Detailed Quty. For R/R Wall Estimate As HPPWD Shedule Rate 2019

This document provides a cost estimate for random rubble (RR) wall construction. It lists 7 items with quantities and rates. The total estimated cost is Rs. 1,014,464 (Rupees One Million Fourteen Thousand Four Hundred Sixty Four only). The estimate includes costs for excavation, concrete work, RR masonry construction, weep holes, PCC work and a 60% premium for work.

Uploaded by

rahul
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLS, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
150 views6 pages

Detailed Quty. For R/R Wall Estimate As HPPWD Shedule Rate 2019

This document provides a cost estimate for random rubble (RR) wall construction. It lists 7 items with quantities and rates. The total estimated cost is Rs. 1,014,464 (Rupees One Million Fourteen Thousand Four Hundred Sixty Four only). The estimate includes costs for excavation, concrete work, RR masonry construction, weep holes, PCC work and a 60% premium for work.

Uploaded by

rahul
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLS, PDF, TXT or read online on Scribd
You are on page 1/ 6

Detailed quty.

For r/r wall estimate as hppwd shedule rate 2019


S.NO. ITEMS no. L B H qty. t.qty unit Rate
1 Cutting in earth work and disposal of
excavated earth upto lead of 20m
Pick/Jumper work = 1.43sqm 1 20 8.94 6.61 590.934 590.934 cum 163.5

2 Excavation in foundation trenches


etc.In earthwork lift up to 1.5 metres
stacking the excavated soil not more
than 3 meters clear from the edge of
the excavation and then returning
the stacked soil in 15 cm layers
when required in to plinth sides
of foundation etc. pick/jumper =1.71sqm 1 20 2.93 0.6 35.16 35.16 cum 180.5

3 Providing and laying cement


concrete 1:4:8(1cement 4sand
18 graded stone aggregate 40mm
nominal size) and curing complete
excluding the cost of form work
in foundation . ( for r/r work) 1 20 2.93 0.3 17.58 17.58 cum 2300.65
4 Random rubble masonary/ polygonal rubble

masonary ( uncoursed / brought to course)

with hard stones of approved quality in

foundation and plinth including

plinth level in cement mortar

1:5 (1 cement : 5 sand) 1 20 2.3 1.23 56.58


1 20 1.87 1.25 46.75
1 20 1.43 1.25 35.75
1 20 1 1.31 26.2
165.28 cum 2563.5
5 Providing P.C.C. bonds
in the wall (1:4:8) ( 1 cement: 1 20 2.12 0.15 6.36
4 sand : 8 graded stone aggerigates 20mm 1 20 1.65 0.15 4.95
nominal size ) 1 20 1.21 0.15 3.63
14.94 cum 2563.5
6 Providing weapholes in brick masonary/
stone masonary/ plain reinforced concrete
abutment, wing wall return wall with 100mm
dia P.V.C pipe extending through the full
with of the structure with slop 1 (v) : 20(h)
towards drawings and technical
specifications 4 10 40 40 nos 253.7

7 Laying of P.C.C. layer at top surface of wall 1 20 0.78 0.19 2.964 2.964 cum 2300.65
(1:4:8) ( 1 cement:4 sand : 8graded stone
aggerigates 20mm nominal size )

total
Add 60% work premium
add 3% contingencies charges
G.total
or Say
TEN LAKH FOURTEEN THOUSAND FOUR HUNDRED SIXTY FOUR ONLY

Prepared By:-
Amount

96617.709

6346.38

40445.427
423695.28

38298.69

10148

6819.1266
622370.61
373422.37
18671.12
1014464.10
1014464
`