Preparatory Survey For Metro Manila Interchange Construction Project (Vi) in The Republic of The Philippines
Preparatory Survey For Metro Manila Interchange Construction Project (Vi) in The Republic of The Philippines
Preparatory Survey For Metro Manila Interchange Construction Project (Vi) in The Republic of The Philippines
FINAL REPORT
SUMMARY
NOVEMBER 2012
TABLE OF CONTENTS
LOCATION MAP
TABLE OF CONTENTS
LIST OF TABLES AND FIGURES
LIST OF ABBREVIATIONS
EXECUTIVE SUMMARY
1. INTRODUCTION .................................................................................................................... i
2. CONFIRMATION OF VALIDITY ....................................................................................... ii
3. TRAFFIC FLOW ANALYSIS AND DEMAND FORECAST .............................................. iii
4. STUDY OF INTERCHANGE ................................................................................................. v
5. IMPLEMENTATION SCHEDULE ....................................................................................... xi
6. EVALUATION OF PROJECT FECTIVENESS ........................................................... xv
7. STUDY OF ENVIRONMENTAL AND SOCIAL CONSIDERATIONS ........................... xvi
8. C-3 MISSING LINK ........................................................................................................... xviii
9. THE CONCEPTUAL STUDY FOR THE TRAFFIC
CAPACITY EXPANSION ALONG EDSA ........................................................................ xxii
10. SEMINAR ON LATEST JAPANESE ROAD AND BRIDGE CONSTRUCTION
TECHNOLOGY .................................................................................................................. xxv
SUMMARY
CHAPTER 1
INTRODUCTION ................................................................................................................................... 1
CHAPTER 2
CONFIRMATION OF VALIDITY AND NECESSITY OF THE PROJECT........................................ 4
Table of Contents 1
Preparatory Survey for Metro Manila Interchange Construction Project (VI)
PROJECT ................................................................................................................................. 5
CHAPTER 3
TRAFFIC FLOW ANALYSIS AND DEMAND FORECAST .............................................................. 8
CHAPTER 4
STUDY OF EACH INTERCHANGE .................................................................................................. 20
Table of Contents 2
Preparatory Survey for Metro Manila Interchange Construction Project (VI)
CHAPTER 5
PREPARATION OF IMPLEMENTATION SCHEDULE ................................................................... 40
CHAPTER 6
EVALUATION OF PROJECT EFFECTIVENESS ............................................................................. 68
Table of Contents 3
Preparatory Survey for Metro Manila Interchange Construction Project (VI)
CHAPTER 7
STUDY OF ENVIRONMENTAL AND SOCIAL CONSIDERATIONS ........................................... 98
7.2 LAND ACQUISITION AND RESETTLEMENT ACTION PLAN (RAP) ........................ 100
CHAPTER 8
C-3 MISSING LINK ........................................................................................................................... 101
8.1 BACKGROUND TO THE STUDY ON THE C-3 MISSING LINK .................................. 101
Table of Contents 4
Preparatory Survey for Metro Manila Interchange Construction Project (VI)
CHAPTER 9
THE CONCEPTUAL STUDY FOR THE TRAFFIC CAPACITY EXPANSION ALONG EDSA .. 114
9.4 CONFIRMATION OF OPEN SPACES FOR TUNNEL PLAN AND VIADUCT PLAN . 114
CHAPTER 10
SEMINAR ON LATEST JAPANESE ROAD AND BRIDGE CONSTRUCTION TECHNOLOGY ....
