Proposed Construction of (Lb+Ub+S+10) Hotel-Cum-Multiplex Building Project AT Mouza - Chandrashekharpur, Bhubaneswar

Download as pdf or txt
Download as pdf or txt
You are on page 1of 64

ENVIRONMENT MANAGEMENT PLAN REPORT

OF
PROPOSED CONSTRUCTION OF (LB+UB+S+10) HOTEL-CUM-
MULTIPLEX BUILDING PROJECT
AT
MOUZA- CHANDRASHEKHARPUR, BHUBANESWAR

Promoted by
M/s Risk Software Solutions Pvt. Ltd.

Applicant Name:
Mr.Mohinder Prakash, Director
&
Mr.Anup Kumar Lakhotia,Director
BMC Bhawani Saheed nagar Enclave
Saheed Nagar, Bhubaneswar- 751007
CONTENT

Chapter Description Page No.

Chapter-I Introduction 03 to 11

Chapter-II Project & Site Details 12 to 36

Chapter-III Environment Management Plan 37 to 52

Chapter-IV Energy Conservation 52 to 55

Chapter-V Rainwater Harvesting 56 to 62


CHAPTER-1
INTRODUCTION

Project at a Glance

Sl.No Name of the Company : M/s Risk Software Solution Pvt. Ltd.
01. Constitution : Private Limited Company
Hotel-cum-Multiplex Building Project at
02. Project
mouza- Chandrasekharpur, Bhbaneswar
Regd. Office Address:
M/s Risk Software Solution Pvt. Ltd.
269, GT Road, Liluah, Howrah, Pin-711204
Branch Office
BMC Bhawani Saheed nagar Enclave
03. Location : Saheed Nagar, Bhubaneswar- 751007
Phone : No.:0674-2542707-
Construction Site
Chandrasekharpur , Infront of CIPET
ENGINEERING COLLEGE ,Bhubaneswar,
Odisha.
04. Total Capital Investment : 37.00 crores .
Mr.Mohinder Prakash
(Director)

05. Promoters/Directors &

Mr. Anup Kumar Lakhotia.


(Director)
M/s Risk Software Solution Pvt. Ltd.
06. Implementation : 36 Months
The project is technically feasible, economically
Conclusion & viable eco-friendly, hence is recommended for
07. :
Recommendation immediate implementation and merit
institutional support/funding.
1.1 INTRODUCTION

The Hotel Building Project will be developed by M/s Risk Software Solution Pvt.Ltd.
The site is located at Village Mouza Chandrasekharpur, Bhubaneswar, District-
Khorda, on a land measuring 8096.26 Sq.mt. The project will provide good
infrastructure facilities and state of the art technology and will be developed taking
into account eco-friendly features in order to provide a healthier environment. There
is requirement of environmental clearance from the State Impact Assessment
Authority (SEIAA) as the built up area is 35,942.14 Sq.mt as and the project falls in
item 8(a) of Building and construction project as per the EIA Notification,2006 and
2009 and subsequent amendments theretof of MoEF & CC . The project cost is 35.00
crores.

1.2 JUSTIFICATION OF THE PROPOSAL

With a consistently growing middle class and increasing disposable income, the
tourism and hospitality sector is witnessing a healthy growth and accounts for 7.5 per
cent of the country's GDP and 8.78 percent of the total employment in the country.
The Indian tourism and hospitality industry has materialized as one of the key drivers
of growth among the services sectors in India. According to a report by KPMG, the
hospitality sector in India is expected to grow at 16.1 per cent CAGR to reach Rs
2,796.9 thousand crore in 2022.The hospitality sector encompasses a wide variety of
activities within the services sector and is a major job provider both direct and
indirectly. The growth in the hospitality sector and its contributions to the GDP will
continue to be substantially higher than other sectors of the economy on the back of
huge tourism potential in the country. The proposed project is of the latest additions
to contribute to the hospitality and service sector.
Moreover, Bhubaneswar the capital city of Odisha is growing at a faster rate. The
population of the city is growing. Corporate houses and Govt. offices are coming up
in Bhubaneswar. There is a demand for shopping, entertainment and social
gatherings.
Bhubaneswar located in the eastern part of India is one of the popular tourist
destinations. With well known pilgrimage venue, historical temples and sightseeing
places and close to Puri and Konark become main attraction for tourist all over the
world. There is immense demand for hotel accommodations throughout the year.
M/s. Risk Software Solution Pvt. Ltd. will cater the demand for hotel industries,
shopping and entertainment with this project.
1.2.1 STRENGTH OF THE PROJECT

 The Developer and its sister concern are all well experienced with proven track
records and market understanding in the hotel development field for last few
years.
 The proposed project is located at a very prime location of the city suburbs. Thus
marketing of the project is expected to be very smooth and hassle free.

 In house team of well-qualified and experienced engineers, supervisors, and


professionals passed out from the premier institutions of the country totally
committed to quality assurance and well equipped with modern techniques in
totally computerized environment.

 Stringent control to ensure quality construction and workmanship of highest


standards to execute the project well before the proposed schedule.

 State of the art structural designs by highly qualified and competent design
engineers to provide a safe and secure habitat to its apartment owners.

 Financial strength of the developer had ensured uninterrupted work and timely
completion of the project undertaken by the group. The project is expected to draw
strength from this.

 Provisions for most modern and sophisticated safety and security arrangements are
expected to instill confidence amongst the probable customers.

 In house internal control system and stringent monitoring system will eliminate
any kind of complacency creeping in among work force. This is expected to
ensure uniformity in the workmanship.

 Construction work will be carried out in strict conformity to the building rules and
other applicable provisions of laws & Statutes presently applicable in the country.

1.3 ABOUT THE COMPANY


The Hotel –cum-Multiplex Building Project is backed by unparalleled experience
of Risk Software Solution Private Limited., which has been providing quality
infrastructure in the city of Bhubaneswar. The company has been in the industry
for more than 5 years aiming towards lifetime commitment. Risk Software
Solution Private Limited, today continues to be a dedicated property developer
and is at the forefront of the industry in introducing luxurious multiplex, hotels,
residential apartments, etc with affordable living concepts.
Risk Software Solution Private Limited is a private company and the Registered
Office of the Company is situated in the National Capital Territory of Delhi.

The objects for which the Company is established are:

1. To design, develop, assemble, import, export, buy, sell, trade, consultancy


and to deal in computer, software, hardware, peripherals and to provide all
kinds of information technology in and outside india and to use technology by
means of internet, e-mail and Websites.

2. To carry on the business of sale, purchase. import, export, stockiest,


distributors, designers, agents traders. exchangers and jobbers in all kinds
of computers, computer software development, data entry, data mining, data
processing. infrastructure for information technologies or information
technologies enabled services companies, software implementation, Computer
Aided Design, hardware and software and other related items in India and
abroad.

3. To carry on the business of maintenance, manufacturer, repair and recondition


of all type of software and hardware computer, networks, equipment and
computer of all type whether hardware or software, to carry on the business
of providing business process outsourcing, IT enabled services, call centers,
KPOand to setup in India or abroad call center, business process outsourcing
cetnre’s giving advise relating to business of BPO's (Business Process
Outsourcing) and call centers.

4. To provide consultancy services in India and abroad on preparation of


projects reports, computer system, software, computer personnel and on
computerization in general and to providing software and hardware personnel
to work at customer sites in India and abroad and to develop Information
Technology based solution by adopting and integrating computer
communication strategy and to provide consulting services related to
establishing any BPO or KPO.

5. To design, develop software, internet services, web designing, website,


portal, software solution of other wise conduct research, development in all
disciples of software in India or abroad and to run internet related services
such as e-commerce, cyber cafe, internet consultancy, web designing, internet
programming any other activity related to internet access and communication.

6. To carry on the business as manufacturers, traders, importers and exporters of


and dealers in aluminium utensils, steel utensils, and all other such types of
utensils and kitchen requisities of all types.

7. To act as business consultant, give advice, to engage in dissemination of


information in all aspects of business, organisation and industry in India and to
advise upon the means and methods for extending and developing systems
or processes relating to production, storage, distribution, marketing, and
securing of orders for sale of good in India and abroad and/or relating to
the rendering of services.

8. To carry on the business of running motor lorries, motor taxies, mini


buses and conveyances of all kinds and to transport passengers, and goods and
to do the business of common carriers.

9. To carry on business by whole sale or retail, or otherwise of interior


decorators and furnishers, upholsters, and dealers in and hirers, repairs,
cleaners, stores and warehouses of furniture, carpets, linoleums furnishing
fabrics and such other floor coverings, household utensils, china and glass
goods, fittings, curtains and such other household requisites of all types.

10. To carry on the business as brewers, distillers, bottlers, canners


preservers, coopers dehidrators, malsters and merchants of and dealers in
fruits, herbs, vegetables, plants and liquors by products therefrom, whether
intoxicating or not, tonics, vitamin, beverages, flavoured drinks, nector, punch
aerated waters and drinks whether soft or otherwise.

11. To carry on the business of tobacconists in all its branches and to sell,
make-up and manufacture tobacco, cigars, cigarettes and snuff.

12. To act as cargo agents, travel agents, ship brokers, charter party contractors,
ship agents, packing forwarding and clearing agent, salvors, wreck
removers, wreck raisers, auctioneers, inspectors and observers of quality
control custom-house agents, commission agents and general sales agents for
any of the air lines, steam-ship companies, railway and transport companies or
any such person.

13. To carry on the business of cold storage of fruits, vegetable seeds,


fish, meat, agricultural products, milk, dairy products and such other perishable
items of all types.

14. To carry on the business of production, distribution or exhibition of films and


motion pictures and the running of theatres, cinemas, studios and
cinematographic shows and exhibitions.

15. To trade, deal in and undertake manufacturing, of bricks, tiles, pipes, cement,
lime and building construction requisites and to carry on all or any of the
business of builders, contractors, architects, decorators, furnishers and to
acquire, hold, mortgage lease, take on lease, exchange or otherwise deal in
lands, buildings, house, flats, bungalows, shops, here-dita-ments of any tenure
or freehold for residential or businesses purposes.

16. To cultivate, grow, produce or deal in any agricultural, vegetable or fruit


products and to carry on all or any of the businesses of farmers, dairyman,
milk contractors, dairy farmers, millers, purveyors and vendors of milk and
milk products, condensed milk and powdered milk, cream, cheese, butter,
poultry, fruits, vegetables, cash crops and provisions of all kinds.

17. To cultivate, tea, coffee, chinchona and any other such similar product and to
carry on the business of planters in all its branches, to carry on and do
the business of cultivators, winners and buyers of every kind of
vegetable mineral or such other product of soil, dispose of and deal in any
such produce, either in its prepared, manufactured or raw state and either by
wholesale or retail.

18. To carry on the business of manufacturers of or dealers in pulp and paper of


all kinds and articles made from paper and pulp such as card boards and wall
and ceiling papers and packaging cartons and newspapers and newsprints.

19. To carry on the business of purchase and sale of petroleum products, to act
as dealers and distributors for petroleum companies, to run service stations for
the repair and servicing of automobilies and to manufacture or deal in fuel
oils, cutting oils and greases.
20. To carry on the business of iron-founders, makers of scientific, industrial and
surgical instruments, mechanical engineers, and manufacturers of agricultural
implements and other machinery, steel castings and forgings and malleable iron
and steel castings, tools makers, brass founders, metal workers, boiler-
makers, mill wrights, machinists, iron and steel converters, smiths,
builders, painters, mettallurgists, electrical engineers, water supply
engineers, gas makers, farmers, printers, carriers and merchants and to buy,
sell, manufacture, repair, convert, alter, let on hire and deal in machinery,
implements and rolling stock.

