Hard Rock Cafe
Hard Rock Cafe
Hard Rock Cafe
OM Assignment- Group 09
1. Identify the critical path and its activities for Rockfest. How long does the
project take?
Q.3. Identify five major challenges a project manager faces in events such as this one.
Ans: A manager faces various challenges in these events such as in:
Q4. Why is a work breakdown structure useful in a project such as this/ take the 26
activities and break them into what you think should be level-2, level-3, and level-4 tasks.
Ans:
1.0 Rockfest event, with site selected (A) [level 1]
1.1 Select local promoter (B) [level 2]
1.1.1 Web site (D) [level 3]
1.1.2 TV deal (E)
1.1.3 Hire director (F)
1.1.3.1 Camera placement (G) [level 4]
1.1.4 Headline entertainers (H)
1.1.4.1 Support entertainers (I)
1.1.4.2 Travel for talent (J)
1.1.5 Staff travel (P)
1.1.6 Merchandise deals (Y)
1.1.6.1 On-line sales of merchandise (Z)
1.1.7 Hire sponsor coordinator (Q)
1.1.7.1 Finalize sponsors (R)
1.1.7.2 Signage for sponsors (S)
1.2 Hire production manager (C)
1.2.1 Sound/staging (N)
1.2.2 Venue capacity (K)
1.2.2.1 Ticketmaster contract (L)
1.2.2.2 On-site ticketing (M)
1.3 Hire operations manager (T)
1.3.1 Site plan (U)
1.3.1.1 Power, etc (X)
1.3.2 Security director (V)
1.3.2.1 Set police/fire plan (W)