.................................................................................................................................. 127
Table of Contents 5
Preparatory Survey for Metro Manila Interchange Construction Project (VI)
LIST OF TABLES
Table of Contents 6
Preparatory Survey for Metro Manila Interchange Construction Project (VI)
Table 5.5-8 Proposed Implementation Plan (STEP Scheme & General Loan Scheme) ......... 62
Table 5.5-9 Proposed Implementation Schedule for EDSA/Roosevelt/Congressional ........... 63
Table 5.5-10 Proposed Implementation Schedule for EDSA/North/West ................................ 64
Table 5.5-11 Proposed Implementation Schedule for West/Mindanao ..................................... 66
Table 5.5-12 Proposed Implementation Schedule for C5-Green Meadows/Acropolis/
Calle Industria ...................................................................................................... 67
Table 6.1-1 Model Configuration ............................................................................................ 69
Table 6.1-2 Economic Benefit - DPWH BVOC Table (PhP) ................................................. 69
Table 6.1-3 Annual Investment Schedule (%)......................................................................... 69
Table 6.1-4 Financial and Economic Costs of C-3/E. Rodriguez (PhP million) ..................... 70
Table 6.1-5 Economic Benefit - VOC Saved of C-3/ E. Rodriguez (PhP million, 2018-37) .. 70
Table 6.1-6 Financial and Economic Costs of EDSA/Roosevelt/Congressional
(PhP million) ........................................................................................................ 71
Table 6.1-7 Economic Benefit - VOC Saved of EDSA/Roosevelt/Congressional
(PhP million, 2018-37) ......................................................................................... 71
Table 6.1-8 Financial and Economic Costs of EDSA/North/West (PhP million) ................... 72
Table 6.1-9 Economic Benefit - VOC Saved of EDSA/North/West (PhP million, 2018-37) . 72
Table 6.1-10 Financial and Economic Costs of North/Mindanao (PhP million)....................... 73
Table 6.1-11 Economic Benefit - VOC Saved of North/Mindanao (PhP million, 2018-37) .... 73
Table 6.1-12 Financial and Economic Costs of C-5/Green Meadows (PhP million) ................ 74
Table 6.1-13 Economic Benefit - VOC Saved of C-5/Green Meadows
(PhP million, 2018-37) ......................................................................................... 74
Table 6.1-14 Financial and Economic Costs: Aggregate (PhP million) .................................... 75
Table 6.1-15 Economic Benefit - VOC Saved (PhP million, 2018-37) .................................... 75
Table 6.1-16 EIRR and ENPV by Intersection.......................................................................... 76
Table 6.1-17 Sensitivity Analysis.............................................................................................. 79
Table 6.1-18 EIRR and Attributes of Scarce Resource (2018-37) ............................................ 80
Table 6.2-1 Model Configuration (STEP Loan) ...................................................................... 81
Table 6.2-2 Annual Investment Schedule (%)......................................................................... 81
Table 6.2-3 Financial and Economic Costs of EDSA/Roosevelt/Congressional
(STEP Loan, PhP million) ................................................................................... 82
Table 6.2-4 Economic Benefit - VOC Saved of EDSA/Roosevelt/Congressional
(STEP Loan, PhP million, 2018-37) .................................................................... 82
Table 6.2-5 Financial and Economic Costs of EDSA/North/West (PhP million) ................... 83
Table 6.2-6 Economic Benefit - VOC Saved of EDSA/North/West
(STEP Loan, PhP million, 2018-37) .................................................................... 83
Table 6.2-7 Financial and Economic Costs of North/Mindanao (PhP million)....................... 84
Table of Contents 7
Preparatory Survey for Metro Manila Interchange Construction Project (VI)
Table of Contents 8
Preparatory Survey for Metro Manila Interchange Construction Project (VI)
LIST OF FIGURES
Table of Contents 9
Preparatory Survey for Metro Manila Interchange Construction Project (VI)
Figure 6.2-8 Economic Cost and Export Parity Benefit, and EIRR
(North/ Mindanao, STEP Loan) ........................................................................... 88
Figure 6.2-9 Economic Cost and Benefit Streams, and EIRR
(C-5/Green Meadows, STEP Loan) ..................................................................... 89
Figure 6.2-10 Cost and Benefit Streams, and EIRR (STEP Loan) ............................................. 90
Figure 6.4-1 Monitoring Location for Traffic Volume Count and Travel Speed (EDSA/
Roosevelt/Congressional Ave. Intersection: Along EDSA – Cubao Side) ............... 93
Figure 6.4-2 Monitoring Location for Traffic Volume Count and Travel Speed
(EDSA/North Ave./West Ave. Intersection: Along EDSA – Cubao Side) .......... 93
Figure 6.4-3 Monitoring Location for Traffic Volume Count and Travel Speed
(North Ave. /Mindanao Ave. Intersection: Along North Avenue – EDSA/SM Side) ..