21. To carry on the business of hoteliers, moteliers, restaurant owners,


sweet-meat merchants, refreshments, room proprietors, refreshment contractors
and own run garages, shops, stores, godowns, refreshment rooms,
cafetarias, discotheques, restaurants and places for sale, custody, bailment,
deposit or protection of the valuable goods and commodities.

22. To carry on the business of manufacturing and dealing, in assembling, buying,


selling, reselling, exchanging, altering repairing, importing, exporting, hiring,
letting, on hire, distributing, or dealing in motor cars, motor cycles,
scooters, motor buses, motor lorries, motor vans, trucks, locomotive
engines, trains and, all other road and rail conveyances, ships, boats,
barges, launches, steamers and other vessels, aeroplanes, aeroengines flying
boats, hydroplanes, and aircrafts and aerial conveyances of every description
and kind for transport or conveyance of passengers, merchandise or goods of
description, whether propelled or moved or assisted by means of petrol,
spirit, electricity, steam, oil vapour, gas, petroleum, mechanical, animal or any
other such motive power of all types.

23. To carry on the business manufacturing, dyeing, colouring, spinning, weaving,


buying selling, importing, exporting or otherwise dealing in all fabrics and
other fibrous substances and preparations and manufacturers of and dealers in
cotton, silk, woollen, linen, hemp, jute, rayon, nylon, artificial silk and such
other yarn and all kinds of woven synthetic blended textiles manufactured
from such yarn.

24. To carry on the business manufacturers of and dealers in industrial


machinery, bearings, speed reduction units, pumps, machine tools,
agricultural machinery and earth-moving machinery including road rollers,
bull-dozers, dumpers, scrapers, loaders, shovels and drag lines and light
engineering, goods such as cycle and sewing machines.

25. To carry on the business of manufacturers of or dealers in ferrous or non-


ferrous metals iron & steel aluminium, brass, tin, nickel, special, steel and their
products.

26. To carry on the business of manufacturers, stockists, importers and


exporters of and dealers, in engineering drawing sets, builders of requisites,
steel rules, measuring tapes, cutting tools, hand tools, precision measuring
tools, machine tools, garage tools, hardware tools, instruments, apparatus and
such allied machinery, plant, equipment and appliances of all types.

27. To carry on the business as manufacturers, stockists, importers and


exporters of and dealers in bolts, nuts, nails, hooks, and such other hardware
items of all types.

28. To carry on business as manufacturers, stockists, importers, and exporters


of and dealers in forging, castings, stampings of all metals, machinery parts,
moulds, press tools, jigs, fixtures and compression moulding, steel products and
automobile parts.

29. To carry on business as manufacturers stockists, importers exporters and


repaires of and dealers in dynamos, motors, armatures, magnets, batteries,
conductors, insulators, transformers, convertors, switch-boards, cockers,
enginers presses and insulating material.

30. To carry on business as manufacturers, stockists, importers and exporters of


and dealers in wearable and unwearable fabrics, high density polyethelene and
polypropylene, woven snacks and tarpaulins.

31. To carry on business as manufacturers of and dealers in and as stockists,


importers, and exporters of packing material, jointing and belting materials,
asbestos materials and fibres, insulation material and welding fluxes, cartons,
containers, boxes and cases made of paper, boards, wood glass, plastic, pulp,
cellulose films, polythene, rubber, metals, metal foils gelatine, tin flexible,
treated, and laminated, or other materials.

32. To carry on business as manufacturers of and dealers in as stockists,


importers and exporters of bottles, jars, fibrite boxes, corrugated containers,
aluminium foils of all types, wooden drums, packing cases, rods, wires,
ropes, strips, conductors equipment required for generation, distribution and
transmission of electric energy, cables, motors, fans, lamps , batteries and
accumulators.

33. To sell, breed, import, export, improve, prepare, deal and trade in cattie,
bird, poultry, game, live and dead-stock of every description eggs, pork-pipes
sausages, pickles spices, sauces, jams, jelly, custard, prawn, potted meats,
macaroni, spaghetti table delicacies, bread, biscuit, wine biscuits and such
other ferinaceous goods and products cocoa, confectionery , cakes and buns.

34. To carry on the traders and business of meal manufacturers, dealers in


consumable stores and provisions of all kinds roods stuffs, grains, flour, seeds,
folder, cane, oils, corn, wheal, wheat products, stores, vegetable oils, ghee and
vanaspati products.

35. To set up a tanners and to carry on the business as manufacturers of and


dealers in and importers and exporters of leather and raw hides and skins.

36. To carry on the business as manufacturers of and dealers in or as stockists,


importers and exporters of plastics, synthetic resins, natural resins, polymer
products and chemicals required for the manufacture, processing and
fabrication of plastics and similar other such products, tubes, pipes, sheets,
films whether moulded extruded casted, formed or foamed.

37. To purchase, hold and acquire mines, mining leases, mining rights, mining
claims and metalliferrous lands and explore, work, exercise, develop and turn
to account all sorts of major and major minor minerals working of deposits of
all kinds of minerals and subsoil materials and to crush, win, set, quarry, smelt,
calcine, refine, dress, amalgamate, manipulate and prepare for market ores,
metals, and mineral substances of all kinds and to carry on metallurgical
operations in all its branches and to prepare, process, manufacture, assemble,
fabricate, cast fit, press machine, treat, weld, harden, plate, temper, anneal any
kind of metals and consequential products.

38. To produce, manufacture, trade, deal in all dispose of alkalies, dyes,


chemicals, acids, gases, compounds, fertilisers, chemical,
productsofeverynature and description, intermediates, derivatives, all types of
floatation regents wetting agents, insecticides, fumigates, dyestuffs, catalytic
agents, direct colours, basic colours pigments, drugs, bioloqical pharmaceuticals,
serums, vitamin products, harmones and products, derived from phosphate
mines, limestone quarries, bauxite mines, petroleum, natural gas and other
natural deposits useful or suitable in the manufacture of chemicals and chemical
products and to undertake the business of spraying of pesticides.

39. To manufacture, generate, produce, sell, dispose of and deal in industrial


gases domestic gases for heating and lighting gas, system, heat light or any other such
motive power obtained by incinerating, burning forest refuse, wood and plants.

40. To manufacture, buy, sell, import, export, alter, improve, manipulate, prepare
for market, exchange, install, repaire, service, let on hire and deal in all kinds of
surgicals X-ray units, X-ray equipments, telecommunication machines, business
machines, intercoms, teleprinters, dictating, and recording machines, broadcasting
apparatuses, loud-speakers, radios, auto-radio reverberators, tape-players, cassette
tapes, headphones, stereo-complex speakers, radios control equipments, cameras,
binoculars, microscopes, projectors, telescopes, television sets, refrigerators, coolers,
radars, computers and spare parts.

Promoters Background

1. Sri Ashok Kumar Lakhotia along with his two sons Sri Anup Lakhotia and Sri Aditya
Vikram Lakhotia are the promoters of the Bhawani Group.

The group was established in the 1980’s by Sri Ashok Kumar Lakhotia which was later
joined by his two talented sons to handle and manage the group business to take to it
heights and achieve their goals.

The group is a diversified in nature having different business in all fields. They are well
known for the well managed and most modern diagnostic centre consisting of MRI and
CT Scanners.

They have many more business in the field of packaging, Iron and Steel, Aluminium
circles Plastic Tubes and Pipes and above all is well renowned in the field of Real Estate
and development.

They are also having a Banquet Hall named as Lakhotia Palace in the heart of Liluah in
Howrah. The said Banquet hall is well reputed and is given on hire for the marriages and
other social functions.

They have vast goodwill and highly reputed in all its buisness fields mainly in West
Bengal and Orissa. The group is managed by young professional talents to committed to
quality, progress and profit Entrepreneurship, integrity, hard work and commitment
towards people and society is the main object of the group.

Features:

 Huge Shopping complex in Bhubaneshwar


 Close proximity to the City, Railway Station and Airport.
Hotel-cum- Multiplex Building Project
At Mouza Chandrasekharpur, Bhubaneswar,Dist-Khorda

 Multiplex, Entertainment-centres and Galleries


 Cafés, Pubs and Fast-food joints
 Restaurants ,Clubs , Shops
 Adequate parking places
Previous Projects And Experience

They have completed many big and small project since its incorporation. The main few
projects completed by them are given below:

 Utkal Housing Complex : It was a joint venture project with Cuttack Development
Authority over plot No. 1566 P Sector 6 Bidanasi Cuttack on land area 2 acre. the said
complex is comprised of 34 independent Duplex HIG Houses.
 Jubilee Tower : A joint venture Project with Cuttack Municipal Corporation over .5 acre
plot No.488 Jublee market, Choudhary bazar , Cuttack.The said project was built up having a
built up area of 55000 Sq. Ft.
 Bhawani Enclave Phase I : It was a joint Venture Project with Cuttack Development
Authority over Sector 9 Bidanasi Cuttack on 1.25 acre land area. The said complex is
comprised of 18 independent Duplex HIG Houses.
 Bhawani Enclave Phase II : It was a joint Venture project with Cuttack Development
Authority over plot No. IL/B/2 Sector 8 Bidanasi Cuttack on land area 1.75 acre. The said
complex is comprised of 21 independent Duplex HIG Houses.

The Group is having a vast goodwill and has good bureaucrats connections all over Orissa mainly in
Cuttack and Bhubaneswar. And the Orissa Government is having good comfort to work with the
group in all respects and is also highly satisfied with the quality and other aspects of their working
profile. Their previous experiences with the group in the field of work and performances allow them
to work with freedom in any type of project big or small.

1.3.1 The Risk Software Solution Private Limited Guarantee

Risk Software Solution Private Limited has multiplexes,hotels, built homes and offices in
Bhubaneswar and West Bengal. These projects have been made possible due to our
commitment to quality workmanship, services and business ethics, values to which we
have put the Express Seal of Guarantee.
 Top Quality Construction
We use only the best of material and manpower in our construction activities. We build
homes and offices with quality architectural support.
 Personalized Service
Our clients come before everything else. Full customer support has kept Express owners
fully satisfied across the country
 Clean Clear Dealing
Honest, straight deal, clean and clear paperwork mark Risk Software Solution Private
Limited commitment to proper business ethics. Our aim is to build lasting relationships
with our clients.
 Amenities
All projects have one distinguishing feature and that is that they have excellent amenities
such as clubhouse, sports etc.
19
Hotel-cum- Multiplex Building Project
At Mouza Chandrasekharpur, Bhubaneswar,Dist-Khorda

1.3.2 Philosophy

Risk Software Solution Private Limited is committed towards conducting its business in
accordance with not only applicable laws, rules and regulations but also with high
standards of business ethics. It believes that its Board of Directors as well as Senior
Management should follow and promote honest and ethical conduct of the business along
with complying with applicable laws, rules and regulations. They must abide by the
policies and procedures so as to ensure its commitment to compliance and create and
maintain a culture of high ethical standards and maintain a work environment that
encourages not only the staff but also the stakeholders to raise their faith in the
management of the Company. The Board of the Company hereby presents the Code of
Conduct with an intention to provide guidance and mechanisms to help foster abidance to
its above-illustrated philosophy on Code of Conduct.

