This document provides a sample schedule for the construction of a 6,000 square foot custom home. It outlines 48 tasks across 6 phases of the project, from contracts and document review through to foundation work. Key details include dividing the project into components, estimating time needed for each, and including hours for supervision. The schedule accounts for inspections, permit processes, and shows how cash flow is tied to completion of milestones. Actual schedules may vary based on project specifics, site conditions, availability of materials and contractors, and inevitable changes during construction.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
96 views13 pages

Man-Hour Productivity: Manuel L. Quezon University

This document provides a sample schedule for the construction of a 6,000 square foot custom home. It outlines 48 tasks across 6 phases of the project, from contracts and document review through to foundation work. Key details include dividing the project into components, estimating time needed for each, and including hours for supervision. The schedule accounts for inspections, permit processes, and shows how cash flow is tied to completion of milestones. Actual schedules may vary based on project specifics, site conditions, availability of materials and contractors, and inevitable changes during construction.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 13

MANUEL L.

QUEZON UNIVERSITY
School of Architecture

MAN-HOUR
PRODUCTIVITY

Submitted by:

Garduque, Rafaella Nette B.

15-00568

Submitted to:

Ar. Edgar M. Chavez

SP 2 Professor
How to Calculate Man Hours
Estimating Man-Hours for a Project Bid

 Divide your project into components


 Determine the type of workers you need
 Estimate the time needed to complete each component
 Include hours for supervisors.
 Use your estimates to prepare a project timeline
 Prepare and submit your bid
 Adjust your man-hour estimates as the work progresses

Reporting Man Hours for Contract Jobs

 Collect information on your workers


 Track your workers’ time
 Send your client payroll reports at regular intervals
 Use your records to prepare future estimates

A Sample Residential Construction Schedule - (for a 6,000 square foot custom


home)

Notice that because construction draws from the lender typically follow the
completion of various phases, or milestones, the cash flow on a project can be very irregular.
While the money flowing out of a construction company; for employee salaries, benefits,
office space, vehicles, insurance, equipment and other company expenses, typically occurs
on a regular calendar based timeline, the money used to pay these expenses follows an
event driven schedule. Therefore, besides the "normal" unplanned events that can affect the
progress of a home building project, it is not uncommon for home builders to rearrange
construction schedules in order to gain access to draw money so that they are able to pay
subcontractors and suppliers in a timely manner.

