Articulo 21
Articulo 21
South Africa.
Synopsis
The optimization of the cycle time to increase productivity at Ruashi Mining was an on-site project
investigation conducted from December 2017 to January 2018. The main objective of the investigation
Correspondence to: was to determine the actual cycle time components. These comprise the queuing time, loading time,
I.N.M. Nday hauling time, and dumping time of ADTs (articulated dump trucks). Data was also collected on two
hydraulic shovels to identify where these could be optimized. The actual cycle time obtained was
compared to the theoretical cycle time to ascertain the constraints, which affect productivity. By applying
Email: Systems Thinking to the cycle time, man-made constraints of the actual cycle time were identified and
[email protected] recommendations to mitigate them suggested to optimize the cycle time. However, rainfall is a natural
constraint that adversely affects the actual cycle time, and which cannot be mitigated.
In addition, both the theoretical and actual cycle time were analysed, as well as the theoretical and
Dates:
Received: 6 Feb. 2019 actual productivity for the year 2017. Based on the findings, conclusions and recommendations were
Revised: 5 Apr. 2019 made to optimize the cycle time.
Accepted: 16 Apr. 2019
Published: July 2019 Keywords
opencast mining, cycle time, optimization, productivity.
How to cite:
Nday, I.N.M. and Thomas, H.
Optimization of the cycle time to
increase productivity at Ruashi
Mining.
The Southern African Insitute of Introduction
Mining and Metallurgy The aim of the project was to increase Ruashi Mining’s productivity by 39%, from about 7.537 Mt of
DOI ID: broken material mined to 12..367 Mt targeted in 2017.
http://dx.doi.org/10.17159/2411-
Background
9717/624/2019
Ruashi Mining is a copper (main commodity), cobalt (by-product), and acid producer located in the
ORCiD ID:
Democratic Republic of Congo (DRC), 10 km from the city of Lubumbashi. Figure 1 shows the location
I.N.M. Nday
https://orchid.org/0000-0003- of the Ruashi Mining open pit.
1802-3609 Ruashi Mining started production in 1911 and in 2005 the mine was registered as a DRC
company owned by Metorex Group Limited. In November 2013, the Chinese company Jinchua Group
International Resources Co. Ltd. bought a majority stake in the business. Ruashi Mining currently
produces 38 000 t of copper and 4400 t of cobalt per annum. The company has contracted NB Mining
(a contract mining company) to transport its ore. To optimize the productivity of the mine, considering
ore flow delivery at Ruashi Mining, the cycle time is the indicator used in this project. The cycle time
components were recorded on site using a stopwatch.
Problem statement
There are many ways in which the productivity of a mine can be optimized, one way being by
decreasing the actual cycle time. At Ruashi Mining there are constraints affecting and extending the
cycle as shown in Figure 2. The constraints need to be identified and eliminated or mitigated to optimize
the cycle time, which will increase productivity in terms of the tonnage of broken rock transported per
annum.
Literature survey
To structure this project, a Master’s project on the optimization of the haulage cycle model for open pit
mining using a simulator and a context-based alert system was reviewed.
By utilizing mining software, simulations of an actual system in a process can be generated.
Parameters of the simulation can be modified several times with the aim of looking for the ultimate
optimization model. In this way it is possible to save costs, resources, and time.
The Journal of the Southern African Institute of Mining and Metallurgy VOLUME 119 JULY 2019 631 ◀
Figure 1—Location of Ruashi Mining in the southern part of the DRC (Google Earth, 2018)
▶ 632 JULY 2019 VOLUME 119 The Journal of the Southern African Institute of Mining and Metallurgy
Interpretation of data
The interpretation of the data (analysis and results) included
statistical calculations to find the average loading, hauling, and
manoeuvring time (dumping and queuing times). The actual
cycle time was then compared to the theoretical cycle time and the
excess times were determined for each cycle time component.
Figure 3—Five focusing steps to identify and eliminate constraints
Systems Thinking applied to optimize the cycle time
Approach to optimize the cycle time
numbers for both excavators and haulage to operate at maximum
efficiency. The operational conditions such as the weather, By definition, Systems Thinking is a management discipline used
breakdowns, and maintenance were to be considered because to comprehend different components constituting a system and
these conditions could disrupt the hauling and loading operation. examine how these components link and interact to contribute to
Achieving shovel productivity is dependent on having the overall system efficiency (Lane, 2018). Figure 4 shows the
adequate ADT coverage to minimize shovel delays. In cycle time system with individual activities.
addition, the availability of the shovel and ADT system is a The cycle time system consists of different activities; namely,
crucial parameter to consider, as it dictates the utilization and the loading time, travelling time with ADTs loaded, queuing time
subsequently the output (productivity) of the system. at the run-of-mine (ROM) pad, dumping time at the ROM pad
The parameters affecting the loading/haulage cycle were stockpiles, hauling time with ADTs unloaded, and queuing time
identified and simulated accordingly to determine the optimum at the loading point. For an optimal cycle time to be achieved,
operation cycle. Furthermore, the results have shown that for the abovementioned activities must be performing efficiently.
a distance of 2.7 km, six ADTs should be used for optimal Therefore, to optimize the cycle time, the constraining activity
efficiency (Vemba, 2004). must be identified and mitigated.
