Document(s)

The document outlines the tasks and timeline for a Balance Management System project from September 2019 to January 2020. It involves 4 main phases - Planning from September to October, Analysis from October to October, Design from October to November, and Implementation from November to January. Key tasks include interviewing sponsors, developing requirements, modeling current and new systems, designing architecture and interfaces, building, testing, and deploying the system.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
51 views1 page

Document(s)

The document outlines the tasks and timeline for a Balance Management System project from September 2019 to January 2020. It involves 4 main phases - Planning from September to October, Analysis from October to October, Design from October to November, and Implementation from November to January. Key tasks include interviewing sponsors, developing requirements, modeling current and new systems, designing architecture and interfaces, building, testing, and deploying the system.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

ID Task Name DurationStart Finish October 2019 November 2019 December 2019 January 2020

9 12 15 18 21 24 27 30 3 6 9 12 15 18 21 24 27 30 2 5 8 11 14 17 20 23 26 29 2 5 8 11 14 17 20 23 26 29 1 4 7 10 13 16 19 22
0 Balance Management System 84 d 9/16/19 1/9/20

1 Planning 14 d 9/16/19 10/3/19

2 Interview Project Sponsor 1d 9/16/19 9/16/19 Project Manager


3 Create System Request 2d 9/17/19 9/18/19 Project Manager
4 Plan Alternative Scenarios 5d 9/19/19 9/25/19 Project Manager
5 Feasibility Analysis 3d 9/26/19 9/30/19 Project Manager
6 Develop Work Breakdown Structure 1d 10/1/19 10/1/19 Project Manager
7 Create Schedule of The Project 1d 10/2/19 10/2/19 Project Manager
8 Staffing Plan 1d 10/3/19 10/3/19 Project Manager
9 Analysis 12 d 10/4/19 10/21/19

10 Model the Current System 1d 10/4/19 10/4/19 System Analyst


11 Formulate the New System 2d 10/4/19 10/7/19 System Analyst
12 Develop the System Concept 5d 10/8/19 10/14/19 System Analyst
13 Create Business Model 3d 10/15/19 10/17/19

14 Business Data Modelling 3d 10/15/19 10/17/19 System Analyst


15 Business Process Modelling 3d 10/15/19 10/17/19 System Analyst
16 Develop a System Proposal 2d 10/18/19 10/21/19 System Analyst
17 Design 22 d 10/22/19 11/20/19

18 Develop a Design Strategy 5d 10/22/19 10/28/19 Technical Lead


19 Design Architecture and Interfaces 5d 10/29/19 11/4/19 Technical Lead
20 Design Database and File Spesifications 5d 11/5/19 11/11/19 Technical Lead
21 Define the Program Design 7d 11/12/19 11/20/19

22 Design Balance Mapping 3d 11/12/19 11/14/19 Technical Lead


23 Design Debit Credit Core 5d 11/12/19 11/18/19 Technical Lead
24 Design Front End 3d 11/18/19 11/20/19 Technical Lead
25 Implementation 36 d 11/21/19 1/9/20

26 Build the System 17 d 11/21/19 12/13/19

27 Core Balance Mapping 5d 11/21/19 11/27/19 Back End Programmer


28 Develop Debit Credit Core 10 d 11/21/19 12/4/19 Back End Programmer
29 Develop Database System 5d 11/21/19 11/27/19 Back End Programmer
30 Core Backend and Database Integration 5d 11/28/19 12/4/19 Back End Programmer
31 Develop Front End 7d 12/5/19 12/13/19

36 Testing the System 5d 12/16/19 12/20/19

37 Unit Testing 2d 12/16/19 12/17/19 Quality Assurance Manager


38 Automated Testing 3d 12/18/19 12/20/19 Quality Assurance Manager
39 Deployment 9d 12/23/19 1/2/20

40 Deployment to Development Environment 3d 12/23/19 12/25/19 Technical Lead


41 Deployment to SIT Environment 3d 12/26/19 12/30/19 Technical Lead
42 Deployment to Production Environment 3d 12/31/19 1/2/20 Technical Lead
43 System Socialization 2d 1/3/20 1/6/20 Quality Assurance Manager
44 Support and Maintenance 3d 1/7/20 1/9/20 Quality Assurance Manager

Task Summary Inactive Milestone Duration-only Start-only External Milestone Manual Progress
Project: Balance Management S
Split Project Summary Inactive Summary Manual Summary Rollup Finish-only Deadline
Date: 10/2/19
Milestone Inactive Task Manual Task Manual Summary External Tasks Progress

Page 1