IS.9759.1981 - Code For Dewatering in Construction PDF
IS.9759.1981 - Code For Dewatering in Construction PDF
IS.9759.1981 - Code For Dewatering in Construction PDF
Indian Standard
GUIDELINES FOR
DEWATERING DURING CONSTRUCTION
© Copyright 1981
Gr 8 December 1981
IS: 9759.1981
Indian Standard
GUIDELINES FOR
DEWATERING DURING CONSTRUCTION
Chairman RefJ,.ese"lin~
PROF DINESH ~10HAN Central Building Research Institute (CSIR),
Roorkee
Members
DR R K. BHANDARI Central Boddrog Research Institute (CSIR),
Rocrkee
CHIEF ENGINEFR Calcutta Port Trust. Calcutta
SHRt S GtiHA (Alterndte)
SHRt M. G. DANDAVATE The Concrete ASSoCIatIon of India, Bombay
SHRl N C. DUOQAL (Allernat!)
SHRl A G DMTIDAR In personal capacity (5 Hungerford Road, 121
Huneaford Street, Calcutta)
SaRI V. C. DFSHPANDE The Pressure Prlmg Co (I) Pvt Ltd, Bombay
DIRECTOR (CSMRS) Central Water & Power Oomrmssion, New Deihl
DEPUTY DIRECTOR (CSMRS) (Alternate)
SHRI A H DIVANTI Asia Foundations and Construction Co Pvt Ltd.
Bombay
:-'HRI A. N JANGLE (Allt"NlQlt')
DR R. K. DAS GVPTA Simplex Concrete Piles (India) Pvt Ltd. Calcutta
ADDITIONAL CHI£P ENGINEER (.4lternak)
DR JAGDISH NARAI"l Indian Oeotechmc Society, New Delhi
PROF SWAMI SARAN (Alternate)
SHRT G. S.JAlN G. S. Jam &. Associates, Rocrkee
SHRI AmOK KTJM~RJAIN (Alternate)
JOINT DIRECTOR (Dt National Burldmgs Organisation, New Delhi
SHlU SU""IL B~RY (Alternate)
JOINTDIRECTOR RESEARCH (51\..1) Ministry of Railways (RDSO)
]OlNT DZRECTOR RESEARCH (B&5) (Alternate)
DR R K. KATTt Indian l nsnrute of Te-chnology, Bombay
SHRI S. R KllLKARNI M. N Dastur & Co Pvt Ltd, Calcutta
SHRI S Roy (Alternate)
SHRIO. P. MALHOTRA Public Works Department, C han dig a r h
Adnurustration
SHRI A. P J\.IATHUR Central Warehousing Corporation, New Delhi
SHRl V. B. MATHUR Machenzres Limited, Bombay
SHRT T K D MUNlII Engineers India Limned, New Delhi
SHRI M IYENGAR (Alternate)
(Contmued on page 2)
Members RepreJtnlmg
SHRl B. K PANTHAKY The Hmdustan Construction Company Limited,
Bombay
SHRIV. M. MADGE (Aturnatt)
SIIRI M. R PuN] ..... Cerrundra Co Ltd, Bombay
SHRI S. MUKHERJEE (AlJulIQJe)
SHRI N. E. V RAGHVA"'l The Braithwaite Burn & Jessop Construction Co
Ltd, Calcutta
5HFll A A R"'Ju Vliavariag ar Steel Plant (SAll. New De/til
PROF (.OPAL kANJAN Unrc ersny of Roorkee, Roorkee
SHRT T N. StlDDA RAO Gammon India Limited, Bombay
Smll S A. REDDI (Allcrnatr)
SHRI Y V NARA'>TMHA RAO Bokarn Steel Plant (Steel Autborary of India),
Bokaro
DR V V. S Reo Nagadr Consultants Pvt Ltd, New Deihl
SHRI ARJUN RIJHSINGIIANI Cement Corporation of India, New Delhi
SHRJ 0 S SRI v ASTAVA {Altanal",}
DR A SARGUNAN College of Engmeenng, GUlOdy
SHRI S BOOMI"'4'ATHAN (Atlernnlf)
SURI K. R. SAnNA Pubhc works Department, Government of Andh ra
Pradesh, Hyderabad
DR S. P ';HRIVASTAVA United Technical Consultants Pvt Ltd, New Delhi
UR R KAPlTR (Aflemate)
BIlIG OMBIN. SINGH Engmeer-m-Chref?s Branch, Army Headquarters,
New Delhi
J...l"'J H K HIIlTT<\NI (Alternale)
SURI N SIVAliURU Muustrv or Shipping and Transport, New Delhi
'sHRI n \'
~11l.K'" {A/ter,ralf')
SUPER1NTENDI~(. b N GIN r; r R Ce-ntral Pubhl- WOrks Department, New Dt"lhl
(UE.!>IG"'Sl
EXEClJTIVF ENC.JNHR (DFSIGNS) V (Alternate)
I;jHRI M D TAMBE"'AR Bombay Port Trust, Bombay
DR i\ \ ARAOARAJA!>l Indian Ineutuce of Technology, New Deihl
DR R KANIRAJ (Altanale)
~HRI G RAMA.... Director General, B1S (E~-offiClo Ml'mber)
Director {en' Engg)
Secretary
SHRT K. M. MATHUR
Deputy Director (en' Engg), DIS
Convener
SHR( SHiTALA SHARAN Pubhc Works Department. Luckncw
Membtrf
SHRI E. T ANTIA The Concrete ASSOCiation of India, Bombay
SliRI N C. DtJGGAL (Alternate)
CHIllY hNrlNEER (Ro ... os) Mmrstry of Transport and Shipping (Roads Wm.rr),
New Delhi
(Continued on page 36)
2
AMENDMENT NO.1 MARCH 1989
TO
IS : 9759 • 1981 GUIDELINES FOR DEWATERING
DURING CONSTRUCTION
( Pag' 6, claus, 4.3.1.5, ,nformlll table) - Substitute 'k X 10-' ' for
, k '.