1.3.3 Vision and Mission

 To provide a high quality houses to our customers that will stand on the strong roots of
technical professionalism.
 To consistently achieve client satisfaction by providing all construction related services
including design on turnkey basis & assuring timely completion of projects within budget
& with excellent quality.
 To give the best possible value for every rupee the customers invest in the houses built by
us.
 To fulfill the growing demands of people for dream homes in the Capital City of
Bhubaneswar. We are committed to provide Duplex homes and Apartments at
competitive prices.
 We strive hard to meet the customer’s choice, specifications and other requirements by
exploring the best possible options through our professional team of experts.
 We believe in Customer First philosophy. Our projects are litigation free and we can
assure our customers to live tension free.

1.3.4 Responsibility to the Community and the Environment

Risk Software Solution Private Limited its employees embrace responsible citizenship
and corporate responsibility. They believe that they are collectively responsible to
substantively contribute to the communities in which they live and work to help develop
their communities. It encourages employee volunteerism, civic, charitable and
community involvement. Utilizing corporate resources, Risk Software Solution Private
Limited: engages in a selected range of charitable and philanthropic activities to honor
and enhance peoples' lives and to offer its talents and its wealth to help improve the
world it shares. It aspires to be a role model business leader.
It committed to safe guarding, protecting and preserving its physical environment for
present and future generations to use and enjoy. It will develop and implement business

20
Hotel-cum- Multiplex Building Project
At Mouza Chandrasekharpur, Bhubaneswar,Dist-Khorda

practices consistent with sound environmental management and encourage and influence
others to do the same. It will not engage in activities or develop products that that have
any significant negative impact on the environment.
It responsible stewards of its natural and physical environment and natural resources
including our soil, trees and plants, water, air, wild life and farm animals. It recognizes
that they are essential to the perpetuation of its communities and generations, and commit
to care for and protect them.

1.3.4 Performance

The pursuit of superior performance permeates every Risk Software Solution Private
Limited: activity. It aspires to be distinguished as an exemplary company and an
outstanding corporate citizen. They must therefore never settle for doing less than their
best, while they continue to surpass what already has been achieved.

1.3.5 Management

Genesis of Greatness lies in pursuit of vision and commitment to hard work and human
values.
Risk Software Solution Private Limited: has moved through monumental stages from its
inception, growth, and expansion to deliver quality hotel projects & Real Estate Projects.
The Company is expanding into newer horizons with a missionary zeal and a dynamic
team under the leadership of a strong visionary of member of Board Directors.

Speciality:

 Commercial
 Residential

21
Hotel-cum- Multiplex Building Project
At Mouza Chandrasekharpur, Bhubaneswar,Dist-Khorda

CHAPTER-2
PROJECT & SITE DETAILS

2.1 SITE LOCATION AND SITE SURROUNDINGS

This chapter is an introduction to the site for proposed development with respect to its
location. Reconnaissance survey has been carried out along the site surroundings for better
understanding of the local settings.
M/s. Risk Software Solution Pvt. Ltd. is coming up a multi storied project ‘Hotel Cum
Multiplex’ in Chadrasekharpur in Bhubaneswar, Odisha State. The project envisages
construction of a multi-storied building with LB+UB+G+10 floors over Plot No.-7, Rev Plot
No.65(P), 66(P), 67(P), Khata No. 612 at mouza Chandrasekharpur of Bhubaneswar, Dist –
Khorda, Odisha. Bhubaneswar is the capital city of Odisha. It is a city of Temples, Culture,
Information Technology & Educational hub. The majestic temple of Lord Lingaraj needs no
introduction. Bhubaneswar is one of the planned cities of modern India. The site is around
5 km from centre of Bhubaneswar city, the state capital. The site is well connected with road.
The nearest railway station is Bhubaneswar on SE Railway which is around 9 km. from the
site and the nearest airport is Bhubaneswar which is at distance of 10 Km. The proposed
Hotel Multiplex Building Project, you live here, breathe here, fell happy and enjoy your life
to the fullest. With its beauty, design, and openness and of course living space that gives
your life an elegant class of sophisticated and classic living. The project site is such a
beautiful place that fulfills your every dream and desire. Being located in the most spacious
township of Bhubaneswar, it truly elevated its image beyond the height of glory and pride. It
is an ideal combination of a great location and world class amenities.

22
Hotel-cum- Multiplex Building Project
At Mouza Chandrasekharpur, Bhubaneswar,Dist-Khorda

SATELLITE IMAGE OF PROPOSED PROJECT SITE

Proposed Project site

Page 23
Hotel-cum- Multiplex Building Project
At Mouza Chandrasekharpur, Bhubaneswar,Dist-Khorda

Page 24
Hotel-cum- Multiplex Building Project
At Mouza Chandrasekharpur, Bhubaneswar,Dist-Khorda

LAYOUT PLAN OF THE PROJECT SITE

Page 25
Hotel-cum- Multiplex Building Project
At Mouza Chandrasekharpur, Bhubaneswar,Dist-Khorda

TOPO MAP SHOWING 10 KM BUFFER AREA FROM THE PROPOSED PROJECT SITE

Page 26
Hotel-cum- Multiplex Building Project
At Mouza Chandrasekharpur, Bhubaneswar,Dist-Khorda

VICINITY MAP SHOWING 10 KM BUFFER AREA FROM THE PROPOSED PROJECT SITE

Page 27
Hotel-cum- Multiplex Building Project
At Mouza Chandrasekharpur, Bhubaneswar,Dist-Khorda

ANNEXURE – IV
DRAINAGE PATTERN OF THE STUDY AREA WITH IN 10 KM RADIUS FROM
PROJECT SITE

Page 28
Hotel-cum- Multiplex Building Project
At Mouza Chandrasekharpur, Bhubaneswar,Dist-Khorda

M/s. Risk Software Solution Pvt. Ltd. is coming up a multi storied project ‘Hotel Cum
Multiplex’ in Mouza- Chadrasekharpur, Bhubaneswar, Odisha consisting of 87 shops
and 95 suites/rooms, multiplex in LB+UB+G+10 floors of the proposed commercial/
residential multiplex along with party lawn, party hall, lobby, food court, games area,
ATM, Swimming pool, Spa, Salon, Gym, Restaurants, club and other common facilities.

It is already mentioned that the proposed development is commercial/ residential in


nature. Therefore, prior importance has been given upon the flexibility of spaces as well
as the built form of the building. While designing the project, the built form has mostly
followed the function. Side by side, the building has been conceived as a most
contemporary and futuristic in character. The shape of the building has followed the
shape of the project site. Most advanced building materials will be utilized in
construction. In a nutshell, it can be said the proposed development will enhance the
regional aesthetics.

The Building utilities have been planned in accordance with Standard practice
followed in such types of Proposed Commercial Areas at Bhubaneswar. It is intended to
present in the following, an overall view of the design criteria adopted for the MEP
Services.
This report spells out the brief design concepts to be adopted in this project for various
services relating to Ventilation, Plumbing, Water supply, Fire, Electrical (Internal,
External, including Substation) etc. as follows:
1.0 Ventilation System
2.0 Electrical System
3.0 Plumbing/Sanitary/Water & Waste Water Treatment
4.0 Fire Protection & Sprinkler System.

Page 29
Hotel-cum- Multiplex Building Project
At Mouza Chandrasekharpur, Bhubaneswar,Dist-Khorda

AREA STATEMENT

The total plot area of project is estimated 8,096.26 Sqmt m2 (or 2.0 acres). The detailed area
statement is provided below in Table 1
Table 1: Area Statement

Sl. Particulars Area (in m2)


No.
1. Possession Plot Area 8096.26
2. 1st Basement Area 6897.36
3. Service Area 1988.05
4. Parking Area 4909.31
5. 2nd Basement Area 6906.45
4. Service Area 1863.57
5. Parking Area 5042.88
6. Ground Floor Area 4262.99

7. 1st Floor Area 3576.16


8. 2nd Floor Area 3215.89
9. 3rd Floor Area 4221.56
10. 4th Floor Area 1989.66
11 5th Floor Area 419.56
12 6th Floor Area 1519.75
13 Typical Hotel Floor Area (5 nos) – 586.55 sqmt 2932.76
14 Total Floor Area 22138.33
15 Total Built up Area 35942.19
16 Total Parking Area 9952.19
17 Total FAR Area 22138.33
FAR….2.73
18 20% Plantation Area 1619.253

Page 30
Hotel-cum- Multiplex Building Project
At Mouza Chandrasekharpur, Bhubaneswar,Dist-Khorda

POPULATION DENSITY

The total population for the project is 2421 persons.


The detailed population breakup is given below in the following Table 2.

Table 2: Population Break up

S. Unit Type Occupancy PPU Total


No. Population
1. Rooms 89 @2/3 persons 189
per
2. Visitors - Room
- 122
3. Staff (including maintenance staff) - - 225
4. Banquet - - 350
5. Shops 87 @4 persons per 348
Shop
6. Shop Visitors 87 @4 persons per 368
shop
7. Multiplex Visitors 830 - 830

Total Population 2432

WATER REQUIREMENT

During operation phase, water supply will be through borewells. The total water requirement is
approx. 321 KLD, out of which total domestic water requirement is 181 KLD. The fresh water
requirement is approx. 181 KLD. The daily water requirement calculation is given below in Table 3:

Table 3: Calculation for Water Requirement

S. Description Total Rate of Total Water


Occupancy/ water Requirement
No.
Area(m2) demand (KLD)
(lpcd)
A. Domestic Water
1. Rooms 189 230 43.470
2. Staff (including 225 60 13.50
maintenance Staff)

Page 31
Hotel-cum- Multiplex Building Project
At Mouza Chandrasekharpur, Bhubaneswar,Dist-Khorda

3. Visitors 1300 20 26.00


(Hotel/Shops/Muliplex)
4. Banquet hall 350 80 28.00
5. Shops Staff 348 45 15.66
6. Swimming Pool 5 nos. 20000 100.0
Total domestic water demand = 226.63 say 227 KLD
B. Horticulture and Landscape 1619.253 --- 52
development
C. HVAC (300 TR) 10 hrs --- 37
D. DG Set Cooling --- 5
(1X500 KVA + 1 X 320
KVA)
Grand Total (A+B+C+D) = 321 KLD

*Considering 6 hrs per day operation for DG sets

Table 4: Waste Water Calculations

Domestic Water Requirement 227 KLD

 Fresh water (@79.74% of domestic water) 181 KLD

 Flushing water (@ 20% of domestic water ) 46 KLD

Waste Water Generated


135 + 46 = 181 say 200 KLD
(@ 75% fresh water + 100% flushing water)

STP Capacity 200 KLD

Page 32
Hotel-cum- Multiplex Building Project
At Mouza Chandrasekharpur, Bhubaneswar,Dist-Khorda

Water Balance Diagram

Total Water Recycled water


Requirement- 321 Requirement- 140
KLD KLD

Fresh Water Potable Water


135 KLD STP Capacity- 200 KLD
Requirement- 181 (non Flushing) –
(135+46=181 KLD)
KLD 181 KLD

100%

Flushing Water 46 KLD


46 KLD

Horticulture 52 KLD

52 KLD Treated
Waste
Water
HVAC 37 KLD
158 KLD
37 KLD

For DG Set Cooling 5 KLD

5 KLD

For other
Miscellaneous
Purposes 18 KLD

18 KLD

During Non Rainy Season

Page 33
Hotel-cum- Multiplex Building Project
At Mouza Chandrasekharpur, Bhubaneswar,Dist-Khorda

Water Balance Diagram

Total Water
Recycled water
Requirement- 321
Requirement- 140
KLD
KLD

Fresh Water 135 KLD


Potable Water STP Capacity- 200 KLD
Requirement- 181
(non Flushing) –
KLD (135+46=181 KLD)
181 KLD

100%

Flushing Water 46 KLD


46 KLD

HVAC 37 KLD
37 KLD Treated
Waste
Water
For DG Set Cooling
5 KLD
158 KLD
5 KLD

For other 18 KLD


Miscellaneous
Purposes

18 KLD

Discharge to Sewer 52 KLD


52 KLD

During Rainy Season

Page 34
Hotel-cum- Multiplex Building Project
At Mouza Chandrasekharpur, Bhubaneswar,Dist-Khorda

SEWAGE GENERATION AND TREATMENT

During Construction Phase


The quantity of sewage generation during the construction phase will be approx. 5 KLD. Sewage
will be
disposed-off through small septic tanks and soak pits.

