Sheila Estimate

Download as xls, pdf, or txt
Download as xls, pdf, or txt
You are on page 1of 34
At a glance
Powered by AI
The documents provide bills of materials and cost estimates for proposed construction projects including residential and commercial buildings. Common materials listed include concrete, rebar, lumber, tiles, paints. Costs and quantities of each material are broken down.

Common materials listed across the documents include concrete, sand, gravel, lumber, cement, hollow blocks, roofing materials like GI sheets, tiles for floor and walls. Reinforcing materials like rebar are also commonly used.

Typical steps mentioned include site development works like excavation and staking, concreting works, formworks, masonry works, roofing, tiling, painting. Plumbing, electrical and other finishing works are also included.

Project : PROPOSED TWO STOREY BUILDING

Location: Fatima, Ubay, Bohol


Owner : Dra. Janet Aznar

SUBJECT: BILL OF MATERIALS AND COST ESTIMATES

MATERIALS/ITEM QNTY. UNIT COST AMOUNT


I. MOBILIZATION: Staking & Layout, 7,000.00
Temp. Connections Elect'l & Water
A.Bunkhouse
2x3x12 coco lumber 20 pcs. 90.00 P 1,800.00
1/4 ordinary plywood 10 shts. 295.00 2,950.00
10'xga.26 Corrugated G.I. Sheet. 8 shts. 315.00 2,520.00
Assorted CWNails 5 kls. 65.00 325.00
P 7,595.00 P
II.EXCAVATION:
Septic tank 1 -4.0x2.50x2.0 10 cu.m. 600.00 6,000.00
Footings - 1.10x1.10x1.00x14 6 cu.m. 500.00 3,000.00
Wall Footings- .60x.30x65( Tie Beam) 9 cu.m. 500.00 4,500.00
P 13,500.00 P
III.CONCRETE WORKS:
A. Footing:
Portland Cement 30 bags 200.00 6,000.00
River Sand 4 cu.m. 700.00 2,800.00
3/4 Gravel 8 cu.m. 800.00 6,400.00
16mm rebars 25 pcs. 640.00 16,000.00
#16 tie wire 8 kls. 75.00 600.00
P 31,800.00 P
B. Column- Ground Floor :
Portland Cement 50 bags 200.00 10,000.00
River Sand 4 cu.m. 700.00 2,800.00
3/4 Gravel 8 cu.m. 800.00 6,400.00
16mm rebars 50 pcs. 640.00 32,000.00
10mmÆ rebars 60 pcs. 245.00 14,700.00
#16 tie wire 15 kls. 75.00 1,125.00
P 67,025.00 P
C. Ground Floor Slab:
Portland Cement 55 bags 200.00 11,000.00
River Sand 3 cu.m. 700.00 2,100.00
3/4 Gravel 6 cu.m. 800.00 4,800.00
10mm rebars 25 pcs. 245.00 6,125.00
#16 tie wire 5 kls. 75.00 375.00
P 24,400.00 P
E.2nd FLOOR BEAM:
Portland Cement 35 bags 200.00 7,000.00
River Sand 2 cu.m. 700.00 1,400.00
3/4 Gravel 5 cu.m. 800.00 4,000.00
16mm rebars 20 pcs. 640.00 12,800.00
10mm rebars 25 pcs. 245.00 6,125.00
#16 tie wire 10 kls. 75.00 750.00
P 32,075.00 P
IV. FORMWORKS AND SCAFFOLDINGS
A.Column
2X3X12 coco lumber 60 pcs. 90.00 5,400.00
2X2X12 coco lumber 50 pcs. 64.00 3,200.00
1/4 ordinary plywood 3 pcs. 320.00 960.00
Assorted CW Nail 40 kls. 60.00 2,400.00
P 11,960.00 P
V. MASONRY (ground)
B.Wall / Partition 1st Floor
4"CHB 800 pcs. 9.00 7,200.00
Portland cement 50 bags 200.00 10,000.00
River sand 5 cu.m. 700.00 3,500.00
10mm rebars 25 pcs. 245.00 6,125.00
#16 tie wire 20 kls. 75.00 1,500.00
P 28,325.00 P
C. Plastering 1st Floor
Pozzoland Cement (Smooth Fin.) 20 bags 200.00 4,000.00
Pozzoland Cement 25 bags 200.00 5,000.00
River Sand 6 cu.m. 700.00 4,200.00
P 13,200.00 P
VI. PLUMBING
A. WASTE PIPE LINE
a.) Ground floor
4” PVC pipe (orange)-ordinary 8 pcs. 192.00 1,536.00
4” WYE 15 pcs. 61.00 915.00
4x2” WYE 4 pcs. 65.00 260.00
4” 1/8 bend 10 pcs. 28.00 280.00
4” elbow 15 pcs. 36.00 540.00
4” P-Trap 2 pcs. 104.00 208.00
4” clean-out 3 pcs. 29.00 87.00
4x2'' Tee 3 pcs. 54.00 162.00
4x2 Tee 2 pcs. 54.00 108.00
2” PVC pipe (orange)- Atlanta 6 pcs. 82.00 492.00
2” elbow 10 pcs. 13.00 130.00
2” Tee 3 pcs. 18.00 54.00
2” 1/8 bend 2 pcs. 9.00 18.00
2” WYE 5 pcs. 19.00 95.00