The actual schedule of completion for your specific project will vary based upon many
factors including, but not limited to, size and degree of difficulty of the structure, site and
weather conditions, material and contractor availability, crew sizes, effective scheduling and
communication, the knowledge and experience of those managing the project, and
perhaps most significantly, the number, timeliness, and complexity of the changes you will
inevitably make to the original contract after construction has already begun.
ID Outline Name Duratio Predecessors Start Finish
Numbe n
r
1 1 Contracts 0.00d . Thu Thu
6/5/14 6/5/14
2 1.1 - Supply Lot 0.00d . Thu Thu
Sale Agreement 6/5/14 6/5/14
3 1.2 - Supply 0.00d . Thu Thu
Construction 6/5/14 6/5/14
Agreement
4 1.3 - Supply 0.00d 3 Thu Thu
Contract Plans 6/5/14 6/5/14
5 1.4 - Supply 0.00d 3 Thu Thu
Contract 6/5/14 6/5/14
Specifications
6 1.5 - Supply 0.00d 3 Thu Thu
Contract Site 6/5/14 6/5/14
Plan
7 1.6 - Secure 0.00d . Thu Thu
Financing 6/5/14 6/5/14
8 1.7 - Construction 0.00d . Thu Thu
Loan Settlement 6/5/14 6/5/14
9 2 Document 25.00d . Thu Wed
Review & 6/5/14 7/9/14
Revision
10 2.1 - Review & 15.00d 4 Thu Wed
Finalize Plans 6/5/14 6/25/14
11 2.2 - Review & 20.00d 5 Thu Wed
Finalize 6/5/14 7/2/14
Specifications
12 2.3 - Review & 1.00d 6,10 Thu Thu
Finalize Site Plan 6/26/14 6/26/14
13 2.4 - Print 5.00d 10,11,12 Thu Wed
Construction 7/3/14 7/9/14
Drawings
14 2.5 - Approve 0.00d 13 Wed Wed
Revised Plans 7/9/14 7/9/14
15 2.6 - Approve 0.00d 13 Wed Wed
Revised 7/9/14 7/9/14
Specifications
16 2.7 - Approve 0.00d 13 Wed Wed
Revised Site Plan 7/9/14 7/9/14
17 3 Bids & Contracts 24.00d . Thu Tue
7/10/14 8/12/14
18 3.1 - Make Copies 3.00d 14 Thu Mon
of Plans 7/10/14 7/14/14
19 3.2 - Make Copies 2.00d 15 Thu Fri
of Specifications 7/10/14 7/11/14
20 3.3 - Distribute 1.00d 18,19 Tue Tue
Plans & 7/15/14 7/15/14
Specifications
21 3.4 - Receive Bids 10.00d 20 Wed Tue
7/16/14 7/29/14
22 3.5 Review Bids 5.00d . Wed Tue
7/30/14 8/5/14
25 3.6 - Execute 5.00d 23 Wed Tue
Subcontractor 8/6/14 8/12/14
Agreements
26 4 Grading & 17.00d . Thu Fri
Building Permits 7/10/14 8/1/14
27 4.1 - Schedule lot 1.00d 13 Thu Thu
stake-out 7/10/14 7/10/14
28 4.2 - Stake lot 1.00d 27FS+3d Wed Wed
7/16/14 7/16/14
29 4.3 - File Grading 1.00d 16 Thu Thu
Permit 7/10/14 7/10/14
Application
30 4.4 - File Building 3.00d 14,15,16 Thu Mon
Permit 7/10/14 7/14/14
Application
31 4.5 - Post Lot 1.00d 28,29,30 Thu Thu
Identification 7/17/14 7/17/14
32 4.6 - Meet Sed. 1.00d 29FS+2d,28,31 Fri Fri
Control Insp. 7/18/14 7/18/14
33 4.7 - Walk Lot w/ 1.00d 32 Mon Mon
Owner 7/21/14 7/21/14
34 4.8 - Install 1.00d 32,33 Tue Tue
Construction 7/22/14 7/22/14