During Operational Phase


Quantity of sewage generated during operational phase will be app. 181 KLD. Sewage will be
treated through sewage treatment plant of capacity 200 KLD. STP will be provided with MBBR
technology. The treated sewage will be completely re-used for flushing (46 KLD), road washing (18
KLD), HVAC cooling (37 KLD) and greenbelt development (52 KLD). Only 52 KLD treated water
will be excess during monsoon season which may be given to nearby construction sites or discharged
into sewer.

Sewage Treatment Technology


An external sewage network will collect the sewage from all units, and flow by gravity to the sewage
treatment plant. Following are the benefits of providing the Sewage Treatment Plant in the present
circumstances:
Reduced net daily water requirements, source for Horticultural purposes by utilization of the
treated Wastewater.
Reduced dependence on the public utilities for water supply and sewerage systems.
Sludge generated from the Sewage Treatment Plant will be rich in organic content and an excellent
fertilizer for horticultural purposes.
Characteristics of sewage generated and treated water from STP is given below.

Characteristics of Sewage

Daily load 194 KLD


Duration of flow to STP 24 hours
Temperature Maximum 32°C
pH 6.5 -8.5
Color Mild

Page 35
Hotel-cum- Multiplex Building Project
At Mouza Chandrasekharpur, Bhubaneswar,Dist-Khorda

T.S.S. (mg/l) 300-400 mg/l


BOD5 (mg/l) 250-350 mg/l
COD (mg/l) 600-800 mg/l
Oil & Grease Up to 50 mg/l

Final discharge characteristics


(a) PH : 6.5 to 8.5
(b) B.O.D. : <10 mg/l
(c) C.O.D. : <60 mg/l
(d) Total Suspended Solids : <20 mg/l

Moving bed bio-film reactor technology is based on the principle of attached growth process. Raw
sewage will be collected under gravity into the equalization tank after allowing to pass through the
bar screen. Screens will be provided in screen chambers and it will be manually cleaned by going
down to a platform. The bar screen, by removing coarse solids from the sewage help in protecting
the raw sewage pump. Fully submersible centrifugal non-clog sewage handling pump will be
provided in the collection cum equalization tank to pump the collected Sludge to the next MBBR
tanks. Automatic level controller will be provided in the tank to turn the pump off at the low water
level in the tank and to start the pump when water level is high automatically. Air will be introduced
in this tank to prevent any potential foul smell problem & to provide the mixing of wastewater to
avoid the sedimentation of solids in this tank. Air Grid used for aeration purpose will be non-clog.
The sewage collected in equalization tank is pumped the moving bed bioreactor. There will be two
nos. of bioreactors in series for the efficient working and removal of BODs for the required retention
time. The process inside the moving bed bioreactors consists of adding small cylindrical-shaped
polyethylene/polypropylene carrier elements in aerated basins to support bio-film growth. The small
cylinders are provided with a cross inside the cylinder and longitudinal fins on the outside. The
biofilm carriers are maintained in the reactor by the use of a perforated plate with appropriate slot at
the tank outlet. Air agitation or mixers are applied in a manner to continuously circulate the packing.
The packing may fill 25 to 50 percent of the tank volume. Specific surface area of the packing is
about 450- 500m2/m3 of bulk packing volume. The sludge from first bioreactor flows by gravity
through the perforated plate/mesh to the next bioreactor kept in series. Inside the bioreactors, aerobic
bacteria grow in an attached growth from around the moving plastic media inside the reactors. The
bacteria have to reduce BOD & COD of Sludge in the presence of oxygen provided through the air

Page 36
Hotel-cum- Multiplex Building Project
At Mouza Chandrasekharpur, Bhubaneswar,Dist-Khorda

grids located at the bottom of the reactors. The Process does not require any return activated sludge
flow or backwashing. From the bio-reactors, the effluent passes by gravity into the clarifier (Tube
Settling Tank). Clarifier will be a hopper bottom sedimentation tank provided with appropriate size
PVC tube deck media. The suspended solids will settle at the bottom of the tank & clear supernatant
will overflow to filter feed tank through outlet launder. The collected sludge at bottom will be
transferred through pumps to sludge holding tank.
The clear supernatant after clarifier will be collected in to filter feed tank. This tank will act as
housing tank for filter feed pumps. The clarified & dis-infected water will be then fed to filtration
unit.
Filtration unit consisting of Dual Media sand filter, activated carbon filter and ultra-filtration system
(optional) will remove the residual impurities such as odor/color, suspended solids, BOD/COD. The
treated water after the filtration unit will be collected in Irrigation cum Flushing water storage tank
from where it is transferred to flushing water tank at terrace & Irrigation System.
Excess sludge from the bottom of the settling tank will be removed and transferred to sludge holding
tank. Air grid will be provided in this tank to avoid conversion into anaerobic conditions, thickening
of sludge and keep sludge in homogenous condition. The digested & thickened sludge will be further
thickened through Sludge Dewatering System (Filter press with screw pump) and disposed-off
periodically through closed tanker or can be reused as manure.

Page 37
Hotel-cum- Multiplex Building Project
At Mouza Chandrasekharpur, Bhubaneswar,Dist-Khorda

Schematic Diagram of MBBR STP

SOLID WASTE MANAGEMENT

Solid waste would be generated both during construction as well as during operation phase.
Management plans are prepared for both the phases and are given below

During Construction Phase

Solid waste expected to be generated during construction phase will comprise of excavated materials,
used bags, bricks, concrete, MS rods, tiles, wood etc. App. 30-40 kg of waste will be generated
during construction phase. Solid waste management plan for construction phase is given below

Sl.No. Solid Waste Solid Waste Management


1. Waste materials like MS Material would be segregated into recyclable, reusable and
Rods, bricks, concrete, rejected fractions at the site itself. Recyclable material will
broken tiles, wood be sold to authorize dealers. Re-usable material will be
pieces, cement bags etc.stored within project site re-use. Remaining rejects will be
sent for disposal through government authorized vendors at
designated locations.
2. Excavated Soil Soil will be excavated for development of basements and
foundations of the building. Top soil will be separated and
stored in covered condition at the site for landscaping
purpose. Excavated soil can be used within the site for
filling and leveling purpose. Remaining excavated soil, if
any can be disposed off through government authorized
vendors.
3. Domestic Waste Majorly local labour will be hired for construction phase
generated by labour thus there will be no or minimum labour hutments.
Accordingly domestic waste generation by labour at site
will be insignificant. Domestic waste generated (if any) will
be disposed off through local agencies in the area.
Solid waste would be generated both during the construction as well as during the operation phase.
The solid waste expected to be generated during the construction phase will comprise of excavated
materials, used bags, bricks, concrete, MS rods, tiles, wood etc. The following steps are proposed
to be followed for the management solid waste:
 Construction yards are proposed for storage of construction materials.

 The excavated material such as topsoil and stones will be stacked for reuse during later

Page 38
Hotel-cum- Multiplex Building Project
At Mouza Chandrasekharpur, Bhubaneswar,Dist-Khorda

stages of construction
 Excavated top soil will be stored in temporary constructed soil bank and will be reused for
landscaping of the proposed project.
 Remaining soil will be utilized for refilling / road work / rising of site level at locations/
selling to outside agency for construction of roads etc.

During Operational Phase

During the operation phase, estimated quantity of the waste shall be approx. 491 kg per day (@
0.5 kg per capita per day for residents, @ 0.15 kg per capita per day for the visitor, 0.25 kg per
capita per day for staff and landscape waste @ 0.2 kg/acre/day).

Table 6: Calculation of Solid Waste Generation


SI. Waste Generated Waste Generated
Description Occupancy
No. (Kg per capita / day) (kg/capita/day)
1. Rooms 189 0.5 kg/day 94.5
2. Staff 225 0.25 kg/day 56.25
3. Visitors 1300 0.15 kg/day 195
4. Banquet Hall 350 0.15 kg/day 52.5
5. Shop Staffs 348 0.15 kg/day 52.2
Horticultural Waste
6. @ 0.2 kg/acre/day 0.08
(0.400 acres)

7. STP Sludge --- 40

Total Solid Waste Generation = 490.53 say 491 kg/day

Following arrangements will be made at the site in accordance to Solid Waste Management
Rules, 2016.

 Collection and Segregation of waste


 Generated Waste is stored in three separate bins namely bio-degradable, non-
bio-degradable, and domestic hazardous waste.
 All the wastes are segregated at source, these segregated wastes are handover to
the authorized waste pickers and authorized recyclers.
 Litter bin will also be provided in open areas like parks etc.

Page 39
Hotel-cum- Multiplex Building Project
At Mouza Chandrasekharpur, Bhubaneswar,Dist-Khorda

 Treatment of waste
 Bio-Degradable wastes
1. Bio-degradable waste will be subjected to composting by organic waste converter and
the compost will be used as manure.
2. STP sludge is proposed to be used for horticultural purposes as manure.
3. Horticultural Waste is proposed to be composted and will be used for gardening
purposes.
 Recyclable wastes
i. Grass Recycling – The cropped grass will be spread on the green area. It will act as
manure after decomposition.
ii. Recyclable wastes like paper, plastic, metals etc. will be sold off to recyclables.
iii. Used oil from DG Sets will be sold to authorized vendors.
iv. E-waste will be sold to authorized vendors.
 Non-Recyclable/Inert wastes

i. Inert waste will be disposed off through local agencies in area responsible for waste
management.

 Disposal
Recyclable and non-recyclable wastes will be disposed through Govt. approved agency.
Hence, the Municipal Solid Waste Management will be conducted as per the guidelines
of Solid Waste Management Rules, 2016. A Solid waste management Scheme is depicted
in the following figure for the proposed Project.