6” floor drain (stainless) 2 pcs. 180.00 360.00
Solvent cement 2 ltrs. 98.00 196.00
P 5,441.00 P
c.) Distribution line (Moldex Blue)
Water meter 1 pcs. 1000.00 1000.00
3/4 PVC Pipe 0 pcs. 76.00 0.00
1/2 PVC Pipe 15 pcs. 53.00 795.00
1/2 PVC Elbow (plain) 20 pcs. 6.00 120.00
1/2 PVC Tee (plain) 15 pcs. 10.00 150.00
1/2 PVC Elbow (threaded) 10 pcs. 10.00 100.00
1/2 PVC Tee (threaded) 5 pcs. 10.00 50.00
1/2 PVC Union pcs. 35.00 0.00
1/2 PVC Shut-off valve 4 pcs. 275.00 1100.00
3/4 PVC Shut-off valve pcs. 245.00 0.00
3/4x1/2 PVC Reducer pcs. 11.30 0.00
1/2 PE Pipe SGR-9 60 mtrs. 20.00 1200.00
1/2 PE Pipe Union 2 pcs. 87.40 174.80
1/2 PE Tee 5 pcs. 87.40 437.00
Teflon tape (Tombo) 3/4 10 pcs. 16.00 160.00
Solvent cement 2 ltrs. 279.00 558.00
P 5,844.80 P
B.TOILET & BATHROOM FIXTURES
Water closet(Royal tern-colored) 2 sets 5,500.00 11,000.00
Lavatory (Royal tern-colored) sets 2,090.00 0.00
Water closet flexible hose 4 pcs. 56.00 224.00
Lavatory flexible hose 4 pcs. 56.00 224.00
Angle valve 4 pcs. 180.00 720.00
Toilet paper holder pcs. 146.00 0.00
Soap holder pcs. 132.00 0.00
Shower valve 1 pcs. 620.00 620.00
Shower head pcs. 180.00 0.00
Bath Tub (Royal tern-colored) sets 6,425.00 0.00
Individual Water Heater units 6,800.00 0.00
P 12,788.00 P
C.TILEWORKS
c.)Toilet & Bathroom
8x8 Floor tiles 60 pcs. 15.00 P 900.00
8x10 Wall tiles 100 pcs. 19.75 1,975.00
3x8 Border tiles 0 pcs. 18.00 0.00
Tile trim 10 pcs. 45.00 450.00
ABC Tile grout 4 packs 65.00 260.00
Cement tile adhesive -ABC 8 bags 248.00 1,984.00
P 5,569.00 P
VII. ELECTRICAL
Circuit breaker 15A,2P,250V (Koten) 3 pcs. 200.00 600.00
Circuit breaker 20A,2P,250V 4 pcs. 200.00 800.00
Circuit breaker 60A,2P,250V 1 pcs. 200.00 200.00
Circuit breaker 100A,2P,250V pcs. 850.00 0.00
Panel board (8 branches) 1 pcs. 1250.00 1,250.00
#12 THW copper wire stranded 2 boxes 3855.00 7,710.00
#10 THW copper wire stranded 1 boxes 5602.00 5,602.00
#8 THW copper wire stranded 0.5 boxes 8571.00 4,285.50
#6 THW copper wire stranded boxes 14435.00 0.00
32W circular fluorescent lamp w/case 6 sets 620.00 3,720.00
Pinlight with ballast 6 sets 180.00 1,080.00
Switch (flush type)-Anam 8 sets 130.00 1,040.00
Convenience outlet (flush type)-Anam 8 sets 95.00 760.00
Aircon outlet (flush type)-Anam 2 sets 180.00 360.00
Telephone outlet (flush type)-Anam 2 sets 95.00 190.00
2x4 utility box -Poly 35 pcs. 18.00 630.00
Junction box -Poly 20 pcs. 20.00 400.00
½ “ electrical flexible hose (orange) 30 mtrs. 4.50 135.00
½ “ electrical PVC pipe (orange) 20 pcs. 61.00 1,220.00
3/4 “ electrical PVC pipe (orange) 8 pcs. 70.00 560.00
3/4" Entrance cap 2 pc. 35.00 70.00
Electrical tape (Nitto-big) 15 pcs. 25.00 375.00
Solvent cement (S-Blue) 1 ltrs. 279.00 279.00
1/2 PVC Clip 20 pcs. 4.00 80.00
P 31,346.50 P
VIII. FINISHES
A. Windows
Woodencasement windows 5 sq.m. 2,500.00 12,500.00
1/8 Smoked glass 25 sq.ft. 40.00 1,000.00
P 13,500.00
B. Doors
Wooden panel doors .90x2.10m. 2 pcs. 3,100.00 6,200.00
Wooden panel doors .70x2.10m. 1 pcs. 2,900.00 2,900.00
Molded Panel doors .80x2.10m. 2 pcs. 1,900.00 3,800.00
Wooden flush doors .70x2.10m. 1 pcs. 1,300.00 1,300.00
PVC doors .60x2.10m. 2 sets 1,450.00 2,900.00
Main door lock 1 set 1,850.00 1,850.00
Door knobs (Kwikset) 6 sets 650.00 3,900.00
3” loose pin hinges(China) 6 sets 20.00 120.00
Door track sets 1600.00 0.00
Door jamb 7 sets 900.00 6,300.00
P 29,270.00 P
IX. KITCHEN:
Cabinets, Tiles Counter tops
( with hardwares & accessories) 3 sq.m. 4350.00 13,050.00
P 13,050.00

X. TOTAL MATERIAL COST P 353,689.30


XI. LABOR P
XII. CONTINGENCIES,OVERHEAD & EQUIPMENT RENTAL,CLEARING P 12,014.39
PROFESSIONAL FEES ( for elect'l and Plumbing)

