WSM-MSRP-03 Mechanical Static and Rotating Procedure PDF
WSM-MSRP-03 Mechanical Static and Rotating Procedure PDF
WSM-MSRP-03 Mechanical Static and Rotating Procedure PDF
WSM-MSRP-03
MECHANICAL STATIC and ROTATING Rev. 0 15/03/19
PROCEDURE Page 1 of 13
WSM-MSRP-03
Revision Summary
INDEX
1 SCOPE ......................................................................................................................................... 4
2 PURPOSE .................................................................................................................................... 4
3 REFERENCE ................................................................................................................................. 4
4 RESPONSIBILITIES ....................................................................................................................... 4
5 PROCEDURE ............................................................................................................................... 4
5.1 Equipment Receival ........................................................................................................... 4
5.2 Handling of Equipment ...................................................................................................... 5
5.3 Equipment Preparation ...................................................................................................... 5
5.4 Installation of Equipment................................................................................................... 5
5.4.1 Static Equipment ........................................................................................................ 5
5.4.2 Rotating Equipment ................................................................................................... 9
5.5 Final Check for Static Equipment ..................................................................................... 13
5.6 Final Check for Rotating Equipment ................................................................................ 13
6 SAFETY ...................................................................................................................................... 13
Doc. No. WSM-MSRP-03
MECHANICAL STATIC and ROTATING Rev. 0 15/03/19
PROCEDURE Page 4 of 13
1 SCOPE
This method statement contains the general requirements for the equipment site erection
and alignment.
2 PURPOSE
The purpose of this procedure is to provide a general guide line for the receiving and
installation of all kind of equipment static and rotary in accordance with the project specification
and applicable standard.
3 REFERENCE
API 610 : Centrifugal Pumps for Petroleum, Petrochemical
and Natural Gas industries.
API 686 : Recommendation Practice for the installation of
machinery and installation design.
ANSI/ASME B30.5 : Safety Code for Crawler, Locomotive and Truck Cranes
ASNI/ASME : Safety Standard for Sling
4 RESPONSIBILITIES
The following site personal shall be involved as responsible for the equipment erection.
Section Engineer Equipment
Rigging Superintendent
Equipment Superintendent
Equipment Supervisor
QC Engineer
QC Equipment Inspector
Surveyor
1. Section Engineer is over all responsible for monitoring equipment erection operation in
accordance with the procedures, specification and construction drawing.
2. QC Inspectors in conjunction with the QC Engineer are responsible for the inspection in
accordance with specification and procedure of the equipment erection and the
compilation of equipment reports and records.
3. The equipment supervisor shall be responsible for the safe operation and quality of work
and shall ensure that the procedures are adhered to and that technical standard is
maintained.
4. The rigging superintendent is responsible for all rigging operation that includes off loading,
transporting, and erection and for the selection of proper crane capacity and rigging gear.
5. The surveyor is responsible for checking elevations and verticality as per construction
drawing.
5 PROCEDURE
5.1 Equipment Receival
1 All equipment received at site shall be inspected in accordance with vendor’s instruction
for site storage, installation and preservation.
2 Equipment shall be off loaded from trailer using the vendor recommended lifting point
and approved techniques.
Doc. No. WSM-MSRP-03
MECHANICAL STATIC and ROTATING Rev. 0 15/03/19
PROCEDURE Page 5 of 13
3 All loose items that are not required for immediate installation shall be suitably identified
and retained in the stores.
4 Protective covers on all equipment’s shall be removed if they appear damage and
equipment inspected before replacing the cover, if any damage has occurred, Discrepancy
report shall be issued with photograph showing damages as necessary.
5 Preservation of rotary equipment will be maintained during storage period, by shaft
rotation as per vendor manual.
6 Preservation for static equipment will be maintained during storing period by observing
the gauge of Nitrogen and recording on weekly basis.
5.2 Handling of Equipment
1 The shall be unpacked in the presence of QC Inspector and Client representative or
vendor representative. All spare parts and tools shall be unpacked clearly marked with
equipment numbers and stored in the warehouse. Fragile parts such as level oiler,
capillary tubes, small piping shall be removed from the equipment after match marked
and stored. The parts shall be clearly identified by the tags with equipment number.
2 All machined surfaces shall be checked and applied with rust-preventatives.
3 The equipment should not be placed directly on the earth, wooden blocks to be used.
4 All couplings shall be uncoupled and coupling elements shall be clearly marked with
equipment numbers matching the shaft hub and stored in the warehouse.
5 After checking the equipment and confirming that there are no discrepancies, equipment
shall be stored or delivered to installation site.
6 Bottom of the base plate shall be cleaned or wiped by suitable means to remove mud oil
or grease before installation.