Entrance
35 4.9 - Install 2.00d 32,33 Tue Wed
Sediment 7/22/14 7/23/14
Controls
36 4.10 - Sediment 1.00d 34,35 Thu Thu
Control Insp. 7/24/14 7/24/14
37 4.11 - Grading 1.00d 36 Fri Fri
Permit Issued 7/25/14 7/25/14
38 4.12 - County 10.00d 30 Tue Mon
Permit Process 7/15/14 7/28/14
39 4.13 - Building 1.00d 38,37 Tue Tue
Permit 7/29/14 7/29/14
Approved
40 4.14 - Pay Permit 1.00d 39FS+2d Fri Fri
Fees and Excise 8/1/14 8/1/14
Taxes
41 4.15 - Building 0.00d 40 Fri Fri
Permit Issued 8/1/14 8/1/14
42 5 Site Work 7.00d . Mon Tue
7/28/14 8/5/14
43 5.1 - Clear Lot 3.00d 37 Mon Wed
7/28/14 7/30/14
44 5.2 - Strip Topsoil & 1.00d 43 Thu Thu
Stockpile 7/31/14 7/31/14
45 5.3 - Stake Lot for 1.00d 43 Thu Thu
Excavation 7/31/14 7/31/14
46 5.4 - Rough grade 1.00d 43,45 Fri Fri
lot 8/1/14 8/1/14
47 5.5 - Excavate for 2.00d 39,45,43,46 Mon Tue
foundation 8/4/14 8/5/14
48 6 Foundation 24.00d . Wed Mon
8/6/14 9/8/14
49 6.1 - Layout 1.00d 47 Wed Wed
footings 8/6/14 8/6/14
50 6.2 - Dig Footings 1.00d 49 Thu Thu
& Install 8/7/14 8/7/14
Reinforcing
51 6.3 - Footing 0.00d 50 Thu Thu
Inspection 8/7/14 8/7/14
52 6.4 - Pour footings 1.00d 51 Fri Fri
8/8/14 8/8/14
53 6.5 - Pin Footings 1.00d 52 Mon Mon
8/11/14 8/11/14
54 6.6 - Stock Block, 1.00d 53 Tue Tue
Mortar, Sand 8/12/14 8/12/14
55 6.7 - Build Block 15.00d 53,54 Wed Tue
Foundation 8/13/14 9/2/14
56 6.8 - Foundation 0.00d 55 Tue Tue
Certification 9/2/14 9/2/14
57 6.9 - Draw #1 0.00d 56 Tue Tue
(Location 9/2/14 9/2/14
Survey)
58 6.10 - Fill Block 1.00d 55 Wed Wed
Cores w/ 9/3/14 9/3/14
Concrete
59 6.11 - Steel Delivery 1.00d 58 Thu Thu
9/4/14 9/4/14
60 6.12 - Set Lintels, 2.00d 59 Fri Mon
Bolts, Cap Block 9/5/14 9/8/14
61 6.13 - Lumber 1.00d 58 Thu Thu
Delivery 9/4/14 9/4/14
62 6.14 - Waterproofin 1.00d 61 Fri Fri
g and Drain Tile 9/5/14 9/5/14
63 7 Rough 44.00d . Tue Fri
Carpentry 9/9/14 11/7/14
64 7.1 - Set Steel 1.00d 60 Tue Tue
9/9/14 9/9/14
65 7.2 - 1st Floor Deck 4.00d 64 Wed Mon
Framing 9/10/14 9/15/14
66 7.3 - 1st Floor Wall 4.00d 65 Tue Fri
Framing 9/16/14 9/19/14
67 7.4 - Draw #2 (First 0.00d 66 Fri Fri
Floor Deck) 9/19/14 9/19/14
68 7.5 - 2nd Floor 2.00d 67 Mon Tue
Deck Framing 9/22/14 9/23/14
69 7.6 - Draw #3 0.00d 68 Tue Tue
(Second Floor 9/23/14 9/23/14
Deck)
70 7.7 - 2nd Floor Wall 3.00d 69 Wed Fri
Framing 9/24/14 9/26/14
71 7.8 - Set Roof 2.00d 70 Mon Tue
Trusses 9/29/14 9/30/14
72 7.9 - Frame Roof 7.00d 71 Wed Thu
10/1/14 10/9/14
73 7.10 - Install Roof 5.00d 72 Fri Thu
Plywood 10/10/1 10/16/1
4 4
74 7.11 - Install 2.00d 73,111 Wed Thu
Windows & 10/22/1 10/23/1
Doors 4 4
75 7.12 - Frame 3.00d 72,81 Fri Tue
Basement 10/10/1 10/14/1
4 4
76 7.13 - Frame 2.00d 75,87,93 Thu Fri
Basement 11/6/14 11/7/14