XIII. TOTAL CONSTRUCTION COST P 492,589.92


CHRYSLER S. GUDITO
Arhitect UAP Owner/Representative
PRC No. 18292
PTR No. 6749363
Date Issued : 01-08-09
Place Issued: Ubay, Bohol
Actual Labor Cost No. of days

LABOR

2,278.50 0.3 1

4,050.00 0.3 1

6,360.00 0.2 1

26,810.00 0.4 1

9,760.00 0.4 1
12,830.00 0.4 #VALUE! 1

4,784.00 0.4 1

9,913.75 0.35 1

12,540.00 0.95 1

2,176.40 0.4 1
1,753.44 0.3 1

3,197.00 0.25 1

4,455.20 0.8 1

19
11,754.94 0.375 1

1,350.00 0.1 1

4,390.50 0.15 1

8,482.50 0.65 1

0.025
126,886.23

480,575.53
resentative
Project : PROPOSED TWO STOREY BUILDING
Location: Fatima, Ubay, Bohol
Owner : Dra. Janet Aznar

SUBJECT: BILL OF MATERIALS AND COST ESTIMATES

MATERIALS/ITEM QNTY. UNIT COST AMOUNT


I. MOBILIZATION: Staking & Layout, 7,000.00
Temp. Connections Elect'l & Water
A.Bunkhouse
2x3x12 coco lumber 20 pcs. 90.00 P 1,800.00
1/4 ordinary plywood 10 shts. 295.00 2,950.00
10'xga.26 Corrugated G.I. Sheet. 8 shts. 315.00 2,520.00
Assorted CWNails 5 kls. 65.00 325.00
P 7,595.00 P
II.EXCAVATION:
Septic tank 1 -4.0x2.50x2.0 20 cu.m. 600.00 12,000.00
Footings - 1.10x1.10x1.00x14 16.95 cu.m. 500.00 8,475.00
Wall Footings- .60x.30x65( Tie Beam) 11.7 cu.m. 500.00 5,850.00
P 26,325.00
III.BACKFILL (88x.40=35.5cu.m.)
Anapog 35.5 cu.m. 350.00 12,425.00
P 12,425.00 P
IV.CONCRETE WORKS:
A. Footing:
Portland Cement 68 bags 200.00 13,600.00
River Sand 4 cu.m. 700.00 2,800.00
3/4 Gravel 8 cu.m. 800.00 6,400.00
16mm rebars 45 pcs. 640.00 28,800.00
#16 tie wire 8 kls. 75.00 600.00
P 52,200.00 P
Tie-Beam:
Portland Cement 40 bags 200.00 8,000.00
River Sand 2 cu.m. 700.00 1,400.00
3/4 Gravel 4 cu.m. 800.00 3,200.00
16mm rebars 50 pcs. 640.00 32,000.00
10mm rebars 45 pcs. 245.00 11,025.00
#16 tie wire 10 kls. 75.00 750.00
P 56,375.00 P
B. Column- Ground Floor :
Portland Cement 76 bags 200.00 15,200.00
River Sand 4 cu.m. 700.00 2,800.00
3/4 Gravel 8 cu.m. 800.00 6,400.00
16mm rebars 104 pcs. 640.00 66,560.00
10mmÆ rebars 100 pcs. 245.00 24,500.00
#16 tie wire 15 kls. 75.00 1,125.00
P 116,585.00 P
C. Ground Floor Slab:
Portland Cement 85 bags 200.00 17,000.00
River Sand 4.5 cu.m. 700.00 3,150.00
3/4 Gravel 12 cu.m. 800.00 9,600.00
10mm rebars 86 pcs. 245.00 21,070.00
#16 tie wire 5 kls. 75.00 375.00
P 51,195.00 P
D. Second Floor Slab
Portland Cement 115 bags 200.00 23,000.00
River Sand 6 cu.m. 700.00 4,200.00
3/4 Gravel 12 cu.m. 800.00 9,600.00
10mm rebars 330 pcs. 245.00 80,850.00
#16 tie wire 25 kls. 75.00 1,875.00
P 119,525.00 P
E.2nd FLOOR BEAM:
Portland Cement 70 bags 200.00 14,000.00
River Sand 3.5 cu.m. 700.00 2,450.00
3/4 Gravel 7 cu.m. 800.00 5,600.00
16mm rebars 78 pcs. 640.00 49,920.00
10mm rebars 70 pcs. 245.00 17,150.00
#16 tie wire 20 kls. 75.00 1,500.00
P 90,620.00 P
VI. FORMWORKS AND SCAFFOLDINGS
A.Column
2X3X12 coco lumber 300 pcs. 90.00 27,000.00
2X2X12 coco lumber 400 pcs. 64.00 25,600.00
1/4 ordinary plywood 60 pcs. 320.00 19,200.00
Assorted CW Nail 40 kls. 60.00 2,400.00
P 74,200.00 P
VII. MASONRY (ground)
B.Wall / Partition 1st Floor
4"CHB 2,400 pcs. 9.00 21,600.00
Portland cement 100 bags 200.00 20,000.00
River sand 9.5 cu.m. 700.00 6,650.00
10mm rebars 135 pcs. 245.00 33,075.00
#16 tie wire 20 kls. 75.00 1,500.00
P 82,825.00 P
C. Plastering 1st Floor
Pozzoland Cement (Smooth Fin.) 20 bags 200.00 4,000.00
Pozzoland Cement 120 bags 200.00 24,000.00
River Sand 12 cu.m. 700.00 8,400.00
P 36,400.00 P
VIII. PLUMBING
A. WASTE PIPE LINE
a.) Ground floor
4” PVC pipe (orange)-ordinary 8 pcs. 192.00 1,536.00
4” WYE 15 pcs. 61.00 915.00
4x2” WYE 4 pcs. 65.00 260.00
4” 1/8 bend 10 pcs. 28.00 280.00
4” elbow 15 pcs. 36.00 540.00
4” P-Trap 2 pcs. 104.00 208.00
4” clean-out 3 pcs. 29.00 87.00
4x2'' Tee 3 pcs. 54.00 162.00
4x2 Tee 2 pcs. 54.00 108.00
2” PVC pipe (orange)- Atlanta 6 pcs. 82.00 492.00
2” elbow 10 pcs. 13.00 130.00
2” Tee 3 pcs. 18.00 54.00
