HSBGN 2018
HSBGN 2018
HSBGN 2018
Tahun 2018
Provinsi Kalimantan Timur
Kabupaten Penajam Paser Utara
( dalam Rupiah)
GEDUNG NEGARA
TIDAK SEDERHANA SEDERHANA
6,270,000 5,110,000
RUMAH NEGARA
TIPE A TIPE B TIPE C,D,E
6,260,000 5,900,000 4,370,000
Page 1
NO URAIAN KETERANGAN SATUAN HARGA SATUAN Bahan Pengganti
II BAHAN PEREKAT
1 Semen (50 Kg) Semen Indonesia zak 70,000
2 Semen Warna Semen Indonesia kg 14,000
IV BAHAN KAYU
1 Kayu Klas I Jati m3 5,000,000 Ulin
2 Kayu Klas II Kamper m3 3,371,000 Kapur
3 Kayu Klas III Meranti m3 2,920,000
4 Kayu Klas IV Terentang m3 1,790,000 Keruing
5 Dolken dia 8 s/d 10 cm p. 4 m btg 8,000 Galam
V BAHAN ALMUNIUM
1 Kusen Almunium 3", Alexindo m' 125,000
2 Rangka Jendela Almunium Alexindo m' 148,000
3 Rangka Pintu Almunium Alexindo m' 148,000
4 Kusen & Pintu PVC toilet Maspion unt 625,000
5 Engsel 3", ex Bos bh 75,000
7 Handle pintu type HRE 75.01 ex. Cisa bh 150,000
8 Selinder type 08510 ex. Cisa bh 110,000
9 Door Stoper bh 90,000
10 Door closer bh 250,000
11 Slot Tanam bh 55,000
12 Kait Angin bh 15,000
13 Grendel bh 15,000
VI BAHAN PELAPIS :
1 Triplek t. 3 mm Uk 120x240 cm lbr 55,000
2 Triplex t. 4 mm Uk 120x240 cm lbr 75,000 plywood
3 Triplex t. 9 mm Uk 120x240 cm lbr 135,000
Page 1
NO URAIAN KETERANGAN SATUAN HARGA SATUAN Bahan Pengganti
VII BAHAN LANTAI & DINDING KERAMIK
1 Keramik 30/30 ex Masterina m2 65,000
2 Granite Tile 40/40 ex Granito tile m2 237,600
3 Plint Keramik 10/30 cm ex. Roman bh 2,000
4 Plint Granitetile 10/40 cm ex. Granito bh 9,900
IX BAHAN KACA :
1 Kaca Polos 3 mm m2 85,000
2 Kaca Polos 5 mm m2 154,000
3 Kaca Polos 8 mm m2 235,000
XI BAHAN FINISHING :
1 Cat kayu/Besi ex. SEIV Kg 56,000
2 Plamir Kayu Kg 21,600
3 Meni kayu ex. Nippon kg 21,600
4 Wood Filler Impra Kg 35,000
5 Thinner ND IMPALA Ltr 21,600 Thinner A Aries
6 Amplas Kayu Lbr 3,000
7 Kwas cat bh 15,000
8 Cat Tembok kw1 ex. Dulux ; Warna standard Kg 117,500
9 Cat Tembok kw2 ex. Vinilex ; Warna standard Kg 73,750
10 Plamir Tembok Kg 35,000 Cat Alkali
11 Lem Kayu kg 25,000
12 Seal tape bh 7,000
13 Minyak bekisting Ltr 18,000 residu
Page 2
NO URAIAN KETERANGAN SATUAN HARGA SATUAN Bahan Pengganti
XIV BAHAN SALURAN AIR
1 Pipa PVC dia 1/2" ex. Wavin ; P. 4 m m' 5,750
2 Pipa PVC dia 3/4" ex. Wavin ; P. 4 m m' 7,000
3 Pipa PVC dia 1" ex. Wavin ; P. 4 m m' 9,500
4 Pipa PVC dia 2" ex. Wavin ; P. 4 m m' 22,500
5 Pipa PVC dia 3" ex. Wavin ; P. 4 m m' 42,500
6 Pipa PVC dia 4" ex. Wavin ; P. 4 m m' 67,500
7 Stop kran dia 1" ex. Onda bh 25,000
8 Klep diameter 3/4" ex. Onda bh 66,000
9 Tangki air 1000 liter EXEL bh 1,300,000 Grand 1200 Liter
10 Tangki air 500 liter EXEL bh 950,000 Grand 700 Liter
11 Pelampung otomatis bh 50,000
12 Roof Drain Metal Bh 183,000
13 Mesin Jet Pump kap.250 watt Groundfos unt 1,030,000 Shimizu
14 Mesin Pompa tekan kap. 150 watt Groundfos unt 875,000 Panasonic
XV PERALATAN ELEKTRIKAL
1 Box panel PVC isi 4 MCB Legran bh 620,000
2 MCB 6 A Legran bh 60,000
3 MCB 4 A Legran bh 50,000
4 Kabel NYM 2 x 2,5 mm2 m' 10,400
5 Kabel NYM 3 x 2,5 mm2 m' 13,800
6 Kabel telephone 4 x 0.5 mm m' 650
7 Isolasi bh 5,000
8 Saklar tunggal Broco bh 18,000
9 Saklar ganda Broco bh 20,000
10 Stop kontak Broco bh 18,000
11 Outlet TV Broco bh 60,000
12 Outlet Telephone Broco bh 41,000
13 Down light / PLC 13 W bh 125,000
14 Fitting plafond + lampu SL Panasonic bh 65,000
15 Lampu TL 2 x 18 watt grille Panasonic bh 596,000
16 Lampu TL 2 x 36 watt grille Panasonic bh 898,000
Page 3
menu ANALISA HARSA SATUAN
Berdasarkan SNI 2007 - 2008
10%
Overhead
HARGA UPAH JUMLAH HARGA
SUMBER DATA UNIT URAIAN SATUAN KOEFISIEN Asuransi TOTAL PEMBULATAN
DAN MATERIAL
Material Upah lain-lain
I. PEKERJAAN PERSIAPAN :
RSNI T-12-2002 M2 Pembersihan lapangan & Perataan tanah - 11,650 10% 12,815 12,800
Pekerja org/hr 0.100 110,000 11,000
Mandor org/hr 0.005 130,000 650
-
RSNI T-12-2002 M Pengukuran & Pasang bouwplank - 300 15,750 10% 17,655 17,700
Kayu Kaso 5 / 7 (borneo) m3 0.012 - -
Kayu Papan 3 / 20 borneo m3 0.007 - -
Paku 5 s/d 10 cm kg 0.020 15,000 300
Pekerja org/hr 0.080 110,000 8,800
Tukang Kayu Kasar org/hr 0.040 125,000 5,000
Kepala Tukang Kayu org/hr 0.010 130,000 1,300
Mandor org/hr 0.005 130,000 650
(dinding tripleks 6 -
RSNI T-12-2002 M2 Pembuatan direksi keet mm+ atap asbes 120,600 195,000 10% 347,160 347,200
Kaso kamper medan gelombang+ m3 0.050 - -
Triplex t. 4 mm Dinding lbr 0.800 75,000 60,000
Triplex t. 4 mm Plafond lbr 0.700 75,000 52,500
Paku 4 s/d 7 cm kg 0.500 - -
Paku payung bh 9.000 - -
Triplex t. 9 mm Pintu m2 0.060 135,000 8,100
Cat plafond acrylic emulsion KW.III m2 1.000 - -
Pekerja org/hr 1.200 110,000 132,000
Tukang Kayu Kasar org/hr 0.400 125,000 50,000
Kepala Tukang Kayu org/hr 0.040 130,000 5,200
Mandor org/hr 0.060 130,000 7,800
Page 1
menu ANALISA HARSA SATUAN
Berdasarkan SNI 2007 - 2008
10%
Overhead
HARGA UPAH JUMLAH HARGA
SUMBER DATA UNIT URAIAN SATUAN KOEFISIEN Asuransi TOTAL PEMBULATAN
DAN MATERIAL
Material Upah lain-lain
Kwas cat bh 0.200 15,000 3,000
Cat kayu/Besi kg 0.400 56,000 22,400
Semen (50 Kg) zak 0.500 70,000 35,000
Pasir Beton m3 0.060 515,000 30,900
Batu Split Pecah Mesin 3/5 m3 0.100 450,000 45,000
Pekerja org/hr 0.630 110,000 69,300
Tukang Kayu Kasar org/hr 1.000 125,000 125,000
Tukang Cat Biasa org/hr 0.500 125,000 62,500
Kepala Tukang Kayu org/hr 0.100 130,000 13,000
Mandor org/hr 0.100 130,000 13,000
-
PEKERJAAN TANAH : -
-
SNI DT 91-0006-2007 M2 Stripping tanah tebal 20 cm - - 6,150 10% 6,765 6,800
Pekerja org/hr 0.050 110,000 5,500
Mandor org/hr 0.005 130,000 650
-
SNI 2835:2008 - 6.1 M3 Galian tanah, dalam s/d 1 m - - 85,750 10% 94,325 94,300
Pekerja org/hr 0.750 110,000 82,500
Mandor org/hr 0.025 130,000 3,250
-
SNI 2835:2008 - 6.9 M3 Urugan tanah kembali 1/3 dari harga galian - - 28,583 10% 31,442 31,400
Pekerja org/hr 0.250 110,000 27,500
Mandor org/hr 0.008 130,000 1,083
-
-
SNI 2835:2008 - 6.11 M3 Pas. Urugan pasir - 162,000 34,300 196,300 196,300
Pasir Urug m3 1.200 135,000 162,000
Pekerja org/hr 0.300 110,000 33,000
Mandor org/hr 0.010 130,000 1,300
-
-
SNI 2835:2008 - 6.8 M3 Buang tanah Jarak angkut +/- 15 M - - 37,600 10% 41,360 41,400
Pekerja org/hr 0.330 110,000 36,300
Mandor org/hr 0.010 130,000 1,300
Page 2
menu ANALISA HARSA SATUAN
Berdasarkan SNI 2007 - 2008
10%
Overhead
HARGA UPAH JUMLAH HARGA
SUMBER DATA UNIT URAIAN SATUAN KOEFISIEN Asuransi TOTAL PEMBULATAN
DAN MATERIAL
Material Upah lain-lain
SNI DT 91-0006-2007 M3 Pas. Urugan tanah 162,000 30,750 10% 212,025 212,000
Tanah Urug m3 1.200 135,000 162,000
Pekerja org/hr 0.250 110,000 27,500
Mandor org/hr 0.025 130,000 3,250
PEKERJAAN PONDASI :
SNI 7395-2008-6.9 M3 Aanstamping batu kali 585,720 144,690 10% 803,451 803,500
Batu kali m3 1.200 302,700 363,240
Pasir Beton m3 0.432 515,000 222,480
Pekerja org/hr 0.780 110,000 85,800
Tukang Batu Kasar org/hr 0.390 125,000 48,750
Kepala Tukang Batu org/hr 0.039 130,000 5,070
Mandor org/hr 0.039 130,000 5,070
-
SNI 7395-2008-6.2 M3 Pas. pondasi batu kali 1:4 - 661,640 278,250 10% 1,033,879 1,033,900
Batu kali m3 1.200 302,700 363,240
Semen (50 Kg) zak 3.260 70,000 228,200
Pasir Pasang m3 0.520 135,000 70,200
Pekerja org/hr 1.500 110,000 165,000
Tukang Batu Kasar org/hr 0.750 125,000 93,750
Kepala Tukang Batu org/hr 0.075 130,000 9,750
Mandor org/hr 0.075 130,000 9,750
-
PEKERJAAN BETON : -
SNI 7394:2008-6.5 M3 Beton K - 175 Sitemix - 1,078,971 230,305 10% 1,440,204 1,440,200
Semen (50 Kg) zak 6.520 70,000 456,400
Pasir Beton m3 0.543 515,000 279,571
Batu Split Pecah Mesin 1/2 m3 0.762 450,000 343,000
Pekerja org/hr 1.650 110,000 181,500
Tukang Batu Kasar org/hr 0.275 125,000 34,375
Kepala Tukang Batu org/hr 0.028 130,000 3,640
Page 3
menu ANALISA HARSA SATUAN
Berdasarkan SNI 2007 - 2008
10%
Overhead
HARGA UPAH JUMLAH HARGA
SUMBER DATA UNIT URAIAN SATUAN KOEFISIEN Asuransi TOTAL PEMBULATAN
DAN MATERIAL
Material Upah lain-lain
Mandor org/hr 0.083 130,000 10,790
-
SNI 7394:2008-6.6 M3 Beton K - 200 Sitemix - 1,105,370 230,305 10% 1,469,243 1,469,200
Semen (50 Kg) zak 7.040 70,000 492,800
Pasir Beton m3 0.522 515,000 268,904
Batu Split Pecah Mesin 1/2 m3 0.764 450,000 343,667
Pekerja org/hr 1.650 110,000 181,500
Tukang Batu Kasar org/hr 0.275 125,000 34,375
Kepala Tukang Batu org/hr 0.028 130,000 3,640
Mandor org/hr 0.083 130,000 10,790
-
SNI 7394:2008-6.7 M3 Beton K - 225 Sitemix - 1,125,164 230,305 10% 1,491,016 1,491,000
Semen (50 Kg) zak 7.420 70,000 519,400
Pasir Beton m3 0.499 515,000 256,764