Bulkheads
77 8 Concrete Slabs 8.00d . Thu Mon
9/18/14 9/29/14
78 8.1 - Basement 2.00d 65,91 Thu Fri
Slab Preparation 9/18/14 9/19/14
79 8.2 - Termite 1.00d 78 Mon Mon
Treatment 9/22/14 9/22/14
Basment Slab
80 8.3 - Slab 1.00d 79 Tue Tue
Inspection 9/23/14 9/23/14
81 8.4 - Pour 1.00d 80 Wed Wed
Basement Slab 9/24/14 9/24/14
82 8.5 - Prep Garage 1.00d 81 Thu Thu
Slab 9/25/14 9/25/14
83 8.6 - Termite 1.00d 82 Fri Fri
Treatment 9/26/14 9/26/14
Garage Slab
84 8.7 - Pour Garage 1.00d 83 Mon Mon
Slab 9/29/14 9/29/14
85 9 H.V.A.C. 17.00d . Fri Mon
10/10/1 11/3/14
4
86 9.1 - HVAC Layout 1.00d 72 Fri Fri
& Measure 10/10/1 10/10/1
4 4
87 9.2 - HVAC Rough- 5.00d 86,111 Wed Tue
in 10/22/1 10/28/1
4 4
88 9.3 - HVAC Set 2.00d 81,87 Wed Thu
Indoor Units 10/29/1 10/30/1
4 4
89 9.4 - HVAC 2.00d 88 Fri Mon
Temporary Heat 10/31/1 11/3/14
4
90 10 Plumbing 37.00d . Tue Wed
Rough-in 9/16/14 11/5/14
91 10.1 - Plumbing 2.00d 65 Tue Wed
Sub-slab 9/16/14 9/17/14
92 10.2 - Plumbing 1.00d 91,87 Wed Wed
Layout 10/29/1 10/29/1
4 4
93 10.3 - Plumbing 5.00d 92 Thu Wed
rough-in 10/30/1 11/5/14
4
94 11 County 0.00d 91 Wed Wed
Plumbing Sub- 9/17/14 9/17/14
slab Inspection
95 12 County 0.00d 93 Wed Wed
Plumbing 11/5/14 11/5/14
Rough-in
Inspection
96 13 Electric Rough-in 19.00d . Fri Wed
10/24/1 11/19/1
4 4
97 13.1 - Set Electric 2.00d 74 Fri Mon
Boxes 10/24/1 10/27/1
4 4
98 13.2 - Install Electric 2.00d 97 Tue Wed
Service Panel 10/28/1 10/29/1
4 4
99 13.3 - Electrical 1.00d 98 Thu Thu
Walk-through 10/30/1 10/30/1
4 4
10 13.4 - Electrical 14.00d 99 Fri Wed
0 Rough-wire 10/31/1 11/19/1
4 4
10 14 Specialty Rough- 5.00d . Thu Wed
1 ins 11/20/1 11/26/1
4 4
10 14.1 - Central 5.00d 100 Thu Wed
2 Vacuum Rough- 11/20/1 11/26/1
in 4 4
10 14.2 - Alarm System 5.00d 100 Thu Wed
3 Rough-in 11/20/1 11/26/1
4 4
10 14.3 - Telephone 5.00d 100 Thu Wed
4 System Rough-in 11/20/1 11/26/1
4 4
10 14.4 - Television 5.00d 100 Thu Wed
5 System Rough-in 11/20/1 11/26/1
4 4
10 14.5 - Audio Visual 5.00d 100 Thu Wed
6 Rough-in 11/20/1 11/26/1
4 4
10 15 County 0.00d 96,101 Wed Wed
7 Electrical 11/26/1 11/26/1
inspection 4 4
10 16 Draw #5 0.00d 95,107 Wed Wed
8 (Rough-ins 11/26/1 11/26/1
complete) 4 4
10 17 County Framing 0.00d 95FS+1d,107FS+1 Thu Thu
9 Inspection d 11/27/1 11/27/1
4 4
11 18 Roofing 68.00d . Fri Tue
0 10/17/1 1/20/15
4
11 18.1 - Roofing 3.00d 73 Fri Tue
1 Paper Installed 10/17/1 10/21/1
4 4
11 18.2 - Draw #4 0.00d 74,111 Thu Thu
2 (Roof, windows, 10/23/1 10/23/1
doors) 4 4
11 18.3 - Stock Roof 1.00d 112 Fri Fri
3 Shingles 10/24/1 10/24/1
4 4
11 18.4 - Install Roof 7.00d 113,119 Mon Tue
4 Shingles 1/12/15 1/20/15
11 19 Exterior Finishes 56.00d . Fri Fri
5 10/24/1 1/9/15
4