Page 40
Hotel-cum- Multiplex Building Project
At Mouza Chandrasekharpur, Bhubaneswar,Dist-Khorda

Figure 5: Solid Waste Management Scheme (Operation Phase)

GREEN AREA
Total area measuring 1619.253 sq m i.e. 20 % of the total plot area is proposed to be put under green
cover.
Evergreen trees, ornamental trees, ornamental shrubs are proposed to be planted in green area. Only
native species and some ornamental species with less water requirement will be planted within the
site. Proper aftercare and monitoring of developed green belt will be done. Details of green area are
given in table. Green area will be developed as per CPCB guideline on Green belt, 2000 and urban
standard plantation norms.

Page 41
Hotel-cum- Multiplex Building Project
At Mouza Chandrasekharpur, Bhubaneswar,Dist-Khorda

Details of Green Area

Particulars Details
Plantation Area 1619.253
As Per MoEF&CC Guidelines One tree per 80 sqmt. of total area out of which
minimum 50 % to be in the category of evergreen
trees.
Trees Required 8096.26 sq m/80= 102 Trees
Number of Trees Proposed To Be 102
Planted

GREENBELT DEVELOPMENT PLAN

All the developments are associated with the pollution of one or more environmental component.
Plants are the natural sink of that pollution. Plants help in abatement of the pollution and restore the
degraded environment. Green belt lowers down the air pollution by providing a surface to settle
down or by absorbing the pollutants, attenuate noise level and uses the waste water. Phyto-
remediation is one of the most successful available technologies of restoring the degraded
environment. Green cover will comprise of peripheral green belt, terrace garden, small lawns and
planters. Green belt will be proper maintained and monitored. Species which can be planted at the
site is given in the Table 16.

Species of Trees, Shrubs and herbs

Sl.No. Scientific Names Common Name


1. Cassia fistula Linn. Indian Laburnum
2. Azadirachtaindica A. Juss. Indian Lilac
3. Saraca indica Ashoka Tree
4. Plumbera rubra Firangipani
5. Albizialebbeck (Benth) Black Siris Tree
6. Delonixregia Flame Boyant
7. Bauhinia purpurea Linn. Butterfly Tree
8. Callistemon sp. Bottlebrush
9. Salix babylonica Weeping Willow
10. Alstonia scholaris Devils Tree
11. Bauhinia varigata Kachnar
12. Nerium indicum Kaner
13. Anthocephalus cadamba Cadamba
14. Jasminum sambac Jasmine
15. Duranta repens Duranta
16. Bougainvillea glabra Bougainvillea
17. Bougainvillea sp. Bougainvillea
18. Sansevieria trifasciata Snake Plant

Page 42
Hotel-cum- Multiplex Building Project
At Mouza Chandrasekharpur, Bhubaneswar,Dist-Khorda

19. Ranunculus sp. Butter cups

CONSTRUCTION MATERIAL

The basic building materials for the construction of the proposed development are cement, sand
stone chip, brick and steel as reinforcement. Through it is too early for estimation of
consumption of building materials in this stage, but a sincere attempt has been made for
preliminary assessment for such consumption; which is presented below.
Consumption of different building materials is assessed as follow:

Item Quantity
Bricks 70,50,000 nos.
Sand 25,800 cum
Stone chips 10,085 cum
Cement 40,200 qntl
Steel 1000 MT
Tile 2,20,600 sft

List of Machinery Used during construction Phase


Dumper
Concrete mixer with hopper
Excavator
Concrete Batching Plant
Cranes
Road roller
Bulldozer
Tower Cranes
Hoist
Construction period of the project has been preliminarily considered as 36 months.

POWER REQUIREMENT

POWER DETAILS AND BACK UP

Power requirement for the project is approx. 1000 KW. 2 nos. transformers of 750 kVA each will be
provided at the site. Source of power will be OSEB. 2 nos. D.G. sets of total capacity 820 kVA
(1 X 500 + 1 X 320 kVA) will be provided for power back up. These sets will be operated through an
‘Auto start, auto load management and auto stop PLC panel and be able to take care of the part load

Page 43
Hotel-cum- Multiplex Building Project
At Mouza Chandrasekharpur, Bhubaneswar,Dist-Khorda

conditions depending upon the occupancy and ambient conditions. The DG sets will be located at
service yard outside the building. DG sets are provided with the acoustic enclosures and are open to
air. Stacks will be provided with DG sets so as emissions can be discharged at app. 5 m above the
terrace level as per CPCB norms.

Source Of Power:

The overall maximum demand is approximately 1000 KW at power factor 0.9. It is proposed to
have Grid supply at 33KV from Electricity Supply Company. Supply to the project shall be
brought through Overhead /underground, 33 KV, HT Cables and shall be terminated to the
33 KV H.T metering cum switchgear panel located in the HT Panel room at ground floor near
main entrance.

2.2 WATER REQUIREMENT

The water requirement for the proposed project can be divided into two stages:
i) Construction Stage
ii) Operational Stage

Water Requirement during construction stage

It is difficult to assess the daily water requirement of the project construction purpose, as water is
required for a wide range of construction activities in varied quantities. However, for major
construction activities daily requirement will be varies from 20 m3 (average) & 50 m3 (peak
demand) per day. Water consumption for the nonresident labourers will be 60 x @30lpcd = 1800
liters and during peak time 2700 liters. 40 labourers/persons on an average will be residing at the
project site. Considering per capita water requirement as 70 liters per day for their household
activities, daily water requirement under this head will be 2800 liters. Water requirement for dust
suppression which will be about 5 KLD (Avg.) and 8 KLD (Peak).
During construction, required water will be sourced from tankers hired from safe areas / bore
wells.

Page 44
Hotel-cum- Multiplex Building Project
At Mouza Chandrasekharpur, Bhubaneswar,Dist-Khorda

i) During Operation Stage

Total Fresh Water Requirement 181 KLD


Effluent /Treated Water Recovered from 158 KLD
STP (as per Water Balance diagram)
Recycled Water used for Flushing, Horticulture, HVAC 46+52+37+5=140 KLD
& cooling tower for DG set
Excess recycled water from STP to be used for basement/ 18 KLD
floor/ road washing etc.

WATER TREATMENT:

The following water filtration & bacteriological treatment is proposed to handle parameters
in accordance to that for potable domestic water supply.

i. Filtration: Pressurized through dual media pressure sand filters/Activated carbon filter

ii. Bacteriological treatment by Chlorination/UV treatment.


Final treatment process will only be decided when test report for bore well water sample
is taken at the start of monsoon, during high flood and during normal period.

TRAFFIC AND PARKING DETAILS

The internal traffic generated by visitors shall be regulated and managed through well laid road
and parking system in the multiplex. A car parking of capacity 230 vehicles will provided.
The road system has been designed in accordance with the CBDA, NBC codes/regulations.
Pavement shall be designed in accordance with the IRC / MORTH standards and codes.
Necessary signs and road furniture shall be provided to ensure regulation and smooth flow of
traffic.
Parking space has been provided at Basement Floor area. Provision is made for reserved parking
areas for use by physically challenged persons. The requirement of parking area is provided as
per BDA guidelines. The vehicular traffic movement within the multiplex will be such that it will
not disturb the landscaped areas and organized open spaces. Parking lots are properly demarcated
for two wheelers and four wheelers.
The basement floor parking area allocated as per layout plan is 9952.19 sqmt. Total No. of car
capacity in the parking space provided is 230 nos.

Page 45
Hotel-cum- Multiplex Building Project
At Mouza Chandrasekharpur, Bhubaneswar,Dist-Khorda

PARKING PLAN INSIDE PROJECT LAYOUT PLAN

Page 46
Hotel-cum- Multiplex Building Project
At Mouza Chandrasekharpur, Bhubaneswar,Dist-Khorda

CHAPTER-3
ENVIRONMENT MANAGEMENT PLAN

3. ENVIRONMENT MANAGEMENT PLAN


The Environment Management Plan (EMP) consist of all mitigation measures for each component of
the environment due to the activities increased during the construction, operation and the entire life
cycle to minimize adverse environmental impacts resulting from the activities of the project. It would
also delineate the environmental monitoring plan for compliance of various environmental
regulations. It will state the steps to be taken in case of emergency such as accidents at the sites
including fire. The detailed EMP for the project is given below.
3.1 Environmental Management Plan
The Environment Management Plan (EMP) is a site specific plan developed to ensure that the project
is implemented in an environmental sustainable manner where all contractors and subcontractors,
including consultants, understand the potential environmental risks arising from the project and take
appropriate actions to properly manage that risk. EMP also ensures that the project implementation is
carried out in accordance with the design by taking appropriate mitigation actions to reduce adverse
environmental impacts during its life cycle. The plan outlines existing and potential problems that
may adversely impact the environment and recommends corrective measures where required. Also,
the plan outlines roles and responsibility of the key personnel and contractors who will be in-charge
of the responsibilities to manage the project site.
3.1.1 The EMP is generally
Prepared in accordance with rules and requirements of the MoEF and CPCB/ SPCB.
To ensure that the component of facility are operated in accordance with the design.
A process that confirms proper operation through supervision and monitoring.
A system that addresses public complaints during construction and operation of the facilities and
A plan that ensures remedial measures is implemented immediately.
The key benefits of the EMP are that it offers means of managing its environmental performance
thereby allowing it to contribute to improved environmental quality. The other benefits include cost
control and improved relations with the stakeholders.
EMP includes four major elements:
Commitment & Policy: The management will strive to provide and implement the Environmental
Management Plan that incorporates all issues related to air, water, land and noise.

Page 47
Hotel-cum- Multiplex Building Project
At Mouza Chandrasekharpur, Bhubaneswar,Dist-Khorda

Planning: This includes identification of environmental impacts, legal requirements and setting
environmental objectives.
Implementation: This comprises of resources available to the developers, accountability of
contractors, training of operational staff associated with environmental control facilities and
documentation of measures to be taken.
Measurement & Evaluation: This includes monitoring, counteractive actions and record keeping.
It is suggested that as part of the EMP, a monitoring committee would be formed by M/s Risk
Software Solution Pvt. Ltd. comprising of the site in-charge/coordinator, environmental group
representative and project implementation team representative. The committee’s role would be to
ensure proper operation and management of the EMP including the regulatory compliance.
The components of the environmental management plan, potential impacts arising, out of the project
and remediation measures are summarized below
SUMMARY OF POTENTIAL IMPACTS AND REMEDIAL MEASURES
Sl.No. Environmental Potential Potential Control through Impact Remedial
Components Impacts Source of EMP & Design Evaluation Measures
Impact

1. Ground Water Ground Water Construction Waste water No significant Waste water
Phase will be managed impact as arising from the
Quality Contamination to maximum majority of project is to be
Waste water extent and to labors would disposed
generated from maintain be locally conforming to
temporary labor hygienic deployed CPCB by septic
tents. condition at site tanks/soak pits.