5.3 Equipment Preparation
1 Dress up to be completed as much as possible in horizontal position, dress up for
platforms and ladders for all elevations from top to bottom including all insulation
required.
2 Before installation, all location, elevation and orientation of the equipment foundation
and support structures shall be checked and verified in accordance with installation
drawing.
3 All documents related to the equipment should be at job site with the concerned crew
following erection.
4 Dress up items, which cannot be erected in horizontal position will be erected in vertical
position after make alignment and vertically.
5.4 Installation of Equipment
5.4.1 Static Equipment
5.4.1.1 Preparation
Before erection of equipment, the job site shall be thoroughly surveyed and the
activity carefully planned, taking into consideration the following items.
o Equipment shape, dimension, weight and material, centre of gravity as well as
confirming the latest vendor drawings information to rigging plan.
o Cranes swing radius, crane movements and work space around the lifting area.
Any backfilling, laying of load spreading mats for the cranes shall be in accordance
with the allowable Ground Bearing Pressure (GBP) for the unit/area. This need to
be identified by EPC contractor and supplied to subcontractor (XXX).
Area ground compaction shall be done as per the requirement shown in the rigging
plan.
Doc. No. WSM-MSRP-03
MECHANICAL STATIC and ROTATING Rev. 0 15/03/19
PROCEDURE Page 6 of 13
Hook up the lifting tackles using the platform ladder or A-Frame ladder on both
the lifting lugs and tailing lugs of the tank.
During the tilting procedure, do note, not to jerk so as to ensure the titling is
smooth.
When the equipment is almost in vertical position, slowly release the tailing
cranes hook till there is no tension, and after which, lower the tank till its
approximately 500mm away from the ground.
Remove all the tailing lifting gears away from the equipment.
The signalman will instructed the crane operator to swing the telescopic boom
towards the designate equipment foundation for installation work.
After which follow as per direct lifting procedure for installation on the
foundation.
Rigger with walkie talkie and/or whistle will also be station to look out for any
obstruction during the lifting work.
If any obstruction is identified, rigger will notify by walkie talkie or by blowing the
whistle to stop the lifting work.
The equipment will now be hoist down slowly through the structure beam as
directly by the signalman communicating with the crane operator.
Equipment is to be lowered to a height of 200mm above the foundation packer
plate for the fitters to check its alignment and orientation.
Fitters will use plumb-bob and auto-level for orientation check.
Upon confirmation from the supervisor on site, lifting supervisor will take over
and coordinate the lowering of the pump on its packer plate and anchor bolts.
1 Vertically
2 Level
3 Installation Position
4 Elevation
1 Vertically
2 Level
3 Installation Position
4 Elevation
Temporary cover on all opening shall remain on the item until the related
pipelines are to be connected. Oil and foreign matters stuck on the surface of
Doc. No. WSM-MSRP-03
MECHANICAL STATIC and ROTATING Rev. 0 15/03/19
PROCEDURE Page 10 of 13
legs, beds, frames etc. which will come in contact with grouting mortar shall
be completely removed.
5.4.2.2 Foundation
Foundation shall be checked for the following items, before starting the
installation:
Dimensions.
Positions (center marking) and height (level marking).
Disorders in concrete such as cracks, abnormal concentration of
aggregates, porous state, surface condition etc.
Dimensions and cleanliness of anchor bolts pockets, if applicable.
Surface of foundation shall be conditioned for proper seating and bonding of the
grouting material with foundation. The surface shall be chipped around area of the seating
equipment. Foreign matters such as oil, grease, dirt, dust, loose concrete etc. shall be
completely removed from the surface.
Packing plate, i.e. liner plates, to be used, in general, shall be made of carbon steel,
unless otherwise specified by manufacturer or process requirement. Packing plate shall be
arranged so that the load of the equipment is uniformly distributed on the foundation.
5.4.2.3 Installation
Installation of equipment shall be executed in accordance with this procedure
taking precautions so that the anchor bolts and foundations will not be damaged and the
equipment not distorted. When anchor holes are used, the curing time of the grout mortar
filled in the holes shall be checked before the starting of the levelling work.
5.4.2.4 Leveling of Equipment
Liners and Wedges
In general, liners and wedges shall be prepared as indicated in below:
The dimensions may be modified as necessary or each application
A pair of wedges shall be used and the inclined surface of each wedge shall be
contact with each other more than 60 percent of the surface.
Liners and wedges shall be located on both sides of each anchor bolt and shall
beplaced close to the anchor bolts. Where the distance between the anchor bolts is
larger than 80cm, extra liners and wedges shall be located between the anchor bolts
to prevent the base plate from bending.
The concrete surface where the liner plates will be placed shall be chipped smoothly
and be cleaned completely.