( Page 12, clause 6.3.4.5 ) - Substitute' V' fOT ' V ' appearing for
vacuum at pump intake.
'N ~ 'N'
(Page 27, claus, 11-1.10 ) - Substitute N; fOT Nf
appearing at
two places.
( Page 30, Table Z, col 3 ) - Substitute the followmg for the value
of' Q' m lines I, 2 and 4 respectively:
kD.
a) -t- (H - h. )
kx
b) -2L (H' - he' )
( Page 31, Table 3, col 3, ltn« 2) - Substitute the following for the
value of f Q ':
( Page 31, Table 3, Nole) - Substitute the fullowing for the value
of' h':
'he + (H - hel f: ~ ,
( Page 32, Table 4, last Itne ) - Substitute' ho 'foT ' he ' appearing at
two places.
( Page 32, Table 5, col 3 ) - Substitute' W. 'for' kD, "
J
( Page 33, Tnbl« 6, col 3 ) - Substitute the following value of 'Qw'
agamst ' Gravity':
• h[(H-S)' - /']
I. ( R/rw )
[I + (03+ IOrW)
H
. \·8S].
11. H
(Pag. 33, Tabl. 6, col 3 ) - Substitute the following against the
value of' Qwp':
2nkD ( H - hw ) G
'. ( Rlrw )
(Pag. 33, Tabl« 6, NOll) - Substitute the following for the value
off G '0
D
w (I + 7) .Jzw--rw COl 1t
n2
- WID
-
(HOC.3 )
2
Pnnt,ed at Ne_ Indul PrlDtlft' Pr.... K.burJa. Indj.
IS : 9759· 1981
Indian Standard
GUIDELINES FOR
DEWATERING DURING CONSTRUCTION
o. FOR E W 0 R D
0.1 This Indian Standard was adopted by the Indian Standards Institution
on 27 February 1981, after t he draft fina lized by the Foundation Engineering
Sectional Committee had bee n approved hy the CIVU Engineering Division
Council
0.2 The problem ofdewater mg d urmg co nvtructron 1S met wrth in most of the
civil r-ngmr crmg constructions The concerned technical committee has,
rhr-rcfore, felt thdt some guidehnc s for dewarermg at least for the most
common cases could be formulated. An attempt has, therefore, been made
In thi .. standard to givr- some guide line .. for dcwatermg for normal construc-,
tton works other than rrve r valley projects (that is, the earth dams, etc, for
which reference may be made to IS· 5050-1963*). In construction of power-
houses in boulderjgrave l reaches, the dewatering conditions are entirely
different and arc not covered In rhrs standard
0.3 In the Iorrnulanon of this standard, considerable assistance has been
rendered by thr- Central Building Research Institute, Roorkee , which has
furnished the vanous data included in the standard
0.4 For the purpose of deciding whether a particular requirement of this
standard is comphed with, the final value, observed or calculated, expressing
the result of a test or analysts, shall be rounded off In accordance WIth
IS . 2·1960t. The number of significant place' retained III the rounded off
value should be the same as that of the specified value in th ts standar-d.
I. SCOPE
1.1 T'his standard provides J. aiude lme for dc v.. a termg durmg construction
of'foundaoon and excavanon.
2. TERMINOLOGY
2.0 1'01 th, purpo,e of this vrnnd.u d, the followrng defimuons shall apply.
2.1 Anode Povit rvely chat-gr-d electrode.
*Code of practice for design, construe.non and maintenance of relief wells,
[Rules for rounding off nuun ucal values (revmd)
3
IS : 9759. 1981
2.2 Cathode - Ncganvely charged electrode.
2.3 Discharge Line -- Steel, alu miruum or plasuc conduits to conduct
flows from pump.
2.4 Electro-Osmosis -- Electrical drainage method for dewatering
2.5 Equipotential Line - Line in flow regron at a ll point" on wlur-h Llu-
total head IS the same.
