Earned Value Analysis
Earned Value Analysis
Presented by-
Represents the actual work that has been completed till the
time of measurement.
Time Variance
The time variance is the difference in the time scheduled
for the work that has been performed (ST) and the actual
time used to perform it (AT).
ST - AT = Time Variance
Variance : SV & CV illustration
Earned Value : Cost/ Schedule + or -
Six Possible Arrangements of AC, EV and PV
Let's calculate the Cost Variance (CV) for the ACME Home Building
Project -
Cost
Time
Variances: Cost Variance example
Cost
Time
Variances: Cost Variance example
Variances: Schedule Variance Example
Let's calculate the Schedule Variance (SV) for the ACME Home
Building Project -
Cost
Time
Variances: Schedule Variance Example
Cost
Time
Variances: Schedule Variance Example
Variances: Review
Performance Indices: CPI example
Let's calculate the Cost Performance Index (CPI) for the ACME Home
Building Project -
Cost
Time
Performance Indices: CPI example
Potential Causes of Favorable & Unfavorable Cost Performance
Performance Indices: SPI example
Let's calculate the Cost Performance Index (CPI) for the ACME Home
Building Project -
Cost
Time
Performance Indices: SPI example
Potential Causes of Favorable & Unfavorable Schedule Performance
Review of Variance and Performance Indices
Estimate at Completion (EAC) & Budget at Completion (BAC)
The Project BAC must always equal the Project Total PV. If
they are not equal, your earned value calculations and analysis
will be inaccurate.
Estimate at Completion
Calculating Estimate at Completion