Design and Build
Design and Build
Engineering, procurement, and construction (EPC) contracts, sometimes called turnkey contracts are
similar to design and build contracts, in that there is a single contract for the design and construction of
the project, but generally with an EPC contract, the client has less say over the design of the project and
the contractor takes more risk.
On a design and build project, the client may produce an outline design upon which tenders are sought.
On an EPC project, the client may seek tenders based on a performance specification and then have no
input into the design, other than if variations are instructed.
Payment can be on a lump sum, cost reimbursable basis, or some other basis, but generally
the client would be likely to seek a fixed price, lump sum agreement where the responsibility for cost
control is taken by the contractor. This gives the client a relatively risk-free arrangement, with one point of
responsibility and cost certainty. They can therefore operate the contract with the minimum resource.
The clients main risk lies in the definition of the specification upon which the contract is based. If
the specification is not well developed and concise otherwise the quality and performance of the
completed development may be compromised (see performance specification and output-based
specification for more information)
Generally, EPC contracts are used on engineering and infrastructure projects, or industrial projects,
where the aesthetics of design might be considered less important to
the client than performance and cost certainty.
The FIDIC Conditions of Contract for EPC Turnkey Projects (The Silver Book) is an example of
an engineering procurement and construction contract.
When planning a new data center project, the most important decision is who we are
making responsible for such an important project. What is better? A turnkey project, same contractor designing
and building the data center or hiring an independent consultant for the design, and a contractor to build it.
The turnkey option has been used for a long time, mainly in building civil infrastructure projects, or with public
and governmental bids, or when the project has a high level of complexity and there is a well-defined scope on
behalf of the owner. But in recent years it has been used indiscriminately in contractual processes of IT projects,
On the other hand, a “design and build” project seeks to separate the design from the construction and
implementation process. By previously creating a design – this may be conceptual or detailed engineering
drawings-, the preliminary studies and technical specifications are tailored to the requirements of the project and
of the customer, so that bidders interested in building will have enough information and adequate specs to prepare
their proposals accordingly, minimizing or eliminating assumptions that are required in order to develop this
turnkey project.
Both of these options are valid, however, there are some advantages and disadvantages on both options. While
The advantages of a turnkey project, some of which are misguiding and the opposite ends up happening:
1. Reduced total time during the contractual process by having just one process instead of two separate
ones. This does not necessarily imply less construction time.
2. A seemingly “lower cost” when integrating “all” the elements under one provider.
3. Minimizing orders of change (those of which generate more costs against the contractor) during the
implementation of the project because the changes and adjustments fall under responsibility of the
only contractor.
4. This is a practical solution for smaller projects, such as communications rooms or small computer
rooms, these usually have a limited budget for the project.
5. Definitely, the main advantage of this service is the peace of mind the owner gets when it hands over
full responsibility of the project to “only one contractor”, it is much easier for the owner to manage and
communicate with one provider, which means “one neck to choke”.
The greater responsibility assumed by the only supplier, ironically is what causes most of thedisadvantages in
Finally, when assigning full responsibility of the project, the owner gives up all rights to interfere and control
the project, and things such as topology, specs, scalability etc. as well as the materials and equipment that needs
to be employed.
On the other hand, assuming that the company that designs does not have any conflicting interests in the
implementation phase and expecting it to be really independent from the construction companies,
by the owner regarding the technology, materials and equipment to be implemented, and there is more knowledge
gained on the capacities and scope of the physical infrastructure. In this case, the savings go to the owner and
There is no such thing as a perfect recipe to design and build a data center, every company and team assigned to
each project will have different standards on what is more important for them and the project. For example,
complying with the budget, the time to market or have the best data center, no matter the cost or what it takes. On
the contrary, it is fundamental for the people responsible of data center projects to measure well the advantages
and disadvantages of both options, to decide which method is more convenient in accordance to the interests and
Design-build is typically used when an opportunity exists for the owner or agency
to save time by having construction begin before the final design has been
completed. By contrast, in the traditional system of design-bid-build, the owner
contracts separately with a designer and a builder, and the design must be
completed before the owner puts out a call for construction bids. By combining
both aspects of project delivery under a single agreement, and thus a single
bidding process, design-build can save time and, in some cases, money for the
owner.
Characteristics of Design-Build
The defining characteristic of design-build contracts is simply the presence of
only one contract. All other types of standard construction contracts include at
least two contracts. Design-build is often described as "single-source" or "sole-
source" contracting. If there is a problem or change with either the design or the
construction, the owner works with a single source—the contractor—for
resolution or approval.
Turnkey delivery does not remove the Agency from the equation; they are
present throughout the Design-Build process, attend all design and
construction meetings, and exercise a large degree of control over the
direction of the project. While profoundly involved throughout the entire
process, the Agency’s time is leveraged by the expertise of the development
team for greater efficiency. With the aid of the development team, the Agency
avoids the minutia of the process while maintaining focus on their end-product
goals. Design approval is verified through a design review process, where the
Agency has the opportunity to review and approve the design packages
created by the Design-Build team. During construction, the Agency can retain
3rd party inspectors and commissioning agents to independently verify that
the Design-Build team is meeting all the requirements of the agreement. In
this way, the Agency can maintain laser focus on meeting all of the objectives
of the project end-users.
