progress report on a given date. Question 4 provides predecessor relationships for 20 jobs labeled A to T and asks to develop the network. Question 6 gives precedence relationships between 11 events labeled A to M and asks to draw the PERT network. Question 7 asks to number the events of a given network using Fulkerson's rule. Question 8 asks to explain

Uploaded by

Kaushal Kumar
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
129 views2 pages

Assignment 1 CTM2019

This document contains an assignment with 8 questions related to project scheduling and network diagrams. Question 1 involves drawing a bar chart and network diagram for a 10 event project plan. Question 2 asks to draw a network diagram based on specified predecessor relationships. Question 3 involves drawing a bar chart for a multi-activity project with specified durations and precedence relationships. It also asks for the expected completion date and progress report on a given date. Question 4 provides predecessor relationships for 20 jobs labeled A to T and asks to develop the network. Question 6 gives precedence relationships between 11 events labeled A to M and asks to draw the PERT network. Question 7 asks to number the events of a given network using Fulkerson's rule. Question 8 asks to explain

Uploaded by

Kaushal Kumar
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 2

Assignment # 01 Date : 09/08/2019

CTM Due Date: 17/08/2019 (11:55 PM)

Qno. 1. A Project plan consisting of 10 events having predecessor relationships as under:

Event Immediate Duration Event Immediate Duration


Predecessor (weeks) Predecessor (weeks)
1 - 2 6 3, 5 2
2 1 3 7 3, 4 3
3 2 1 8 3, 7 1
4 2 2 9 7 3
5 2 4 10 3, 6, 8, 9 2
Draw the (a) Bar Chart Diagram (b) Network Diagram for the Project Plan.

Qno. 2. Draw the network for the following case,

i. A and D start at origin


ii. C follows A but precedes G
iii. B follows A but precedes F
iv. H follows D but precedes L
v. E follows B and C
vi. K follows G and H
vii. J follows F but precedes K
viii. K, L and E are terminal activities.
ix. F is independent of C
x. L is independent of J

Qno. 3 (a). The following project is to be represented by a bar chart. The duration for
each activity is in days. Thease are the actual work days. The project commences on
Wednesday, November 15, with five work days a week. Draw the bar chart with the
horizontal scale denoting calendar dates.
Activity 1 8 days
Activity 2 4 days
Activity 3 7 days
Activity 4 9 days
Activity 5 3 days
Activity 6 3 days
Activity 7 14 days
Activity 8 17 days
Activities 1 and 2 can occur concurrently, Activity 3 can take place after activity 2 is
completed. Activities 4, 6 and 3 can occur concurrently. Activity 8 can start 4 days after the
commencement of activity 6. Activity 7 should follow activity 5. Activity 5 can begin
concurrently with activity 8.
(b). On what calendar date can we expect the project to be completed?
(c). On December 3, what is the progress report?

Kaushal Kumar JUIT, Waknaghat


Assignment # 01 Date : 09/08/2019
CTM Due Date: 17/08/2019 (11:55 PM)

Qno. 4. A Project manager was interested in developing a network for a project involving 20
jobs labeled from A to T. He listed all its predecessors as best as he could determine as
indicated below.
Immediate Immediate
Job Job
predecessor predecessor
A - K G
B - L F, G, K
C - M H, I
D A, B N H, I, J, L
E A, B, C O J, L
F A, B, C P M, N
G C Q O, P
H D, E R O
I D, E, F S Q, R
J F, G T S
Qno. 6. In a construction project, events have been identified as A, B, C, D, E, F, G, H, J, K, L
and M. A is the start event, B occurs after A; C succeeds B and precedes L but restrains the
occurrence of G; D occurs after B, before K and restrains C; F succeeds C, precedes H and
restrains E; E succeeds B but precedes J; G success F and precedes H; H precedes L and
restrains J; L occurs after J but before K; M succeeds K. Draw a PERT network. Number the
events according to Fulkerson’s rule.

Qno. 7. Using Fulkerson’s rule, number the events of the network shown in the figure below

Qno. 8. Explain various types of ‘errors’ related to network diagram.