Assignment-3 Model Answer

This document contains an assignment on project scheduling techniques: 1. A table is given with task information including optimistic, most likely, and pessimistic times to calculate the expected time using the PERT formula. Students are asked to complete the table with the calculations and draw the activity on arrow (AOA) network diagram. 2. A second question provides a network diagram with node numbers and activity letters/times. Students are asked to draw the AOA network and identify all paths and their lengths. They also identify the critical path as the longest path through the network.

Uploaded by

Mochamad Rakha
Copyright
© © All Rights Reserved
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
44 views

Assignment-3 Model Answer

This document contains an assignment on project scheduling techniques: 1. A table is given with task information including optimistic, most likely, and pessimistic times to calculate the expected time using the PERT formula. Students are asked to complete the table with the calculations and draw the activity on arrow (AOA) network diagram. 2. A second question provides a network diagram with node numbers and activity letters/times. Students are asked to draw the AOA network and identify all paths and their lengths. They also identify the critical path as the longest path through the network.

Uploaded by

Mochamad Rakha
Copyright
© © All Rights Reserved
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 3

Kingdom of Saudi Arabia

‫المملكة العربية السعودية‬


Ministry of Higher Education
‫وزارة التعليم العالي‬
Princess Noura bint Abdulrahman University ‫جامعة االميرة نورة بنت عبد الرحمن‬
College of Computer & Information Sciences ‫كلية علوم الحاسب والمعلومات‬

Assignment -3
-
Submission Rules:

 It's individual assignment


 Submission on http://dropitto.me/amalbinessa PW:pnu@1234512345
 The document name should include your name , section , assignment's
number and your email
 Due date on 11/2/1436 H.
 All parties involved in cheating will be prosecuted no matter who copied from
whom, it's your duty to keep your assignment secure.

Question 1:
Given the following table:

PERT
Task ImmediatePredecessors Optimistic Most Likely Pessimistic
(Expected time)
A None 5 7 12 (5+4*7+12)/6=7.5
B None 8 8 8 (8+4*8+8)/6=8
C A 2 6 10 (2+4*6+10)/6=6
D A,B 12 14 19 (12+4*14+19)/6=14.5
E C,D 6 6 12 (6+4*6+12)/6=7
F B,E 3 12 18 (3+4*12+18)/6=11.5
G F 6 8 10 (6+4*8+10)/6=8

A. Complete the above table.( Show all calculations)


B. Draw the AOA Network.
C =6
1 3
A=7.5
E=7
Begin D =14.5
B=8
2 4 F =11.5 G =8
5 End
Kingdom of Saudi Arabia
‫المملكة العربية السعودية‬
Ministry of Higher Education
‫وزارة التعليم العالي‬
Princess Noura bint Abdulrahman University ‫جامعة االميرة نورة بنت عبد الرحمن‬
College of Computer & Information Sciences ‫كلية علوم الحاسب والمعلومات‬

C. Find the critical path.


Path1: A,C,E,F,G Length: 7.5+6+7+11.5+8= 40 days
Path2: A,B,D,E,F,G Length: 7.5+8+14.5+7+11.5+8= 56.5 days
Critical path is the longest path through the network diagram,
Path2: A,B,D,E,F,G length is 56.5 days that is critical path .

Question 2:
Consider the following table which is Network Diagram Data for a
project. All durations are in Days; and the network proceeds from Node
1 to Node 9.

a. Draw an AOA network Diagram representing the project. Put the node
numbers in circles and draw arrows from node to node, labeling each
arrow with the activity letter and estimated time.

E=3 H=3 K=1


3 6 8 9
B=3
I=5 J=2
A=3
C=5 F=4
1 2 4 7
D=6 G=8
5

b. Identify of all paths on the network diagram and note how long they
are.
Kingdom of Saudi Arabia
‫المملكة العربية السعودية‬
Ministry of Higher Education
‫وزارة التعليم العالي‬
Princess Noura bint Abdulrahman University ‫جامعة االميرة نورة بنت عبد الرحمن‬
College of Computer & Information Sciences ‫كلية علوم الحاسب والمعلومات‬

Path1: A,B,E,H,K Length: 3+3+3+3+1 = 13 days


Path2: A,C,F,J,K Length: 3+5+4+2+1 = 15 days
Path3: A,D,G,J,K Length: 3+6+8+2+1 = 20 days
Path4: A,B,E,I,J,K Length: 3+3+3+5+2+1 = 17 days

c. What is the critical path for this project and how long is it.
Critical path is the longest path through the network diagram,
path3: A,D,G,J,K, length is 20 days that is critical path .