CEM 515 SPC Quiz Student Name: - Student No
CEM 515 SPC Quiz Student Name: - Student No
CEM 515 SPC Quiz Student Name: - Student No
2. You are plotting a control chart and the last two of three parts are greater than 2 ,
four out of the last five point are beyond readings are beyond 1o and eight
successive points are on one side of the center line ; you should
a. 6R/d2
b. 2xA2R
c. R/d2
d. D4
1
Dr. Abdulaziz A Bubshait, Department of Construction Engineering & Management
7. An X- bar and R chart was prepared for an operation using twenty samples with
five pieces in each sample X-bar was found to be 33.6 and R-bar was 6.20.
During production, a sample of five was taken and the pieces measured 36, 43,
37, 25, and 38. At the time, this sample was taken:
8. Calculate the standard deviation of the population for the following set of five
sample observation:
1.5, 1.2, 1.1, 1.0, 1.6
a. 1.280
b. 0.259
c. 0.231
d. 0.518
9 Variance is:
a. The total variation of all activities of a mold, cavities of a die cast machine
or spindles of an automatic assembly line.
b. The inherent variation of the machine
c. The total variation over a shift.
d. The variation in a short run of consecutively produced parts
2. You are plotting a control chart and the last two of three parts are greater than 2 ,
four out of the last five point are beyond readings are beyond 1o and eight
successive points are on one side of the center line ; you should
a. 6R/d2
b. 2xA2R
c. R/d2
d. D4
3
Dr. Abdulaziz A Bubshait, Department of Construction Engineering & Management
7. An X- bar and R chart was prepared for an operation using twenty samples with
five pieces in each sample X-bar was found to be 33.6 and R-bar was 6.20.
During production, a sample of five was taken and the pieces measured 36, 43,
37, 25, and 38. At the time, this sample was taken:
8. Calculate the standard deviation of the population for the following set of five
sample observation:
1.5, 1.2, 1.1, 1.0, 1.6
e. 1.280
f. 0.259
g. 0.231
h. 0.518
9 Variance is:
e. The total variation of all activities of a mold, cavities of a die cast machine
or spindles of an automatic assembly line.
f. The inherent variation of the machine
g. The total variation over a shift.
d. The variation in a short run of consecutively produced parts
4
Dr. Abdulaziz A Bubshait, Department of Construction Engineering & Management
2. You are plotting a control chart and the last two of three parts are greater than 2 ,
four out of the last five point are beyond readings are beyond 1o and eight
successive points are on one side of the center line ; you should
a. 6R/d2
b. 2xA2R
c. R/d2
d. D4
5
Dr. Abdulaziz A Bubshait, Department of Construction Engineering & Management
7. An X- bar and R chart was prepared for an operation using twenty samples with
five pieces in each sample X-bar was found to be 33.6 and R-bar was 6.20.
During production, a sample of five was taken and the pieces measured 36, 43,
37, 25, and 38. At the time, this sample was taken:
8. Calculate the standard deviation of the population for the following set of five
sample observation:
1.5, 1.2, 1.1, 1.0, 1.6
i. 1.280
j. 0.259
k. 0.231
l. 0.518
9 Variance is:
h.The total variation of all activities of a mold, cavities of a die cast machine
or spindles of an automatic assembly line.
i. The inherent variation of the machine
j. The total variation over a shift.
d. The variation in a short run of consecutively produced parts
CEM 515 SPC quiz Student name:_______________________ Student No_______
2. You are plotting a control chart and the last two of three parts are greater than 2 ,
four out of the last five point are beyond readings are beyond 1o and eight
successive points are on one side of the center line ; you should
a. 6R/d2
b. 2xA2R
c. R/d2
d. D4
7. An X- bar and R chart was prepared for an operation using twenty samples with
five pieces in each sample X-bar was found to be 33.6 and R-bar was 6.20.
During production, a sample of five was taken and the pieces measured 36, 43,
37, 25, and 38. At the time, this sample was taken:
8. Calculate the standard deviation of the population for the following set of five
sample observation:
1.5, 1.2, 1.1, 1.0, 1.6
m. 1.280
n. 0.259
o. 0.231
p. 0.518
9 Variance is:
k.The total variation of all activities of a mold, cavities of a die cast machine
or spindles of an automatic assembly line.
l. The inherent variation of the machine
m. The total variation over a shift.
d. The variation in a short run of consecutively produced parts
CEM 515 SPC quiz Student name:_______________________ Student No_______
2. You are plotting a control chart and the last two of three parts are greater than 2 ,
four out of the last five point are beyond readings are beyond 1o and eight
successive points are on one side of the center line ; you should
a. 6R/d2
b. 2xA2R
c. R/d2
d. D4
7. An X- bar and R chart was prepared for an operation using twenty samples with
five pieces in each sample X-bar was found to be 33.6 and R-bar was 6.20.
During production, a sample of five was taken and the pieces measured 36, 43,
37, 25, and 38. At the time, this sample was taken:
8. Calculate the standard deviation of the population for the following set of five
sample observation:
1.5, 1.2, 1.1, 1.0, 1.6
q. 1.280
r. 0.259
s. 0.231
t. 0.518
9 Variance is:
n. The total variation of all activities of a mold, cavities of a die cast machine
or spindles of an automatic assembly line.
o. The inherent variation of the machine
p. The total variation over a shift.
d. The variation in a short run of consecutively produced parts
10