A final check shall be made to ensure that the center of the equipment matches the
center line marked of the foundation.
Doc. No. WSM-MSRP-03
MECHANICAL STATIC and ROTATING Rev. 0 15/03/19
PROCEDURE Page 11 of 13
5.4.2.5 Grouting
Preparation for Grouting
The top of surface of the foundation shall be wetted thoroughly with fresh water
prior to the grouting work. If pipe sleeves are used for anchor bolts, standing water in the
sleeves shall be removed by a manual air pump, etc.
Material
Non-shrinking mortar shall be used under the outer frame of the base plate and in
the sleeves. Portland cement may be used in the base plate and in the sleeves to
grout the equipment, unless otherwise specified in the Instruction Manual.
The mixing ratio of non-shrinking mortar, portland cement, and clean fine sand, and
the ratio of water to cement shall be as specified by the non-shrinking mortar
manufacturer.
The mixing ratio of portland cement and clean fine sand shall be 1 : 2 in volume, and
the ratio of water, to cement shall be less than 40 percent in volume, unless
otherwise specified. Compressive strength of epoxy and non-shrink cementations is
630㎏/㎠ at 7 days.
Grouting Procedure
Sleeves used for anchor bolts shall be filled with grouting mortar under witness of
the CONTRACTOR engineer after which, unless otherwise specified in the Instruction
Manual.
The base plate shall be grouted as follows:
o The base plate shall be grouted ram the grout hole.
o The grout shall cover all wedges and liners.
o All trapped voids under the base plate shall be vented to allow full penetration
of the grouting mortar.
The surface of the mortar outside the base plate shall be finished smoothly.
All liners and wedges shall not be removed.
Grouting shall be inspected using light hammering to confirm that the mortar is filled
fully in the base plate voids and no cracks shall occur on the hardened surface.
Compressive Strength Test
Grouting shall be sample, cured, and tested for compressive strength in accordance
with ASTM C172, C31 and C39. Compressive test cylinder shall be prepared in oneset
cylinder per each mixing batch for test/and all tests must be carried out in testing
laboratory.
5.4.2.6 Epoxy Grouting
Grout for base-mounted or skid-mounted reciprocating machinery or critical
centrifugal/rotary compressors and pumps including drivers shall be epoxy type.
Compliance with minimum requirements of equipment vendors regarding grout materials
and installation is mandatory. Handling and placement of proprietary grouts shall be in
strict accordance with the manufacturer's recommended practice.
Procedure
All surfaces must be clean, free from standing water and all loosely adhering particles.
Cement latency must be removed, by mechanical means.
Doc. No. WSM-MSRP-03
MECHANICAL STATIC and ROTATING Rev. 0 15/03/19
PROCEDURE Page 12 of 13
Mix with a slow speed electric drill for 1-2 minutes. Then add the aggregate and
continue mixing until a homogeneous mortar is achieved.
Application
o When grouting under bearing hates, ensure there is sufficient pressure to
maintain movement of the grout. Air must be allowed to escape.
o For large volumes, apply in more than one layer, ensuring that the previous layers
have hardened and cooled.
Clean all tolls and equipment immediately after use with thinner.
5.4.2.7 Alignment of Equipment
Initial Alignment
After completion of the grouting and prior to connecting piping, alignment of
equipment shall be performed as follows :
1. The parallelism of the end surface of the equipment coupling hub and the driver
coupling hub, the clearance between the coupling hubs, and the parallelism of the
center lines of the shafts hall be measured with a dial gauge at the four points at 90
degree intervals, and shall be adjusted by inserting shims under the lug or the saddle
of the driver and/or speed exchanger.
2. Tolerance of alignment shall be indicated in Table 3. The material of the shims for
alignment shall be of brass or of stainless steel. The size of the shims shall be at
least150mm in width, and 0.03, 0.04, 0.05, 0.1, 0.2, 0.5, 1 and 2mm in thickness, and
if legs or saddles of the equipment are smaller than 150mm in which, the size of the
shims shall be the same as the width of the equipment.
6 SAFETY
1. Job safety analysis attached.
2. All workers shall conduct orientation course.
3. Work at height full body harness shall be used with 100%Tie off.
4. Make sure access completely safe on scaffolding with green tag.
5. Hot work, A Gas/Oxygen level check through the use of gas detector shall be used prior
to any hot work (welding-gas cutting).
6. Confined space ventilation using air mover is required for any vessel prior to entry for
any internal activity.
7. 24V or 12V power lighting shall be used as required.
8. Working area shall be barricaded. (Crane operation area, erection or dismantling of
Scaffolding)
9. All warning signs shall be fixed in proper location to ensure personnel safety.
10. Rigging operation will be done under control of rigging superintendent all using rigging
study or lift plan as required for each lift.