2” 1/8 bend 2 pcs. 9.00 18.00
2” WYE 5 pcs. 19.00 95.00
6” floor drain (stainless) 2 pcs. 180.00 360.00
Solvent cement 2 ltrs. 98.00 196.00
P 5,441.00 P
c.) Distribution line (Moldex Blue)
Water meter 1 pcs. 1000.00 1000.00
3/4 PVC Pipe 0 pcs. 76.00 0.00
1/2 PVC Pipe 15 pcs. 53.00 795.00
1/2 PVC Elbow (plain) 20 pcs. 6.00 120.00
1/2 PVC Tee (plain) 15 pcs. 10.00 150.00
1/2 PVC Elbow (threaded) 10 pcs. 10.00 100.00
1/2 PVC Tee (threaded) 5 pcs. 10.00 50.00
1/2 PVC Union pcs. 35.00 0.00
1/2 PVC Shut-off valve 4 pcs. 275.00 1100.00
3/4 PVC Shut-off valve pcs. 245.00 0.00
3/4x1/2 PVC Reducer pcs. 11.30 0.00
1/2 PE Pipe SGR-9 60 mtrs. 20.00 1200.00
1/2 PE Pipe Union 2 pcs. 87.40 174.80
1/2 PE Tee 5 pcs. 87.40 437.00
Teflon tape (Tombo) 3/4 10 pcs. 16.00 160.00
Solvent cement 2 ltrs. 279.00 558.00
P 5,844.80 P
B.TOILET & BATHROOM FIXTURES
Water closet(Royal tern-colored) 1 sets 5,500.00 5,500.00
Lavatory (Royal tern-colored) sets 2,090.00 0.00
Water closet flexible hose 4 pcs. 56.00 224.00
Lavatory flexible hose 4 pcs. 56.00 224.00
Angle valve 4 pcs. 180.00 720.00
Toilet paper holder pcs. 146.00 0.00
Soap holder pcs. 132.00 0.00
Shower valve 1 pcs. 620.00 620.00
Shower head pcs. 180.00 0.00
Bath Tub (Royal tern-colored) sets 6,425.00 0.00
Individual Water Heater units 6,800.00 0.00
P 7,288.00 P
C.TILEWORKS
c.)Toilet & Bathroom
8x8 Floor tiles 131 pcs. 15.00 P 1,965.00
8x10 Wall tiles 290 pcs. 19.75 5,727.50
3x8 Border tiles 0 pcs. 18.00 0.00
Tile trim 10 pcs. 45.00 450.00
ABC Tile grout 4 packs 65.00 260.00
Cement tile adhesive -ABC 8 bags 248.00 1,984.00
P 10,386.50 P
IX. SEPTIC TANK
4” CHB 425 pcs. 9.00 3,825.00
Portland Cement 56 bags 200.00 11,200.00
River Sand 5 cu.m. 700.00 3,500.00
3/4 Gravel 2 cu.m. 800.00 1,600.00
12mm rebars 41 pcs. 355.00 14,555.00
10mm rebars 24 pcs. 245.00 5,880.00
#16 tie wire 8 kls. 75.00 600.00
P 41,160.00 P
X. ELECTRICAL
Circuit breaker 15A,2P,250V (Koten) 3 pcs. 200.00 600.00
Circuit breaker 20A,2P,250V 4 pcs. 200.00 800.00
Circuit breaker 60A,2P,250V 1 pcs. 200.00 200.00
Circuit breaker 100A,2P,250V pcs. 850.00 0.00
Panel board (8 branches) 1 pcs. 1250.00 1,250.00
#12 THW copper wire stranded 2 boxes 3855.00 7,710.00
#10 THW copper wire stranded 1 boxes 5602.00 5,602.00
#8 THW copper wire stranded 0.5 boxes 8571.00 4,285.50
#6 THW copper wire stranded boxes 14435.00 0.00
32W circular fluorescent lamp w/case 6 sets 620.00 3,720.00
Pinlight with ballast 6 sets 180.00 1,080.00
Switch (flush type)-Anam 8 sets 130.00 1,040.00
Convenience outlet (flush type)-Anam 8 sets 95.00 760.00
Aircon outlet (flush type)-Anam 2 sets 180.00 360.00
Telephone outlet (flush type)-Anam 2 sets 95.00 190.00
2x4 utility box -Poly 50 pcs. 18.00 900.00
Junction box -Poly 40 pcs. 20.00 800.00
½ “ electrical flexible hose (orange) 60 mtrs. 4.50 270.00
½ “ electrical PVC pipe (orange) 40 pcs. 61.00 2,440.00
3/4 “ electrical PVC pipe (orange) 8 pcs. 70.00 560.00
3/4" Entrance cap 2 pc. 35.00 70.00
Electrical tape (Nitto-big) 15 pcs. 25.00 375.00
Solvent cement (S-Blue) 1 ltrs. 279.00 279.00
1/2 PVC Clip 20 pcs. 4.00 80.00
P 33,371.50 P
XI. FINISHES
A. Windows
Woodencasement windows 10.8 sq.m. 2,500.00 27,000.00
1/8 Smoked glass 108 sq.ft. 40.00 4,320.00
P 31,320.00
B. Doors
Wooden panel doors .90x2.10m. 2 pcs. 3,100.00 6,200.00
Wooden panel doors .70x2.10m. 1 pcs. 2,900.00 2,900.00
Molded Panel doors .80x2.10m. 3 pcs. 1,900.00 5,700.00
Wooden flush doors .70x2.10m. 1 pcs. 1,300.00 1,300.00
PVC doors .60x2.10m. 2 sets 1,450.00 2,900.00
Main door lock 1 set 1,850.00 1,850.00
Door knobs (Kwikset) 6 sets 650.00 3,900.00
3” loose pin hinges(China) 10 sets 20.00 200.00
Door track sets 1600.00 0.00
Door jamb 7 sets 900.00 6,300.00
P 31,250.00 P
XII. KITCHEN:
Cabinets, Tiles Counter tops
( with hardwares & accessories) 3 sq.m. 4350.00 13,050.00
P 13,050.00