Batu Split Pecah Mesin 1/2 m3 0.776 450,000 349,000
Pekerja org/hr 1.650 110,000 181,500
Tukang Batu Kasar org/hr 0.275 125,000 34,375
Kepala Tukang Batu org/hr 0.028 130,000 3,640
Mandor org/hr 0.083 130,000 10,790
-
SNI 7394:2008-6.8 M3 Beton K - 250 Sitemix - 1,138,490 230,305 10% 1,505,675 1,505,700
Semen (50 Kg) zak 7.680 70,000 537,600
Pasir Beton m3 0.494 515,000 254,557
Batu Split Pecah Mesin 1/2 m3 0.770 450,000 346,333
Pekerja org/hr 1.650 110,000 181,500
Tukang Batu Kasar org/hr 0.275 125,000 34,375
Kepala Tukang Batu org/hr 0.028 130,000 3,640
Mandor org/hr 0.083 130,000 10,790
-
SNI 7394:2008-6.17 Kg Tulangan besi beton U-24 - 12,900 1,788 10% 16,157 16,200
Besi Beton U-24 kg 1.0500 12,000 12,600
Kawat beton kg 0.0150 20,000 300
Pekerja org/hr 0.0070 110,000 770
Tukang Besi Tulangan org/hr 0.0070 125,000 875
Kepala Tukang Besi org/hr 0.0007 130,000 91
Mandor org/hr 0.0004 130,000 52
Page 4
menu ANALISA HARSA SATUAN
Berdasarkan SNI 2007 - 2008
10%
Overhead
HARGA UPAH JUMLAH HARGA
SUMBER DATA UNIT URAIAN SATUAN KOEFISIEN Asuransi TOTAL PEMBULATAN
DAN MATERIAL
Material Upah lain-lain
-
SNI 7394:2008-6.17 Kg Tulangan besi beton U-39 - 14,475 1,788 10% 17,889 17,900
Besi Beton U-39 kg 1.0500 13,500 14,175
Kawat beton kg 0.0150 20,000 300
Pekerja org/hr 0.0070 110,000 770
Tukang Besi Tulangan org/hr 0.0070 125,000 875
Kepala Tukang Besi org/hr 0.0007 130,000 91
Mandor org/hr 0.0004 130,000 52
-
SNI 7394:2008-6.21 M2 Bekisting sloof beton - 137,700 96,460 10% 257,576 257,600
Kayu Klas III m3 0.045 2,920,000 131,400
Paku 5 s/d 10 cm kg 0.300 15,000 4,500
Minyak bekisting ltr 0.100 18,000 1,800
Pekerja org/hr 0.520 110,000 57,200
Tukang Kayu Kasar org/hr 0.260 125,000 32,500
Kepala Tukang Kayu org/hr 0.026 130,000 3,380
Mandor org/hr 0.026 130,000 3,380
-
SNI DT 91-0006-2007 M2 Bekisting Praktis beton - 5,530 96,460 10% 112,189 112,200
Kayu Klas IV Kayu klas IV m3 0.002 1,790,000 3,580
Paku 5 s/d 10 cm kg 0.010 15,000 150
Minyak bekisting ltr 0.100 18,000 1,800
Pekerja org/hr 0.520 110,000 57,200
Tukang Kayu Kasar org/hr 0.260 125,000 32,500
Kepala Tukang Kayu org/hr 0.026 130,000 3,380
Mandor org/hr 0.026 130,000 3,380
-
-
SNI 7394:2008-6.24 M2 Bekisting beton plat lantai 272,215 122,430 10% 434,110 434,100
Triplex t. 9 mm lbr 0.350 135,000 47,250
Paku 5 s/d 10 cm kg 0.400 15,000 6,000
Kayu Klas II Balok,Kayu klas III m3 0.015 3,371,000 50,565
Kayu Klas III Kaso, Kayu klas IV m3 0.040 2,920,000 116,800
Dolken dia 8 s/d 10 cm btg 6.000 8,000 48,000
Minyak bekisting ltr 0.200 18,000 3,600
Pekerja org/hr 0.660 110,000 72,600
Page 5
menu ANALISA HARSA SATUAN
Berdasarkan SNI 2007 - 2008
10%
Overhead
HARGA UPAH JUMLAH HARGA
SUMBER DATA UNIT URAIAN SATUAN KOEFISIEN Asuransi TOTAL PEMBULATAN
DAN MATERIAL
Material Upah lain-lain
Tukang Kayu Kasar org/hr 0.330 125,000 41,250
Kepala Tukang Kayu org/hr 0.033 130,000 4,290
Mandor org/hr 0.033 130,000 4,290
-
SNI 7394:2008-6.22 M2 Bekisting kolom beton - 240,215 122,430 10% 398,910 398,900
Triplex t. 9 mm lbr 0.350 135,000 47,250
Paku 5 s/d 10 cm kg 0.400 15,000 6,000
Kayu Klas II Balok, Kayu klas IV m3 0.015 3,371,000 50,565
Kayu Klas III Kaso, Kayu klas IV m3 0.040 2,920,000 116,800
Dolken dia 8 s/d 10 cm btg 2.000 8,000 16,000
Minyak bekisting ltr 0.200 18,000 3,600
Pekerja org/hr 0.660 110,000 72,600
Tukang Kayu Kasar org/hr 0.330 125,000 41,250
Kepala Tukang Kayu org/hr 0.033 130,000 4,290
Mandor org/hr 0.033 130,000 4,290
-
SNI 7394:2008-6.23 M2 Bekisting balok beton - 250,328 122,430 10% 410,034 410,000
Triplex t. 9 mm lbr 0.350 135,000 47,250
Paku 5 s/d 10 cm kg 0.400 15,000 6,000
Kayu Klas II Balok,Kayu klas III m3 0.018 3,371,000 60,678
Kayu Klas III Kaso, Kayu klas IV m3 0.040 2,920,000 116,800
Dolken dia 8 s/d 10 cm btg 2.000 8,000 16,000
Minyak bekisting ltr 0.200 18,000 3,600
Pekerja org/hr 0.660 110,000 72,600
Tukang Kayu Kasar org/hr 0.330 125,000 41,250
Kepala Tukang Kayu org/hr 0.033 130,000 4,290
Mandor org/hr 0.033 130,000 4,290
-
M2 Pas. Lantai kerja beton tumbuk 1:3:5 t. 10 cm - 90,795 - 10% 99,875 99,900
Semen (50 Kg) zak 0.300 70,000 21,000
Pasir Beton m3 0.063 515,000 32,445
Batu Split Pecah Mesin 1/2 m3 0.083 450,000 37,350
Pekerja org/hr 0.130 110,000 14,300
Tukang Batu Kasar org/hr 0.100 125,000 12,500
Kepala Tukang Batu org/hr 0.010 130,000 1,300
Mandor org/hr 0.010 130,000 1,300
Page 6
menu ANALISA HARSA SATUAN
Berdasarkan SNI 2007 - 2008
10%
Overhead
HARGA UPAH JUMLAH HARGA
SUMBER DATA UNIT URAIAN SATUAN KOEFISIEN Asuransi TOTAL PEMBULATAN
DAN MATERIAL
Material Upah lain-lain
-
PEKERJAAN DINDING -
SNI 6897:2008-6.16 M2 Pas. Dinding bata beton ringan; ad 1:3 - 325,758 61,540 10% 426,028 426,000
Bata beton ringan ex Celcon bh 12.500 14,500 181,250
Semen (50 Kg) zak 0.606 70,000 42,448
Besi angkur d= 8 mm kg 0.280 13,500 3,780
Pasir Pasang m3 0.728 135,000 98,280
Pekerja org/hr 0.350 110,000 38,500
Tukang Batu Kasar org/hr 0.150 125,000 18,750
Kepala Tukang Batu org/hr 0.015 130,000 1,950
Mandor org/hr 0.018 130,000 2,340
-
SNI 6897:2008-6.17 M2 Pas. Dinding bata beton ringan; ad 1:4 - 323,214 61,540 10% 423,229 423,200
Bata beton ringan ex Celcon bh 12.500 14,500 181,250
Semen (50 Kg) zak 0.485 70,000 33,964
Pasir Pasang m3 0.772 135,000 104,220
Besi angkur d= 8 mm kg 0.280 13,500 3,780
Pekerja org/hr 0.350 110,000 38,500
Tukang Batu Kasar org/hr 0.150 125,000 18,750
Kepala Tukang Batu org/hr 0.015 130,000 1,950
Mandor org/hr 0.018 130,000 2,340
-
SNI 6897:2008-6.7 M2 Pas. Dinding batu bata; ad 1:2 - 92,140 48,750 10% 154,979 155,000
Bata Merah bh 70.000 864 60,480
Semen (50 Kg) zak 0.379 70,000 26,530
Pasir Pasang m3 0.038 135,000 5,130
Pekerja org/hr 0.300 110,000 33,000
Tukang Batu Kasar org/hr 0.100 125,000 12,500
Kepala Tukang Batu org/hr 0.010 130,000 1,300
Mandor org/hr 0.015 130,000 1,950
-
SNI 6897:2008-6.7 M3 Pas. Dinding batu bata; ad 1:4 - 82,385 48,750 10% 144,249 144,200
Bata Merah bh 70.000 864 60,480
Semen (50 Kg) zak 0.230 70,000 16,100
Pasir Pasang m3 0.043 135,000 5,805
Page 7
menu ANALISA HARSA SATUAN
Berdasarkan SNI 2007 - 2008
10%
Overhead
HARGA UPAH JUMLAH HARGA
SUMBER DATA UNIT URAIAN SATUAN KOEFISIEN Asuransi TOTAL PEMBULATAN
DAN MATERIAL
Material Upah lain-lain
Pekerja org/hr 0.300 110,000 33,000
Tukang Batu Kasar org/hr 0.100 125,000 12,500
Kepala Tukang Batu org/hr 0.010 130,000 1,300
Mandor org/hr 0.015 130,000 1,950
-
M2 Pas. Dinding partisi gypsumboard Rangka Kayu - 175,410 206,430 10% 420,024 420,000
Kayu Klas III Balok m3 0.028 2,920,000 81,760
Paku 8 s/d 12 cm kg 0.150 15,000 2,250
Gypsumboard t.9 mm lbr 0.860 90,000 77,400
Lem Kayu kg 0.560 25,000 14,000
Pekerja org/hr 0.028 110,000 3,080
Tukang Kayu Halus org/hr 0.150 125,000 18,750
Kepala Tukang Kayu org/hr 0.860 130,000 111,800
Mandor org/hr 0.560 130,000 72,800
-
M2 Pas. Dinding partisi gypsumboard Rangka Metal Furing - 137,400 206,430 10% 378,213 378,200
Rangka plafond Metal furing termasuk ripet m2 1.000 60,000 60,000
Gypsumboard t.9 mm lbr 0.860 90,000 77,400
Pekerja org/hr 0.028 110,000 3,080
Tukang Kayu Halus org/hr 0.150 125,000 18,750
Kepala Tukang Kayu org/hr 0.860 130,000 111,800
Mandor org/hr 0.560 130,000 72,800
-
M2 Pas. Dinding partisi Toilet;triplek 9 mm - 213,660 206,430 10% 462,099 462,100
Kayu Klas III m3 0.028 2,920,000 81,760
Triplex t. 9 mm lbr 0.860 135,000 116,100
Paku Skrup bh 6.000 300 1,800
Lem Kayu kg 0.560 25,000 14,000
Pekerja org/hr 0.028 110,000 3,080
Tukang Kayu Halus org/hr 0.150 125,000 18,750
Kepala Tukang Kayu org/hr 0.860 130,000 111,800
Mandor org/hr 0.560 130,000 72,800
-
-
PEKERJAAN PLESTERAN : -
-
Page 8
menu ANALISA HARSA SATUAN
Berdasarkan SNI 2007 - 2008
10%
Overhead
HARGA UPAH JUMLAH HARGA
SUMBER DATA UNIT URAIAN SATUAN KOEFISIEN Asuransi TOTAL PEMBULATAN
DAN MATERIAL
Material Upah lain-lain
SNI 2837:2008-6.2 M2 Pas. Plester acian; ad. 1:2 t.15 mm; tanpa acian - 17,014 55,650 10% 79,930 79,900
Semen (50 Kg) zak 0.204 70,000 14,314
Pasir Pasang m3 0.020 135,000 2,700
Pekerja org/hr 0.300 110,000 33,000
Tukang Batu Kasar org/hr 0.150 125,000 18,750
Kepala Tukang Batu org/hr 0.015 130,000 1,950
Mandor org/hr 0.015 130,000 1,950
-
SNI 2837:2008-6.4 M2 Pas. Plester acian; ad. 1:4 t.15 mm; tanpa acian - 11,976 55,650 10% 74,389 74,400
Semen (50 Kg) zak 0.125 70,000 8,736
Pasir Pasang m3 0.024 135,000 3,240
Pekerja org/hr 0.300 110,000 33,000
Tukang Batu Kasar org/hr 0.150 125,000 18,750
Kepala Tukang Batu org/hr 0.015 130,000 1,950
Mandor org/hr 0.015 130,000 1,950
