Republic of the Philippines

Department of Education
Region 02
SCHOOLS DIVISION OF CAGAYAN
Aparri West District
ZINARAG ELEMENTARY SCHOOL

BRIGADA ESKWELA
PHYSICAL FACILITIES AND MAINTENANCE NEEDS ASSESSMENT FORM
Instruction: Conduct an occular inspection of the school physical below. Then provide the needed information to facilitate the improvement to be done on these identified facilities. ( if needed,
you may use separate forms for each classroom or school facility.)

CONDITION REMARKS Nature of improvement Material Manpower Needed


(Check One) Needed (eg. Repair, Resources (Indicate Quality and
FACILITIES Satisfactory Unsatisfactory If unsatisfactory, repainting, Needed nature of labor service
describe the problem replacement, etc) ( Indicate kind and quality) needed)
 Roofs/Gutters  Corroded roofs, gutters Replacement, repainting Gutter, paint, nail, sealant, GI sheets 2 laborers/contractual
 Ceilings  Termite infested Replacement Plywood, nail, paint, lumber 2 laborers/ contractual
 Walls  Termite infested Replacement Plywood, nail, paint, lumber 2 laborers/ contractual
 Blackboards  Unpainted Repainting paint Contractual
 Chairs/desks/tables  Unpainted, destroyed Repainting, repairing Paint, nails Contractual
 Water  Incomplete water Installation of additional PVC, sealant, gauge, knots, elbow 2 laborers/contractual
facilities/Drainage facilties water facilities
system
 Signage  No signages posted Reproduction of Tarpauline print, plywood, nail, paint Contractual
signages
 School Garden  Unmaintained gardens Landscaping and Underbrushing Parents, volunteers
underbrushing
 Lighting  Insufficient Replacement, repair of Electric wires, bulb, switch, electrict 2 laborers/contractual
faulty wiring tape, u-nail
 Windows  Broken glasses, poor Replacement of broken Glass, aluminum brace 2 laborers/contractual
foundation due to age glasses
 Doors  Worn out, poor Repair of doors, Plywood, nail, paint, plain GI sheet 2 laborers/contractual
foundation, termite repainting
infested
 Comfort rooms  incomplete Construction, repair of Cement, CHB, round bars, gravel and 3 laborers/contractual
unserviceable toilet sands
bowls
 School Grounds  Unmaintained Underbrushing, Cleaning tools Parents/ contractual
trimming of trees
 School  Delapidated construction Cement, CHB, round bars, gravel and 6 laborers/contractual
Canteen/Clinic sands, GI sheets, lumber, nails
 School Fence/wall  Unpainted Repainting Paint , paint brush 2 laborers/ contractual
 Electricity  Worn out Replacement Electric wires, switch, junction boxes, 2 laborers/ contractual
electric tapes, u nail,
 Alternative Gate  Unpainted Repainting Paint, paintbrush 2 laborers/ contractual
 Reference  Incomplete Request for allotment of Letter to the division office School head
Materials books
 Laboratory  Incomplete Request for the delivery Letter to the division office School head
Equipment of Science equipments
 School Stage  Corroded roofs Replacement GI Sheets, lumber, nails 6 laborers/ contractual
Erroded floors Replacement Gravel and sand, cements, iron bars

Prepared by:

MARIEDEL C. LORENZO ______________ RONNIE F. TEJANO


School Physical Facilities Coordinator Date of Inspection Master Teacher I & In-Charge