XIII. TOTAL MATERIAL COST P 912,381.80


XIV. LABOR P
XV. CONTINGENCIES,OVERHEAD & EQUIPMENT RENTAL,CLEARING P 31,378.45
PROFESSIONAL FEES ( for elect'l and Plumbing)

XVI. TOTAL CONSTRUCTION COST P 1,286,516.35

CHRYSLER S. GUDITO
Arhitect UAP Owner/Representative
PRC No. 18292
PTR No. 0380713
Date Issued : 01-08-08
Place Issued: Tagbilaran City
Actual Labor CosNo. of days

LABOR

2,278.50 0.3 1

3,727.50 0.3 1

10,440.00 0.2 1

22,550.00 0.4 1

46,634.00 0.4 1
20,478.00 0.4 1
2

47,810.00 0.4 1

36,248.00 0.4 #VALUE! 1

29,680.00 0.4 1

28,988.75 0.35 1

34,580.00 0.95 1
2,176.40 0.4 1

1,753.44 0.3 1

1,822.00 0.25 1
8,309.20 0.8 1

16,464.00 0.4 1

19

12,514.31 0.375 1

3,132.00 0.1 1
4,687.50 0.15 1

8,482.50 0.65 1

0.025
342,756.10

1,255,137.90
Project : PROPOSED TWO STOREY RESIDENTIAL BUILDING
Location: Poblacion, Ubay, Bohol
Owner :Mr & Mrs. Escolastico Garcia

