Observations On Work Procedure of Excavation
Observations On Work Procedure of Excavation
Observations On Work Procedure of Excavation
on 09.09.2019:-
The excavation procedure mentioned is for Main Plant Buildings & Grids also needs
correction.
Grid no & Elevations shall be separately mentioned for TB-area and IDCT area.
Drawing at sr. no. 1 &2 shall be as per latest revision issued to TPL.
Excavation, Founding Level & Existing Dewatering Scheme Drawing of Main Plant Area
is to be referred.
6. Chapter 8.3.2 (Slope Protection from Soil erosion to Rain & Wind):- NOTED &
INCORPORATED
It has been mentioned that the slope protection will done during monsoon, however it
shall be done all the time.
Slope of Cut-off Drain is written as 1 in 60 whereas in the sketch it has been shown as 1
in 30.
Table of drain size shall be separate for TB & IDCT area depending upon their
excavation & final finished levels.
Drainage area in the design calculation of surface runoff shall be as per drawings of TB
& IDCT area.
Stack yard area shall be as per approved area allocation of Stackyard location.
10. Chapter 9 (Structure wise Excavation & Levels):- NOTED & INCORPORATED
In the table of Final Excavation Level, grids need to be mentioned as per Elevation.
Also, General area Elevation of 83.4 for IDCT area is not mentioned.
11. Chapter 9.1 (Excavation Details of TB-1 & TB-2):- NOTED & INCORPORATED
Further, deeper excavation scheme below EL83.4 has not been mentioned.
12. Chapter 10 (Plant, Equipment & Resources for Excavation):- NOTED &
INCORPORATED
Standby arrangement for Pumps shall be as per requirement of drawing i.e. 30%
In the remark column of the table it has been inadvertently mentioned for use by
package-I contractor.
Area to be dewatered shall be corrected as 580m X 160m for IDCT & 500m X 180m for
TB area. Top of excavation line is to be considered.
50-60 well points connected to 1 pump has been mentioned instead of 65 as mentioned
elsewhere.
Para 3,4 &5 is not related to procedural part & hence can be deleted.
Discharge from pumping sets has been mentioned through lined drains whereas as
per Item no. 6.2 of BOQ, it is to be done through peripheral pipes upto discharge
location.
No. of well points have been mentioned is not consistent in the document.
Mention Dia of well points, Riser Pipe & Header Pipe.
Sketch shown does not indicate the existing slopes & ramps. Sketch shall be more
specific & elaborate as per the requirement of the drawing.
In chapter 12.3.2, spacing of well points & grid nos is to be mentioned. Stage wise
Length, Width & Perimeter shall be calculated exactly as per drawing.
Details of Intermediaries temp. well points have not been included. Details of Standby
pumps are also to be mentioned in the table.
16. Chapter 12.4 (Dewatering- Field Execution Approach):- NOTED & INCORPORATED
In case of Power failure, for avoiding backflow of dewatered water in header pipe,
provision of NRV in header pipes may be explored.
Dewatering layout shall be such that it does not interfere within building foot print area.
Note is to be added:- All items involved for dewatering system shall be new and conform
to relevant IS.
Sketch for Area lighting scheme & along with Electrical Arrangement around the
excavation area is to be included.
Water level shall be minimum 1m below working level instead of excavation level.
Header to be corrected for Complete Project name as per Work Order. Title of Document
shall be complete.