2.6 Flow, Artesian -- Flow through a perVIOUS stratum bounded above-
and below by Impervious layers
2.7 now, Gravity - Flow undcr gravity through pervious ,011
2.8 Flow Line -- Path followed by a particle of water through a saturated
soil mass
2.9 now Net -- Graphical representation ofAow through soils comprising
flow lines and equipotential hnes
2.10 now Net, Plan - - Flow net which represents the plan view of the
seepagC' pattern.
2.11 Flow Net, Sectional-- Flow net which represents the sectional view
of the seepage pattern
2.12 Head Discharge - Head at which water is discharged from pump.
2.13 Head, Total DynaJDic - Sum total of operatmg vacuum at the
pump intake, discharge head and discharge fricnon losses
2.14 Head Loss, Entrance - Head loss caused due to entrance of water
through weJJ screen
2.15 Head Loss, Friction - Hvdrauhc head loss m pipe' due to fr-iction.
2'.16 Head Loss, Total Sum total of screen entrance head Ioss, friction
head losses due to flow through well screen and riser pipe and the velocity
head loss.
2.17 Head Loss, Velocity - Equals v2 j2g , where "z 15 the velocuv of flow
through the rrscr pipe, and 'g' is the acceleranon due to gravny.
2.18 Line Source - RIver or stream adjacent to well system
2.19 Operating VacuulD -- Vacuum created at the welipoint pumps
hrmted by the atrnoapher-rc pressure
7.20 Piezometric Level- - Hydraulic head level ccmprrsmg total head
(sum of pressure head, datum head and ve locuy head for flow through soils)
2.21 Pipe. Header - The pipe which collects water from the rrser pipe
and leads on to the pump.
4
IS : 9759 - I!IU
7.22 Pipe, Riser - Small diameter vertical pipes connected to the well-
point.
7.23 Radius of lnfluence - Radrus of the circle beyond which the well
has no significant influence on the original ground water level or piezometric
surface.
7.24 WeD, Fully Penetrating -- Well which penetrates to the full depth
of pervious stratum
7.25 WeD, Partially Penetrating - Wen which does not penetrate to the
full depth of the pervIOus stratum
7.26 Wellpoint - Small well screen made with self-jetting tips.
7.'1:7 Wellpoint SystelD - A system consisting of wellpoints around an
excavation, attached to a common header pipe, and connected to a wellpoint
pump.
3. GENERAL
3.1 Dewatering is the operation of lowering of ground water level. It is
resorted to when excavations are made below natural ground water table,
and is usually a temporary measure. Dewatering is also done to relieve the
bottom of an excavation of artesian pressure.
3.7 A properly designed. installed and operated dewatering system can serve
the following purposes:
6
IS : 9759. 1981
NOTE 2 -In case the 'pumping test' IS not conducted at the site, the fol1owinl applOXi-
mate formuJa for determining the coefticient of permeability for fairly uniform sands
in loose state With uniforrmry coefficient not greater than 2 may be wed.
k = C1 DI10
where
k = coefficient of permeabrliry 10 em/s,
C. = a constant, varying between 100 and 150; and
Dto = effective gram size in em.
4.4 Source or Seepage
404.1 NaJu" of Source - The nature of the source of seepage should be
properly determined. The source of seepage depends to a great extent on
the geological features of the area and adjacent streams Or bodies of water,
If the wells are not close to a river or canal, and the only seepage is from
the formation being dewatered, the source may be assumed circular. Streams
close to the wells may act as line sources of seepage, depending on the
distance of the wells from the effecnve source of seepage (see 4.43).
4.4.2 Radius of InJlueru:e (R)
4.4.2.1 DefinitIOn - The radius of influence, R, is defined as the radius
of the circle beyond which the well has no significant influence on the
original ground water level or piezometric surface.
4.4.2.2 Determination of R byfield test- The radius of influence, R,
should be estimated from field pumping test, by determining the drawdown
curve by means of piezometers.
Non - The radius of influence increases with mcreased drawdown and WIth pumping
time. The magnitude of these effects IS difficult to estimate numencaUy; therefore,
the radius ofmfluence should be estimated conservatively.
4.4.2.3 Approximate formula for R - The following empirical relation-
ship' may be used for estimating R:
R = C' (H-k,,)v'J;
where
R = radius of influence in ill,
C' = a constant=Q·g (for gravity flows),
H = depth of natural water table in metres,
"_ = head at the weIJ in me tres, and
k = coefficient of permeability in 10- 0 cm/s.
4.43 Wells Adjacent to River
4.43.1 Lin« source - If the wells are close to a river, the source 0
seepage may be considered as the river, provided the distance L from the
wells to the river is less than R/2.
f.5 Chemiea1 Properties or Gr01llld Water
405.1 Corrosion and Inaustation - Metallic well screens are susceptible to
.Based on Sichordt's equation.
7
IS I 9759 - 1981
8
IS STANDARD SIEVE IS STANDARD SIEVE NUMBERS HYDROMETER
OPENING,. ~'5<m
'" 0 0 0
OU"lQQOOIl'lOG:)
~t.~ ~ IIID CD ... 1"'11 N .......
ice ~~g~2~5:!