...................................................................................................................................... 94
Figure 6.4-4 Monitoring Location for Traffic Volume Count and Travel Speed
(C-5/Greean Meadows/Acropolis/Galle Industria – Pasig City Side).................. 94
Figure 8.3-1 Alternative Alignments – DPWH Study ............................................................ 103
Figure 8.4-1 Effect on Traffic Volume for the Project Interchanges due to Construction
of the C-3 Missing Link ..................................................................................... 110
Figure 8.4-2 Related Projects in Metro Manila ...................................................................... 113
Figure 9.5-1 Locations of Flyover/Underpass and MRT/LRT STATIONS ........................... 115
Figure 9.7-1 Steel Viaduct Piers ............................................................................................. 117
Figure 9.7-2 Location of the Five Most Difficult Construction Site ...................................... 118
Figure 9.8-1 Typical Tunnel Section of 3-Types Tunnel ....................................................... 120
Figure 9.8-2 Tunnel Layout (Plan and Profile) ....................................................................... 121
Figure 9.8-3 General Concept of Ventilation System ............................................................. 122
Figure 9.8-4 General Concept of Vertical Shaft ..................................................................... 123
Table of Contents 10
Preparatory Survey for Metro Manila Interchange Construction Project (VI)
LIST OF ABBREVIATIONS
Table of Contents 11
Preparatory Survey for Metro Manila Interchange Construction Project (VI)
Table of Contents 12
Preparatory Survey for Metro Manila Interchange Construction Project (VI)
Table of Contents 13
Preparatory Survey for Metro Manila Interchange Construction Project (VI)
Table of Contents 14
Preparatory Survey for Metro Manila Interchange Construction Project (VI)
EXECUTIVE SUMMARY
i Executive Summary
Preparatory Survey for Metro Manila Interchange Construction Project (VI)
This Project is consistent with the traffic plans The ex-post evaluation study for Metro Manila
of other agencies such as MMDA and DOTC. Interchange Construction Project (IV) dated
There is no conflict with the traffic plans of June 2008 was undertaken jointly by JBIC
other agencies; it is supportive of the traffic Consultants and the National Economic and
plans of the LGUs and other agencies. However, Development Authority (NEDA). The Report
the following issues need to be noted: identified the following three lessons and the
MRT Line 7 Construction recommended actions that need to be taken into
The proposed intersection scheme for account in future project implementation:
EDSA/West/North/Mindanao Avenues has Lesson-1: Lack of in-depth investigation
during detailed design
been confirmed and approved by the project Lesson-2: Delay in land acquisition and
proponent of MRT 7 and DOTC. However, a resettlement
reconfirmation has to be made during the Lesson-3: Absence of pragmatic project
scheduling
Detailed Design Stage to ensure that there has
Recommendation: Sufficient maintenance
been no change in the scheme that has been funds should be secured
originally approved. The Consolidated Report in January 2011 for
Skyway Stage 3 the Metro Manila Urban Transport Integration
The project is a 14.5km six-lane elevated Project (MMURTRIP) financed by World Bank
viaduct that will connect the north and south identified that bureaucratic processes, changes
expressways via C-3, and has been approved as in administration, and ensuing changes in
a priority project by the government last development policies are the main causes of
August 2012. Correspondingly, implementation delay in project implementation.
of the C-3/E. Rodriguez Interchange has been 2.4 Technical Level for Construction and
deferred by DPWH due to a conflict of its Maintenance of Flyover of the DPWH
alignment with that of the project.