-
SNI 2837:2008-6.27 M2 Pas. Acian PC - 4,550 37,100 10% 45,815 45,800
Semen (50 Kg) zak 0.065 70,000 4,550
Pekerja org/hr 0.200 110,000 22,000
Tukang Batu Kasar org/hr 0.100 125,000 12,500
Kepala Tukang Batu org/hr 0.010 130,000 1,300
Mandor org/hr 0.010 130,000 1,300
-
-
Page 9
menu ANALISA HARSA SATUAN
Berdasarkan SNI 2007 - 2008
10%
Overhead
HARGA UPAH JUMLAH HARGA
SUMBER DATA UNIT URAIAN SATUAN KOEFISIEN Asuransi TOTAL PEMBULATAN
DAN MATERIAL
Material Upah lain-lain
-
SNI DT 91-0012-2007 M2 Pas. Dinding Keramik 300x300 - 111,510 167,100 10% 306,471 306,500
Keramik 30/30 m2 1.060 65,000 68,900
Semen (50 Kg) zak 0.186 70,000 13,020
Pasir Pasang m3 0.018 135,000 2,430
Semen Warna kg 1.940 14,000 27,160
Pekerja org/hr 0.600 110,000 66,000
Tukang Batu Kasar org/hr 0.450 125,000 56,250
Kepala Tukang Batu org/hr 0.045 130,000 5,850
Mandor org/hr 0.300 130,000 39,000
-
-
M Railing Tangga Besi Hollow - 258,500 27,955 10% 315,101 315,100
Besi Plat rata2 kg 15.000 13,500 202,500
Cat kayu/Besi m 1.000 56,000 56,000
Pekerja org/hr 0.150 110,000 16,500
Tukang Batu Kasar org/hr 0.075 125,000 9,375
Kepala Tukang Batu org/hr 0.008 130,000 1,040
Mandor org/hr 0.008 130,000 1,040
-
Page 10
menu ANALISA HARSA SATUAN
Berdasarkan SNI 2007 - 2008
10%
Overhead
HARGA UPAH JUMLAH HARGA
SUMBER DATA UNIT URAIAN SATUAN KOEFISIEN Asuransi TOTAL PEMBULATAN
DAN MATERIAL
Material Upah lain-lain
Semen Warna kg 1.300 14,000 18,200
Pekerja org/hr 0.250 110,000 27,500
Tukang Batu Kasar org/hr 0.125 125,000 15,625
Kepala Tukang Batu org/hr 0.013 130,000 1,690
Mandor org/hr 0.013 130,000 1,690
-
-
-
SNI 7395:2008-6.35 M2 Pas. Lantai Keramik 300x300 - 110,515 129,850 10% 264,401 264,400
Keramik 30/30 m2 1.068 65,000 69,440
Semen (50 Kg) zak 0.200 70,000 14,000
Pasir Pasang m3 0.045 135,000 6,075
Semen Warna kg 1.500 14,000 21,000
Pekerja org/hr 0.700 110,000 77,000
Tukang Batu Kasar org/hr 0.350 125,000 43,750
Kepala Tukang Batu org/hr 0.035 130,000 4,550
Mandor org/hr 0.035 130,000 4,550
-
-
SNI DT 91-0012-2007 M Pas. Plint Keramik 100x300 - 12,663 33,500 10% 50,779 50,800
Plint Keramik 10/30 cm bh 3.333 2,000 6,667
Semen (50 Kg) zak 0.023 70,000 1,596
Pasir Pasang m3 0.030 135,000 4,050
Semen Warna kg 0.025 14,000 350
Pekerja org/hr 0.090 110,000 9,900
Tukang Batu Kasar org/hr 0.090 125,000 11,250
Kepala Tukang Batu org/hr 0.090 130,000 11,700
Mandor org/hr 0.005 130,000 650
-
SNI 7395:2008-6.24 M Pas. Plint Granitetile 100x400 - 29,636 33,500 10% 69,450 69,400
Plint Granitetile 10/40 cm bh 2.650 9,900 26,235
Semen (50 Kg) zak 0.023 70,000 1,596
Pasir Pasang m3 0.003 135,000 405
Semen Warna kg 0.100 14,000 1,400
Pekerja org/hr 0.090 110,000 9,900
Tukang Batu Kasar org/hr 0.090 125,000 11,250
Page 11
menu ANALISA HARSA SATUAN
Berdasarkan SNI 2007 - 2008
10%
Overhead
HARGA UPAH JUMLAH HARGA
SUMBER DATA UNIT URAIAN SATUAN KOEFISIEN Asuransi TOTAL PEMBULATAN
DAN MATERIAL
Material Upah lain-lain
Kepala Tukang Batu org/hr 0.090 130,000 11,700
Mandor org/hr 0.005 130,000 650
-
-
PEKERJAAN LANGIT-LANGIT -
M2 Pas. Rangka Plafond Metal furing 63,000 64,700 10% 140,470 140,500
Rangka plafond Metal furing m2 1.050 60,000 63,000
Pekerja org/hr 0.200 110,000 22,000
Tukang Besi Konstruksi org/hr 0.300 125,000 37,500
Kepala Tukang Besi org/hr 0.030 130,000 3,900
Mandor org/hr 0.010 130,000 1,300
-
SNI 3434:2008-6.19 M2 Pas. Rangka Plafond Kayu Meranti - 54,913 73,150 10% 140,870 140,900
Kayu Klas II kaso m3 0.015 3,371,000 51,913
Paku 5 s/d 10 cm kg 0.200 15,000 3,000
Pekerja org/hr 0.200 110,000 22,000
Tukang Kayu Kasar org/hr 0.300 125,000 37,500
Kepala Tukang Kayu org/hr 0.030 130,000 3,900
Mandor org/hr 0.075 130,000 9,750
-
SNI 3434:2008-6.19 M2 Pas. Rangka Plafond Kayu - 47,968 73,150 10% 133,230 133,200
Kayu Klas III kaso m3 0.015 2,920,000 44,968
Paku 5 s/d 10 cm kg 0.200 15,000 3,000
Pekerja org/hr 0.200 110,000 22,000
Tukang Kayu Kasar org/hr 0.300 125,000 37,500
Kepala Tukang Kayu org/hr 0.030 130,000 3,900
Mandor org/hr 0.075 130,000 9,750
-
SNI 2839:2008-6.7 M2 Pas. Penutup Plafond Gypsumboard t. 9 mm - 32,793 18,550 10% 56,477 56,500
Gypsumboard t.9 mm lbr 0.364 90,000 32,760
Paku Skrup kg 0.110 300 33
Pekerja org/hr 0.100 110,000 11,000
Tukang Kayu Kasar org/hr 0.050 125,000 6,250
Kepala Tukang Kayu org/hr 0.005 130,000 650
Mandor org/hr 0.005 130,000 650
Page 12
menu ANALISA HARSA SATUAN
Berdasarkan SNI 2007 - 2008
10%
Overhead
HARGA UPAH JUMLAH HARGA
SUMBER DATA UNIT URAIAN SATUAN KOEFISIEN Asuransi TOTAL PEMBULATAN
DAN MATERIAL
Material Upah lain-lain
-
SNI 2839:2008-6.5 M2 Pas. Penutup Plafond Triplex t. 4 mm - 28,134 25,450 10% 58,942 58,900
Triplex t. 4 mm lbr 0.375 75,000 28,125
Paku Skrup kg 0.030 300 9
Pekerja org/hr 0.100 110,000 11,000
Tukang Kayu Kasar org/hr 0.100 125,000 12,500
Kepala Tukang Kayu org/hr 0.010 130,000 1,300
Mandor org/hr 0.005 130,000 650
-
SNI 2839:2008-6.8 M Pas. List Profil Gypsum t. 5 cm - 36,753 15,270 10% 57,225 57,200
List Profil 5 cm Gypsum m 1.050 35,000 36,750
Paku Skrup kg 0.010 300 3
Pekerja org/hr 0.060 110,000 6,600
Tukang Kayu Kasar org/hr 0.060 125,000 7,500
Kepala Tukang Kayu org/hr 0.006 130,000 780
Mandor org/hr 0.003 130,000 390
-
-
PEKERJAAN RANGKA & PENUTUP ATAP -
-
M2 Rangka atap baja ringan Zingkalume 185,000 185,000 42,440 10% 250,184 250,200
Rangka atap baja ringan m2 1.000 185,000 185,000
Pekerja org/hr 0.080 110,000 8,800
Tukang Kayu Kasar org/hr 0.240 125,000 30,000
Kepala Tukang Kayu org/hr 0.024 130,000 3,120
Mandor org/hr 0.004 130,000 520
-
SNI 3434:2008-6.13 M3 Pas. Kuda kuda Kayu Konvensional - 3,994,600 2,122,000 10% 6,728,260 6,728,300
Kayu Klas II balok m3 1.100 3,371,000 3,708,100
Besi Plat rata2 kg 15.000 13,500 202,500
Paku 8 s/d 12 cm kg 5.600 15,000 84,000
Pekerja org/hr 4.000 110,000 440,000
Tukang Kayu Kasar org/hr 12.000 125,000 1,500,000
Kepala Tukang Kayu org/hr 1.200 130,000 156,000
Mandor org/hr 0.200 130,000 26,000
-
Page 13
menu ANALISA HARSA SATUAN
Berdasarkan SNI 2007 - 2008
10%
Overhead
HARGA UPAH JUMLAH HARGA
SUMBER DATA UNIT URAIAN SATUAN KOEFISIEN Asuransi TOTAL PEMBULATAN
DAN MATERIAL
Material Upah lain-lain
SNI 3434:2008-6.15 M3 Gording Kayu - 3,955,600 1,273,200 10% 5,751,680 5,751,700
Kayu Klas II Balok m3 1.100 3,371,000 3,708,100
Besi Plat rata2 kg 15.000 13,500 202,500
Paku 8 s/d 12 cm kg 3.000 15,000 45,000
Pekerja org/hr 2.400 110,000 264,000
Tukang Kayu Kasar org/hr 7.200 125,000 900,000
Kepala Tukang Kayu org/hr 0.720 130,000 93,600
Mandor org/hr 0.120 130,000 15,600
-
SNI 3434:2008-6.16 M2 Rangka Atap kayu - 172,300 25,450 10% 217,525 217,500
Kayu Klas II kaso m3 0.014 3,371,000 47,194
Kayu Klas II reng (0,036 m3) m3 0.036 3,371,000 121,356
Paku 5 s/d 10 cm kg 0.250 15,000 3,750
Pekerja org/hr 0.100 110,000 11,000
Tukang Kayu Kasar org/hr 0.100 125,000 12,500
Kepala Tukang Kayu org/hr 0.010 130,000 1,300
Mandor org/hr 0.005 130,000 650
-
SNI 02-3436-1994 M2 Penutup atap Genteng Keramik ex Jatiwangi - 190,000 27,955 10% 239,751 239,800
Genteng Keramik bh 25.000 7,600 190,000
Pekerja org/hr 0.150 110,000 16,500
Tukang Batu Kasar org/hr 0.075 125,000 9,375
Kepala Tukang Batu org/hr 0.008 130,000 1,040
Mandor org/hr 0.008 130,000 1,040
-
SNI 02-3436-1994 M2 Penutup atap Genteng Keramik Glazur ex KANMURI - 388,600 27,955 10% 458,211 458,200
Genteng Keramik Glazur bh 14.500 26,800 388,600
Pekerja org/hr 0.150 110,000 16,500
Tukang Batu Kasar org/hr 0.075 125,000 9,375
Kepala Tukang Batu org/hr 0.008 130,000 1,040
Mandor org/hr 0.008 130,000 1,040
-
SNI 02-3436-1994 M2 Bubungan Genteng Keramik - 184,440 71,860 10% 281,930 281,900
Nok Genteng Keramik bh 5.000 33,000 165,000
Semen (50 Kg) zak 0.216 70,000 15,120
Pasir Pasang m3 0.032 135,000 4,320
Page 14
menu ANALISA HARSA SATUAN
Berdasarkan SNI 2007 - 2008
10%
Overhead
HARGA UPAH JUMLAH HARGA
SUMBER DATA UNIT URAIAN SATUAN KOEFISIEN Asuransi TOTAL PEMBULATAN
DAN MATERIAL
Material Upah lain-lain
Pekerja org/hr 0.400 110,000 44,000
Tukang Batu Kasar org/hr 0.200 125,000 25,000
Kepala Tukang Batu org/hr 0.020 130,000 2,600
Mandor org/hr 0.002 130,000 260
-
SNI 02-3436-1994 M2 Bubungan Genteng Keramik Glazur - 244,440 71,860 10% 347,930 347,900
Nok Genteng Keramik Glasur bh 5.000 45,000 225,000
Semen (50 Kg) zak 0.216 70,000 15,120
Pasir Pasang m3 0.032 135,000 4,320
Pekerja org/hr 0.400 110,000 44,000
Tukang Batu Kasar org/hr 0.200 125,000 25,000
Kepala Tukang Batu org/hr 0.020 130,000 2,600
Mandor org/hr 0.002 130,000 260