Ill' r I' r 'rlll'~JI'1 'I "IIIII'l'1 f 'I' ':111'111
,,
II II I r\ . . 1\
'0
SUB AQUEOUS \1\\1\) I I \11\1\ 1\\w~,,~"'~'';''~,I,J \\ IUlIIII I I
EXCAVATION rw II II i i 1\
_"I '-UIJ'WJ.:lo nlln, •
.. SO .. , , , , , • , , 1\
:z: GROUT CURTAI N
i ij ?O MAY BE; REQUIREO
'"
~
,'- .. , .... ,,"":_--_
"" ,.... "'.... "_~
... , /
> 60
CD
'.1 II [ I
, \
ffi so 111
z
40 I I I \
~
"'JI"l.u.IN~H"-l J I ~
I..... ...., I
11111l1, _,
'" ...z -_ .._-,-~\
w 30 RANGE ~y BE EXTE"---
u BY USING LARGE SUMr, ......
a:
w
e,
WITH GRAVEL FILTERS 1\
~O
\
""" ' 1\
o L\ I \ \ I \ \, II \ I I \ \, \ \ \ \ I 111111111111111111111'
100 50 10 5 1 0·5 0·1 0·05 0'01 0-005
GRAIN SIZE IN mm EiI
10
IS : 9759 - I'ln
o
o·2 -: v-I
V
0- 4 /
WID
o6 /
I
a8
t- 0
o 0'5 io 1·5 2-0
y
FIG. 2 FACTOR r VERSUS RATIO WJD
1·2 1-5
~ <,
1'0
0-8
(
0·5
~ f..-
2
o 2 4 6 8 10 o a as 0'10 0-15
l/he b/ H
3a Factor k1 3b Factor kl
NOTE ~ 2 I is = distance between slots (I ~ width of slots)
II
IS : 9759. 1981
12
IS : 9759 - 1981
NOTE- The top of the wellpomt screen sf culd l e set sligl tly b!LW (h.-H~) LO
ensure mat the wcllpomr J~ submerged; OWUWISf" excessive arr n ay e nrr r t}-( dewatenng
system and reduce its efficiency.
GROUND WAlER
LOWERING ~O 3m POLES
~ ,~
60
50 o GRAVEL
]Q
2\
, .c \fERY FINE GRAVEL
:l
-
20
,-
15 5 __ a COARSE SAND
J -
- 6- ,l
B -
-"! -- VERY FINE
GR"El •• - ---0 MEDIUM SANO
:t
10 7
5-
•9
10
COARSE MEOIUM ----oFtNE SAND
SAND GAND
15
20
25
FIN[ SAND
I~
IS : 9759. 1981
D.. of filter material
D•• of material to be protected
D 15 of filter material
D 15 ufmaterial to be protected
Nora - Pipmg Pretention - The phenomenon of piping may be prevented at seepage
aiD: in an excavanon by provrdmg artrficral devices such as drams and filters. Most
dramege systems make use of porous filter aggregates to collect the water and conduct
it to outlets, often with the aid of perforated or slotted pIpes Proper filter design is
Important for prevention of prpmg
If a filter layer satisfies the cntena, it is virtually Impossible for pIpmg to occur, even
under extremely large hvdrauhc gradients Adequate specrficauons and careful con-
structions are requrred, If the works, as they are constructed, are to be completely safe
from piping troubles.
60
50 1{__
1
--
,I:) GRAVEL
'0 2
2 2 5 _-<> VERY FINE
30
25 ,
1 j.O_.... GRAVEL
3 - GRAVEL
20 5
,
»>:
1
15 2
__ -o COARSE
__5 10 --- SAND
~
'.::~
... -- ~
--
10 15
5
8 < , ... --- --
... ... 6
VERY FINE
GRAVEL
,
6
5
10
7
8
9
10
'5
--- - - -<) MEDIUM
SAND
10 COARSE
3 '5 SAND
FINE
SAND IS
2
MEDIUM
SAND
14
IS : 9759. 1981
NOTE - Where silty sods ale to be drained, the welJpoJDt should be provided with
a graded medium to coarse sand filter designed In accordance with the filter criteria
set forth in 6.35.
16
IS , 9759 - 1981
installeo u" deeper cxc watton below standing water level is required. There
is no :lmit to the depth of drawdown In this way, but the overall width
of excavation at top level becomes very large.
6.3.12.2 Position ~ header pipes - The lowest header of multistage
system should be located not more than about 45 m above subgrade to
ensure that proper drawdown of the ground water level can be achieved
with the vacuum available in the line.
6.3.123 Observations - Observations should be made immediately
prior to and while pumping the upper stage, for discharge and ground
water lowering. Comparison should then be made with the computed
values to check the adequacy of the lower stage pnor to its installation.
63.13 Deep Bored Welts
63.13.1 General - Large diameter deep wells can be used effectively
where the depth of excavation below the water table is large (more than
about 10 m), or where artesian pressure in a deep aquifer beneath an
excavation must be reduced. Deep wells are suitable where the excavation
penetrates or is underlain by sand or coarser granular SOllS. Where
adequate submergence is available and the required rate of pumping is
large, deep bored wells may be preferable to wellpoints.