Mkhatshwa (2009) investigated the Mamatwan opencast
manganese mine in South Africa, which was failing to reach its Constraint identified in the cycle time system
daily production target. This was due to factors such as road By considering the cycle time as a system, and knowing that
conditions, and poor matching of ADTs and shovels. Mkhatshwa every system has a constraint, it is imperative to identify the
further stated that properly designed haul roads result in constraint(s) in the cycle time system to be able to optimize that
minimum traffic congestion and thus increase the production system.
efficiency of the ADTs. From the on-site investigation and data analysis, the
Mkhatshwa also stated that by correctly matching the following constraints were identified:
equipment, production can be improved by minimzsing the ➤ Work ethics of the operators (operators stopping the ADTs
loading time and obtaining 95% loading of ADTs. In practice, it is to discuss trivial matters, e.g. sport, for a short period of
impossible to achieve a 100% load for the ADTs. time)
➤ Mine road conditions
On-site investigation ➤ Condition of equipment
The on-site investigation included the time spent at the Ruashi ➤ Long queuing time of the ADTs at the shovel.
The Journal of the Southern African Institute of Mining and Metallurgy VOLUME 119 JULY 2019 633 ◀
Figure 6—Effect of the the rainfall season on monthly production at Ruashi Mining
▶ 634 JULY 2019 VOLUME 119 The Journal of the Southern African Institute of Mining and Metallurgy
The Journal of the Southern African Institute of Mining and Metallurgy VOLUME 119 JULY 2019 635 ◀
Table I
Theoretical cycle time results
Average time Average time
40 t 50 t 40 t 50 t
Queuing time (min) 0 0 Queuing time (min) 0 0
Loading time (min) EX 870 LCR-3 0.4833 0.4833 Loading time (min) EX 1200 0.4717 0.4717
Hauling time (min) 25.11 27.05 Hauling time (min) 25.11 27.05
Dumping time (min) 0.3433 0.3517 Dumping time (min) 0.3433 0.3517
Average theoretical cycle time (min) 25.937 27.885 Average theoretical cycle time (min) 25.925 27.873
Table II
Actual cycle times for different shovels and payloads
Average time Average time
40 t 50 t 40 t 50 t
Queuing time (min) 03:36.0 03:36.0 Queuing time (min) 03:36.0 03:36.0
Loading time (min) EX 870 LCR-3 02:01.0 02:12.2 Loading time (min) EX 1200 01:43.6 02:00.5
Hauling time (min) 21:59.4 25:59.5 Hauling time (min) 21:59.4 25:59.5
Dumping time (min) 00:25.2 00:24.3 Dumping time (min) 00:25.2 00:24.3
Average theoretical cycle time (min) 28:01.6 32:11.7 Average theoretical cycle time (min) 27:44.2 32:00.0
Theoretical cycle time results It is worth noting that the loading time data was collected for
two different shovels, and that affects the actual cycle times.
The theoretical cycle time is the ideal cycle time. Table I shows
the theoretical cycle time results after calculating different
Theoretical cycle time versus actual cycle time analysis
components making up the total theoretical cycle time.
Different shovels give different loading times, depending on The main differences between the theoretical and actual cycle
their capacities when loading ADTs of different payloads. This times are in the input assumptions.
will result in different theoretical cycle times, as can be seen in The purpose of calculating the theoretical (ideal) cycle time
Table I. was to determine the benchmark to optimize the actual cycle
time. In addition, the theoretical cycle time was calculated with
Actual cycle time calculations the data obtained from the manufacturer’s specification booklets,
The actual cycle time was calculated from the data collected whereas the actual cycle time was calculated with data collected
on site using a stopwatch. A summary of the actual cycle time on site. Figure 9 shows the chart comparing the actual and
components is shown in Table II. theoretical cycle time of a Hitachi EX 1200-6 shovel.
▶ 636 JULY 2019 VOLUME 119 The Journal of the Southern African Institute of Mining and Metallurgy
Figure 10—Actual versus theoretical cycle time for the EX 870 LCR-3
As expected, the actual cycle time is longer than the (planned and achieved) in 2017. By knowing the planned tons
theoretical cycle time. For the B40D, the difference in cycle time production per ADT and the number of trucks operating on the
is 1.52 minutes and for the B50D the difference is 4.13 minutes. mine, the calculations could be done as follows:
By mitigating the constraints identified, the cycle time will be
[5]
optimized, and the actual cycle time will be reduced to a time
equal to or better than the theoretical cycle time. Figure 10 shows
the actual versus theoretical cycle time for a Hitachi shovel EX [6]
870 LCR-3.
From Figure 10, with a Hitachi 870 LCR-3, the difference in
the cycle time of the B40D is 2.08 minutes and that for the B50D
[7]
is 4.24 minutes. There is also a need to optimize this cycle time
as the gap (largely caused by the queuing time) between the
theoretical and the actual cycle time is significant. ADTs and shovels have surpassed the required working
hours, which has become a constraint as identified during the on-
Production calculation site investigation. Consequently, unpredictable breakdowns occur,
which affect the machine availability and utilization as shown in
Production data interpretation
Table III.