-
SNI DT 91-0011-2007 M1 Pas. Lisplank Kayu 3/20 mm - 37,907 39,250 10% 84,872 84,900
Kayu Klas II papan uk. 3/20 m3 0.011 3,371,000 36,407
Paku 5 s/d 10 cm kg 0.100 15,000 1,500
Pekerja org/hr 0.100 110,000 11,000
Tukang Kayu Kasar org/hr 0.200 125,000 25,000
Kepala Tukang Kayu org/hr 0.020 130,000 2,600
Mandor org/hr 0.005 130,000 650
-
M1 Pas. Fleshing seng plat - 30,750 39,250 10% 77,000 77,000
Seng Plat BJLS 30 uk. 3/20 m2 0.450 65,000 29,250
Paku 5 s/d 10 cm kg 0.100 15,000 1,500
Pekerja org/hr 0.100 110,000 11,000
Tukang Kayu Kasar org/hr 0.200 125,000 25,000
Kepala Tukang Kayu org/hr 0.020 130,000 2,600
Mandor org/hr 0.005 130,000 650
-
SNI 7393:2008-6.19 M1 Pas. Talang seng plat - 75,150 58,940 10% 147,499 147,500
Seng Plat BJLS 30 uk. 3/20 m2 1.050 65,000 68,250
Paku 1 s/d 3 cm kg 0.010 15,000 150
Besi Plat rata2 kg 0.500 13,500 6,750
Pekerja org/hr 0.150 110,000 16,500
Tukang Kayu Kasar org/hr 0.300 125,000 37,500
Page 15
menu ANALISA HARSA SATUAN
Berdasarkan SNI 2007 - 2008
10%
Overhead
HARGA UPAH JUMLAH HARGA
SUMBER DATA UNIT URAIAN SATUAN KOEFISIEN Asuransi TOTAL PEMBULATAN
DAN MATERIAL
Material Upah lain-lain
Kepala Tukang Kayu org/hr 0.030 130,000 3,900
Mandor org/hr 0.008 130,000 1,040
-
-
PEKERJAAN PENGECATAN -
PT T-38-2000-C M2 Cat dinding dalam acrylic emulsion KW.I Interior
( 1 Lapis Plamir + 1 - 45,800 11,219 10% 62,721 62,700
Plamir Tembok Lapis Cat Dasar + 2 kg 0.100 35,000 3,500
Cat Tembok kw1 Lapis + 2 Lapis Cat kg 0.100 117,500 11,750
Cat Tembok kw1 kg 0.260 117,500 30,550
Pekerja org/hr 0.020 110,000 2,200
Tukang Cat Biasa org/hr 0.063 125,000 7,875
Kepala Tukang Cat org/hr 0.006 130,000 819
Mandor org/hr 0.003 130,000 325
-
PT T-38-2000-C M2 Cat dinding dalam acrylic emulsion KW.II Interior
( 1 Lapis Plamir + 1 - 30,050 11,219 10% 45,396 45,400
Plamir Tembok Lapis Cat Dasar + 2 kg 0.100 35,000 3,500
Cat Tembok kw2 Lapis + 2 Lapis Cat kg 0.100 73,750 7,375
Cat Tembok kw2 kg 0.260 73,750 19,175
Pekerja org/hr 0.020 110,000 2,200
Tukang Cat Biasa org/hr 0.063 125,000 7,875
Kepala Tukang Cat org/hr 0.006 130,000 819
Mandor org/hr 0.003 130,000 325
-
-
PT T-38-2000-C M2 Cat dinding luar weathershiled KW.I Eksterior
( 1 Lapis Plamir + 1 - 45,800 11,219 10% 62,721 62,700
Plamir Tembok Lapis Cat Dasar + 2 kg 0.100 35,000 3,500
Cat Tembok kw1 Lapis + 2 Lapis Cat kg 0.100 117,500 11,750
Cat Tembok kw1 kg 0.260 117,500 30,550
Pekerja org/hr 0.020 110,000 2,200
Tukang Cat Biasa org/hr 0.063 125,000 7,875
Kepala Tukang Cat org/hr 0.006 130,000 819
Mandor org/hr 0.003 130,000 325
-
PT T-38-2000-C M2 Cat dinding luar weathershiled KW.II Eksterior
( 1 Lapis Plamir + 1 - 30,050 11,219 10% 45,396 45,400
Plamir Tembok Lapis Cat Dasar + 2 kg 0.100 35,000 3,500
Cat Tembok kw2 Lapis + 2 Lapis Cat kg 0.100 73,750 7,375
Page 16
menu ANALISA HARSA SATUAN
Berdasarkan SNI 2007 - 2008
10%
Overhead
HARGA UPAH JUMLAH HARGA
SUMBER DATA UNIT URAIAN SATUAN KOEFISIEN Asuransi TOTAL PEMBULATAN
DAN MATERIAL
Material Upah lain-lain
Cat Tembok kw2 kg 0.260 73,750 19,175
Pekerja org/hr 0.020 110,000 2,200
Tukang Cat Biasa org/hr 0.063 125,000 7,875
Kepala Tukang Listrik org/hr 0.006 130,000 819
Mandor org/hr 0.003 130,000 325
-
-
PT T-38-2000-C M2 Cat plafond acrylic emulsion KW.I Interior
( 1 Lapis Plamir + 1 - 45,800 11,219 10% 62,721 62,700
Plamir Tembok Lapis Cat Dasar + 2 kg 0.100 35,000 3,500
Cat Tembok kw1 Lapis + 2 Lapis Cat kg 0.100 117,500 11,750
Cat Tembok kw1 kg 0.260 117,500 30,550
Pekerja org/hr 0.020 110,000 2,200
Tukang Cat Biasa org/hr 0.063 125,000 7,875
Kepala Tukang Cat org/hr 0.006 130,000 819
Mandor org/hr 0.003 130,000 325
-
PT T-38-2000-C M2 Cat plafond acrylic emulsion KW.II Interior
( 1 Lapis Plamir + 1 - 30,050 11,219 10% 45,396 45,400
Plamir Tembok Lapis Cat Dasar + 2 kg 0.100 35,000 3,500
Cat Tembok kw2 Lapis + 2 Lapis Cat kg 0.100 73,750 7,375
Cat Tembok kw2 kg 0.260 73,750 19,175
Pekerja org/hr 0.020 110,000 2,200
Tukang Cat Biasa org/hr 0.063 125,000 7,875
Kepala Tukang Cat org/hr 0.006 130,000 819
Mandor org/hr 0.003 130,000 325
-
( 1 Lapis Plamir + 1 -
PT T-38-2000-C M2 Cat kayu synthetic Lapis Cat Dasar + 2 - 31,640 30,000 10% 67,804 67,800
Plamir Kayu Lapis Cat Penutup ) kg 0.150 21,600 3,240
Meni kayu kg 0.200 21,600 4,320
Cat kayu/Besi Cat dasar 1x kg 0.170 56,000 9,520
Cat kayu/Besi Cat akhir 2x kg 0.260 56,000 14,560
Pekerja org/hr 0.070 110,000 7,700
Tukang Cat Biasa org/hr 0.090 125,000 11,250
Kepala Tukang Cat org/hr 0.060 130,000 7,800
Mandor org/hr 0.025 130,000 3,250
-
Page 17
menu ANALISA HARSA SATUAN
Berdasarkan SNI 2007 - 2008
10%
Overhead
HARGA UPAH JUMLAH HARGA
SUMBER DATA UNIT URAIAN SATUAN KOEFISIEN Asuransi TOTAL PEMBULATAN
DAN MATERIAL
( 1 Lapis Plamir + 1 Material Upah lain-lain
PT T-38-2000-C M2 Cat besi synthetic Lapis Cat Dasar + 2 - 31,640 30,000 10% 67,804 67,800
Plamir Kayu Lapis Cat Penutup ) kg 0.150 21,600 3,240
Meni kayu kg 0.200 21,600 4,320
Cat kayu/Besi Cat dasar 1x kg 0.170 56,000 9,520
Cat kayu/Besi Cat akhir 2x kg 0.260 56,000 14,560
Pekerja org/hr 0.070 110,000 7,700
Tukang Cat Biasa org/hr 0.090 125,000 11,250
Kepala Tukang Cat org/hr 0.060 130,000 7,800
Mandor org/hr 0.025 130,000 3,250
-
-
PEKERJAAN KUSEN -
SNI 7393:2008-6.11 M Kusen Pintu dan Jendela Alumunium CA 133.333 138,100 10,937 10% 163,941 163,900
Kusen Almunium m 1.100 125,000 137,500
Paku Skrup bh 2.000 300 600
Pekerja org/hr 0.043 110,000 4,730
Tukang Kayu Halus org/hr 0.043 125,000 5,375
Kepala Tukang Kayu org/hr 0.004 130,000 559
Mandor org/hr 0.002 130,000 273
-
SNI 7393:2008-6.11 M Kusen Pintu dan Jendela Alumunium PC 133.333 138,100 10,937 10% 163,941 163,900
Kusen Almunium m 1.100 125,000 137,500
Paku Skrup bh 2.000 300 600
Pekerja org/hr 0.043 110,000 4,730
Tukang Kayu Halus org/hr 0.043 125,000 5,375
Kepala Tukang Kayu org/hr 0.004 130,000 559
Mandor org/hr 0.002 130,000 273
-
unt Kusen & Pintu PVC toilet 133.333 626,800 23,873 10% 715,740 715,700
Kusen & Pintu PVC toilet m 1.000 625,000 625,000
Paku Skrup bh 6.000 300 1,800
Pekerja org/hr 0.045 110,000 4,950
Tukang Kayu Halus org/hr 0.135 125,000 16,875
Kepala Tukang Kayu org/hr 0.014 130,000 1,755
Mandor org/hr 0.002 130,000 293
Page 18
menu ANALISA HARSA SATUAN
Berdasarkan SNI 2007 - 2008
10%
Overhead
HARGA UPAH JUMLAH HARGA
SUMBER DATA UNIT URAIAN SATUAN KOEFISIEN Asuransi TOTAL PEMBULATAN
DAN MATERIAL
Material Upah lain-lain
-
SNI 7393:2008-6.11 M RangkaPintu Alumunium CA 133.333 - 163,400 10,937 10% 191,771 191,800
Rangka Pintu Almunium m 1.100 148,000 162,800
Paku Skrup bh 2.000 300 600
Pekerja org/hr 0.043 110,000 4,730
Tukang Kayu Halus org/hr 0.043 125,000 5,375
Kepala Tukang Kayu org/hr 0.004 130,000 559
Mandor org/hr 0.002 130,000 273
-
SNI 7393:2008-6.11 M Rangka Pintu Alumunium PC 133.333 - 163,400 10,937 10% 191,771 191,800
Rangka Pintu Almunium m 1.100 148,000 162,800
Paku Skrup bh 2.000 300 600
Pekerja org/hr 0.043 110,000 4,730
Tukang Batu Halus org/hr 0.043 125,000 5,375
Kepala Tukang Kayu org/hr 0.004 130,000 559
Mandor org/hr 0.002 130,000 273
-
-
M Rangka Jendela Alumunium 133.333 - 155,700 23,873 10% 197,530 197,500
Rangka Jendela Almunium m 1.050 148,000 155,400
Paku Skrup bh 1.000 300 300
Pekerja org/hr 0.045 110,000 4,950
Tukang Kayu Halus org/hr 0.135 125,000 16,875
Kepala Tukang Kayu org/hr 0.014 130,000 1,755
Mandor org/hr 0.002 130,000 293
-
M Rangka Jendela Alumunium 133.333 - 155,700 23,873 10% 197,530 197,500
Rangka Pintu Almunium m 1.050 148,000 155,400
Paku Skrup bh 1.000 300 300
Pekerja org/hr 0.045 110,000 4,950
Tukang Kayu Halus org/hr 0.135 125,000 16,875
Kepala Tukang Kayu org/hr 0.014 130,000 1,755
Mandor org/hr 0.002 130,000 293
-
-
SNI 3434:2008-6.1 M3 Kusen Pintu dan Jendela Kayu KW.I - 5,543,750 3,713,500 10% 10,182,975 10,183,000
Page 19
menu ANALISA HARSA SATUAN
Berdasarkan SNI 2007 - 2008
10%
Overhead
HARGA UPAH JUMLAH HARGA
SUMBER DATA UNIT URAIAN SATUAN KOEFISIEN Asuransi TOTAL PEMBULATAN
DAN MATERIAL
Material Upah lain-lain
Kayu Klas I Balok m3 1.100 5,000,000 5,500,000
Paku 5 s/d 10 cm kg 1.250 15,000 18,750
Lem Kayu kg 1.000 25,000 25,000
Pekerja org/hr 7.000 110,000 770,000
Tukang Kayu Halus org/hr 21.000 125,000 2,625,000
Kepala Tukang Kayu org/hr 2.100 130,000 273,000
Mandor org/hr 0.350 130,000 45,500
-
SNI 3434:2008-6.2 M3 Kusen Pintu dan Jendela Kayu KW.II - 4,088,950 3,183,000 10% 7,999,145 7,999,100
Kayu Klas II balok m3 1.200 3,371,000 4,045,200
Paku 5 s/d 10 cm kg 1.250 15,000 18,750
