RCC Material Calculator

This document provides calculations for estimating materials needed for cement, sand, aggregate mixtures; brickwork; and plastering work. It outlines ratios and volumes needed for 1 cubic meter of cement/sand/aggregate mixture, brickwork estimating 500 bricks at 10mm thickness, and plastering a 1 square meter area at 25mm thickness. Cost estimates are provided based on material rates.

Uploaded by

Rucheeta Sahaa
Copyright
© © All Rights Reserved
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
210 views

RCC Material Calculator

This document provides calculations for estimating materials needed for cement, sand, aggregate mixtures; brickwork; and plastering work. It outlines ratios and volumes needed for 1 cubic meter of cement/sand/aggregate mixture, brickwork estimating 500 bricks at 10mm thickness, and plastering a 1 square meter area at 25mm thickness. Cost estimates are provided based on material rates.

Uploaded by

Rucheeta Sahaa
Copyright
© © All Rights Reserved
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 3

RCC RATIO FOR CEMENT SAND AGGREGATE BRICK WORK ESTIMATION

CALCULATION WILL BE FOR 1 m3 CALCULATION WILL BE FOR 1 m

cement RATIO 1 I/P AMOUNT OF BRICKS REQUIRED


sand RATIO 0.75 I/P ASSUMING 10 mm THICK MOR
aggregate RATIO 1.5 I/P
VOLUME OF BRICK WITHOUT M
dry volume 1.57 m3
WET VOLUME OF MORTAR FOR
AMOUNT OF MATERIAL REQUIRED IN m3 DRY VOLUME OF MO

cement 0.483077 m3
sand 0.362308 m3 CEMENT RATIO
aggregate 0.724615 m3 SAND RATIO

CEMENT REQUIRED
RATE ANALYSIS SAND REQUIRED

cement 390 per bag I/P RATE ANALYSIS


sand 55 per cf I/P
aggregate 36 per cf I/P cement
sand
BRICKS
cement 5429.395 RS
sand 703.8189 RS cement
aggregate 921.363 RS sand
bricks
total material cost 7055
total material cost

PLASTERING WORKS

AREA 1 m2
cement ratio 1 I/P
sand ratio 3 I/P
thickness 25 mm I/P

VOLUME OF PLASTER 0.025 m3


asummed percentage bulking 54
volume of dry plaster 0.0385

cement required 0.009625


sand required 0.028875

RATE ANALYSIS

CEMENT 390 PER BAG


SAND 55 PER CFT

CEMENT 108.1772
SAND 56.09258

TOTAL 165
BRICK WORK ESTIMATION

CALCULATION WILL BE FOR 1 m3

AMOUNT OF BRICKS REQUIRED 500


ASSUMING 10 mm THICK MORTAR

VOLUME OF BRICK WITHOUT MORTAR 0.001539 m3

WET VOLUME OF MORTAR FOR 1 m3 0.2305 m3


DRY VOLUME OF MORTAR (33 PER) 0.306565 m3

CEMENT RATIO 1 I/P


SAND RATIO 6 I/P

CEMENT REQUIRED 0.043795 m3


SAND REQUIRED 0.26277 m3

RATE ANALYSIS

390 per bag I/P


55 per cf I/P
8 per piece I/P

492.2205 RS
510.457 RS
4000 RS

total material cost 5003