6.3.13.2 Design - The procedure for designing a system of deep wells
is similar to that for wellpoints. Clauses 6.3.1 to 6.3.7 can be referred
to ill this regard.
6.3.133 Sizes of welt and welt screens ~ The wells should be large
enough for the pump required and to keep the head losses low. The well
screen should be of sufficient length to admit the flow with small head
loss Deep wells normally have diameters of 15 to 45 em with screens
of 6 to 22·5 m length.
63.13.4 Use of surf",e pumps- Pumping from wells can be under-
taken by surface pumps with their suction pipes installed in bored wells.
However, the depth of drawdown by this method IS not much more than
7 5 m. If eenrrifugal pumps are used in a deep well system, the pumps
can be located on the excavauon slopes and connected to a common header
pipe. The top of the well screen In such cases should be set below the
computed water surface in the well.
63.13.5 Use ~ deep well pumps- For deep excavations, electrically
powered submersible pumps should be installed, w.ith a rising main to the
surface. It should be seen that there is sufficient depth of pervIOus material
below the level to which the water table is to be lowered, for adequate
submergence of well screen and pump. If wells are located at the top
of the excavation, interference WIth the cxcavanon and construction call
be eliminated.
63.13.6 Selection oj deep well pumps- Turbines or submersible pumps
are used to pump large diameter (150 mm and above) wells. Proper
selection of pumps should be made in respect of pump capacity, from the
17
IS : 9759. 1981
variety of deep well pumps that are available. Discharge from the well
may often be limited by the pump, and not necessarily by the available
yield of the pervious stratum. For determining the approximate maximum
capacity of deep well pumps Table 8 may be used.
NOTE - Pumps should be selected to operate at their normal fated speeds. Addi-
tional capacity is available at speeds greater than normal. Thw, some mergtn of safety
alway! exists.
18
IS : 9759· 1981
7.6 Sand Drains
7.6.1 UJe ~ Troubles may arrse in a dewatering scheme in the form
of breaks in the drawdown curves If impervious layers of silt or clay (even
as thm as 3 mm) are met in water bearing sandy soils. These troubles
can be largely overcome by installing sand drains. Holes can be jetted
on the side of wellpomts away from the excavation and be filled with sand.
These sand columns will provide a path down which the water can seep
through the wellpom t5 more readily than towards the sides of the excava..
non. Weeping from the side of the excavation can thus be prevented.
7.6.2 Design tf Sand Drams
7.6.2.1 Hydraulic head tosses - The drain. should be of such size,
permeability and spacing as to conduct the flow to the lower sand stratum
WIth small hydraulic head loss Sand or gravel filled drains are not effective
when installed in highly pervlOus sods, because they do not have enough.
hydraulic carrying capacity to permit flow to the lower stratum without
excessive head loss
NOTE - For design of sand drams standard formulae be used.
7.7 Installing Header Pipes - After selecting the required header pipes,
the header pipehne should be fitted with plug cocks of suitable size at the
required spacmg. laid along the line. The wellpoints can then be con,
nected to the respective plug cocks through flexible connections. The
header pipeline should be connected through valves to pumps of required.
number and capacity which, in turn, should be connected to a common
discharge pipe leading to a basin or a ditch at a considerable distance
away from the SIde.
19
IS , 9759. 1981
7.9.3 Repairing Choked Wellpoints - In spite of using graded filter materials,
a few wellpoints may get choked by finer silty particles These dead
points can be made active by developing the shrouding material with
jetting of water.
7.9.4 Protection of Pump Bast - Care should be taken to see that the pump
bases are not flooded due to the flow of water through the sandy soil. This
may make the pump base quite slushy and cause tilting of the pumps.
In such situations, a few wellpoints and sand drains can be installed on the
basin side of the pumps to intercept this flow.
20
IS : 9759· 1981
9. SUMP PUMPING
9.1 General- The method is essentral where wcllpointing or bored wells
cannot be used because of boulders or other massive obstructions in the
ground, and it 1<; the only pracucal m . . thod for rock excavations. However,
it has the dls3.dvant"1g~ that th- ground water flows towards the excavation
with a high head on steep alop as, and there is a risk of the coHapsc of the
sides. There is also the risk in open or timbered excavation, of instability
of the base due to upward seepage towards the pumping sump. The
cost of installing and maintaining the plant is, however, comparatively
low.
9.2 Essential Features
9.2.1 The sump should be made below thc general level of thc excava-
tion. It can b- placed at one or more corners or sides.
9.2.2 The floor of the excavation should be made clear of standing
water. For this, a small ditch should be dug around the bottom of the
excavation falling towards the sump. It should be sufficiently wide to
keep the velocity low enough to prevent erosion.
Safeguards against erosion can also be taken by placing boards across
the dttch, or by stone or concrete paving, Open jointed pipes can also
be lard, surrounded by graded stone or gravel filter material.
9.2.3 Where the ground water is present in a permeable stratum over-
lying a clay, and the excavation is taken down mto tile latter material,
it is preferable to have the pumping sump at the base of the permeahle
stratum. This procedure reduces the pumping head and avoids softening
of the day at the base of the excavation.