Lem Kayu kg 1.000 25,000 25,000
Pekerja org/hr 6.000 110,000 660,000
Tukang Kayu Halus org/hr 18.000 125,000 2,250,000
Kepala Tukang Kayu org/hr 1.800 130,000 234,000
Mandor org/hr 0.300 130,000 39,000
-
SNI 3434:2008-6.2 M3 Kusen Pintu dan Jendela Kayu KW.III - 3,547,750 3,183,000 10% 7,403,825 7,403,800
Kayu Klas III balok m3 1.200 2,920,000 3,504,000
Paku 5 s/d 10 cm kg 1.250 15,000 18,750
Lem Kayu kg 1.000 25,000 25,000
Pekerja org/hr 6.000 110,000 660,000
Tukang Kayu Halus org/hr 18.000 125,000 2,250,000
Kepala Tukang Kayu org/hr 1.800 130,000 234,000
Mandor org/hr 0.300 130,000 39,000
-
SNI 3434:2008-6.6 M2 Daun Pintu dan Jendela Kayu KW.I Pintu & jendela kaca - 127,500 424,400 10% 607,090 607,100
Kayu Klas I Papan m3 0.024 5,000,000 120,000
Lem Kayu kg 0.300 25,000 7,500
Pekerja org/hr 0.800 110,000 88,000
Tukang Kayu Halus org/hr 2.400 125,000 300,000
Kepala Tukang Kayu org/hr 0.240 130,000 31,200
Mandor org/hr 0.040 130,000 5,200
-
SNI 3434:2008-6.6 M2 Daun Pintu dan Jendela Kayu KW.II Pintu & jendela kaca - 88,404 424,400 10% 564,084 564,100
Kayu Klas II Papan m3 0.024 3,371,000 80,904
Page 20
menu ANALISA HARSA SATUAN
Berdasarkan SNI 2007 - 2008
10%
Overhead
HARGA UPAH JUMLAH HARGA
SUMBER DATA UNIT URAIAN SATUAN KOEFISIEN Asuransi TOTAL PEMBULATAN
DAN MATERIAL
Material Upah lain-lain
Lem Kayu kg 0.300 25,000 7,500
Pekerja org/hr 0.800 110,000 88,000
Tukang Kayu Halus org/hr 2.400 125,000 300,000
Kepala Tukang Kayu org/hr 0.240 130,000 31,200
Mandor org/hr 0.040 130,000 5,200
-
SNI 3434:2008-6.4 M2 Daun Pintu dan Jendela Kayu KW.III Pintu & jendela kaca - 124,300 173,455 10% 327,531 327,500
Kayu Klas III Papan m3 0.040 2,920,000 116,800
Paku 5 s/d 10 cm kg 0.500 15,000 7,500
Pekerja org/hr 0.350 110,000 38,500
Tukang Kayu Halus org/hr 1.050 125,000 131,250
Kepala Tukang Kayu org/hr 0.011 130,000 1,365
Mandor org/hr 0.018 130,000 2,340
-
SNI 3434:2008-6.5 M2 Daun Pintu Panel KW.I - 212,500 530,500 10% 817,300 817,300
Kayu Klas I papan m3 0.040 5,000,000 200,000
Lem Kayu kg 0.500 25,000 12,500
Pekerja org/hr 1.000 110,000 110,000
Tukang Kayu Halus org/hr 3.000 125,000 375,000
Kepala Tukang Kayu org/hr 0.300 130,000 39,000
Mandor org/hr 0.050 130,000 6,500
-
SNI 3434:2008-6.5 M2 Daun Pintu Panel KW.II - 147,340 530,500 10% 745,624 745,600
Kayu Klas II papan m3 0.040 3,371,000 134,840
Lem Kayu kg 0.500 25,000 12,500
Pekerja org/hr 1.000 110,000 110,000
Tukang Kayu Halus org/hr 3.000 125,000 375,000
Kepala Tukang Kayu org/hr 0.300 130,000 39,000
Mandor org/hr 0.050 130,000 6,500
-
SNI DT 91-0011-2007 M2 Daun Pintu Panel KW.III - 129,300 530,500 10% 725,780 725,800
Kayu Klas III papan m3 0.040 2,920,000 116,800
Lem Kayu kg 0.500 25,000 12,500
Pekerja org/hr 1.000 110,000 110,000
Tukang Kayu Halus org/hr 3.000 125,000 375,000
Kepala Tukang Kayu org/hr 0.300 130,000 39,000
Page 21
menu ANALISA HARSA SATUAN
Berdasarkan SNI 2007 - 2008
10%
Overhead
HARGA UPAH JUMLAH HARGA
SUMBER DATA UNIT URAIAN SATUAN KOEFISIEN Asuransi TOTAL PEMBULATAN
DAN MATERIAL
Material Upah lain-lain
Mandor org/hr 0.050 130,000 6,500
-
SNI 3434:2008-6.8 M2 Daun Pintu double teakwood; rangka kayu KW.II tertutup - 152,225 412,300 10% 620,978 621,000
Kayu Klas II papan m3 0.025 3,371,000 84,275
Lem Kayu kg 0.500 25,000 12,500
Paku 1 s/d 3 cm kg 0.030 15,000 450
Triplek t. 3 mm uk. 90x220 lbr 1.000 55,000 55,000
Pekerja org/hr 0.700 110,000 77,000
Tukang Kayu Halus org/hr 2.100 125,000 262,500
Kepala Tukang Kayu org/hr 0.210 130,000 27,300
Mandor org/hr 0.350 130,000 45,500
-
SNI DT 91-0011-2007 M2 Daun Pintu double triplex; rangka kayu KW.III tertutup - 235,950 424,400 10% 726,385 726,400
Kayu Klas III papan m3 0.025 2,920,000 73,000
Lem Kayu kg 0.500 25,000 12,500
Paku 1 s/d 3 cm kg 0.030 15,000 450
Triplex t. 4 mm uk. 90x220 lbr 2.000 75,000 150,000
Pekerja org/hr 0.800 110,000 88,000
Tukang Kayu Halus org/hr 2.400 125,000 300,000
Kepala Tukang Kayu org/hr 0.240 130,000 31,200
Mandor org/hr 0.040 130,000 5,200
-
SNI 7393:2008-6.4 M2 Pintu besi plat baja t. 2 mm rangkap; rangka besi siku - 646,300 267,160 10% 1,004,806 1,004,800
Besi Plat rata2 besi siku 30.30.3 mm kg 15.000 13,500 202,500
Besi Plat rata2 besi plat kg 32.800 13,500 442,800
Kawat beton kg 0.050 20,000 1,000
Pekerja org/hr 1.050 110,000 115,500
Tukang Besi Konstruksi org/hr 1.050 125,000 131,250
Kepala Tukang Besi org/hr 0.105 130,000 13,650
Mandor org/hr 0.052 130,000 6,760
Page 22
menu ANALISA HARSA SATUAN
Berdasarkan SNI 2007 - 2008
10%
Overhead
HARGA UPAH JUMLAH HARGA
SUMBER DATA UNIT URAIAN SATUAN KOEFISIEN Asuransi TOTAL PEMBULATAN
DAN MATERIAL
Material Upah lain-lain
Tukang Besi Konstruksi org/hr 1.050 125,000 131,250
Kepala Tukang Besi org/hr 0.105 130,000 13,650
Mandor org/hr 0.052 130,000 6,760
-
M2 Pagar Besi Tempa 541,000 267,160 10% 888,976 889,000
Besi Tempa m2 1.200 450,000 540,000
Kawat beton kg 0.050 20,000 1,000
Pekerja org/hr 1.050 110,000 115,500
Tukang Besi Konstruksi org/hr 1.050 125,000 131,250
Kepala Tukang Besi org/hr 0.105 130,000 13,650
Mandor org/hr 0.052 130,000 6,760
Page 23
menu ANALISA HARSA SATUAN
Berdasarkan SNI 2007 - 2008
10%
Overhead
HARGA UPAH JUMLAH HARGA
SUMBER DATA UNIT URAIAN SATUAN KOEFISIEN Asuransi TOTAL PEMBULATAN
DAN MATERIAL
Material Upah lain-lain
Selinder bh 1.000 110,000 110,000
Pekerja org/hr 0.000 110,000 -
Tukang Kayu Halus org/hr 0.500 125,000 62,500
Kepala Tukang Kayu org/hr 0.050 130,000 6,500
Mandor org/hr 0.000 130,000 -
-
BH Pas. Kunci knob pintu kamar mandi - 150,000 82,800 10% 256,080 256,100
Handle pintu bh 1.000 150,000 150,000
Pekerja org/hr 0.000 110,000 -
Tukang Kayu Halus org/hr 0.600 125,000 75,000
Kepala Tukang Kayu org/hr 0.060 130,000 7,800
Mandor org/hr 0.000 130,000 -
-
BH Pas. Door Stoper - 90,000 82,800 10% 190,080 190,100
Door Stoper bh 1.000 90,000 90,000
Pekerja org/hr 0.000 110,000 -
Tukang Kayu Halus org/hr 0.600 125,000 75,000
Kepala Tukang Kayu org/hr 0.060 130,000 7,800
Mandor org/hr 0.000 130,000 -
-
BH Pas. Door Closer - 250,000 82,800 10% 366,080 366,100
Door closer bh 1.000 250,000 250,000
Pekerja org/hr 0.000 110,000 -
Tukang Kayu Halus org/hr 0.600 125,000 75,000
Kepala Tukang Kayu org/hr 0.060 130,000 7,800
Mandor org/hr 0.000 130,000 -
-
M Rel pintu gantung - 2,750,000 414,000 10% 3,480,400 3,480,400
Rel Pintu Lipat 4 Pintu Zinkalume Lokal bh 1.000 2,750,000 2,750,000
Pekerja org/hr 0.000 110,000 -
Tukang Kayu Halus org/hr 3.000 125,000 375,000
Kepala Tukang Kayu org/hr 0.300 130,000 39,000
Mandor org/hr 0.000 130,000 -
-
PT T-30-2000-C BH Pas. Grendel Pintu - 15,000 34,500 10% 54,450 54,500
Grendel bh 1.000 15,000 15,000
Page 24
menu ANALISA HARSA SATUAN
Berdasarkan SNI 2007 - 2008
10%
Overhead
HARGA UPAH JUMLAH HARGA
SUMBER DATA UNIT URAIAN SATUAN KOEFISIEN Asuransi TOTAL PEMBULATAN
DAN MATERIAL
Material Upah lain-lain
Pekerja org/hr 0.000 110,000 -
Tukang Kayu Halus org/hr 0.250 125,000 31,250
Kepala Tukang Kayu org/hr 0.025 130,000 3,250
Mandor org/hr 0.000 130,000 -
-
PT T-30-2000-C BH Pas. Grendel Jendela - 15,000 34,500 10% 54,450 54,500
Grendel bh 1.000 15,000 15,000
Pekerja org/hr 0.000 110,000 -
Tukang Kayu Halus org/hr 0.250 125,000 31,250
Kepala Tukang Kayu org/hr 0.025 130,000 3,250
Mandor org/hr 0.000 130,000 -
-
PT T-30-2000-C BH Pas. Slot tanam pintu doble - 55,000 34,500 10% 98,450 98,500
Slot Tanam bh 1.000 55,000 55,000
Pekerja org/hr 0.000 110,000 -
Tukang Kayu Halus org/hr 0.250 125,000 31,250
Kepala Tukang Kayu org/hr 0.025 130,000 3,250
Mandor org/hr 0.000 130,000 -
-
PT T-30-2000-C BH Pas. Rel pintu lipat 4 pintu - - 17,315 10% 19,047 19,000
#REF! bh 1.000 - -
Pekerja org/hr 0.000 110,000 -
Tukang Kayu Halus org/hr 0.125 125,000 15,625
Kepala Tukang Kayu org/hr 0.013 130,000 1,690
Mandor org/hr 0.000 130,000 -
-
PT T-30-2000-C BH Pas. Engsel pintu - 75,000 17,315 10% 101,547 101,500
Engsel bh 1.000 75,000 75,000
Pekerja org/hr 0.000 110,000 -
Tukang Kayu Halus org/hr 0.125 125,000 15,625
Kepala Tukang Kayu org/hr 0.013 130,000 1,690
Mandor org/hr 0.000 130,000 -
-
PT T-30-2000-C BH Pas. Engsel jendela - 75,000 13,800 10% 97,680 97,700
Engsel bh 1.000 75,000 75,000
Pekerja org/hr 0.000 110,000 -
Page 25
menu ANALISA HARSA SATUAN
Berdasarkan SNI 2007 - 2008
10%
Overhead
HARGA UPAH JUMLAH HARGA
SUMBER DATA UNIT URAIAN SATUAN KOEFISIEN Asuransi TOTAL PEMBULATAN
DAN MATERIAL
Material Upah lain-lain
Tukang Kayu Halus org/hr 0.100 125,000 12,500
Kepala Tukang Kayu org/hr 0.010 130,000 1,300
