0% found this document useful (0 votes)
146 views2 pages

Rate Analysis For Reinforced Cement Concrete

This document provides a rate analysis for reinforced cement concrete. It lists the materials, quantities, and costs for 1 cubic meter of wet concrete containing a 1:1.5:3 ratio of cement, sand, and aggregate. The materials include 8.07 cement bags, 0.42 cubic meters of sand, and 0.84 cubic meters of aggregate. It also lists the labor costs for masonry, laborers, water carriers, bar benders, and mixer operators. It then calculates the prime cost, adds charges for water and sundries, applies the contractor's profit rate of 14%, and calculates the total cost per cubic meter of RCC as well as the cost for the given project data.

Uploaded by

Mahtab Hossain
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
146 views2 pages

Rate Analysis For Reinforced Cement Concrete

This document provides a rate analysis for reinforced cement concrete. It lists the materials, quantities, and costs for 1 cubic meter of wet concrete containing a 1:1.5:3 ratio of cement, sand, and aggregate. The materials include 8.07 cement bags, 0.42 cubic meters of sand, and 0.84 cubic meters of aggregate. It also lists the labor costs for masonry, laborers, water carriers, bar benders, and mixer operators. It then calculates the prime cost, adds charges for water and sundries, applies the contractor's profit rate of 14%, and calculates the total cost per cubic meter of RCC as well as the cost for the given project data.

Uploaded by

Mahtab Hossain
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 2

3

RATE ANALYSIS FOR REINFORCED CEMENT CONCRETE


DOWNLOADED FROM THECONSTRUCTOR.ORG

RCC 1 :1.5 :3 Analysis for 1


Wet Volume 1.00 m 3

Dry Volume 1.54

MATERIAL Qty. Units Rs. / Unit


CEMENT BAGS 8.07 bags 300
SAND 0.42 m3 900
Aggregate 0.84 m3
700
Reinforcement 78.50 Kg 60

LABOUR With
Mechanical Mixer & Vibrartor Days
MASON 0.37 300
LABOUR 3.50 200
WATER CARRIER 1.39 200
BAR BENDER 0.79 200
MIXER OPERTOR 0.071 200
MIXER VIBRATOR 0.071 200
0.00
PRIME COST (Rs.):

Water Charges 1.5%


Sundries (including mixer machine, transportation etc) 7.5 %
Contractor's Profit 14 %

Total Cost per m3 of RCC =

Cost of RCC for Given Data = Rs.


CONCRETE
Steel % by volume
of Concrete
SLAB 1.00%
BEAM 2.00%
COULMN 2.50%
Road 0.60%
AMOUN SUBTOT
T (Rs.) AL (Rs.)
2421
378
588
4710
8096.75

111.00
700.00
278.00
157.00
14.28
14.28 1274.56

9371

141
703
1312

11527

11527