9.2.4 The greatest depth to which the water table may be lowered by
sump method is not much more than 7,5 m below the sump, depending
upon it, type and mechanical efficiency.
9.2.5 For large depth of excavation, the pumps can be installed at a
Iowa level. Use can also be made of sinking pump or submersible deep
well pumps suspended by chains and progressively lowered down a timbered
shaft or perforated steel tube.
9.2.6 For deep excavations, a useful procedure can be to sink the pumping
sump for the full depth of the excavation by m-ans of a umbered shaft
with spaces between the poling boards to allow the water to flow into the
shaft. Gravel filter materials should be pack d behind the timbers if
excessive fine material is washed through 'I'Ius method ensures dry
working condition for the subsequent bulk excavation, and It also provides
an exploratory shaft for obtaining inform.uron on ground conditions to
supplement that found from borings.
9.2.7 Adequate standby pumping plant of a opacity at least 100 percent
of the steady pumping rate should b- provided for use in emergency.
21
IS : 9759· 1981
9.2.8 Type, of pump' suitable for operating for opcn sumps arc given
in Table 9.
23
IS 9759 - 1981
APPENDIX A
(Clause 5.1, and Table I)
METHOD OF ELECTRO-OSMOSIS
A-I. ELECTRO-OSMOSIS
A-I.I Use -- Some slits, clayey silts and fine clayey silrv sands may be
troublesome to dram, br-causc capillary [OTn s acting on the pore water
prevent It<; flowing Ire.ely under gravity to a filter well or sump. In such
cases successful d-amage can be achn vcd by well" or wcllpom t~ in com hi-
nanon WIth flow of ek ctrn iry through the soil to the we lls The clr ctrrcal
drainage mr thod, or clcctro-osmosrs, 1<; a costly method, but under certatn
circumstances, It is the only practical means of soil stabilization. There
IS al~fl no advantage 1Il applying this method fur de watering unle-ss pern1e-
ability of the SOIl to be dr amcd 15 sigmficanrly lower than 0 5 X 10-' cm/sec.
A..l.2 Electrodes - Anodes can consist of any available conductor, such
as steel P'Pv . Tall, etc Cathodes usually consist of small diameter wells
or wcllpomts, but with sufficient diameter to admit a suction pipe (usually
25 mm diameter) from a pump. Anodes and cathodes should extend
in depth at least 15m 0, low the bottom of the slope or excavation.
A-I.3 Spacing of Electrodes -- Cathodes can be installe d in one or
more Imc-sand "paced on 7 5 to 10.5 m ccn tt cs, WIth anodes mstallr d midway
between tilt" cathodes.
NOfE - The proper spacing of electrodes depends mainly on the voltage available
at the site Potennal gradients of more than 0 5 volr per (j~l between electrodes should
not be exceeded for long tum apphcaucr-s, because }ugh(r gradients result In excessrve
energy losses 10 tht fUI III of I t-,Itmg of the ground
A-I.4 Voltage Requirement - Applu d voJtaW" va, y between 30 and
100 v lb. the IOWIT V( 'ltagt -, bcing satisfactory where the ground water
con ram -, a lllgh conccntr auon of rmnvr als
A-1.5 Power Requirem.ent - POWCl Tl qurrcd per well may range from
0,] to 25 kW, for n <pr-ctive gradients of about 1·5 and 4 volts per 30 em
distance between electrodes.
A-l.6 Current Requirement - Current requirements range between
15 A and 30 A The required current can be esumatc d from the following
cxpreSSlOm,. This equation is not applicable to very low clay contents:
It = 41c-25
where
I current, in A, required per gram of water expelled;
t time in sec; and
24
IS : 9759. 1981
c = cia} content of soil, percent (percent by weight of soil
finer th on 0 002 rn m)
A-I.7 Collection of Water - - When a dire-ct e-lr ctric CUITent is passed
between the electrode s, wate-r contained In the sor! will migratr- through
the ;011 from the anode to the cathode Watn collected in the well (cathode)
can then be removed by pumpmg.
NOTE- Smce the rate of discharge at a cathode IS small, mterrnittent pumping may
suffice.
APPENDIX B
(Clause 6.3,4.3, Note 1)
FLOW NET METHOD
8-1. GENERAL
8-1.1 Use -~~ A flow net can be a useful tool whcn designing dewatering
systems, especially when cornphcated boundary conduions are present
A flow net may be constructed either to represent the plan view of the
seepage pattern, or a sectional view, depending OIl the requlfeIneut in
the design.
8-1.2 Flow Line - The path followed by a particle of water flowing
through a saturated soil mass is called a 'flow line',
25
IS : 9759 - 1981
B-1.S Discharge from Flow Net - From the flow net, the discharge
per unit length perpendicular to the direction of flow can be obtained by:
q k (H-h,) : :
,
where
k coefficient of permeability of the sod,
N, number of flow channels, and
N, total number of equipotential drops between the full head
H and the head h, at the point of oxu.