Mandor org/hr 0.000 130,000 -
-
PT T-30-2000-C BH Pas. Kait angin jendela - 15,000 13,800 10% 31,680 31,700
Kait Angin bh 1.000 15,000 15,000
Pekerja org/hr 0.000 110,000 -
Tukang Kayu Halus org/hr 0.100 125,000 12,500
Kepala Tukang Kayu org/hr 0.010 130,000 1,300
Mandor org/hr 0.000 130,000 -
-
PT T-30-2000-C BH Pas. Kaca polos 3 mm - 89,250 40,720 10% 142,967 143,000
Kaca Polos 3 mm m2 1.050 85,000 89,250
Pekerja org/hr 0.160 110,000 17,600
Tukang Kayu Halus org/hr 0.160 125,000 20,000
Kepala Tukang Kayu org/hr 0.016 130,000 2,080
Mandor org/hr 0.008 130,000 1,040
-
PT T-30-2000-C BH Pas. Kaca polos 5 mm 161,700 40,720 10% 222,662 222,700
Kaca Polos 5 mm m2 1.050 154,000 161,700
Pekerja org/hr 0.160 110,000 17,600
Tukang Kayu Halus org/hr 0.160 125,000 20,000
Kepala Tukang Kayu org/hr 0.016 130,000 2,080
Mandor org/hr 0.008 130,000 1,040
-
PT T-30-2000-C BH Pas. Kaca 8 mm 246,750 40,720 10% 316,217 316,200
Kaca Polos 8 mm m2 1.050 235,000 246,750
Pekerja org/hr 0.160 110,000 17,600
Tukang Kayu Halus org/hr 0.160 125,000 20,000
Kepala Tukang Kayu org/hr 0.016 130,000 2,080
Mandor org/hr 0.008 130,000 1,040
PEKERJAAN SANITER
RSNI T-15-2002 BH Pas. Washtafel keramik - 2,335,000 345,750 10% 2,948,825 2,948,800
Page 26
menu ANALISA HARSA SATUAN
Berdasarkan SNI 2007 - 2008
10%
Overhead
HARGA UPAH JUMLAH HARGA
SUMBER DATA UNIT URAIAN SATUAN KOEFISIEN Asuransi TOTAL PEMBULATAN
DAN MATERIAL
Material Upah lain-lain
Wastafel bh 1.000 2,328,000 2,328,000
Seal tape bh 1.000 7,000 7,000
Pekerja org/hr 1.200 110,000 132,000
Tukang Batu Halus org/hr 1.450 125,000 181,250
Kepala Tukang Batu org/hr 0.150 130,000 19,500
Mandor org/hr 0.100 130,000 13,000
RSNI T-15-2002 BH Pas. Kloset Duduk Keramik 3,750,000 516,880 10% 4,693,568 4,693,600
Kloset duduk bh 1.000 3,750,000 3,750,000
Pekerja org/hr 3.300 110,000 363,000
Tukang Batu Halus org/hr 1.100 125,000 137,500
Kepala Tukang Batu org/hr 0.110 130,000 14,300
Mandor org/hr 0.016 130,000 2,080
-
RSNI T-15-2002 BH Pas. Urinoir Keramik 2,960,000 516,880 10% 3,824,568 3,824,600
Urinoir bh 1.000 2,960,000 2,960,000
Pekerja org/hr 3.300 110,000 363,000
Tukang Batu Halus org/hr 1.100 125,000 137,500
Kepala Tukang Batu org/hr 0.110 130,000 14,300
Mandor org/hr 0.016 130,000 2,080
-
RSNI T-15-2002 BH Pas. Kloset Jongkok Keramik - 606,400 153,880 10% 836,308 836,300
Kloset Jongkok bh 1.000 598,000 598,000
Semen (50 Kg) zak 0.120 70,000 8,400
Pekerja org/hr 0.000 110,000 -
Tukang Batu Halus org/hr 1.100 125,000 137,500
Kepala Tukang Batu org/hr 0.110 130,000 14,300
Mandor org/hr 0.016 130,000 2,080
Perlengkapan -
-
RSNI T-15-2002 BH Pas. Bak Air Fiberglass - 650,000 620,000 10% 1,397,000 1,397,000
Bak air fibreglass bh 1.000 650,000 650,000
Pekerja org/hr 1.800 110,000 198,000
Tukang Batu Halus org/hr 2.700 125,000 337,500
Kepala Tukang Batu org/hr 0.540 130,000 70,200
Mandor org/hr 0.110 130,000 14,300
Page 27
menu ANALISA HARSA SATUAN
Berdasarkan SNI 2007 - 2008
10%
Overhead
HARGA UPAH JUMLAH HARGA
SUMBER DATA UNIT URAIAN SATUAN KOEFISIEN Asuransi TOTAL PEMBULATAN
DAN MATERIAL
Material Upah lain-lain
Perlengkapan harga 0.180 -
-
RSNI T-15-2002 BH Pas. Shower spray - 274,175 13,800 10% 316,773 316,800
Shower Spray bh 1.000 274,000 274,000
Seal tape bh 0.025 7,000 175
Pekerja org/hr 0.000 110,000 -
Tukang Batu Halus org/hr 0.100 125,000 12,500
Kepala Tukang Batu org/hr 0.010 130,000 1,300
Mandor org/hr 0.000 130,000 -
-
RSNI T-15-2002 BH Pas. Shower set - 884,175 153,880 10% 1,141,861 1,141,900
Shower Set bh 1.000 884,000 884,000
Seal tape bh 0.025 7,000 175
Pekerja org/hr 0.000 110,000 -
Tukang Batu Halus org/hr 1.100 125,000 137,500
Kepala Tukang Batu org/hr 0.110 130,000 14,300
Mandor org/hr 0.016 130,000 2,080
-
RSNI T-15-2002 BH Pas. Tempat sabun keramik - 94,400 32,550 10% 139,645 139,600
Tempat Sabun bh 1.000 86,000 86,000
Semen (50 Kg) zak 0.120 70,000 8,400
Pekerja org/hr 0.000 110,000 -
Tukang Batu Halus org/hr 0.250 125,000 31,250
Kepala Tukang Batu org/hr 0.010 130,000 1,300
Mandor org/hr 0.000 130,000 -
-
RSNI T-15-2002 BH Pas. Kitchenzink stainlees stell 1 lubang - 1,469,000 261,000 10% 1,903,000 1,903,000
Kitchenzink bh 1.000 1,130,000 1,130,000
Fitting, Stop valve & support set 0.300 1,130,000 339,000
Pekerja org/hr 1.000 110,000 110,000
Tukang Batu Halus org/hr 1.000 125,000 125,000
Kepala Tukang Batu org/hr 0.100 130,000 13,000
Mandor org/hr 0.100 130,000 13,000
-
RSNI T-15-2002 BH Pas. Kran zink - 620,175 13,800 10% 697,373 697,400
Kran zink bh 1.000 620,000 620,000
Page 28
menu ANALISA HARSA SATUAN
Berdasarkan SNI 2007 - 2008
10%
Overhead
HARGA UPAH JUMLAH HARGA
SUMBER DATA UNIT URAIAN SATUAN KOEFISIEN Asuransi TOTAL PEMBULATAN
DAN MATERIAL
Material Upah lain-lain
Seal tape bh 0.025 7,000 175
Pekerja org/hr 0.000 110,000 -
Tukang Batu Halus org/hr 0.100 125,000 12,500
Kepala Tukang Batu org/hr 0.010 130,000 1,300
Mandor org/hr 0.000 130,000 -
-
RSNI T-15-2002 BH Pas. Kran dinding - 286,175 13,800 10% 329,973 330,000
Kran dinding bh 1.000 286,000 286,000
Seal tape bh 0.025 7,000 175
Pekerja org/hr 0.000 110,000 -
Tukang Batu Halus org/hr 0.100 125,000 12,500
Kepala Tukang Batu org/hr 0.010 130,000 1,300
Mandor org/hr 0.000 130,000 -
-
RSNI T-15-2002 BH Pas. Floor Drain - 465,400 153,880 10% 681,208 681,200
Floordrain bh 1.000 457,000 457,000
Semen (50 Kg) zak 0.120 70,000 8,400
Pekerja org/hr 0.000 110,000 -
Tukang Batu Halus org/hr 1.100 125,000 137,500
Kepala Tukang Batu org/hr 0.110 130,000 14,300
Mandor org/hr 0.016 130,000 2,080
-
RSNI T-15-2002 BH Pas. Roof Drain - 191,400 153,880 10% 379,808 379,800
Roof Drain Metal bh 1.000 183,000 183,000
Semen (50 Kg) zak 0.120 70,000 8,400
Pekerja org/hr 0.000 110,000 -
Tukang Batu Halus org/hr 1.100 125,000 137,500
Kepala Tukang Batu org/hr 0.110 130,000 14,300
Mandor org/hr 0.016 130,000 2,080
-
unt Pas. Meja Pantry uk. 600x 1500 mm 1,011,222 - 10% 1,112,344 1,112,300
Beton K - 200 m3 0.090 1,469,200 132,228
Tulangan besi beton U-24 kg 9.000 16,200 145,800
Bekisting beton plat lantai m2 0.990 434,100 429,759
Pas. Dinding Keramik 300x300 m2 0.990 306,500 303,435
Page 29
menu ANALISA HARSA SATUAN
Berdasarkan SNI 2007 - 2008
10%
Overhead
HARGA UPAH JUMLAH HARGA
SUMBER DATA UNIT URAIAN SATUAN KOEFISIEN Asuransi TOTAL PEMBULATAN
DAN MATERIAL
Material Upah lain-lain
PEKERJAAN PIPA
RSNI T-15-2002 M1 Pipa PVC dia. 4" 104,625 28,073 10% 145,968 146,000
Pipa PVC dia 4" m 1.200 67,500 81,000
Perlengkapan m 0.350 67,500 23,625
Pekerja org/hr 0.081 110,000 8,910
Tukang Batu Halus org/hr 0.135 125,000 16,875
Kepala Tukang Batu org/hr 0.014 130,000 1,755
Mandor org/hr 0.004 130,000 533
RSNI T-15-2002 M1 Pipa PVC dia. 3" 65,875 28,060 10% 103,329 103,300
Pipa PVC dia 3" m 1.200 42,500 51,000
Perlengkapan m 0.350 42,500 14,875
Pekerja org/hr 0.081 110,000 8,910
Tukang Batu Halus org/hr 0.135 125,000 16,875
Kepala Tukang Batu org/hr 0.014 130,000 1,755
Mandor org/hr 0.004 130,000 520
RSNI T-15-2002 M1 Pipa PVC dia. 2" 34,875 18,711 10% 58,945 58,900
Pipa PVC dia 2" m 1.200 22,500 27,000
Perlengkapan m 0.350 22,500 7,875
Pekerja org/hr 0.054 110,000 5,940
Tukang Batu Halus org/hr 0.090 125,000 11,250
Kepala Tukang Batu org/hr 0.009 130,000 1,170
Mandor org/hr 0.003 130,000 351
RSNI T-15-2002 M1 Pipa PVC dia. 1" 14,725 12,474 10% 29,919 29,900
Pipa PVC dia 1" m 1.200 9,500 11,400
Perlengkapan m 0.350 9,500 3,325
Pekerja org/hr 0.036 110,000 3,960
Tukang Batu Halus org/hr 0.060 125,000 7,500
Kepala Tukang Batu org/hr 0.006 130,000 780
Mandor org/hr 0.002 130,000 234
Page 30
menu ANALISA HARSA SATUAN
Berdasarkan SNI 2007 - 2008
10%
Overhead
HARGA UPAH JUMLAH HARGA
SUMBER DATA UNIT URAIAN SATUAN KOEFISIEN Asuransi TOTAL PEMBULATAN
DAN MATERIAL
Material Upah lain-lain
RSNI T-15-2002 M1 Pipa PVC dia. 3/4" 10,850 12,474 10% 25,656 25,700
Pipa PVC dia 3/4" m 1.200 7,000 8,400
Perlengkapan m 0.350 7,000 2,450
Pekerja org/hr 0.036 110,000 3,960
Tukang Batu Halus org/hr 0.060 125,000 7,500
Kepala Tukang Batu org/hr 0.006 130,000 780
Mandor org/hr 0.002 130,000 234
RSNI T-15-2002 M1 Pipa PVC dia. 1/2" 8,913 12,474 10% 23,525 23,500
Pipa PVC dia 1/2" m 1.200 5,750 6,900
Perlengkapan m 0.350 5,750 2,013
Pekerja org/hr 0.036 110,000 3,960
Tukang Batu Halus org/hr 0.060 125,000 7,500
Kepala Tukang Batu org/hr 0.006 130,000 780
Mandor org/hr 0.002 130,000 234
Page 31
menu ANALISA HARSA SATUAN
Berdasarkan SNI 2007 - 2008
10%
Overhead
HARGA UPAH JUMLAH HARGA
SUMBER DATA UNIT URAIAN SATUAN KOEFISIEN Asuransi TOTAL PEMBULATAN