11 19.1 - Siding 3.00d 74 Fri Tue
6 10/24/1 10/28/1
4 4
11 19.2 - Exterior Trim 7.00d 116 Wed Thu
7 10/29/1 11/6/14
4
11 19.3 - Brick Arch 1.00d 117 Fri Fri
8 Forms 11/7/14 11/7/14
11 19.4 - Brick Veneer 45.00d 118 Mon Fri
9 11/10/1 1/9/15
4
12 20 Insulation 5.00d . Fri Thu
0 11/28/1 12/4/14
4
12 20.1 - Caulk & Air 1.00d 109 Fri Fri
1 Seal 11/28/1 11/28/1
4 4
12 20.2 - Draft & Fire 1.00d 121 Mon Mon
2 Stop 12/1/14 12/1/14
12 20.3 - Batt Insulation 3.00d 121,122 Tue Thu
3 12/2/14 12/4/14
12 21 County 0.00d 123,120 Thu Thu
4 Insulation 12/4/14 12/4/14
Inspection
12 22 BGE Energy Wise 0.00d 124 Thu Thu
5 Inspection 12/4/14 12/4/14
12 23 Drywall 26.00d . Fri Fri
6 12/5/14 1/9/15
12 23.1 - Stock Drywall 1.00d 124 Fri Fri
7 12/5/14 12/5/14
12 23.2 - Hang Drywall 5.00d 127 Mon Fri
8 12/8/14 12/12/1
4
12 23.3 - Remove 1.00d 128 Mon Mon
9 Scrap Drywall 12/15/1 12/15/1
4 4
13 23.4 - Tape and 15.00d 128,129 Tue Mon
0 Finish Drywall 12/16/1 1/5/15
4
13 23.5 - Sand Drywall 1.00d 130 Tue Tue
1 1/6/15 1/6/15
13 23.6 - Drywall Point- 3.00d 131 Wed Fri
2 up 1/7/15 1/9/15
13 24 Draw #6 0.00d 128,126 Fri Fri
3 (Insulation & 1/9/15 1/9/15
drywall applied)
13 25 Floor Finishes 76.00d . Tue Tue
4 1/13/15 4/28/15
13 25.1 - Ceramic Tile 15.00d 142 Tue Mon
5 1/13/15 2/2/15
13 25.2 - Install 4.00d 146 Fri Wed
6 Hardwood Floor 3/27/15 4/1/15
13 25.3 - Sand, Stain, 5.00d 196 Thu Wed
7 Seal Hardwood 4/16/15 4/22/15
13 25.4 - Install Carpet 4.00d 137 Thu Tue
8 4/23/15 4/28/15
13 25.5 - Final Coat 2.00d 196 Thu Fri
9 Hardwood 4/16/15 4/17/15
14 26 Paint 59.00d . Wed Mon
0 1/7/15 3/30/15
14 26.1 - Prep Drywall 2.00d 131 Wed Thu
1 for Prime Coat 1/7/15 1/8/15
14 26.2 - Prime Paint 2.00d 141 Fri Mon
2 Drywall 1/9/15 1/12/15
14 26.3 - Prep Trim for 2.00d 142,152 Wed Thu
3 Prime Coat 1/21/15 1/22/15
14 26.4 - Prime Trim 2.00d 143 Fri Mon
4 1/23/15 1/26/15
14 26.5 - Finish Coat 10.00d 144,156 Mon Fri
5 Trim 2/23/15 3/6/15
14 26.6 - Finish Coat 14.00d 145,132 Mon Thu
6 Drywall 3/9/15 3/26/15
14 26.7 - Caulk Exterior 1.00d 146,117 Fri Fri
7 Windows & 3/27/15 3/27/15
Doors
14 26.8 - Finish Coat 1.00d 147 Mon Mon
8 Exterior Trim & 3/30/15 3/30/15
Siding
14 27 Draw #7 0.00d 114,157 Tue Tue
9 (Roofing, 3/31/15 3/31/15
masonry, siding)
15 28 Interior Trim 29.00d . Tue Fri
0 1/13/15 2/20/15
15 28.1 - Interior Trim 1.00d 142 Tue Tue
1 Delivery 1/13/15 1/13/15
15 28.2 - Install Interior 5.00d 151 Wed Tue
2 Doors 1/14/15 1/20/15
15 28.3 - Install Interior 15.00d 152 Wed Tue
3 Trim 1/21/15 2/10/15
15 28.4 - Install 5.00d 153 Wed Tue
4 Cabinetry 2/11/15 2/17/15
15 28.5 - Install 1.00d 154 Wed Wed
5 Appliances 2/18/15 2/18/15
15 28.6 - 1st Punch-out 2.00d 155,144 Thu Fri