The PMO-URPO is in charge of flyover
2.2 Confirmation of Necessity and Priority construction and its maintenance is undertaken
of the Proposed Flyover Project by NCR Regional Office. Technical level of
The five interchange under this proposal are both agencies is fairly high and capable enough
included in the list of priority projects for NCR to construct and maintain flyovers, but there is
under DPWH’s Public Investment Plan some room for improvement in the following
2011-2016. Proposed budget for the Metro processes:
Manila Interchange Construction Project is 1. Bureaucratic procurement process
about P7.36 Billion. The construction of five 2. Prolonged relocation process
3. Casual maintenance approach rather
interchanges has a total allocation of P5.17 than preventive
ii Executive Summary
Preparatory Survey for Metro Manila Interchange Construction Project (VI)
Daily vehicle-km, daily-vehicle hour and average travel speed of each interchange are shown in Tables
3-2 to 3-5.
Table 3-2 Daily Vehicle-Km, Vehicle-Hour and Average Travel Speed
(C-3/E. Rodriguez Intersection)
2018 (Daily) 2028 (Daily)
Vehicle 2011
Indicator 2018 2018 With - 2028 2028 With -
Category (Daily)
(With) (Without) Without (With) (Without) Without
Car 90,049 174,597 175,989 -1,392 111,650 112,375 -724
Jeepney 9,346 18,453 18,432 20 30,503 30,529 -26
UtilityVehicle 9,618 18,353 18,574 -222 11,950 12,071 -121
Vehicle Km Bus 449 836 805 32 559 536 23
Truck 2,881 5,531 5,624 -93 3,517 3,541 -23
Motorcycle 41,595 86,428 81,010 5,418 139,866 130,296 9,570
Total 153,938 304,197 300,433 3,764 298,046 289,347 8,699
Car 3,293 5,842 7,326 -1,483 3,627 4,603 -977
Jeepney 340 610 767 -158 985 1,190 -205
UtilityVehicle 356 605 778 -173 382 511 -129
Vehicle Hour Bus 16 27 34 -6 18 21 -3
Truck 106 164 230 -67 101 143 -42
Motorcycle 1,518 2,541 3,270 -730 4,050 5,900 -1,850
Total 5,629 9,788 12,405 -2,617 9,162 12,369 -3,206
Car 67,712 132,486 132,376 111 84,621 84,692 -71
Jeepney 7,379 14,518 14,529 -11 23,964 24,062 -98
UtilityVehicle 6,917 13,393 13,417 -24 8,687 8,717 -30
Traffic Volume Bus 352 632 628 4 421 421 0
Truck 2,001 3,890 3,903 -14 2,460 2,443 16
Motorcycle 28,668 55,779 55,808 -28 90,305 89,762 542
Total 113,029 220,698 220,660 38 210,458 210,098 360
Car 27.3 29.9 24.0 5.9 30.8 24.4 6.4
Jeepney 27.5 30.3 24.0 6.2 31.0 25.6 5.3
UtilityVehicle 27.0 30.4 23.9 6.5 31.3 23.6 7.7
Average Travel Speed
Bus 27.5 30.8 24.0 6.9 31.9 25.7 6.2
(Km/Hour)
Truck 27.2 33.8 24.4 9.4 34.8 24.7 10.1
Motorcycle 27.4 34.0 24.8 9.2 34.5 22.1 12.4
Average 27.3 31.1 24.2 6.9 32.5 23.4 9.1
iv Executive Summary
Preparatory Survey for Metro Manila Interchange Construction Project (VI)
4. STUDY OF EACH INTERCHANGE The road has 827m long and four lanes with a
total width of 20.0m and highest embankment
4.1 Design Standard for Highway and
height of 1.55m.