DAN MATERIAL
Material Upah lain-lain
Roof Drain Metal m 1.200 183,000 219,600
Semen (50 Kg) zak 0.120 70,000 8,400
Pekerja org/hr 0.000 110,000 -
Tukang Batu Halus org/hr 1.100 125,000 137,500
Kepala Tukang Batu org/hr 0.110 130,000 14,300
Mandor org/hr 0.016 130,000 2,080
M1 Mesin Jet Pump kap.250 watt 1,236,000 188,880 10% 1,567,368 1,567,400
Mesin Jet Pump kap.250 watt m 1.200 1,030,000 1,236,000
Pekerja org/hr 1.000 110,000 110,000
Tukang Listrik org/hr 0.500 125,000 62,500
Kepala Tukang Listrik org/hr 0.110 130,000 14,300
Mandor org/hr 0.016 130,000 2,080
Page 32
menu ANALISA HARSA SATUAN
Berdasarkan SNI 2007 - 2008
10%
Overhead
HARGA UPAH JUMLAH HARGA
SUMBER DATA UNIT URAIAN SATUAN KOEFISIEN Asuransi TOTAL PEMBULATAN
DAN MATERIAL
Material Upah lain-lain
UNIT Septictank Pas. Bata kap. 3,00 m3 + Rembesanuk. 2 X 1,5 X 1 m + Rembesan 4,532,915 - 10% 4,986,206 4,986,200
Galian tanah, dalam s/d 1 m 3 m3 3.000 94,300 282,900
Pas. Urugan pasir m3 0.300 196,300 58,890
Pas. Lantai kerja beton tumbuk 1:3:5 m2 3.000 99,900 299,700
Pas. Dinding batu bata; ad 1:2 m2 10.500 155,000 1,627,500
Pas. Plester acian; ad. 1:2 m2 12.000 79,900 958,800
Beton K - 200 Balok & Tutup manhole m3 0.360 1,469,200 528,912
Pipa PVC dia. 4" AW m' 5.400 - -
Pipa PVC dia. 1" AW m' 1.200 - -
Galian tanah, dalam s/d 1 m m3 3.375 94,300 318,263
Batu Kerikil urugan m3 1.050 402,500 422,625
Pipa PVC dia. 4" AW perforated m' 9.000 - -
Urugan tanah kembali m3 1.125 31,400 35,325
Page 33
menu ANALISA HARSA SATUAN
Berdasarkan SNI 2007 - 2008
10%
Overhead
HARGA UPAH JUMLAH HARGA
SUMBER DATA UNIT URAIAN SATUAN KOEFISIEN Asuransi TOTAL PEMBULATAN
DAN MATERIAL
Material Upah lain-lain
UNIT Septictank Pas. Bata + Rembesan kap. 6,00 m3 uk. 2 X 1,5 X 2 m + Rembesan 6,462,515 - 10% 7,108,766 7,108,800
Galian tanah, dalam s/d 1 m 6 m3 6.000 94,300 565,800
Pas. Urugan pasir m3 0.300 196,300 58,890
Pas. Lantai kerja beton tumbuk 1:3:5 m2 3.000 99,900 299,700
Pas. Dinding batu bata; ad 1:2 m2 17.000 155,000 2,635,000
Pas. Plester acian; ad. 1:2 m2 20.000 79,900 1,598,000
Beton K - 200 Balok & Tutup manhole m3 0.360 1,469,200 528,912
Pipa PVC dia. 4" AW m' 5.400 - -
Pipa PVC dia. 1" AW m' 1.200 - -
Galian tanah, dalam s/d 1 m m3 3.375 94,300 318,263
Batu Kerikil urugan m3 1.050 402,500 422,625
Pipa PVC dia. 4" AW berlobang m' 9.000 - -
Urugan tanah kembali m3 1.125 31,400 35,325
PEKERJAAN ELEKTRIKAL
TTK TTK Pas. Box Panel 922,800 310,000 10% 1,356,080 1,356,100
Box panel PVC isi 4 MCB Legran bh 1.000 620,000 620,000
MCB 6 A bh 2.000 60,000 120,000
MCB 4 A bh 2.000 50,000 100,000
Kabel NYM 3 x 2,5 mm2 m 6.000 13,800 82,800
Pekerja org/hr 0.500 110,000 55,000
Tukang Listrik org/hr 1.000 125,000 125,000
Kepala Tukang Listrik org/hr 1.000 130,000 130,000
Mandor org/hr 0.000 130,000 -
TTK TTK Pas. Instalasi stop kontak 85,750 34,000 10% 131,725 131,700
Kabel NYM 3 x 2,5 mm2 m 6.000 13,800 82,800
Isolasi bh 0.500 5,000 2,500
Klem bh 3.000 150 450
Pekerja org/hr 0.050 110,000 5,500
Tukang Listrik org/hr 0.020 125,000 2,500
Kepala Tukang Listrik org/hr 0.100 130,000 13,000
Mandor org/hr 0.100 130,000 13,000
Page 34
menu ANALISA HARSA SATUAN
Berdasarkan SNI 2007 - 2008
10%
Overhead
HARGA UPAH JUMLAH HARGA
SUMBER DATA UNIT URAIAN SATUAN KOEFISIEN Asuransi TOTAL PEMBULATAN
DAN MATERIAL
Material Upah lain-lain
TTK TTK Pas. Instalasi lampu 65,350 34,000 10% 109,285 109,300
Kabel NYM 2 x 2,5 mm2 m 6.000 10,400 62,400
Isolasi bh 0.500 5,000 2,500
Klem bh 3.000 150 450
Pekerja org/hr 0.050 110,000 5,500
Tukang Listrik org/hr 0.020 125,000 2,500
Kepala Tukang Listrik org/hr 0.100 130,000 13,000
Mandor org/hr 0.100 130,000 13,000
TTK TTK Pas. Instalasi antena TV 2,950 34,000 10% 40,645 40,600
#REF! m 10.000 - -
Isolasi bh 0.500 5,000 2,500
Klem bh 3.000 150 450
Pekerja org/hr 0.050 110,000 5,500
Tukang Listrik org/hr 0.020 125,000 2,500
Kepala Tukang Listrik org/hr 0.100 130,000 13,000
Mandor org/hr 0.100 130,000 13,000
TTK TTK Pas. Instalasi telephone 9,450 34,000 10% 47,795 47,800
Kabel telephone 4 x 0.5 mm m 10.000 650 6,500
Isolasi bh 0.500 5,000 2,500
Klem bh 3.000 150 450
Pekerja org/hr 0.050 110,000 5,500
Tukang Listrik org/hr 0.020 125,000 2,500
Kepala Tukang Listrik org/hr 0.100 130,000 13,000
Mandor org/hr 0.100 130,000 13,000
Page 35
menu ANALISA HARSA SATUAN
Berdasarkan SNI 2007 - 2008
10%
Overhead
HARGA UPAH JUMLAH HARGA
SUMBER DATA UNIT URAIAN SATUAN KOEFISIEN Asuransi TOTAL PEMBULATAN
DAN MATERIAL
Material Upah lain-lain
Page 36
menu ANALISA HARSA SATUAN
Berdasarkan SNI 2007 - 2008
10%
Overhead
HARGA UPAH JUMLAH HARGA
SUMBER DATA UNIT URAIAN SATUAN KOEFISIEN Asuransi TOTAL PEMBULATAN
DAN MATERIAL
Material Upah lain-lain
BH BH Pas. Down light & PLC 13 W 126,250 33,250 10% 175,450 175,500
Down light / PLC 13 W ex bh 1.000 125,000 125,000
Isolasi bh 0.250 5,000 1,250
Pekerja org/hr 0.100 110,000 11,000
Tukang Listrik org/hr 0.100 125,000 12,500
Kepala Tukang Listrik org/hr 0.050 130,000 6,500
Mandor org/hr 0.025 130,000 3,250
Page 37
menu ANALISA HARSA SATUAN
Berdasarkan SNI 2007 - 2008
10%
Overhead
HARGA UPAH JUMLAH HARGA
SUMBER DATA UNIT URAIAN SATUAN KOEFISIEN Asuransi TOTAL PEMBULATAN
DAN MATERIAL
Material Upah lain-lain
Isolasi bh 0.250 5,000 1,250
Pekerja org/hr 0.100 110,000 11,000
Tukang Listrik org/hr 0.100 125,000 12,500
Kepala Tukang Listrik org/hr 0.050 130,000 6,500
Mandor org/hr 0.025 130,000 3,250
Page 38
SPESIFIKASI BG BERTINGKAT
TABEL A1
SPESIFIKASI TEKNIS BANGUNAN GEDUNG NEGARA
GEDUNG
NO. URAIAN BERTINGKAT TIDAK BERTINGKAT Keterangan
TIDAK SEDERHANA SEDERHANA TIDAK SEDERHANA SEDERHANA
Page 1
RAB BG BERTINGKAT SEDERHANA 1/4
A PEKERJAAN SRUKTUR
A.1 Pekerjaan Pondasi Rp. 509,280,788
A.2 PEKERJAAN STRUKTUR Rp. 1,100,828,107
B. PEKERJAAN ARSITEKTUR
B.1 Pekerjaan Lantai Rp. 370,686,901
B.2 Pekerjaan Dinding Rp. 621,369,045
B.3 Pekerjaan Plafond Rp. 172,554,270
B.4 Pekerjaan Atap Rp. 529,975,484
B.5 Pekerjaan Kusen Rp. 385,631,682
C. PEKERJAAN UTILITAS
C.1 Pekerjaan Plumbing Rp. 134,676,406
C.2 Pekerjaan Elektrikal Rp. 68,042,320
D. PEKERJAAN FINISHING Rp. 197,835,837
A PEKERJAAN SRUKTUR
A.1 Pekerjaan Pondasi
1 Pas. Urugan tanah Peninggian lantai m3 824.72 212,000 174,839,580
2 Galian tanah, dalam s/d 1 m m3 58.72 94,300 5,537,522
3 Pas. Urugan pasir t. 10 cm; Pondasi m3 11.81 196,300 2,319,230
4 Aanstamping batu kali t. 15 cm m3 96.90 803,500 77,859,150
5 Pas. pondasi batu kali 1:4 m3 14.14 1,033,900 14,622,965 275,178,447
6 Pas. Lantai kerja beton tumbuk 1:3:5 t. 5 cm m3 5.91 99,900 590,145
7 Bekisting sloof beton m2 66.00 257,600 17,001,600
8 Tulangan besi beton U-39 Besi beton dia 19 kg 1,856.61 17,900 33,233,319
9 Tulangan besi beton U-39 Besi beton dia 13 kg 755.47 17,900 13,522,869
0 Tulangan besi beton U-24 Besi beton 10 kg 135.52 16,200 2,195,424
10 Beton K - 250 m3 39.46 1,505,700 59,408,899 125,952,256
12 Bekisting sloof beton m2 118.30 257,600 30,474,080
13 Tulangan besi beton U-39 Besi beton dia 16 kg 1,832.21 17,900 32,796,523
14 Tulangan besi beton U-24 Besi beton dia 10 kg 826.06 16,200 13,382,107
15 Beton K - 225 m3 21.13 1,491,000 31,497,375 108,150,085
Pekerjaan Tangga
1 Bekisting beton plat lantai m2 24.16 434,100 10,486,771
2 Tulangan besi beton U-39 Besi beton dia 13 kg 202.67 17,900 3,627,714
3 Tulangan besi beton U-24 Besi beton dia 10 kg 186.14 16,200 3,015,415
4 Beton K - 250 m3 3.86 1,505,700 5,808,125 22,938,025
Pekerjaan Balok
1 Bekisting balok beton m2 198.49 410,000 81,378,850
2 Tulangan besi beton U-39 Besi beton dia 19 kg 259.56 17,900 4,646,124
3 Tulangan besi beton U-39 Besi beton dia 16 kg 2,604.10 17,900 46,613,353
4 Tulangan besi beton U-39 Besi beton dia 13 kg 101.66 17,900 1,819,707
5 Tulangan besi beton U-24 Besi beton dia 10 kg 1,050.53 16,200 17,018,528
6 Beton K - 250 m3 26.40 1,505,700 39,750,480 191,227,041
Page 1
RAB BG BERTINGKAT SEDERHANA 2/4
Pekerjaan Ringbalk
1 Beton K - 250 m3 11.81 1,505,700 19,374,827
2 Tulangan besi beton U-39 Besi beton dia 16 kg 1,101.19 17,900 21,485,404
3 Tulangan besi beton U-39 Besi beton dia 13 kg 257.52 17,900 5,024,535
4 Tulangan besi beton U-24 Besi beton dia 10 kg 665.28 16,200 11,747,514
5 Bekisting Praktis beton m2 148.36 112,200 18,144,437 75,776,718
Page 2
RAB BG BERTINGKAT SEDERHANA 3/4
Page 3
RAB BG BERTINGKAT SEDERHANA 4/4
Page 4
RAB BG TDK BERTINGKAT SEDERHANA 1/3
A PEKERJAAN STRUKTUR
A.1 Pekerjaan Pondasi 104,348,390
A.2 Pekerjaan Struktur 130,080,940
B PEKERJAAN ARSITEKTUR