SUBJECT: BILL OF MATERIALS AND COST ESTIMATES

MATERIALS/ITEM QNTY. UNIT COST AMOUNT LABOR


I. MOBILIZATION: Staking & Layout, 7,000.00
Temp. Connections Elect'l & Water
A.Bunkhouse
2x3x12 coco lumber 20 pcs. 90.00 P 1,800.00
1/4 ordinary plywood 10 shts. 295.00 2,950.00
10'xga.26 Corrugated G.I. Sheet. 8 shts. 315.00 2,520.00
Assorted CWNails 5 kls. 65.00 325.00
P 7,595.00 P 2,278.50 0.3
II.EXCAVATION:
Septic tank 1 -4.0x2.50x2.0 10 cu.m. 600.00 6,000.00
Footings - 1.10x1.10x1.00x14 6 cu.m. 500.00 3,000.00
Wall Footings- .60x.30x65( Tie Beam) 9 cu.m. 500.00 4,500.00
P 13,500.00 P 4,050.00 0.3
III.CONCRETE WORKS:
A. Footing:
Portland Cement 30 bags 200.00 6,000.00
River Sand 4 cu.m. 700.00 2,800.00
3/4 Gravel 10 cu.m. 800.00 8,000.00
16mm rebars 30 pcs. 640.00 19,200.00
#16 tie wire 8 kls. 75.00 600.00
P 36,600.00 P 7,320.00 0.2
B. Column- Ground Floor :
Portland Cement 25 bags 200.00 5,000.00
River Sand 4 cu.m. 700.00 2,800.00
3/4 Gravel 6 cu.m. 800.00 4,800.00
16mm rebars 20 pcs. 640.00 12,800.00
10mmÆ rebars 30 pcs. 245.00 7,350.00
#16 tie wire 15 kls. 75.00 1,125.00
P 33,875.00 P 13,550.00 0.4
C. Ground Floor Slab:
Portland Cement 25 bags 200.00 5,000.00
River Sand 5 cu.m. 700.00 3,500.00
3/4 Gravel 6 cu.m. 800.00 4,800.00
10mm rebars 15 pcs. 245.00 3,675.00
#16 tie wire 5 kls. 75.00 375.00
P 17,350.00 P 6,940.00 0.4
E.2nd FLOOR BEAM:
Portland Cement 60 bags 200.00 12,000.00
River Sand 10 cu.m. 700.00 7,000.00
3/4 Gravel 12 cu.m. 800.00 9,600.00
16mm rebars 30 pcs. 640.00 19,200.00
10mm rebars 25 pcs. 245.00 6,125.00
#16 tie wire 10 kls. 75.00 750.00
P 54,675.00 P 21,870.00 0.4
IV. FORMWORKS AND SCAFFOLDINGS
A.Column
2X3X12 coco lumber 100 pcs. 90.00 9,000.00
2X2X12 coco lumber 70 pcs. 64.00 4,480.00
1/4 ordinary plywood 3 pcs. 320.00 960.00
Assorted CW Nail 40 kls. 60.00 2,400.00
P 16,840.00 P 6,736.00 0.4
V. MASONRY (ground)
B.Wall / Partition 1st Floor
4"CHB 1,500 pcs. 9.00 13,500.00
Portland cement 30 bags 200.00 6,000.00
River sand 5 cu.m. 700.00 3,500.00
10mm rebars 30 pcs. 245.00 7,350.00
#16 tie wire 15 kls. 75.00 1,125.00
P 31,475.00 P 11,016.25 0.35
C. Plastering 1st Floor
Pozzoland Cement (Smooth Fin.) 20 bags 200.00 4,000.00
Pozzoland Cement 23 bags 200.00 4,600.00
River Sand 6 cu.m. 700.00 4,200.00
P 12,800.00 P 12,160.00 0.95
VI. PLUMBING
A. WASTE PIPE LINE
a.) Ground floor
4” PVC pipe (orange)-ordinary 8 pcs. 192.00 1,536.00
4” WYE 15 pcs. 61.00 915.00
4x2” WYE 4 pcs. 65.00 260.00
4” 1/8 bend 10 pcs. 28.00 280.00
4” elbow 15 pcs. 36.00 540.00
4” P-Trap 2 pcs. 104.00 208.00
4” clean-out 3 pcs. 29.00 87.00
4x2'' Tee 3 pcs. 54.00 162.00
4x2 Tee 2 pcs. 54.00 108.00
2” PVC pipe (orange)- Atlanta 6 pcs. 82.00 492.00
2” elbow 10 pcs. 13.00 130.00
2” Tee 3 pcs. 18.00 54.00
2” 1/8 bend 2 pcs. 9.00 18.00
2” WYE 5 pcs. 19.00 95.00
6” floor drain (stainless) 2 pcs. 180.00 360.00
Solvent cement 2 ltrs. 98.00 196.00
P 5,441.00 P 2,176.40 0.4
c.) Distribution line (Moldex Blue)
Water meter 1 pcs. 1000.00 1000.00
3/4 PVC Pipe 0 pcs. 76.00 0.00
1/2 PVC Pipe 15 pcs. 53.00 795.00
1/2 PVC Elbow (plain) 20 pcs. 6.00 120.00
1/2 PVC Tee (plain) 15 pcs. 10.00 150.00
1/2 PVC Elbow (threaded) 10 pcs. 10.00 100.00
1/2 PVC Tee (threaded) 5 pcs. 10.00 50.00
1/2 PVC Union pcs. 35.00 0.00
1/2 PVC Shut-off valve 4 pcs. 275.00 1100.00
3/4 PVC Shut-off valve pcs. 245.00 0.00
3/4x1/2 PVC Reducer pcs. 11.30 0.00
1/2 PE Pipe SGR-9 60 mtrs. 20.00 1200.00
1/2 PE Pipe Union 2 pcs. 87.40 174.80
1/2 PE Tee 5 pcs. 87.40 437.00
Teflon tape (Tombo) 3/4 10 pcs. 16.00 160.00
Solvent cement 2 ltrs. 279.00 558.00
P 5,844.80 P 1,753.44 0.3
B.TOILET & BATHROOM FIXTURES
Water closet(Royal tern-colored) 2 sets 5,500.00 11,000.00
Lavatory (Royal tern-colored) sets 2,090.00 0.00
Water closet flexible hose 4 pcs. 56.00 224.00
Lavatory flexible hose 4 pcs. 56.00 224.00
Angle valve 4 pcs. 180.00 720.00
Toilet paper holder pcs. 146.00 0.00
Soap holder pcs. 132.00 0.00
Shower valve 1 pcs. 620.00 620.00
Shower head pcs. 180.00 0.00
Bath Tub (Royal tern-colored) sets 6,425.00 0.00
Individual Water Heater units 6,800.00 0.00
P 12,788.00 P 3,197.00 0.25
C.TILEWORKS
c.)Toilet & Bathroom
8x8 Floor tiles 60 pcs. 15.00 P 900.00
8x10 Wall tiles 100 pcs. 19.75 1,975.00
3x8 Border tiles 0 pcs. 18.00 0.00
Tile trim 10 pcs. 45.00 450.00
ABC Tile grout 4 packs 65.00 260.00
Cement tile adhesive -ABC 8 bags 248.00 1,984.00
P 5,569.00 P 4,455.20 0.8

