LETTER REQUEST FOR INSPECTION

BFAR-RFTFCD
Tabaco City

Sir/Madam:

This is to inform your good office that the project titled “Labor and
Materials for the Repair and Replacement of Work-out/Dilapidated
Roofing of Training/Mess Hall Facility” has been completed on August
25, 2018, with a contract amount of Three Hundred Forty Thousand Six
Hundred Pesos (Php 340,687.17) which was completed earlier than
expected. Project was 100% completed last May 9, 2018.

Very truly yours,

RAM BERCES DYANGKO


PROPRIETOR

Conforme:

Bicol University Tabaco


Date: ________________