Draft Letter Payment Schedule
Draft Letter Payment Schedule
Draft Letter Payment Schedule
2019
To
The Team Leader,
MSV International Inc.
in association with MSPARK Futuristics & Associates,
2nd Floor, Plot No.55, Raghuvanshi Rajendrapuri Colony,
Natinia Dai, Nawalpur, Shivpur, Varanasi – 221 003 (UP)
Ref: 1) GM(T) – UP, NHAI HQ, New Delhi letter no. Varanasi-Gorakhpur/NH-
29/Pkg- II/EPC/UP(Tech-Div)/2014/97694 dated 31.03.2017
2) PD, NHAI,PIU , Varanasi letter no. 11015/PD Varanasi/NH-29, Pkg-II/2019-
20/33537 dated 03.06.2019
3) Our letter no.PNC/VGHP/PD/NHAI/742 dated 18.06.2019
4) Your letter no.MSV-MSPARK/VNS-GRKH/PIU/571 dated 25.06.2019
5) PD, NHAI,PIU , Varanasi letter no. 11015/PD Varanasi/NH-29, Pkg-II/2019-
20/33801 dated 10.07.2019
6) Your letter no.MSV-MSPARK/VNS-GRKH/EPC/670 dated 16.07.2019
Dear Sir,
1.0 We are surprised to read the contents of your letter No. MSV-
MSPARK/VNS-GRKH/EPC/670 dated 16.07.2019, returning the stage
payment statement -21 in original for reanalyzing and resubmitting the
same in accordance with the provision of contract, which is unlawfully,
unwarrantedly and violating the provisions of the Contract Agreement.
2.0 Your above letter was issued based on the direction from the Project
Director, NHAI, Varanasi vide letter No. 11015/PD Varanasi/NH-29, Pkg-
II/2019-20/33801 dated 10.07.2019, stating interalia as under;
PNC/VGHP/AE/MSV Date: 22.07.2019
Quote
Consequent upon availability of 90.80% of the project length for
road construction as per the joint inspection/joint memorandum
dated 30.04.2019, this office, vide letter referred at (iii) asked you to
adjust the payment schedule suitably as per provisions of contract
and as stipulated vide para 2 of NHAI HQ letter referred at (ii)
above
You have submitted the Stage Payment Statement no.21 for the
works done during the period 1st May 2019 to 31st May 2019, which
is based on the actual work done by the contractor during the
said period it has not been analysed in terms of contract provisions
as directed vide this office letter referred at (iii)
Unquote
Quote
b) The Authority declared the appointed date 31.03.2017 after 144 days
of signing the agreement without fulfilling the obligation to provide the
90% Hindrance and obstruction free land to the EPC contractor for the
project execution as protected under clause 4.1.3
c) Article 4.1.3 fulfilled only after lapse of 760 days from the appointed
date. (90.8% of land handed over to us as on 30.04.2019)
Quote
4.0 In fact the material breach committed by NHAI continued for failure to
handover 90% Hindrance and obstruction free land to the EPC contractor
for the project execution within a period of 15 (fifteen days) from the
date of singing of Contract Agreement CA and also failed to handover
total site to Contractor no later than 90 (ninety) days of the Appointed
Date.
5.0 This signified that in the event the Reciprocal obligations, as undertaken
by NHAI be not discharged, the relevant provisions of The Indian Contract
Act, 1872’ shall be attracted inter-alia the provisions of section 52 and
Section 54 thereof would be enforceable which stipulated as under:-
Quote
‘Where the order in which reciprocal promises are to be performed is
expressly fixed by the contract, they shall be performed in that order; and
where the order is not expressly fixed by the contract, they shall be
performed in that order which the nature of the transaction required.’
&
‘When a contract consists of reciprocal promises, such that one of them
cannot be performed or that its performance cannot be claimed till the
other has been performed, and the promisor of the promise last
PNC/VGHP/AE/MSV Date: 22.07.2019
6.0 In short, it was the paramount obligations of NHAI to hand over complete
project of 72.15 Km. in encumbrance free utility removed condition
before 28.06.2017 and not later. Any delay on this score is to be deeded
as failure, material breach of contract by NHAI and non discharging of
Reciprocal obligations by NHAI and for which they would be liable and
must make payment of compensation of all losses and damages suffered
by the Contractor.
7.0 Failure on the part of NHAI to fulfill this prime Reciprocal obligations would
invalidate the ‘Implementation period’ as the same really affected the
Scheduled project completion date and constitute material breach of
the Agreement by NHAI
9.0 We have time and again, requested the NHAI for handing over of land to
us, but we would like to point out, that even with the best efforts made by
NHAI, the land could not be made available, probably due to the
procedural delays etc.
Upon perusal, you will kindly observe that 90.8% of the land has been
acquired only after 904 days of signing of the Contract Agreement
PNC/VGHP/AE/MSV Date: 22.07.2019
10.0 You will kindly appreciate, due to such unprecedented and abnormal
delay, we are suffering huge losses by way of unutilized plants and
machinery, idle manpower, inflationary costs etc., the burden of which is
substantial in financial terms and most of it could have been avoided,
one site was handed over to us, in due time, as per Contract Agreement
11.0 90.8% of land handed over to us as on 30.04.2019 and the NHAI has failed
to hand over full site after 3 months from the date of handing over of
90.8% land, as well as have failed to indicate the date when full site shall
be handed over.
Quote
In order for the above dlspensation to come into operation, it is
necessary that a suitable mechanism (like escrow account) is
evolved between the parties to the effect that the payments
released to the contractor under the above dispensation would be
used for completion of the project in the first instance and shall be
available to the Contractor only after meeting his project related
commitments
Unquote
16.0 We humbly submit, leaving aside the provisions of the Contract
Agreement, in spite of our several reminders, we have neither been
delivered the ‘Site’ free from encumbrances to the Contractor till date,
nor we have been informed, as to when the said obligation shall be
discharged by the Employer
PNC/VGHP/AE/MSV Date: 22.07.2019
17.0 Kindly provide us now at least, a definite date about the discharge of
your reciprocal promise,/obligations in this regard, so that we could
mobilize all our resources and complete the work expeditiously, working
at accelerated pace, even with compensatory increased costs
18.0 It is the responsibility of the employer to take good care to see that there
is no misinterpretation as to physical status of site, since the contractor is
presumed to have worked out the rate in accordance with data given in
the contract or tender document. The need to work as per program
requires undisturbed possession of site. It is there - fore imperative that the
employer should completely satisfy himself that the contractor is not put
to disadvantageous position. The consequences of such default leading
to disruption of activities of the contractor would be that of Employer,
having induced the EPC Contractor to mobilize and plan construction
activities on the presumption of having valid possession of desired land.
20.0 You will kindly appreciate, even now number of stretches have not been
handed over to us and at present, stands to be 28 months from the
Appointed date. With the present situation of 90.80% of availability also
there are 53 gaps in project length. The value of work involved in the 53
gaps are Rs.150,00,00,000/- which is 20% of Project value. It clearly shows
that financial status of handing over is only 80% of project value.
(affected length and financial value(detailed calculation) in the
affected area is attached as annexure – 2)
22.0 We shall appreciate, In the interest of the project and public at large, we
request you to kindly release the aforesaid payments and we undertake
to extend full cooperation and complete the project soonest possible
after handing over of the full site.
Thanking you and assuring you of our best services at all times.
Yours faithfully,
For PNC Infratech Limited
PNC/VGHP/AE/MSV Date: 22.07.2019
(N. K. Singh)
Senior Project Manager