Operation No treated or No negative Waste water


Phase untreated water impact on generated will be
will be ground water treated in STP
Discharge discharged in quality Proposed inside
from the project sewer except envisaged. the Project
site 52 KLD during Premises and will
monsoon be used for HVAC
cooling,
landscaping,
flushing and road
washing

2. Ground Water Ground Water Construction No water No impact Treated water
Phase ponding will be will be supplied
Quality Depletion allowed at site from tankers for
No impact as meeting
ground water construction water
will not be used requirement

Operation Water No Impact Using water


Phase conservation will efficiently
be practiced to
Water will be conserve water. Re-cycle & Re-
Rain water

Page 48
Hotel-cum- Multiplex Building Project
At Mouza Chandrasekharpur, Bhubaneswar,Dist-Khorda

supplied by harvesting will use of water


tankers during be carried out
operation and the rain Use of Water
phase. In case water will be Efficient fixtures
water supply is recharged to like flow
not available, ground to regulators, dual
ground water augment the flushing cisterns,
may be used ground water low flow taps, low
after taking level. Permission flow urinals
permission should be taken
from CGWB from CGWA Provision of
prior usage of RWH pits to
ground water collect rain water
for ground water
recharge

Permission
should be taken
from CGWA prior
usage of ground
water

3. Surface Water Surface water Construction Water & Measures will Silt traps and
Quality contamination Phase Sewage be taken to diversion ditches
management will restrict the will be constructed
Contaminated be carried out at run-off from to control surface
surface runoff the site to control site. run-off during site
from site during water pollution development.
construction
activity. Curing will be
done by spraying
water to reduce
runoff.

Toilets will be
provided at the site
to prevent open
defecation and the
sewage will be
disposed through
septic tanks and
soak pits.

Site will be kept


clean and the
material will be
handled carefully
to minimize the
spillage.

Operation No untreated No negative Treated water will


Phase water will be impact on be recycled and re-
discharged surface water used for flushing,
Discharge outside project quality horticulture,
from Project site envisaged. HVAC cooling and
Site road/car washing.
52 KLD of surplus
water during
monsoon season
will be given to

Page 49
Hotel-cum- Multiplex Building Project
At Mouza Chandrasekharpur, Bhubaneswar,Dist-Khorda

nearby
construction site
for construction
phase.

4. Air Quality Dust Construction Suitable control Dust Water sprinklers


Emissions Phase measures will be generation will be provided
(PM) adopted for will be
Construction reducing the PM temporary and Regular
activities level in the air as will settle fast sweeping of
per air pollution due to dust construction site
Vehicular control plan. suppression
movement techniques. Construction
Impact will be material & debris
restricted to carrying vehicles
small area. will be covered.

SO2, NO2 and Construction Rapid on-site Impact will be Regular


CO Phase construction for short monitoring of
duration emissions and
Vehicular control measures
exhaust will be taken to
reduce the
Running D.G. emission levels.
set
Use of low sulfur
(back up) diesel

Regular
maintenance and
servicing of
vehicles.

Emissions of Operation Suitable control Not Stack height of


PM, SO2, Phase measures will be significant. DG as per CPCB
NOx and CO adopted for standards
Vehicular reducing Regular
movement emissions monitoring of Use of low sulfur
air quality will diesel
Vehicular be carried out
exhaust to maintain air Traffic
quality management
Running D.G.
set (back up) Providing
Footpath

Developing
Green belt

All vehicles will


carry PUC

5. Noise Construction Noise Impact will be Provision of


Environment phase Management by temporary and Noise shields
adopting suitable will be
Construction measures. restricted to DG sets will be
Activities small area. provided with
acoustic enclosures
Operation of
Machinery Construction

Page 50
Hotel-cum- Multiplex Building Project
At Mouza Chandrasekharpur, Bhubaneswar,Dist-Khorda

Operation of activities involving


DG sets high level noise
generation will be
restricted to day
time

Provision of ear
muffs to workers

Traffic
Management at
site to prevent
honking

Use of machinery
of modern make,
meeting the noise
standards

Operation Noise Not Development of


Phase Management by Significant. green belt
adopting suitable
Noise from measures DG sets will be
vehicular provided with
movement acoustic enclosure

Noise from Proper traffic


DG set management &
circulation. Speed
operation limit restricted to
15 kmph for speed
regulation.

Honking will be
prohibited in the
premises

6. Land Soil Construction By controlling No significant Construction


Environment Contamination Phase soil erosion and impact. debris will be used
maintaining soil for leveling or will
Disposal of quality by Impact will be be sent to landfill
construction periodic soil restricted to for disposal
debris quality project site
monitoring Proper work
Spillage of oil management to
or paints avoid spillage

Excavation of Excavated soil


soil will be reused for
landscaping in
project area.

Silt traps and


dykes will be
develop

Operation Solid waste Since solid MSW


Phase management as waste is Management as
per MSW Rules, handled by the per MSW Rules,
Municipal authorized 2016 by the

Page 51
Hotel-cum- Multiplex Building Project
At Mouza Chandrasekharpur, Bhubaneswar,Dist-Khorda

solid Waste 2016. agency, waste authorized agency.


dumping will
not be Treatment of
practiced thus compostable waste
impact is not within project site
significant.
Recyclable waste
will be sold to
authorized dealers

Inert waste will


be disposed-off by
authorized agency

Used oil
generated will be
disposed as per
norms to
authorized vendors

Negligible
impact.

Used oil from


D.G. set

7. Biological Displacement Construction Important No significant No clearing of


Environment of Flora and Phase species of trees, vegetation trees.
Fauna on site if any, will be exists at
Site identified and project site so
Development marked and will no tree felling
during be merged with involved.
construction landscape plan

Operation Development Positive Green belt will


Phase of Green Belt Impact be developed along
periphery
Site
Development Avenue
plantation will be
carried out

Proper after care


& maintenance
will be done

Socio- Population Construction Generation of Positive Generation of


Economic displacement Phase employment for Impact employment for
Environment local people skilled, unskilled
Construction especially labor and semiskilled
activities may people
lead to
temporary Development of
relocation an area due to
improved
infrastructure

Page 52
Hotel-cum- Multiplex Building Project
At Mouza Chandrasekharpur, Bhubaneswar,Dist-Khorda

Employment
preferably to be
given to local
people

Implementation
of EMP to prevent

Operation Enhancement Positive 


Phase of tourism as the impact
project will
Site operation generate the good
accommodation
facility at the site
for tourist.

Increased
employment
opportunities

9. Traffic Plan Increase in Construction Proper Traffic Impact will Provision of


traffic Phase Management & only be for adequate parking
circulation short time space
Import of (construction
construction phase) Proper traffic
material at site circulation system
at site
Export of
construction Proper signage
debris from system
project site
Restrict hours of
material transport

Operation Proper Traffic Not Provision of


Phase Management & Significant as adequate parking
circulation project site is space
Vehicles of well
staff & visitors connected via Proper traffic
network of circulation system
roads. at site

Informatory &
directive Sign
boards will be
provided

Provision of
pedestrian path to
encourage parking

Page 53
Hotel-cum- Multiplex Building Project
At Mouza Chandrasekharpur, Bhubaneswar,Dist-Khorda

3.2 ENVIRONMENT MANAGEMENT PLAN


An Environmental Management Plan (EMP) will be required to mitigate the predicted adverse
environmental impacts during construction and operation phase of the project and these are discussed
in later subsections.
3.2.1 EMP for Air Environment
Construction Phase
To mitigate the impacts of PM during the construction phase of the project, the following measures
are recommended for implementation:
A dust control plan
Procedural changes to construction activities
Dust Control Plan
The most cost-effective dust suppressant is water because water is easily available on construction
site. Water can be applied using water trucks, handled sprayers and automatic sprinkler systems.
Furthermore, incoming loads could be covered to avoid loss of material in transport, especially if
material is transported off-site.
Procedural Changes to Construction Activities
Idle time reduction: Construction equipment is commonly left idle while the operators are on break
or waiting for the completion of another task. Emission from idle equipment tends to be high, since
catalytic converters cools down, thus reducing the efficiency of hydrocarbon and carbon monoxide
oxidation. Existing idle control technologies comprises of power saving mode, which automatically
off the engine at preset time and reduces emissions, without intervention from the operators.
Improved Maintenance: Significant emission reductions can be achieved through regular
equipment maintenance. Contractors will be asked to provide maintenance records for their fleet as
part of the contract bid, and at regular intervals throughout the life of the contract. Incentive
provisions will be established to encourage contractors to comply with regular maintenance
requirements.
Reduction of On-Site Construction Time: Rapid on-site construction would reduce the duration of
traffic interference and therefore, will reduce emissions from traffic delay.
Operation Phase
To mitigate the impacts of pollutants from DG set and vehicular traffic during the operational phase
of the Project, following measures are recommended for implementation:
 DG set emission control measures
 Vehicular emission controls and alternatives

Page 54
Hotel-cum- Multiplex Building Project
At Mouza Chandrasekharpur, Bhubaneswar,Dist-Khorda

 Greenbelt development
Diesel Generator Set Emission Control Measures
Adequate stack height will be maintained to disperse the air pollutants generated from the operation
of DG set to dilute the pollutants concentration within the immediate vicinity.
Vehicle Emission Controls and Alternatives
During construction, vehicles will be properly maintained to reduce emission.
Footpaths and Pedestrian ways: Adequate footpaths and pedestrian ways would be provided at the
site to encourage non-polluting methods of transportation.
Greenbelt Development
Increased vegetation in the form of greenbelt is one of the preferred methods to mitigate air and
noise pollution. Plants serve as a sink for pollutants, act as a barrier to break the wind speed as well
as allow the dust and other particulates to settle on the leaves. It also helps to reduce the noise level
at large extent.
3.2.2 EMP FOR NOISE ENVIRONMENT
Construction Phase
To mitigate the impacts of noise from construction equipment during the construction phase on the
site, the following measures are recommended for implementation.
Time of Operation: Noisy construction equipment would not be allowed to use at night time.

Job Rotation and Hearing Protection: Workers employed in high noise areas will be employed on
shift basis. Hearing protection such as earplugs/muffs will be provided to those working very close to
the noise generating machinery.

Operation Phase
To mitigate the impacts of noise from diesel generator set during operational phase, the following
measures are recommended:
Adoption of Noise emission control technologies
Greenbelt development

Noise Emission Control Technologies


DG sets are provided with integrated acoustic enclosures as per E (P) Act, GSR (E) and its
amendments.

