Case Study 2 Submission
Case Study 2 Submission
Case Study 2 Submission
Case Study#2
Shakeena Sparks
BMGT 488
20 July 2019
University of Maryland
[SHORTENED TITLE UP TO 50 CHARACTERS] 2
A green company is a business that uses recyclable and natural materials to make
products. They aim to protect the environment, societies, and communities by providing the safe
products. The company also focuses on the health of its employees and wish to bring dignity in
Green company will be producing solar windows. The scope of making these windows is
described below:
• Green company will be producing solar windows at the company main manufacturing
location.
• Solar windows will use “thermochromism’’ that enables the windows to change color
• Glass for creating windows will be aluminum-framed, which enable it to become energy
• The aluminum-framed glass will be recyclable, durable, and reduce the amount of heat
• Customer requirements will be a focus while creating windows. Windows will be made
• The project will start on 1st August, and the Project will be completed within three
• The Green Company will produce solar panels 3000 units per month.
• After developing the solar windows Company will deliver it to its supplier ‘’XRP
company’’.
• A green company is not responsible for installation after the product has been delivered
Name Department/Position
Director of Project Management
Phil Graham
Project manager
Rosalie
Functional Manager
Keith
Customer
Supplier
XRP Company
Lab for testing and approval products
ABC Lab
Safety inspection
OSHA
Supplier of thermochromism
YYZ Company
[SHORTENED TITLE UP TO 50 CHARACTERS] 4
Risk Matrix:
Likelihood
Almost Could Known to Common
impossible Not likely occur occur occurrence
20 (Schedule
5 10 15 25 (Cost risk)
Catastrophic risk)
12 16
8 (Governance
4 (Legal (Performance 20
risk)
Major risk) risk)
Impact
Moderate 3 6 9 12 15
Minor 2 4 6 8 10
Insignificant 1 2 3 4 5
Low risk
Medium risk
Significant
risk
High risk
1. The project manager should have realized that schedule was out of scope at the time of
agreement. No contract must be signed without intimation of schedule agreed in writing and signed
by both parties. In this case, the project manager didn’t know the delivery schedule and didn’t
know the number of panels to be produced. So, he estimated 3000 units to be produced within a
month. When the project manager got the information that the plant will be available two months
ahead at that point, the project manager should have again determined the schedule. The budgetary
costs closely link with the schedules. Therefore, the project manager must have calculated the risk
[SHORTENED TITLE UP TO 50 CHARACTERS] 5
of overrun budget cost due to no fixed delivery schedule and lack of information on requirements
by the regulatory authorities of the industry i.e. OSHA and EPA, at the time of contract.
The project manager must have renegotiated the terms of the contract related to rescheduling and
budget when Green informed him of early arrival of their production plant.
2. It is the responsibility of OSHA and EPA to ensure the safety of workers working within an
organization. OSHA provides requirements for approval of the product. In this case, the final set
of specifications depending on the requirement Of OSHA and EPA. The execution of the contract
started about 6 months before any clear specifications reached at ABC. That’s the reason customers
could not provide a specification to the functional manager. When customers provide specification
after six months so, the company had to remake 6000 production units because they cannot meet
There were also defects and errors in the product which occurred because the specifications were
not provided for product standards. The delays in production was caused by errors and defects in
the product. These errors and defects were not due to the working by the staff, but rather due to
to face meetings, annual meetings, and general meetings must be conducted between managers.
memos can also be a good tool for communication. Communication was not effective between the
functional manager and project manager. Meetings must be organized so that the manager can
communicate and share their suggestions. The primary issue was the functional manager were
[SHORTENED TITLE UP TO 50 CHARACTERS] 6
communicating unwanted to the employees about their overtime. This creates unrest between the
employees, and unrest as generally employees wish to earn more through option of overtime.
4. The risk for the functional manager and the project manager were as:
Schedule Risk: There was no fixed schedule for deliverables, so the company was not able to
Performance Risk: The authorities did not provide clear Specifications like OSHA and EPA. They
were waiting for testing of the plant. There was a risk to meet the expected specifications.
Cost Risk: As schedules and specifications were not provided, it ultimately lead to high cost. So
References
001150-01-2195-OL3-
7380/Case%20Overrun%20pdf.pdf?_&d2lSessionVal=oeOK1HT8wlSSrroxbcMXhZ6lf
a-green-company/