VII. ELECTRICAL
Circuit breaker 15A,2P,250V (Koten) 3 pcs. 200.00 600.00
Circuit breaker 20A,2P,250V 4 pcs. 200.00 800.00
Circuit breaker 60A,2P,250V 1 pcs. 200.00 200.00
Circuit breaker 100A,2P,250V pcs. 850.00 0.00
Panel board (8 branches) 1 pcs. 1250.00 1,250.00
#12 THW copper wire stranded 2 boxes 3855.00 7,710.00
#10 THW copper wire stranded 1 boxes 5602.00 5,602.00
#8 THW copper wire stranded 1 boxes 8571.00 8,571.00
#6 THW copper wire stranded boxes 14435.00 0.00
32W circular fluorescent lamp w/ca 6 sets 620.00 3,720.00
Pinlight with ballast 6 sets 180.00 1,080.00
Switch (flush type)-Anam 8 sets 130.00 1,040.00
Convenience outlet (flush type)-Ana 8 sets 95.00 760.00
Aircon outlet (flush type)-Anam 2 sets 180.00 360.00
Telephone outlet (flush type)-Anam 2 sets 95.00 190.00
2x4 utility box -Poly 35 pcs. 18.00 630.00
Junction box -Poly 20 pcs. 20.00 400.00
½ “ electrical flexible hose (orange) 15 mtrs. 4.50 67.50
½ “ electrical PVC pipe (orange) 15 pcs. 61.00 915.00
3/4 “ electrical PVC pipe (orange) 8 pcs. 70.00 560.00
3/4" Entrance cap 2 pc. 35.00 70.00
Electrical tape (Nitto-big) 15 pcs. 25.00 375.00
Solvent cement (S-Blue) 1 ltrs. 279.00 279.00
1/2 PVC Clip 10 pcs. 4.00 40.00
P 35,219.50 P 13,207.31 0.375
VIII. FINISHES
A. Windows
Woodencasement windows 5 sq.m. 2,500.00 12,500.00
1/8 Smoked glass 15 sq.ft. 40.00 600.00
P 13,100.00 1,310.00 0.1
B. Doors
Wooden panel doors .90x2.10m. 2 pcs. 3,100.00 6,200.00
Wooden panel doors .70x2.10m. 1 pcs. 2,900.00 2,900.00
Molded Panel doors .80x2.10m. 2 pcs. 1,900.00 3,800.00
Wooden flush doors .70x2.10m. 1 pcs. 1,300.00 1,300.00
PVC doors .60x2.10m. 2 sets 1,450.00 2,900.00
Main door lock 1 set 1,850.00 1,850.00
Door knobs (Kwikset) 6 sets 650.00 3,900.00
3” loose pin hinges(China) 6 sets 20.00 120.00
Door track sets 1600.00 0.00
Door jamb 7 sets 900.00 6,300.00
P 29,270.00 P 4,390.50 0.15
IX. KITCHEN:
Cabinets, Tiles Counter tops
( with hardwares & accessories) 3 sq.m. 4350.00 13,050.00
P 13,050.00 8,482.50 0.65

X. TOTAL MATERIAL COST P 351,992.30 0.025


XI. LABOR P 124,893.10
XII. CONTINGENCIES,OVERHEAD & EQUIPMENT RENTAL,CLEARING P 11,922.14
PROFESSIONAL FEES ( for elect'l and Plumbing)
XIII. TOTAL CONSTRUCTION COST P 488,807.54

CHRYSLER S. GUDITO
Arhitect UAP Owner/Representative
PRC No. 18292
PTR No. 6749363
Date Issued : 01-08-09
Place Issued: Ubay, Bohol
Actual Labor Cost No. of days

#VALUE! 1
1

1
1

19
1

476,885.40
Project : PROPOSED TEN UNIT APARTMENT
Location: Poblacion, Panglao, Bohol
Owner/Representative: Ms. Marieta G. Fudolin

SUBJECT: BILL OF MATERIALS AND COST ESTIMATES

MATERIALS/ITEM QNTY. UNIT COST/UNIT AMOUNT


I. Staking and layout, bunkhouse, P 5000.00
temporary connection of electricity and water

II. Excavation
septic tank 16 cu.m. 800 P 12800.00
column and wall footing 5.12 cu.m. 800 P 4096.00

III. Concreting Works


portland cement 30 sack 250 P 7500.00
gravel # 3/4 4 cu.m. 900 P 3600.00
sand 8 cu.m. 900 P 7200.00
16mm.dia. Def.rebar 40 pc. 640 P 25600.00
12mm.dia. Def.rebar 20 pc. 450 P 9000.00
10mm.dia. Def.rebar 20 pc. 250 P 5000.00
tie wire #16 15 kg. 60 P 900.00

IV. Formworks and Scaffoldings


2x2x12 coco lumber 40 pc. 100 P 4000.00
2x2x10 coco lumber 40 pc. 90 P 3600.00
1/4 ordinary plywood 20 pc. 350 P 7000.00
Assorted CW Nail 20 kg. 60 P 1200.00

V. Masonry Works, Flooring and Walling


4" CHB 210 pc. 11 P 2310.00
portland cement 5 sack 250 P 1250.00
sand 3 cu.m. 900 P 2700.00
3/16 thk. ficem board 35 pc. 380 P 13300.00
2x2x10 gemilina wood 45 pc. 100 P 4500.00
1/2" thk marine plywood 12 pc. 600 P 7200.00

VI. Trusses and Purlins


2x5x10 gemilina wood 24 pc. 300 P 7200.00
2x4x10 gemilina wood 20 pc. 250 P 5000.00
2x3x10 gemilina wood 50 pc. 250 P 12500.00

VII. Roofing
# 24 corrogated G.I. sheets, 6' 40 pc. 250 P 10000.00
# 24 plane G.I. sheets 10 pc. 250 P 2500.00
# 24 G.I. pre-fabricated gutter, 10' 10 pc. 280 P 2800.00
facia board 10 pc. 200 P 2000.00
umbrella nail 5 kg. 60 P 300.00

VIII. Plumbing Fixtures P 10000.00

IX. Electrical Fixtures P 20000.00

X. TOTAL MATERIAL COST P 200056.00

XI. LABOR COST P 80022.40

XII. TOTAL CONSTRUCTION COST P 280,078.40

ENGR. ELMER A. LUSICA MS. MARIETA G. FUDOLIN


PRC No. 011067 Owner/Representative
PTR No. 2398596
Date Issued : 01-17-11
Place Issued: Tagbilaran City
TA G. FUDOLIN
Project : PROPOSED TWO STOREY EXTENSION RESIDENTIAL BUILDING
Location: BOOL DISTRICT, TAGBILARAN CITY, BOHOL
Owner/Representative: SHEILA ESCALERA