Throughout the design and construction process, it is essential for the Agency
to establish its level of involvement. One Agency may want to actively
supervise the Design-Build process, while another may only want to be
involved during key design phases. Turnkey delivery offers varying degrees of
project involvement and consistently delivers on cost and schedule
guarantees.
Another exciting feature of turnkey delivery is that it offers the Agency more
opportunity to provide input into design refinements focused on the
experience of the facility end-users. The integrated Design-Build approach of
turnkey delivery allows design refinements to be incorporated more quickly,
reducing any cost or schedule impacts to the project. As detailed in the case
study on page 15, the use of mock ups enable design refinements to be made
in real time with input from actual users of the planned space. If decisions
cannot be made regarding future refinements, the project team can make
provisions to accommodate the refinements at a later date. The use of a
collaborative team approach can extend to senior level leadership when a
special executive leadership team is established. This partnering approach
ensures all members of the project team are aligned and able to determine
the course of action when the unexpected occurs.
What is EPC?
“Engineering, Procurement, and Construction” (EPC) is a particular form of contracting
arrangement used in some industries where the E P C Contractor is made responsible
for all the activities from design, procurement, construction, to commissioning and
handover of the project to the End-User or Owner.
The engineering and construction contractor will carry out the detailed engineering
design of the project, procure all the equipment and materials necessary, and then
construct to deliver a functioning facility or asset to their clients. Companies that
deliver EPC Projects are commonly referred to as EPC Contractors.
What is a turnkey project?
One of the special modes of carrying out international business is a turnkey project. The
turnkey projects meaning, a contract under which a firm agrees to fully design, construct
and equip a manufacturing/ business/ service facility and turn the project over to the
purchaser when it is ready for operation for remuneration.
The term turn-key project (Turn-key delivery) describes a project(or the delivery of such)
in which the supplier or provider is responsible to the client for the entire result of the
project and presents it to the client completely finished and ready to use.
The term turn-key project (Turn-key delivery) describes a project ( or the delivery of
such) in which the supplier or provider is responsible to the client for the entire result of
the project and presents it to the client completely finished and ready to use. In fact, the
client should be able “just to turn the key.” The supplier of a turn-key project is called the
general contractor (or main supplier, direct supplier or main contractor). Synonyms for
the term turn-key project are a turn-key solution, turn-key delivery, or ready-to-use.
The turn-key project is usually very complex and may involve the development and
design, the production and the delivery and set-up or installation of the project.
Related Posts
Tips For Driving Down Fleet Fuel Bills
Keys to Managing an Electrical Contracting Business
Human engineering skill – will it be replaced by computers?
The Best Flow Meters For Oil And Gas Measurement
These jobs for engineering, procurement and construction are useful but they can
involve some great differences. It is good to see what differences can be found
between EPC and turnkey contracting.
The first thing involves the depth of the project that is being handled. An EPC project
will involve a contractor working with basic engineering procedures. This can work to
help with ensuring that a business will be set up properly with the right engineering
plans for great needs.
A turnkey project will involve more specific rules for technical procedures. This is often
used to help make it a little easier for a person to handle more types of controls without
an issue getting in the way of things.
The next difference involves who is responsible for getting a design for EPC and
turnkey contracting ready. An EPC plan will involve the contractor getting a full design of
a system ready to where it will be more effective and easy to read. Meanwhile, a
turnkey process will involve a contractor dealing with special considerations for handling
property and the contractor designing things based solely on the type of specifications
that come with the property.
There is also the point about the contractor having to work with assigning the right
people for the construction process. An EPC process will involve that contractor working
to get another party to get the startup construction process handled. The turnkey
process will involve the contractor being fully responsible for every single part of what is
going on here. This is often used to help make it a little easier for a property to be
arranged as carefully as possible for getting engineering plans ready.
The interesting point about getting EPC and turnkey contracting plans going comes
from how they are both ones that work with getting different kinds of procedures to work
with different costs in mind. However, the total cost of getting EPC and turnkey
contracting India ready should be the same regardless of the type of control that is
being handled in the process. This is a very interesting point that makes it a little easier
for anyone to get contracting functions handled for all kinds of business purposes
around India.
The differences that come between EPC and turnkey contracting are great points that
must be seen when trying to find ways of how to get different kinds of procedures
handled. This is used as a means of helping to see how it works and whether or not a
person is going to be controlled as well as it can for the best possible needs that a
business will have.
Thus if all components E, P & C are awarded to the same company, it is, in essence, an
EPC turnkey project.
Conclusion
So in short EPC is a contract comprising Engineering, Procurement, and Construction.
If you look at the definition, you may find no difference between two concepts, but there
are some differences between two concepts as follows;
1- In EPC, an employer will provide basic engineering to a contractor and the latter shall
perform detailed design based on a received basic design.
2- In Turnkey, Employer will only provide certain technical specifications of the project
and it is the responsibility of the contractor to prepare basic and detail design of the
project.
References:
https://epcandturnkeycontracting.weebly.com/
https://www.quora.com
https://www.wikipedia.org/