LABOUR SCHEDULE FOR THE ERECTION AND COMPLETION OF 1 NO.

3-STOREY REGIONAL COORDINATING COUNCIL OFFICE


PROJECT DURATION
MONTHS
No. MANPOWER DESCRIPTION
1 2 3 4 5 6 7 8 9
Oct-01 Nov-01 Dec-01 Jan-01 Feb-01 Mar-01 Apr-01 May-01 Jun-01
I INDIRECT MANPOWER
1 Project Manager 1 1 1 1 1 1 1 1 1
2 Project Engineer 1 2 2 2 2 2 1 1 1
3 Project Quantity Surveyor 2 2 2 3 3 3 3 2 2
4 Procurement Officer 2 3 3 3 3 3 3 3 2
5 Planning Engineer 2 2 2 2 2 2 2 2 2
6 Safety Personnel 2 2 2 2 2 2 2 2 2
7 Site Engineer 1 1 1 1 1 1 1 1 1
8 Site Supervisor 1 2 3 3 3 3 3 2 1
9 MEP Engineer 2 2 2 2 2 2 2 2 2
Subtotal - indirect 14 17 18 19 19 19 18 16 14
II DIRECT MANPOWER
1 Foreman 4 4 4 4 4 4 4 4 1
3 Carpenter 12 15 17 14 14 14 12 10 10
4 Plumber 8 9 12 12 13 14 12 8 8
5 Steel bender 15 15 15 15 15 15 15 10 10
6 Electrician 21 21 15 15 20 20 20 6 6
7 AC Technician 14 14 14 14 14 20 20 8 6
8 ICT Technician 8 8 9 10 10 10 10 10 10
9 Unskilled Labour 21 21 21 32 45 56 56 9 9
Subtotal - direct 103 107 107 116 135 153 149 65 60
TOTAL INDIRECT & DIRECT MANPOWER 117 124 125 135 154 172 167 81 74