Page 55
Hotel-cum- Multiplex Building Project
At Mouza Chandrasekharpur, Bhubaneswar,Dist-Khorda

3.2.3 EMP FOR WATER ENVIRONMENT


Construction Phase
To prevent degradation and to maintain the quality of the water source, adequate control measures
have been proposed. The following management measures are suggested to protect the water source
being polluted during the construction phase:
Avoid excavation during monsoon season
Care would be taken to avoid soil erosion
Common toilets will be constructed on site during construction phase and the waste water would be
channelized to the septic tanks in order to prevent waste water to enter into the nearby water bodies
Any area with loose debris within the site shall be planted
To prevent surface and ground water contamination by oil and grease, leak-proof containers would
be used for storage and transportation of oil and grease. The floors of oil and grease handling area
would be kept effectively impervious. Any wash off from the oil and grease handling area or
workshop shall be drained through imperious drains
Collection and settling of storm water, prohibition of equipment wash downs and prevention of soil
loss and toxic release from the construction site are necessary measure to be taken to minimize water
Pollution
Operation Phase
In the operation phase of the project, water conservation and development measures will be taken,
including all possible potential for rain water harvesting. Following measures will be adopted:
Water source development.
Minimizing water consumption.
Promoting reuse of water after treatment and development of closed loop systems for different
water
streams.
Water Source Development
Water source development shall be practiced by installation of scientifically designed Rain Water
Harvesting system. Rainwater harvesting promotes self-sufficiency and fosters an appreciation for
water as a resource.
Most of the storm water produced on site will be harvested for ground water recharge. 2 Nos. of
RWH pits will be provided at the site put the storm water into the ground for recharging groundwater
aquifers. Thus proper management of this resource is a must to ensure that it is free from
contamination.
Page 56
Hotel-cum- Multiplex Building Project
At Mouza Chandrasekharpur, Bhubaneswar,Dist-Khorda

A detailed storm water management plan will be developed which will consider the possible impacts
from above sources. The plan will incorporate best management practices which will include
following:
Regular inspection and cleaning of storm drains
Clarifiers or oil/separators will be installed in all the parking areas. Oil / grease separators installed
around parking areas and garages will be sized according to peak flow guidelines. Both clarifiers and
oil/water separators will be periodically pumped in order to keep discharges within limits
Covered waste storage areas
Avoid application of pesticides and herbicides before wet season
Conducting routine inspection to ensure cleanliness
Provision of slit traps in storm water drains
Good housekeeping in the above areas
Minimizing Water Consumption
Consumption of fresh water will be minimized by combination of water saving devices and other
domestic water conservation measures. The following section discusses the specific measures, which
shall be implemented:
Consumption/Usage
Use of water efficient plumbing fixtures (dual flushing cisterns, low flow showers, pressure taps
and
faucets). Water efficient plumbing fixtures uses less water with no marked reduction in quality and
service
Leak detection and repair techniques.
Meter water usage: Implies measurement and verification methods.
Monitoring of water uses is a precursor for management.
Horticulture
Usage of STP treated water for horticulture
Promoting Reuse of Water after Treatment
Quantity of sewage generated during operational phase will be app. 181 KLD. Sewage will be
treated through sewage treatment plant of capacity 200 KLD. STP will be provided with MBBR
technology. The treated sewage will be completely re-used for flushing (46 KLD), miscellaneous
uses (18 KLD), HVAC cooling (37 KLD) and greenbelt development (52 KLD). Only 52 KLD
treated water will be excess during monsoon season which may be given to nearby construction sites
or discharged into sewer.
Page 57
Hotel-cum- Multiplex Building Project
At Mouza Chandrasekharpur, Bhubaneswar,Dist-Khorda

3.2.4 EMP FOR LAND ENVIRONMENT


Construction Phase
The waste generated from construction activity includes construction debris, biomass from land
clearing activities, waste from the temporary make shift tents for the labors and hazardous waste.
Following section discuss the management of each type of waste. Besides waste generation,
management of the topsoil is an important area for which management measures are required.
Construction Debris
Construction debris is bulky and heavy and re-utilization and recycling is an important strategy for
management of such waste. As concrete and masonry constitute the majority of waste generated and
this waste can be recycled by conversion to aggregate which can be further used as construction raw
material. Mixed debris with high gypsum, plaster, shall not be used as fill, as they are highly
susceptible to contamination, and will be send to designated solid waste landfill site. Metal scrap
from structural steel, piping, concrete reinforcement and sheet metal work shall be removed from the
site by construction contractors. A significant portion of wood scrap will be reused on site.
Recyclable wastes such as plastics, glass fiber insulation, roofing etc. shall be sold to recyclers.
Construction and Demolition Waste will be managed as per C & D Waste Rules, 2016.
Hazardous waste
Construction sites are sources of many toxic substances such as paints, solvents wood preservatives,
pesticides, adhesives and sealants. Hazardous waste generated during construction phase shall be
stored in sealed containers and disposed off as per The Hazardous & Other Waste, 2016.
Some management practices to be developed are:
Herbicides and pesticide will not be over applied (small-scale applications) and not applied prior to
rain
Paintbrushes and equipment for water and oil based paints shall be cleaned within a contained area
and will not be allowed to contaminate soil, water courses or drainage system
Provision of adequate hazardous waste storage facilities. Hazardous waste collection containers
will be located as per safety norms and designated hazardous waste storage areas which will be
located away from storm drains or natural watercourses
Segregation of potentially hazardous waste from non-hazardous construction site debris
Well labeled hazardous waste containers with the waste being stored and the date of generation
Instruct employees and subcontractors in identification of hazardous and solid waste

Page 58
Hotel-cum- Multiplex Building Project
At Mouza Chandrasekharpur, Bhubaneswar,Dist-Khorda

Waste from Temporary Makes Shift Tents for Labors


Local labour will be hired and there will be no or minimal requirement of setting up of labour camp.
Wastes generated from temporary make shift labor tents if any will mainly comprise of household
domestic waste, which will be managed by the contractor at the site. The sewage generated will be
channelized to the septic tank.
Top Soil Management
To minimize disruption of soil and for conservation of top soil, the contractor shall keep the top soil
cover separately and stockpile it. After the construction activity is over, top soil will be utilized for
landscaping activity. Other measures, which would be followed to prevent soil erosion and
contamination include:
Maximize use of organic fertilizer for landscaping and green belt development
To prevent soil contamination by oil/grease, leak proof containers would be used for storage and
transportation of oil/grease and wash off from the oil/grease handling area shall be drained through
impervious drains and treated appropriately before disposal
Removal of as little vegetation as possible during the development and re-vegetation of bare areas
after the project is completed.
Working in a small area at a point of time (phase wise construction)
Construction of erosion prevention troughs/berms.
Operational Phase
During operation phase, waste comprise of municipal waste. Details of municipal waste generation
and management
SOLID WASTE MANAGEMENT PLAN
1. Compostable wastes
Compostable waste will be composted in organic convertor and will be used as manure.
STP sludge will be stabilized and is proposed to be used for horticultural purposes as manure.
Horticultural Waste will also be composted and will be used as manure.
2. Recyclable wastes
Recyclable wastes like paper, plastic, metals etc. will be sold off to authorized recyclers
Used oil from DG sets will be sold to authorized vendors
E-waste will be sold to authorized vendors
3. Non-Recyclable/Inert wastes
Inert waste will be disposed off through local agencies in area responsible for waste

Page 59
Hotel-cum- Multiplex Building Project
At Mouza Chandrasekharpur, Bhubaneswar,Dist-Khorda

Management

3.2.5 EMP FOR ECOLOGICAL ENVIRONMENT


Site does not support any vegetation thus no impact on ecology would be there due to project
development. During operation phase a green belt is proposed at the project site. Approx.
1619.253 m2 of area is kept under green cover which is approx. 20% of net plot area.

3.2.6 EMP FOR SOCIO-ECONOMIC ENVIRONMENT

During construction stage only local labour will be hired for construction purpose which will provide
employment to local people. Environmental management plan was implemented at the site which
prevented the environmental pollutionin the area and problems to the people in the project site
surroundings.
During operation phase, environment management plan will be implemented to manage sewage,
storm water, emissions and waste from the site. Thus there are no impacts due to the project on
socio-economy. Further the project is one of the best working spaces in the city.

3.2.7 EMP FOR ENERGY CONSERVATION


Energy conservation program will be implemented through measures taken both on energy demand
and supply. Energy conservation is integral part of our project planning. Energy saving will help
saving the energy as well as the cost for the power usage. The conservation efforts would consist of
the following:
Architectural design
1) Maximum utilization of solar light will be done by providing glazed glass walls and façade
2) The orientation of the buildings will be done in such a way that maximum soft daylight is
available.
3) Overhangs will be provided to regulate the sum heat entering the building.
4) Provision of green belt within the site
Energy Saving Practices
1) Energy efficient lamps will be provided within the project site
2) Solar street lights for external lighting
3) Constant monitoring of energy consumption and defining targets for energy conservation.
4) Adjusting the settings and illumination levels to ensure minimum energy used for desired comfort
levels.

Page 60
Hotel-cum- Multiplex Building Project
At Mouza Chandrasekharpur, Bhubaneswar,Dist-Khorda

Behavioral Change on Consumption


1) Promoting staff and visitors awareness on energy conservation
2) Training staff on methods of energy conservation and to be vigilant to such opportunities.

3.3 ENVIRONMENTAL MANAGEMENT SYSTEM AND MONITORING PLAN


1) Promoting awareness on energy conservation through signage
2) Training staff on methods of energy conservation and to be vigilant to such opportunities

3.3.1 Environmental Management Budget


Emp Budget For Construction Phase
Sl.No. Activity Capital Cost (Lacs) Recurring Cost (Lacs)

1. Temporary Construction Raw 1.0 0.1

material storage yard

2 Temporary excavated soil storage yard 0.5 0.05

3. Solid waste Management 2.0 2.0

4. Health & safety of Workers 1.5 0.3

5. Environmental Monitoring 1.04 1.04

Total 6.04 3.49

Emp Budget For Operational Phase

Sl.No. Activity Capacity/ Area/Nos. Capital Cost Recurring Cost


(Lacs) (Lacs)

1. STP 200 KLD 25.0 20

2 Landscaping & 1619.253 15.0 2.0

planting trees

3. Solid waste Management 491 Kg/day 4.0 2.0

4. RWH Pit Installation 2. nos. 4.0 0.5

5. Environmental Air, Water, Soil & 1.6 3.2


Monitoring* Noise

Page 61
Hotel-cum- Multiplex Building Project
At Mouza Chandrasekharpur, Bhubaneswar,Dist-Khorda

Total 49.6 9.7

* Environment monitoring to be carried out twice in year so recurring cost per annum is double that of
onetime cost of environmental monitoring.

3.3.2 Environmental Monitoring


The purpose of environmental monitoring is to evaluate the effectiveness of implementation of
Environmental Management Plan (EMP) by periodic monitoring. The important environmental
parameters within the impact area are selected so that any adverse effects are detected and time
action can be taken. The project proponent will monitor ambient air Quality, Ground Water Quality
and Quantity, and Soil Quality in accordance with an approved monitoring schedule.

3.3.3 Awareness and Training


Training and human resource development is an important link to achieve sustainable operation of
the
facility and environment management. For successful functioning of the project, relevant EMP
would be communicated to:
Hotel guests, Staff & Contractors
Hotel guests, staff & contractors must be made aware of the importance of waste segregation and
disposal, water and energy conservation.

Page 62
Hotel-cum- Multiplex Building Project
At Mouza Chandrasekharpur, Bhubaneswar,Dist-Khorda

CHAPTER-4
ENERGY CONSERVATION

4.1 CONSERVATION OF ENERGY

The buildings shall be designed to achieve maximum solar gain in winter and minimize in
summer combines three strategies via orientation, glazing and thermal mass.

ORIENTATION

Orientation refers to the location of a building and direction to which a building point, crucial for
determining the amount of sun rays a building receives.

1. Surfaces facing south receive sun round the year. The dominant direction of the sun is from
the South, especially in winter. For this reason, solar panels and windows that will capture solar
warming in winter will face as close to South as possible. Solar receipts start to fall noticeably
outside the band South-Southeast to South-Southwest. Surfaces facing Southeast or Southwest
receive 10% less solar energy during the year than surfaces facing due south direction.
The winter sun is low, the summer sun is high. Vertical South facing windows work best for
maximizing solar heating in the winter as they capture the low winter sun.
The high summer sun is a blessing when if comes to designing shading for vertical windows.
Only a small overhang is needed to completely shade a vertical South facing windows in
summer. They receive no direct sun in winter, but they fully face the low evening and morning
sun in summer. West facing rooms are particularly prone to overheating and will need curtains or
shades.
A well functioning eco building will have glazing as possible in vertical windows facing between
South East to South West and as few windows as possible facing North East through to North
West.

