Gantt Chart Project

This Gantt chart outlines 12 tasks for a thesis project over a 6 month period from June to December, including selecting a thesis title, conducting a literature review, proposal writing, data sourcing, flow simulator practicing, flow modeling, writing chapters, thesis review, and final defense. It lists the duration, start and finish dates, and predecessor tasks for each item.

Uploaded by

Daniel Inemugha
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
36 views1 page

Gantt Chart Project

This Gantt chart outlines 12 tasks for a thesis project over a 6 month period from June to December, including selecting a thesis title, conducting a literature review, proposal writing, data sourcing, flow simulator practicing, flow modeling, writing chapters, thesis review, and final defense. It lists the duration, start and finish dates, and predecessor tasks for each item.

Uploaded by

Daniel Inemugha
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

Gantt Chart

ID Task Task Name Duration Start Finish Predecessors Resource Names


Mode
1 Selection of Thesis Title 14 days Sat 6/15/19 Wed 7/3/19

2 Literature 21 days Mon 7/8/19 Mon 8/5/19 1


Review/Preliminary Studies

3 Proposal Writing 21 days Fri 8/2/19 Fri 8/30/19 2


4 Sourcing for Actual Field Data 14 days Wed 9/4/19 Mon 1
9/23/19
5 Flow Assurance Simulator 23 days Wed 9/4/19 Fri 10/4/19 3
Software Practicing

6 Flexible Flowline Flow 22 days Thu 9/26/19 Fri 10/25/19 5


Assurance Modelling using
the Simulator

7 Editing Chapter 3 - Material 12 days Fri 10/18/19 Mon 6


and Methods 11/4/19

8 Writing Chapter 4 - Results 10 days Tue 11/5/19 Mon 7


11/18/19
9 Writing Chapter 5 - 5 days Tue 11/19/19 Mon 8
Discussion 11/25/19
10 Conclusion 5 days Tue 11/26/19 Mon 12/2/199
11 Thesis Review/Completion 3 days Tue 12/3/19 Thu 12/5/19 10

12 Final Defence 9 days Fri 12/6/19 Wed 12/18/1911