B.1 Pekerjaan Lantai 87,154,821
B.2 Pekerjaan Dinding 155,822,024
B.3 Pekerjaan Plafond 66,085,620
B.4 Pekerjaan Atap 231,065,300
B.5 Pekerjaan Kusen 162,678,844
C PEKERJAAN UTILITAS
C.1 Pekerjaan Plumbing 63,718,710
C.2 Pekerjaan Elektrikal 28,492,800
D. PEKERJAAN FINISHING 75,402,756
B PEKERJAAN ARSITEKTUR
B.1 Pekerjaan Lantai
1 Pas. Urugan pasir t. 10 cm m3 17.70 196,300 3,475,486
2 Pas. Lantai kerja beton tumbuk 1:3:5 t. 5 cm m3 7.56 99,900 755,244
3 Pas. Lantai Keramik 300x300 ex Masterina m2 243.40 264,400 64,354,960
Page 1
RAB BG TDK BERTINGKAT SEDERHANA 2/3
Page 2
RAB BG TDK BERTINGKAT SEDERHANA 3/3
Page 3
SPESIFIKASI RUMAH NEGARA
TABEL A2
SPESIFIKASI TEKNIS BANGUNAN RUMAH NEGARA
RUMAH
NO. URAIAN Keterangan
TIPE A TIPE B TIPE C,D,E
Page 1
SPESIFIKASI RUMAH NEGARA
- kuda-kuda
Baja profil Galvalume Baja ringan Zinkalume Kayu klas III
- rangka atap
6. Kemiringan Atap minimal 30°
Page 2
RAB RUMAH NEGARA TYPE A 1/4
A. PEKERJAAN STRUKTUR
A.1 Pekerjaan Pondasi 103,328,620
A.2 Pekerjaan Struktur 161,108,865
B. PEKERJAAN ARSITEKTUR
B.1 Pekerjaan Lantai 152,424,392
B.2 Pekerjaan Dinding 304,895,496
B.3 Pekerjaan Plafond 80,115,570
B.4 Pekerjaan Atap 294,166,400
B.5 Pekerjaan Kusen 75,390,015
C. PEKERJAAN UTILITAS
C.1 Pekerjaan Plumbing 77,609,810
C.2 Pekerjaan Elektrikal 15,076,900
D. PEKERJAAN FINISHING 158,906,823
Page 1
RAB RUMAH NEGARA TYPE A 2/4
Page 2
RAB RUMAH NEGARA TYPE A 3/4
C. PEKERJAAN UTILITAS
C.1 Pekerjaan Plumbing
C.1.1 Pekerjaan Sanitary
1 Pas. Washtafel keramik TOTO LW 240 CJ bh 2.00 2,948,800 5,897,600
2 Pas. Kloset Duduk Keramik TOTO CW 660 J / SW 660 J bh 2.00 4,693,600 9,387,200
3 Pas. Kloset Jongkok Keramik TOTO CE 7 bh 1.00 836,300 836,300
4 Pas. Bak Air Fiberglass Fibre glass bh 1.00 1,397,000 1,397,000
5 Pas. Shower spray TOTO THX 20 NBP1V bh 2.00 316,800 633,600
6 Pas. Shower set TOTO TX423SZ bh 2.00 1,141,900 2,283,800
7 Pas. Floor Drain TOTO TX 1 BN bh 4.00 681,200 2,724,800
8 Pas. Tempat sabun keramik TOTO S 11 N bh 3.00 139,600 418,800
9 Pas. Kitchenzink stainlees stell 1 lubang HWACO bh 1.00 1,903,000 1,903,000
10 Pas. Kran zink TOTO T 30 AR13V7N bh 1.00 697,400 697,400
11 Pas. Kran dinding TOTO T 23 B 13 bh 3.00 330,000 990,000 27,169,500
C.1.2 Pekerjaan Sumur Dalam
1 Pengeboran Sumur m' 36.00 75,000 2,700,000
2 Pipa PVC dia. 3" Casing; Wavin m' 36.00 103,300 3,718,800
3 Pipa PVC dia. 2" Casing; Wavin m' 10.00 58,900 589,000
4 Pipa PVC dia. 3/4" ex Wavin m' 36.00 25,700 925,200
5 Klep diameter 3/4" bh 1.00 126,300 126,300
6 Stop kran dia. 1" bh 1.00 50,800 50,800
7 Mesin Jet Pump kap.250 watt Groundfos bh 1.00 1,567,400 1,567,400 9,677,500
C.1.3 Tanki Air
1 Pipa PVC dia. 1" Sparing pam; ex Wavin m' 12.00 29,900 358,800
2 Pipa PVC dia. 1" Inst. d/ pompa ke tanki air; ex Wavin m' 8.00 29,900 239,200
3 Pipa PVC dia. 3/4" ex Wavin m' 4.00 25,700 102,800
4 Tangki air 1000 liter Exel bh 1.00 1,692,800 1,692,800
5 Dudukan tangki air Besi siku bh 1.00 1,247,300 1,247,300
6 Mesin pompa kap.150 watt GROUNFOS bh 1.00 1,362,800 1,362,800
7 Stop kran dia. 1" ex Onda bh 2.00 50,800 101,600
8 Stop kran dia. 1" ex Onda bh 1.00 50,800 50,800
9 Stop kran dia. 1" ex Onda bh 1.00 50,800 50,800 5,206,900
C.1.4 Pekerjaan Reservoir
1 Galian tanah, dalam s/d 1 m m3 5.63 94,300 530,909
2 Pas. Urugan pasir m3 0.12 196,300 23,556
3 Pas. Lantai kerja beton tumbuk 1:3:5 m2 3.75 99,900 374,625
4 Bekisting beton plat lantai m2 21.00 434,100 9,116,100
5 Tulangan besi beton U-24 kg 315.00 16,200 5,103,000
6 Beton K - 200 m3 2.10 1,469,200 3,085,320 18,233,510
C.1.5 Instalasi Air Bersih
1 Pipa PVC dia. 1" ex Wavin m' 36.00 29,900 1,076,400
2 Pipa PVC dia. 3/4" ex Wavin m' 32.00 25,700 822,400
3 Pipa PVC dia. 1/2" ex Wavin m' 36.00 23,500 846,000 2,744,800
C.1.6 Instalasi Air Kotor & air bekas
1 Pipa PVC dia. 4" ex Wavin m' 20.00 146,000 2,920,000
2 Pipa PVC dia. 3" ex Wavin m' 28.00 103,300 2,892,400
3 Pipa PVC dia. 2" ex Wavin m' 20.00 58,900 1,178,000
4 Pipa PVC dia. 1" ex Wavin m' 16.00 29,900 478,400 7,468,800
C.1.7 Pekerjaan Septictank
1 Septictank Pas. Bata + Rembesan kap. 6,00 m3 UNIT 1.00 7,108,800 7,108,800 7,108,800
Jumlah C.1 .... Rp 77,609,810
C.2 Pekerjaan Elektrikal
C.2.1 Panel
1 Pas. Box Panel ex Legrand bh 2.00 1,356,100 2,712,200 2,712,200
C.2.2 Instalasi
1 Pas. Instalasi lampu Supreme NYM 2 x 1.5 mm ttk 26.00 109,300 2,841,800
2 Pas. Instalasi exhausfan Supreme NYM 2 x 1.5 mm ttk 2.00 109,300 218,600
3 Pas. Instalasi antena TV ttk 5.00 40,600 203,000
4 Pas. Instalasi stop kontak Supreme NYM 3 x 2.5 mm ttk 15.00 131,700 1,975,500 5,238,900
Page 3
RAB RUMAH NEGARA TYPE A 4/4
Page 4
RAB RUMAH NEGARA TYPE B 1/4
A. PEKERJAAN STRUKTUR
A.1 Pekerjaan Pondasi 40,302,607
A.2 Pekerjaan Struktur 58,829,219
B. PEKERJAAN ARSITEKTUR
B.1 Pekerjaan Lantai 64,783,208
B.2 Pekerjaan Dinding 181,471,587
B.3 Pekerjaan Plafond 37,196,791
B.4 Pekerjaan Atap 89,212,280
B.5 Pekerjaan Kusen 40,014,645
C. PEKERJAAN UTILITAS
C.1 Pekerjaan Plumbing 39,562,800
C.2 Pekerjaan Elektrikal 8,505,100
D. PEKERJAAN FINISHING 83,354,956
Page 1
RAB RUMAH NEGARA TYPE B 2/4
Page 2
RAB RUMAH NEGARA TYPE B 3/4
Page 3
RAB RUMAH NEGARA TYPE B 4/4
Page 4
RAB Rumah type C, D E 1/3
A. PEKERJAAN STRUKTUR
A.1 Pekerjaan Pondasi 25,630,025
A.2 Pekerjaan Struktur 46,746,564
B. PEKERJAAN ARSITEKTUR
B.1 Pekerjaan Lantai 30,695,004
B.2 Pekerjaan Dinding 49,606,981
B.3 Pekerjaan Plafond 12,510,715
B.4 Pekerjaan Atap 49,128,928
B.5 Pekerjaan Kusen 22,138,304
C. PEKERJAAN UTILITAS
C.1 Pekerjaan Plumbing 17,331,800
C.2 Pekerjaan Elektrikal 4,226,700
D. PEKERJAAN FINISHING 19,978,631
B. PEKERJAAN ARSITEKTUR
B.1 Pekerjaan Lantai
1 Pas. Urugan pasir t. 10 cm m3 7.61 196,300 1,492,960
2 Pas. Lantai kerja beton tumbuk 1:3:5 t. 5 cm m2 76.06 99,900 7,597,895
3 Pas. Lantai Keramik 300x300 ex Masterina m2 76.06 264,400 20,108,942
4 Pas. Rabat beton; finish acian Beton 1:3:5 m2 9.15 163,500 1,495,208
Jumlah B.1 .... Rp 30,695,004
B.2 Pekerjaan Dinding
1 Pas. Dinding batu bata; ad 1:4 Batu bata merah m2 169.99 144,200 24,512,017
2 Pas. Plester acian; ad. 1:2 t. 15 mm; tanpa acian; interior m2 10.32 79,900 824,568
3 Pas. Plester acian; ad. 1:4 t. 15 mm; tanpa acian; eksterior m2 326.22 74,400
24,270,396
Jumlah B.2 .... Rp 49,606,981
Page 1
RAB Rumah type C, D E 2/3
Page 2
RAB Rumah type C, D E 3/3
Page 3
TABEL A3
SPESIFIKASI TEKNIS BANGUNAN PAGAR
PAGAR
NO. URAIAN Keterangan
GEDUNG RUMAH
Page 1
RAB PAGAR BANGUNAN GEDUNG NEGARA
I BIAYA KONSTRUKSI
A PAGAR DEPAN tinggi 1,50 m Rp. 2,960,000
I BIAYA KONSTRUKSI
B PAGAR SAMPING tinggi 2 m Rp. 2,080,000
I BIAYA KONSTRUKSI
C PAGAR BELAKANG tinggi 3,00 m Rp. 2,040,000
pilar ;
3 Pas. Dinding batu bata; ad 1:4 Spesi 1 : 4 m2 15.60 144,200 2,249,520
4 Pas. Plester acian; ad. 1:4 Spesi 1 : 4 m2 31.20 74,400 2,321,280
Page 1
RAB PAGAR BANGUNAN GEDUNG NEGARA
5 Cat dinding dalam acrylic emulsion KW.II ex Mowilex m2 31.20 45,400 1,416,480
V. Pekerjaan Dinding
1 Pas. Dinding batu bata; ad 1:4 Spesi 1 : 4 m2 16.30 144,200 2,350,460
2 Pas. Plester acian; ad. 1:4 Spesi 1 : 4 m2 32.60 74,400 2,425,440
3 Cat dinding dalam acrylic emulsion KW.II ex Mowilex m2 32.60 45,400 1,480,040 6,255,940
Page 2
RAB PAGAR BANGUNAN GEDUNG NEGARA
V. Pekerjaan Dinding
1 Pas. Dinding batu bata; ad 1:4 Spesi 1 : 4 m2 10.00 144,200 1,442,000
2 Pas. Plester acian; ad. 1:4 Spesi 1 : 4 m2 20.00 74,400 1,488,000
3 Cat dinding dalam acrylic emulsion KW.II ex Mowilex m2 20.00 45,400 908,000 3,838,000
Page 3
RAB PAGAR RUMAH NEGARA
I BIAYA KONSTRUKSI
A PAGAR DEPAN tinggi 1,50 m Rp. 2,380,000
I BIAYA KONSTRUKSI
B PAGAR SAMPING tinggi 2 m Rp. 1,360,000
I BIAYA KONSTRUKSI
C PAGAR BELAKANG tinggi 2,50 m Rp. 1,360,000
pilar ;
3 Pas. Dinding batu bata; ad 1:4 Spesi 1 : 4 m2 8.70 144,200 1,254,540
4 Pas. Plester acian; ad. 1:4 Spesi 1 : 4 m2 17.40 74,400 1,294,560
Cat dinding dalam acrylic
5 ex Mowilex m2 17.40 45,400 789,960 3,339,060
emulsion KW.II
Page 1
RAB PAGAR RUMAH NEGARA
Page 2
RAB PAGAR RUMAH NEGARA
Page 3
MODEL GEDUNG TIDAK SEDERHANA BACK Spesifikasi Gedung Negara
Page 1
Page 2
MODEL GEDUNG SEDERHANA BACK Spesifikasi Gedung Negara
Page 3
MODEL RUMAH NEGARA TIPE A BACK Spesifikasi Rumah Negara
Page 4
MODEL RUMAH NEGARA TIPE B BACK Spesifikasi Rumah Negara
Page 5
MODEL RUMAH NEGARA TIPE C BACK Spesifikasi Rumah Negara
Page 6
MODEL RUMAH NEGARA TIPE D BACK Spesifikasi Rumah Negara
Page 7
MODEL RUMAH NEGARA TIPE E BACK Spesifikasi Rumah Negara
Page 8
MODEL PAGAR BACK Spesifikasi Pagar
Page 9