B-1.6 Piau Flow N~t - The plan flow net should be drawn with thc
assumption that the flow hnes are horizontal and as such, the equipotential
lines are vertical. The analysis thus essentially requires the flow to be
two-dimensional. The slot/wells, therefore, need to be fully penetrating.
CorrectIOns to be made for partially penetrating cases are mentioned in
B-1.10.
B-1.7 Discharg~ frOID Plan Flow Net - The total discharge Q is
obtained from plan flow net by multiplying the value of 'q' (given in B-l.S)
by the thickness D of the pervious stratum, as follows:
Q = g.D
B-1.8 Spacing of Wellpoints{Wells frOID Flow - Wclb should be
spaced proportionally to the flow lines
&1.9 Limitations in the UR of Plan Flow Net - As mentioned in
B-l.6 plan tow net analysis is effective for two-dimensional problems.
j
head htIJ at the well taking into consideranon the penetration of the well,
and also the fact that the system consist, of a finite group of wells and not
a continuous slor. are grven below:
Q"N.l a
H -h.. = - (n - 1- - In - - ) : for full) penetrating wells
k» N! '2 21fT"
and
27
r;;
TAlILE I COMPARATIVE STUDIES OF DEWATElUNG SYSTEMS
(Clause 5 1)
Sc ME:.TKOD SoiLS SUITA.8LE USES ADVANTAGE! DISADV ANT AGES ,
No. FOR TREi\TIofE",-r
5 Jet eductoe Sands (with pro- a) Deep excava- a, No hmuauon on a) Imual installation l!'1
system per control can tions (m space account of draw-down fairly costly
also be used in so confined b) Rakmg holes are h) RISk of flooding
Silty sands and that mulu- possible excavauon If high
sandy Silt) stage wellpomt- pressure water main
mg cannot be 15 ruptured
used) c) Optimum operation
b) Usually mere dIfficult to control
appropnate to
low permeability
soils
~
'"
1il
....~
...j
..
fIl
Q tDx (H-h,)
PartlaHy-penetrattn/it slot Artesian
o
'" - L-'+ Ell.
Fo' LfH;;'3
Non: - The maximum residual head, hD downstream from the slot can be computed from the following r-XPII:S310ns'
for L/H;;'3
TABLE 3 FLOW TO A SLOT FROM TWO LINE SOURCES
(Clause 6.2.2)
<.0 GCd.Vlty Q.~ (0 73+027 H-he)~ (H2._h,J e ) W=penetration of the slot uno the
H L pel YIOllS stratum (To be deter-
- nuned from Fig. 2)
Fully penetraung slot The flow IS twrce that computed NOTE - The slot IS nudway between
from Table 2 for the respective the hne sources
cases
NOTE -- At distances J from the slot, III excess of <i.bout 1 3 D the head II increases linearly as y increases, and can be
computed as follows.
D
It -he-HH-ke) y'r-
L+yD
!i:
~•
..
!
IS : 9759 - 1981
FLOW
PENETRATION I-lE.AD REDUCTION AT THE WELLS
CONDmoN
Q. I,,_a_ Q.L
Artesian n-s; -
2.,..kD 21f T II' + kD.
Fully
penetraung
well 2Q.L Q. a
Gravnv H'l.-h 2 w =
""""k(J + --;k In
21TT.
Partially
penetra llOg
Artesian H-h. ~
Q.
kD <+ + 8. )
Gravity The formula for fully pcnctratmg case can be used
provided Q. IS computed from an appropriate
equation.
32
TABLE 6 FLOW TO A SINGLE WELL CfRCULAR SOURCE
(Claus, 62.4)
Fully penetration Artesian 2"kD (H-h.) (1) Q." = flow to the well
well Q. In (Rlr.)
In which wID equals the penetration of the well screen mto the pervious stratum expressed as a decimal. ,
..!~
IS : 9759 - 1981
FLOW
DISCHARC.L FORMULAE. REMARKS
CONDITIO-,
10 115 90
11') IJ 160
I:' 20 450
0"
20 -J 600
25 30 1200
30 35 1 BOO
3j 40 2400
40 4", 3000
34
IS I 9759. 1981
SL TYPE OF OuTPUT
No. PUMP
Handlift From 54·6 math for 3 em suction; SUitable for intermittent pump-
diaphragm up to 655 mlJh for 10 em sue- 109 m small quantities
lion
2 Motor-driven From 983 m'/h for 7 5 em suction Can deal with sand and silt In
diaphragm up to 1 747 mSIh. for 10 em limited quantities
suction
3 Pneumatic sump From 1 310 m3/h against 15 m Useful for intermittent pumping
pumps head to 2 620 IIl'/h agamst S m on sues where compressed air
head. at 7·3 kg/em"' airpressure is available, can deal with
sand and silt in limited
quannues
4 Self-pnmmg From 2 184 m'fh for 5 em suction Sand and sdt in water cause
centrifugal to 19656 mll/h for 20 em suc- excessive wear on impeller for
tion long periods of pumpmg,
therefore. desirable to have
efficient filter around sump
or pump sucnon. Widely
used for steady pumpmg of
fairly clean water. Smallest
Units can be carried by one
man
6 Sinking pumps From 875 m3jh for 5 em suction Can pump against 60 m head.
to 10 920 m 3 /h for ) 5 em Suc- SUitable for working In deep
tion shafts or other confined spaces
where pumps must be pro..