6 Interior Trim 2/19/15 2/20/15
15 29 H.V.A.C. Trim 1.00d 140 Tue Tue
7 3/31/15 3/31/15
15 29.1 - Install Grills & 1.00d 131 Tue Tue
8 Registers for 3/31/15 3/31/15
Paint
15 29.2 - Set Outdoor 1.00d 165 Tue Tue
9 Units 3/31/15 3/31/15
16 30 Plumbing Trim 5.00d . Thu Wed
0 4/2/15 4/8/15
16 30.1 - Set Fixtures 4.00d 135,136,146,154 Thu Tue
1 4/2/15 4/7/15
16 30.2 - Connect 1.00d 161 Wed Wed
2 Appliances 4/8/15 4/8/15
16 31 County Final 0.00d 160 Wed Wed
3 Plumbing 4/8/15 4/8/15
Inspection
16 32 Exterior 32.00d . Mon Tue
4 Landscaping 1/12/15 2/24/15
16 32.1 - Rough Final 1.00d 119 Mon Mon
5 Grade 1/12/15 1/12/15
16 32.2 - Patios 7.00d 165,119 Tue Wed
6 1/13/15 1/21/15
16 32.3 - Porches 5.00d 166,119 Thu Wed
7 1/22/15 1/28/15
16 32.4 - Sidewalks 7.00d 167,119 Thu Fri
8 1/29/15 2/6/15
16 32.5 - Decks 7.00d 168,119 Mon Tue
9 2/9/15 2/17/15
17 32.6 - Driveways 2.00d 165,169 Wed Thu
0 2/18/15 2/19/15
17 32.7 - Final Grade 3.00d 170,166,167,168 Fri Tue
1 and Seed 2/20/15 2/24/15
17 33 Electrical Final 160.00d . Tue Wed
2 Trim 6/5/14 1/14/15
17 33.1 - Switch & Plug 2.00d 142,100 Tue Wed
3 1/13/15 1/14/15
17 33.2 - Install Fixtures 1.00d 146 Thu Thu
4 3/27/15 3/27/15
17 33.3 - Connect 1.00d 155,162 Thu Thu
5 Appliances 4/9/15 4/10/15
17 34 Hardware 12.00d . Fri Mon
6 3/27/15 4/13/15
17 34.1 - Door 2.00d 145,146 Fri Mon
7 Hardware 3/27/15 3/30/15
17 34.2 - Bath 2.00d 145,146 Fri Mon
8 Hardware 3/27/15 3/30/15
17 34.3 - Mirrors 5.00d 178 Tue Mon
9 3/31/15 4/6/15
18 34.4 - Shower Doors 10.00d 178 Tue Mon
0 3/31/15 4/13/15
18 35 Draw #8 (Prime 0.00d 142,152,154 Tue Tue
1 paint, cabinets, 2/17/15 2/17/15
doors)
18 36 Draw #9 (Trim, 0.00d 153,181 Tue Tue
2 furnace, hrdwd, 2/17/15 2/17/15
tile, rails)
18 37 Draw #10 0.00d 146,182 Thu Thu
3 (Plumbing & 3/26/15 3/26/15
elec. trim, final
paint)
18 38 Final Building 0.00d 183 Thu Thu
4 Inspection 3/26/15 3/26/15
18 39 Use & 0.00d 184FS+3d Tue Tue
5 Occupancy 3/31/15 3/31/15
Certificate
18 40 First Walk-thru 0.00d 185 Tue Tue
6 3/31/15 3/31/15
18 41 Draw #11 (Final 0.00d 186 Tue Tue
7 payment per 3/31/15 3/31/15
contract)
18 42 Final Punch-out 9.00d . Wed Mon
8 4/1/15 4/13/15
18 42.1 - Punch Out 4.00d 186 Wed Mon
9 Walk-thru List 4/1/15 4/6/15
19 42.2 - Trim and 2.00d 184,189 Tue Wed
0 Adjust Doors 4/7/15 4/8/15
19 42.3 - Paint Touch- 3.00d 190 Thu Mon
1 up 4/9/15 4/13/15
19 43 Cleaning 14.00d . Fri Wed
2 3/27/15 4/15/15
19 43.1 - Windows 3.00d 145,146 Fri Tue
3 3/27/15 3/31/15
19 43.2 - Rough Clean 3.00d 193 Wed Fri
4 4/1/15 4/3/15
19 43.3 - Final Clean 2.00d 176,188 Tue Wed
5 4/14/15 4/15/15
19 44 Final Walk- 0.00d 187,188,192 Wed Wed
6 through 4/15/15 4/15/15
19 45 Move-in 0.00d 196FS+1d Thu Thu
7 4/16/15 4/16/15