The production data to be analysed was collected on the mine. As a result, there was a 39.06% shortfall in production in
Shift data: 2017–2018, with 4 830 403.91 t of unmoved material being the
➤ Two shifts per day outcome of the longer cycle time due to the constraints.
➤ Eleven hours per shift (ideal scenario)
➤ Nine effective working hours per shift, i.e. 18 effective
Conclusions
working hours per day. There are two types of constraints identified in the production
mining cycle. There are man-made constraints identified through
Planned versus actual production per annum Systems Thinking analysis (i.e. the mine roads and condition
Equations [5] to [7] are used to calculate the annual production of equipment, lack of work ethic from the operators, bucket fill
The Journal of the Southern African Institute of Mining and Metallurgy VOLUME 119 JULY 2019 637 ◀
Table III
Comparative production calculation results (predicted actuals) for each truck type matched with each shovel
factor of the shovel, and the queuing of ADTs at the shovel). data must have been caused by the shovel bucket filling
There is also a naturally occurring constraint, which is the rainfall factor. NB Mining must reinforce its operator-training
from mid-November to the beginning of April. This constraint programme so that the operators have the competency to
cannot be mitigated. operate the shovels at full efficiency
From the analysis of the results, the actual cycle time of ➤ The following formula can be used to calculate the number
a B40D ADT can be reduced by 8% (from 28.02 minutes to of trucks required per shovel. This will reduce the queuing
25.94 minutes) when used with the Hitachi 870 LCR-3 shovel. time of the ADTs at the shovel. For the purpose of this
Moreover, the actual cycle time for the B50D ADT can be reduced calculation, the actual hauling and loading cycle times are
by 13.2% (from 32.12 minutes to 27.89 minutes) using the used because they are based on the data collected on-site.
Hitachi 870 LCR-3. When excavating with the Hitachi 1200-6
shovel, the actual cycle time can be reduced by 5.5% (from 27.44
minutes to 25.94 minutes) for the B40D ADT and by 12.9%
(from 32 minutes to 27.87 minutes) for the B50D ADT. [8]
Finally, a reduction in cycle time increases production as
it can achieve a higher tonnage per hour and per shift. The
production can be increased with the same resources and fixed Future studies can be conducted on:
costs by optimizing the productivity through Systems Thinking.
Eventually, the increase in the financial performance of the mine ➤ Application of Systems Thinking in mining to optimize a
may extend the life of mine (LOM) as it will allow access to mine’s throughput
previously uneconomical reserves. Ultimately, the positive impact ➤ Adding value to a mine by saving costs on diesel when
on the country will be tangible through royalties, taxes, and the implementing ’stop-start systems’ on ADTs.
economy.
References
Recommendations Goldratt, E. Not dated. Theory of Constraints – Lean Manufacturing. https://www.
leanproduction.com/theory-of-constraints.html [accessed 29 March 2018].
➤ Scheduled mine roads and equipment maintenance. Mine Vasquez Coronado, P.P. 2014. Optimization of the haulage cycle model for open pit
roads must be regularly maintained, especially during mining using a discrete-event simulator and a context-based alert system. The
the rainy season, to allow smooth running of the mine University of Arizona. http://hdl.handle.net/10150/321594
operations Ercelebi, S. and Bascetin, A. 2009. Optimization of shovel-truck system for surface
➤ Empowering the workers would be an effective way to mining. Journal of the Southern African Institute of Mining and Metallurgy,
vol. 109. pp. 434–437.
overcome their poor work ethic, by demonstrating the
Lane, G. 2018. Systems Thinking for mining. Industrial and Research Seminar II.
impact their work has on the overall mine operation and
University of the Witwatersrand, Johannesburg.
output. Proving to workers how losing minutes discussing
Mkhatshwa, S. 2009. Optimization of the loading and hauling fleet at Mamatwan
trivial matters adversely affects the daily, monthly, and open pit mine. Journal of the Southern African Institute of Mining and
yearly cycle time, therefore, the productivity (Lane, 2018) Metallurgy, vol. 109. pp. 225–226.
➤ It was observed from the on-site investigation and proven Vemba, M. 2004. Loading and transport system at SMC – Optimization. Journal of the
by data analysis that the inconsistency in the loading time South African Institute of Mining and Metallurgy, vol. 104. pp. 141–146. u
▶ 638 JULY 2019 VOLUME 119 The Journal of the Southern African Institute of Mining and Metallurgy