GLAZING

Structural glazing (double glazing) to the extent of 30% is used for the facade with the u-value of
3.3 W/ sqm oc and relative heat gain of 257 W/ sqm.
Plain float glass is used for windows. Venetian blinds / frosted stickers are used to suppress full
light / sunrays penetration.
Air Leakage for glazed swinging entrance door will be designed to ensure that the air leakage
does not exceed to 2.0 l/s- m2.

Page 63
Hotel-cum- Multiplex Building Project
At Mouza Chandrasekharpur, Bhubaneswar,Dist-Khorda

INSULATION
Roofs are provided with insulation suitable to achieve a maximum of U-factor of overall
assembly of 0.409 W/ m2- oC and minimum R-value of insulation alone of 2.1 m2- oC /W. In
accordance with the climatic zone which is warm and humid.

EXTERIOR FINISH

30% of the area is provided with double walled structural glazing.


30% is treated with ACP (Aero Cement Panels)
30% is treated with natural clay tiles
10% is treated with plastering
Thus the above treatment helps in reducing solar heat gain and serves as an insulator.

INTERIORS
Interiors provide filtered sun light, flow of air and visual effects.
Interior partition is done using eco-friendly Autoclaved Aerated Concrete Panels using fly ash
and cement. The product serves as an insulator and acoustic dampener.

DESIGN ASPECTS
The design of the various buildings has taken into consideration the following aspects;
 Orientation of the buildings utilizes east lighting and minimal use of west lighting.
 North and South of the buildings are provided with good number of windows.
 To avoid direct west sun shading devices are provided in the building such as pergolas,
louvers, sunshades and roof over hands.
 Stacking of the building helps to create shades on terraces.
 Single door corridors to allow lighting.
 Providing Open to sky areas to allow light and air.
Adequate set back around the buildings to allow access for natural light and wind.

ENERGY SAVING DEVICES


Power Conservation measures have been taken to optimize power consumption.
(1) The active measures are:

 Use of copper wound high efficiency transformers and motors.


 Use of CFL instead of tube lights.
 Use of electronic ballast in place of conventional ballast.

Page 64
Hotel-cum- Multiplex Building Project
At Mouza Chandrasekharpur, Bhubaneswar,Dist-Khorda

 Use of solar water heater.


 Use of solar light for street and parking area lighting.
 Use of energy efficient armour cables and wires
 Use of VFD in all major motors.
 Use of VAV in HVAC system.
 Use of water level controller

(2) The passive protection measures and Passive solar features as described
below:

 Proper solar orientation i.e. building is oriented in north-south direction giving


indirect light from north.
 South west light exposure and low exposure to east light
 Lower exposure to reduce heat gain.
 Optimum window position for low heat gain.
 Planting of deciduous trees to reduce heat gain.
 Glazing tiles on the roof and high florescent paint on the wall to reduce heat gain.
 Proper space plan reduce air conditioning.
 Use of vegetation, lawns and water fountains
 Natural lighting of rooms is enhanced with raised roofing with low emissivity
glasses.

Page 65
Hotel-cum- Multiplex Building Project
At Mouza Chandrasekharpur, Bhubaneswar,Dist-Khorda

CHAPTER-5

RAINWATER HARVESTING

5.0 RAINWATER HARVESTING

5.1 STORM WATER MANAGEMENT SYSTEM

Storm water drainage system will be provided at project site for channelizing storm water and
prevents local flooding. Covered storm water drains will be provided at the site for carrying the storm
water. Storm water from site will be collected and recharged to ground through RWH pits. RWH pits
are designed for peak hourly rainfall for Bhubaneswar, i.e. 10.1 cm. Project site lies in the
Chandrashekhar Mouza. Ground water level in project area is >10.64 m bgl. Hydrologically water
bearing formation in the project area is sand, pebble, gravel etc. in nature. Potential for ground water
recharge is good in area. Stage of ground water develop in the block is 52.11% and falls under safe
category as per CGWB assessment. Project site lies in safe zone but recharging of storm water will
help in flooding during monsoon and also replenishing the ground water aquifers.

5.2 RAINWATER HARVESTING & ARTIFICIAL RECHARGING

Rainwater harvesting is the process of collection and storage of rain. The stored water can be used or
recharged to ground water system. Ground Water recharging is a process whereby ground water
resource is being augmented by artificial means. There are various methods or techniques of ground
water recharging suitable to different hydrogeological conditions.

Harvesting Plan of the Project

Rainwater available from the entire project area will be collected and recharged to ground water
system. Depending upon the quality of available rainwater, the following methods will be followed
for recharging.

1. Rainwater to be generated from the roof top areas of the project building will be recharged to
deeper ground water system through injection well at the centre of a filtration cum storage
chamber (Recharging Structure).
2. Rainwater available from the paved and plantation area will be recharged to shallow aquifer
through recharge pits

Page 66
Hotel-cum- Multiplex Building Project
At Mouza Chandrasekharpur, Bhubaneswar,Dist-Khorda

Rainwater generated from the roofs of the building will be channelized through PVC Pipe which
will be connected to the recharging structure. Rainwater falling on paved, plantation and other area
will be channelized through open/ closed drain to recharge pits to recharge the shallow aquifers.

Volume of Water Available for Recharging

The volume of rainwater available for harvesting and recharging depends upon two factors i.e.
volume of rainfall in the region and the surface receiving rainfall both its nature and area.

The area receives maximum rainfall during 7 months i.e. May to November. The average annual
rainfall ( 2004-2015) is 1447 mm. The distribution of rainfall over the months is graphically shown
in figures nos. 8.

Monthly Rainfall (mm) of Bhubaneswar Block

Year/M Jan Feb M Apr Ma Jun July Aug Sept Oct Nov Dec Total
onth ar y
2004 0 0 0 40 27 124 273 238.3 144.2 221 0 0 1067.5

2005 12 0 51 0 44 130 296 166 565 0 0 0 1264

2006 0 0 17 29.5 122 240 416 635 343 79 0 0 1881.5

2007 0 84 0 0 0 180 194 422 581.5 93 15 0 1569.5

2008 6 30 0 54 42 333 219.5 310 488 15 0 0 1497.5

2009 0 0 0 0 97 75 487 440 226 95 17 0 1437

2010 0 0 0 0 171 227 217 316.5 313 215 45 40 1544.5

2011 0 81 0 51 129 242 351 378 296 32 0 0 1560

2012 31 0 0 75 25 146 455.5 273 155 78 113 0 1351.5

2013 0 0 0 29 75 255 241 10 266 722 0 0 1598

2014 0 18 59 4 166 98 482 242 440 129 0 0 1638

Page 67
Hotel-cum- Multiplex Building Project
At Mouza Chandrasekharpur, Bhubaneswar,Dist-Khorda

2015 15 9 25 84 15 75 252 284 135 49 4 12 959

Av. 5.3 18. 12. 30.5 76.1 177. 323.7 309.6 329.4 144. 16. 4.3 1447.3
5 7 1 0 2

Fig.8: Av.Montly Rainfall in Bhubaneswar Block


350

300

250
Rainfall in mm

200

150

100

50

0
J F M A M J J A S O N D
Month

Fig.9:Annual Rainfall in Bhubaneswar Block


2000
1800
1600
1400
Rainfall in mm

1200
1000
800
600
400
200
0
2004 2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015
Year

Page 68
Hotel-cum- Multiplex Building Project
At Mouza Chandrasekharpur, Bhubaneswar,Dist-Khorda

The project spreads over an area of 8096.268 sq.m. Out of the total area roof-top area constitutes
4262.99 sq.m, paved area is 2214.025 sq.m and plantation area is 1619.253 sq.m. Roof top area has
good potential for generation of rainwater which will be available for recharging.

Volume available for harvesting (annual)= Rainfall (m) x Area ( m2)X Runoff co-efficient

The area receives average annual rainfall of 1447 mm (last 12 yrs average). Rainfall available during
monsoon months i.e. May to November will only generate run off and available for harvesting and
recharging. Rainfall during these months is 1360mm.

Again 100% of 1360 mm rainfall will not be available for harvesting as some portion of it will be
lost. This percentage will vary from areas to areas. On the basis of past experience on similar
projects, 90% of it will be taken for roof-top area, 50% for paved and 20% for plantation area. This
percentage of rainfall will be multiplied with the area which will give net water available for
harvesting.

The table no. below shows the volume of rainwater to be generated annually from different area.

Volume of Rainwater available for Harvesting

Sl.No Source Area (m2) Rainwater to be Remarks


generated (m3)

annually

1 Roof 4262.99 5217.9 Recharged to deeper


aquifer through
recharging well

Paved 2214.025 1505.537 Recharged to shallow


aquifer
2

3 Plantation 1619.253 440.4368

Total 8096.268 7163.874

Page 69
Hotel-cum- Multiplex Building Project
At Mouza Chandrasekharpur, Bhubaneswar,Dist-Khorda

Annually 7164 m3 of rainwater will be recharged to ground water system.

5.3 Design of Recharging Structure

1. Injection Well for roof-top rainwater recharging

On analyzing the data available and disposition of aquifer system it is proposed that injection well
would be the most suitable recharging structure for this area. An injection well will be constructed
within a storage cum filtration chamber.

An injection well will be constructed and its depth will be around 100m bgl or will be decided during
drilling of the borewell. 4” (102mm) dia. PVC pipe will be lowered in a 9” dia. drilled borehole. The
area around the pipe will be filled up with gravel. Aquifer zones will be tapped by placing 4” dia.
slotted pipe. After construction of the injection well, it was developed with air compressor to clear
the well of all suspended matter.

Filtration/Storage Chamber

A storage/filtration chamber will be constructed around the injection well. The dimension of the
trench is 3.0 m x 3.0 m x 3.0 m. assuming maximum rainfall intensity of 25mm/hr and intake
capacity of injection well to 2.0 lps. The wall of the trench is made of RBC structure as per the
design shown in fig. no.4. The chamber is filled with filtering material i.e. gravel and medium to fine
sand. The chamber is connected to the roof-tops through PVC Pipe. The approximate design of the
recharge structure is shown in fig.11.

Number of Recharging Structures

On the basis of the volume of rainwater available during maximum intensity of 25mm/hr, it is
proposed to construct 2 nos. of recharging structures. The proposed location of the structures is
shown in the layout plan of the project.

2. Recharge Pits/Recharge Shafts

Rainwater being generated from the paved, plantation and other area will be recharged to
shallow/phreatic aquifer system. Since the area is underlain by sandy formation, recharge pits/shafts
will be most suitable recharging structure. The recharge shafts is a vertical excavation through the
earth connecting the water table. The shafts may be either circular or rectangular, lined and with
naked bottom touching at least water table. It is proposed to construct 3 nos.of recharge pits/shafts
with 2.0m(long)x2.0m(width)x3.0m (deep). The bottom 0.5m of the shaft will be filled with coarse

Page 70
Hotel-cum- Multiplex Building Project
At Mouza Chandrasekharpur, Bhubaneswar,Dist-Khorda

sand. Surface runoff generated from paved, plantation and other area will be channelized through
drains/covered to the recharge shafts. De-silting pits of small dimension will be constructed at
regular intervals within the drains to arrest silts if any.

Page 71
Hotel-cum- Multiplex Building Project
At Mouza Chandrasekharpur, Bhubaneswar,Dist-Khorda

Page 72