gressrvely lowered with falling
water table. Can be vertical
spmdle centruugal pump or
steam operated pulsometer
type
35
IS I 9759. 1981
(Contin""d from Pdge 2)
Memkrs Represenhng
Dsecr-r DIRECTOR Rg<:EARCH Mmmry of Railways (RDSO)
(SM II)
DEPUTY Dtaecroe STANDARD (CB I) (Alternatel
DIRECTOR High\VaY~
Research Laboratory, Madras
SHRI S, MUKHERJEE Cemmdra Company Limned Bombay
SHRI B K. PANTHAKV Hmdustan Construction Company Lunlted,
&mbay
SURf P G RAMAKRI~HNAN EngmeerIng Coustrucnon Corporation Limited,
Madras
SHR. G. B SINGH (AJlerna!/!)
SHRr S A R~DlJl Gammon India Bombay
SURf G R. HARIDAS (Alternate)
SURI A K. SARKAR Public Work~ Department, Government of West
Bengal, Calcutta.
SIlRI D SHA.RMA Central Burldmg Research Instuute. Roorkee
SIIRI AMAR SINOH (Allernat~)
SIIRIO S SRIVASTAVA Cement Corporauon of India, New Delhi
SHiU S K CHATTERJEE (Alterllate)
36
BUREAU OF INDIAN STANDARDS
Qn FC UE • •:
MMIIc m-. 9 ~ Shah zalar Marg, NEW DELHI 110002
TIleplIOMI. 323 0131. 323 3375. 323 ll402
I'M 91 11 3234082. 91 11 3239399. 91 11 3239382
TeIegr...... Menaksanstha
(Common to all Olftces)
Cellini L• • IIfwy; Telephone
Plot No 2019. SU. IV. S8hIl>ead 1n<lJ.lrlal Area, SAHIBABAD 201010 Son 00 32
R.."".., om-:
central Manak Bhaven. 9 Bahadur Shah la18r Marg. NEW DELHI 110002 323 76 17
'Eaal8rn 1114 CIT SCheme VII M, V I P Road, M81lIklola, CALCUTTA 700054 3378662
N"'!hern sec 335-336. Sector 34-A. CHANDIGARH 160022 603843
Southern C.I T campus. IV Cross Road. CHENNAI 600"3 235 23 15
tw..'...n
Man¥alaya, E9 Behind MarDI Telephone Exchanga. An<t1en (East), 832 92 95'
MUMBAI 400093
SIaM" 0",.,.,
·Pushpak·. Nurmohamad Shaikh Marg. Khanpur, AHMEDABAD 38000' 550 1348
tP8ltlya In<lJstnal Ar"", 1st Stags. BangaIor. - Tt.mkur Road, 839 49 55
BANGALORE 560058
Gangotrl Complex, 5th Floor. Bhadbhada Road, T T ~r, BHOPAL 462003 55 40 21
Plot No 62-63. Untt VI, Ganga Nagar. BHUBANESHWAR 751001 40 36 27
Kal81kattur BUtldongs. 670 Avonashl Road. COIMBATORE 641037 21 01 41
Plot No 43, Sector 16 A, Mathur. Road. FARIDABAD 121001 8-28 88 01
SSVI," COfnP'.X, 116 G T Road. GHAZIABAD 20100' 8-71 19 96
53/5 Ward No 29, R G Barua Road. 5th By-Ian•. GUWAHATI 781003 54 11 37
5-&-58C, L N Gupta Marg, Nampally Station Road, HYDERABAD 500001 20 1083
E-52, ChJ'etBnj8l1 Marg, C-Scheme, JAIPUR 302001 372925
"714\6 l!>, S"VOOstB 11_, Kll.IlPUR 2Il6OOS ';n tll76
Seth Bhawan, 2nd FIOOf. BahJnd Laaia CInema. Naval Klshore Road. 23 89 23
LUCKNOW 226001
PaUopulra In<lJslro8l Esta"'. PATNA 600013 262305
T C No 1411421, UnlV....1ty P 0 PaIayam, 621 17
THIRUVANANTHAPURAM 695034
NIT BUtklng. Socond FIoof. Gokulpal M"""'~ NAGPUR 440010 52 51 71
Institution of EngIn_. ( Incla ) BUtlQng. 1332 Slwajl tlaQIII. PUNE 411005 323635
·5.... Ollle. I. at 5
CALCUTTA 700072
ChOwn"'. Appfoach, P 0 Pnncep Str.,.
27 1085
tSales Offica IS at Novally ChamI>er.. Grant Road. MUMBAI 400007 309 65 28
t5aIesOlfice Is al 'F' Block. UNty Budclng. Natashomar..... Square. 222 39 71
BANGALORE 580002