BILL OF MATERIALS AND COST ESTIMATES

MATERIALS/ITEM QNTY. UNIT COST/UNIT AMOUNT

I. Staking and layout, bunkhouse,


temporary connection of electricity and water

II. Excavation
column and wall footing 2.5 cu.m. 800 P 2000.00

III. Concreting Works


portland cement 100 bags 250 P 25000.00
gravel # 3/4 10 cu.m. 1200 P 12000.00
sand 5 cu.m. 1200 P 6000.00
16mm.dia. Def.rebar 54 pc. 350 P 18900.00
12mm.dia. Def.rebar 12 pc. 250 P 3000.00
10mm.dia. Def.rebar 130 pc. 140 P 18200.00
tie wire #16 10 kg. 60 P 600.00

IV. Formworks, Trusses, Wall and Ceiling frame and Scaffoldings


2x6x10 gemilina wood 0 pc. 288 P 0.00
2x4x10 gemilina wood 0 pc. 192 P 0.00
2x3x10 gemilina wood 50 pc. 144 P 7200.00
2X2X10 gemiline wood 100 pc. 80 P 8000.00
3/16" plywood 10 pc. 350 P 3500.00
Assorted CW Nail 10 kgs. 60 P 600.00

V. Masonry Works and Walling


4" CHB 1000 pc. 14 P 14000.00
portland cement 60 sack 250 P 15000.00
sand 10 cu.m. 1200 P 12000.00
10mm.dia. Def.rebar 40 pc. 140 P 5600.00

VI. Roofing
# 24 corrogated G.I. sheets, 6' pc. 350 P 0.00
# 24 plane G.I. sheets pc. 250 P 0.00
facia board pc. 200 P 0.00
umbrella nail kgs. 60 P 0.00

VII. Tile Works P 30000.00

VIII. Painting Works P 30000.00


IX. Plumbing Fixtures P 25000.00

X. Electrical Fixtures P 30000.00

XI. TOTAL MATERIAL COST P 266600.00

XII. LABOR COST P 93310.00

XIII. TOTAL CONSTRUCTION COST P 359,910.00

PREPARED BY:

ENGR. ELMER A. LUSICA SHIELA ESCALERA


SUPERVISING ENGINEER Owner/Representative
Project : PROPOSED ONE BEDROOM RESIDENTIAL BUILDING
Location: TAMBONGAN, CANDIJAY, BOHOL
Owner/Representative: ATTY. MC ALDOUS CASTAÑARES

BILL OF MATERIALS AND COST ESTIMATES

MATERIALS/ITEM QNTY. UNIT COST/UNIT AMOUNT

I. Staking and layout, bunkhouse,


temporary connection of electricity and water

II. Excavation
column and wall footing 2.8 cu.m. 800 P 2240.00

III. Concreting Works


portland cement 55 bags 250 P 13750.00
gravel # 3/4 2 cu.m. 1000 P 2000.00
sand 2 cu.m. 1000 P 2000.00
12mm.dia. Def.rebar 16 pc. 250 P 4000.00
10mm.dia. Def.rebar 20 pc. 140 P 2800.00
tie wire #16 5 kg. 70 P 350.00

IV. Formworks, Trusses, Wall and Ceiling frame and Scaffoldings


2x6x10 gemilina wood (rafter) 15 pc. P 0.00
2x3x10 gemilina wood (purlins) 40 pc. P 0.00
2X2X10 gemiline wood ( facia frame) 30 pc. P 0.00
4"x4"x10' (column) 4 pc. P 0.00
2x6x12' gemilina wood (floor joist) 12 pc. P 0.00
1x6x12' gemilina wood (flooring) 45 pc. P 0.00
2X2X10 gemiline wood ( facia frame) 30 pc. P 0.00
2X2X10 gemiline wood ( wall frame) 85 pc. P 0.00
1/4" plywood 16 pc. 350 P 5600.00
Assorted CW Nail
#4 5 kgs. 70 P 350.00
#3 5 kgs. 70 P 350.00
#2 5 kgs. 70 P 350.00

V. Masonry Works and Walling


4" CHB 500 pc. 14 P 7000.00
portland cement 45 bags 250 P 11250.00
sand 4 cu.m. 1000 P 4000.00
10mm.dia. Def.rebar 22 pc. 140 P 3080.00

VI. Roofing
# 24 corrogated G.I. sheets, 10' 20 pc. 350 P 7000.00
# 24 plane G.I. sheets 20 pc. 250 P 5000.00
facia board ( 1/4" thk ficemboard) 4 pc. 350 P 1400.00
umbrella nail 5 kgs. 70 P 350.00
VII. Tile Works
900 x 150 floor tiles 42 pc. 150 P 6300.00
400 x 400 wall tiles 30 pc. 60 P 1800.00
tile adhesive 10 bags 450 P 4500.00
tile grout 5 bags 150 P 750.00
cement 10 bags 250 P 2500.00

VIII. Painting Works


flat latex white 6 pc. 700 P 4200.00
QDE 6 pc. 650 P 3900.00
body filler 2 pc. 750 P 1500.00

IX. Plumbing Fixtures


1 set WC and Lav 1 pc. 10000 P 10000.00
1 set rain shower 1 pc. 5000 P 5000.00
pipes and fittings 1 lot 1500 P 1500.00

X. Electrical Fixtures
conduits,wires and fixtures 1 lot 10000 P 10000.00

XI. TOTAL MATERIAL COST P 124820.00

XII. LABOR COST P 43687.00

XIII. TOTAL CONSTRUCTION COST P 168,507.00

PREPARED BY:

ENGR. ELMER A. LUSICA ATTY. MC ALDOUS CASTAÑARES


SUPERVISING ENGINEER Owner/Representative