Integration of Primavera & BIM
Integration of Primavera & BIM
Integration of Primavera & BIM
Project Proposal
by
ABHILASH VIJAYAN
GUIDED BY GUIDED BY
CO-GUIDED
Dr Narasimha D.S, Ms Ranjini Menon
Menon,
Professor, Faculty
Dept of Civil Engineering Dept of Civil Engineering
SOE, CUSAT SOE, CUSAT
MAY 2019
DECLARATION
(Abhilash Vijayan)
i
CERTIFICATE
Staff-in-charge Head
Division of Civil Engineering
ii
Table of Contents
iii
1.0 INTRODUCTION
In India, Construction industry is one of the largest contributors to the economy. Over
the last decade, technology has advanced greatly. Every other day, new software is
execution. The use of various tools like knowledge-based systems, computer graphics,
and a combination of the two are used in the construction industry. Construction
industry makes use of a variety of software for simplifying their work. PRIMAVERA is
one such software which is used for project scheduling, resource allocation & leveling,
monitoring and controlling. Though all the scheduling tasks and reports can be achieved
through this, it does not provide a 2D or 3D aspect of the components that are built or
create a common language between all parties and system divisions in a project and
communication, analyzes the project systems for constructability, estimates the cost
and time of projects at any time using quantity takeoffs, draws a big picture of projects
using visualization and builds collaborative teams. Softwares like Synchro, Visual
Simulation, and Navisworks are used for interlinking of schedules and drawings. This
The linkage between the scheduled activities and respective drawings in BIM helps in
identifying construction sequences and in detecting logical errors in the project. It helps
1
monitoring the progress of a construction project. This project aims to show how this
project.
2.1 PRIMAVERA
For the successful completion of a project, planning and scheduling are two important
and management and resources. Project management software is used as a tool for
managing and organizing work which helps industries to grow in a rapid manner.
Primavera P6 provides project managers a comprehensive tool for one of the most
sophisticated, and multifaceted projects. Primavera can easily compare between the
Benefits:
Planning, scheduling and controlling from the simplest to the most complex
projects
performance.
2
Conducting what-if analysis, and analyzing alternative project plans to increase
Enable collaboration of projects so everyone on the project team has the details
2.2 BIM
architecture, engineering, and construction (AEC) professionals the view and the tools
to plan, design, construct and manage buildings and infrastructure more efficiently.
information. It is a service which forms a reliable basis for decision making during its
users to design a building and structure and its components in 3D, annotate the model
with 2D drafting elements and in accessing building information from the building
model's database. Revit is capable of tools which can plan and track various stages in
the building's lifecycle, from concept to construction and later maintenance and/or
demolition.
3
Autodesk Revit, AutoCAD, and Micro-Station). Navisworks allows users to open 3D
models and to combine them, to navigate around them at that point of time and also
review the model using a set of tools including comments, redlining, viewpoint, and
et al., 2018).
BIM has some specific features that can effectively be used in project management.
Clash Detection
One of the common problems of different disciplines’ plans for a construction project is
the geometrical design inconsistencies. This issue happens when there is an overlap
between the plans of different disciplines. Using BIM, it would be possible to bring the
plans together and detect the clashes. Modifying the aesthetic problems is another
Constructability
Using BIM, it would be possible for teammates in a project to review and handle
constructability issues and (if needed) promote issues into RFIs. In addition, visual
information can be provided from a vantage point to show the problems. This visual
information accompanying markup allows further investigation for finding solutions and,
4
Analysis
Helping the project managers, designers and engineers in doing more analyses and
enabling better decision making is another aspect of BIM. By linking the building
consumption of a construction project and then find better solutions such as changing
materials and orientation, mass and space, etc. Moreover, light, mechanical and
acoustics analyses are also available to be performed by BIM (Saeed et al., 2015).
Time and cost estimation are other features of BIM which enable project managers to
visualize the construction project at any point in time and have a clear understanding of
project phases. Time and cost estimation, which are generally called 4D and 5D, can be
properly utilized in the first stages of a project and facilitate the decision making process
with minimum cost and time needed. Furthermore, BIM has the capability to simulate
the various alternatives for a construction project and hence helps project managers
and executives to reliably predict the consequences of their decisions (Saeed et al.,
2015).
Integration
The project team can deal and interact with a unified model when a composite model is
built from an amalgam of various disciplines’ models. Having this capability, and through
the different phases of a construction project, BIM can coordinate the design, analysis,
5
Quantity Take-off
Quantity takeoffs in a BIM model can be very helpful for the project teams and
managers to analyze their decision and have a clear and reliable insight to various
alternatives in the design phase or even throughout the project lifecycle. Since there is a
possibility of integration between the BIM model and a database containing cost
Since the BIM models generally are composed of objects –and not geometries, such as
line, surface, etc. – the whole model can be divided into a specific number of smaller
objects. This breakdown makes it possible to have a defined and clear scope of
projects. The distinction between the elements will result in a better management
Collaboration and team building is another key factor for BIM success on construction
projects. All efforts made by various specialties on a project are unified and applied to
one model. This results in direct correspondence and team building. All disciplines have
Communication
The nature of a unified model to input, modify and analyze the data in BIM models will
6
These unique building models facilitate the communication throughout the project and
Forensic analysis:
Facilities management:
Facilities management departments can use it for renovations, space planning, and
project and react accordingly – dynamically adjusting to the “situation on the ground”.
4D models include planning data such as the start and end date of a component and
interface for the project team and other stakeholders to easily visualize the assembling
The current day demand of construction industry requires a highly accurate planning,
scheduling and management of the process of the project which can enable the overall
optimization of the cost, time and resources. There is immense pressure on the project
managers to cut short the delivery times and thus the current scheduling and progress
7
Hence the use of software for the purpose of planning, scheduling, monitoring &
To develop the BIM model of the proposed building in REVIT software from the
software.
5.0 Methodology
Methodology adopted:
A Work Breakdown Structure (WBS) is prepared to make project control effective and
manageable.
8
Step 3: Initiating scheduling process
Primavera P6 software will be used as the scheduling tool. The project will be
scheduled based on the activities identified in the WBS described in Step 2. This tool
will be used to schedule the project showing the start and completion dates, locating the
critical path(s), showing the sequence and inter-relationships between the activities.
Innovaya) are used to integrate the REVIT drawings with Primavera project plan. It uses
the Revit application programming interface (API) to export the Revit model to the
Innovaya file format. The model is then imported into Visual Simulation.
The percent complete information on the activities will be entered in the database. This
information will be used to calculate the percent complete for each activity. The percent
complete information will be transferred with the help of custom run time application to
PRIMAVERA P6 every time a progress evaluation is made and the application is run.
schedule will show the progress of all the activities as of the new date of the update
(e.g. at the end of every month or daily updates) and the percent complete information.
As the project moves forward and the more and more data are updated a user can
visually associate model objects and scheduled tasks. For example a user can click on
a building object in the 4D visual environment and see its associated task highlighted in
the Gantt chart or vice versa. The users can also have a visual view of how a project
9
appears during the various stages of work, for example a user can ask Revit to show all
The progress of work will be shown in graphical format and in different colors. The
amount of work done on the various activities will be seen in 3D view. The project will
primavera schedule is sent to Visual Simulation. The updating will be done with the help
10