Flyover
Identified Problems
Design standards for Highway and Flyovers
There has been no study yet of the possible
adopt DPWH design standards except for
impacts of flooding on the people living within
seismic acceleration coefficient which was
the vicinity of the project area and also no
increased from 0.4g to 0.5g due to scheduled
documents showing public acceptance on the
change in the ASEP design code.
proposed raising of the current road elevation.
4.2 C-3/E. Rodriguez Avenue Recommendations
4.2.1 Review of Previous Detailed Design The most appropriate countermeasure(s)
against flood, i.e. in case to raise present road
Along C-3
elevations further, etc. should be thoroughly
The total length of the project section along this
studied.
road segment is 2,105m, consisting of 275m of
4-lanes flyover, 205m of approach roads and 4.2.2 Preliminary Design of Interchange
1,625m of embankment roads. The highest (1) Study and Countermeasure against
embankment height is 2.50m. Flood
Along E. Rodriguez Avenue The construction of an elevated highway should
v Executive Summary
Preparatory Survey for Metro Manila Interchange Construction Project (VI)
be provided proper counter measure to the flyover are 729m and 502m, respectively.
fundamental problem of floods and should be Southbound
properly addressed by a flood control Total length of the project section and flyover
management project. are 729m and 500m, respectively.
(2) Comparative Study Identified Problems
The following three (3) alternatives are Total re-planning and redesign will be required
proposed as the most suitable schemes for due to the constructed MRT-3 and Muñoz
comparison: Station and the Pedestrian Bridges at the
Scheme-1 : 275.0m long flyover and 630m intersection.
long 6 lanes additional approach road Recommendations
(Original Design). A careful study of the vertical and horizontal
Scheme-2 : 280.0m long flyover clearances against the constructed Muñoz
Scheme-3 : 280.0m long flyover and 598m Station and MRT-3 viaduct structures should be
long 4 lanes additional approach with undertaken.
RCBC.
4.3.2 Preliminary Design of Interchange
Among the three (3) schemes, scheme-3 was
(1) Comparative Study
selected though it was more expensive than
The following three (3) alternatives are
scheme-2 by approximately 22%. This is due to
proposed as the most suitable schemes for
the 598m extent of elevated road to alleviate
comparison.
effects of flood and provide 2-lanes per
Scheme-1 : Flyover with 422m long and 3
direction of service roads at the at-grade section
lanes per direction. (Maintain of all
which will be deemed sufficient to support the
pedestrian bridges )
activities of people along this road section.
Scheme-2 : Flyover with 366m long and 3
Implementation of the C-3/E. Rodriguez
lanes per direction. (No pedestrian bridges
Interchange was cancelled by the DPWH to
near Muñoz Station)
give priority to the construction of Skyway
Scheme-3 : Flyover with 719m (NB) and
Stage 3, second level, along C-3 under BOT
880m (SB) long. (Maintaining all pedestrian
scheme.
bridges and improving at grade intersection)
(3) Cost Estimate and Construction
Among the three (3) alternatives, scheme-2 was
Duration
selected having the cheapest construction cost,
Estimated cost and construction duration are
shorter construction duration and superior
PhP 492M and 17 months, respectively.
vertical grade against the other schemes.
4.3 EDSA–Roosevelt Ave. / Congressional
(2) Cost Estimate and Construction
Avenue
Duration
4.3.1 Review of Previous Detailed Design Estimated cost and construction duration is PhP
Northbound 630M and 22 months, respectively.
The total length of the project section and the
vi Executive Summary
Preparatory Survey for Metro Manila Interchange Construction Project (VI)
4.4 EDSA/ North Avenue/ West Avenue/ The necessary data and information on the
Mindanao Avenue MRT-3 and LRT Line-1 extension and detailed
design of the Common Station and MRT 7
4.4.1 Review of Previous Detailed Design
should be obtained for Preliminary Design.
EDSA Southbound
4.4.2 Preliminary Design (EDSA/North/
The total length of the project section and the
flyover are 854m and 361m, respectively. The West Interchange)
length of the left turn flyover (EDSA–North (1) Comparative study
Avenue) which is located above the EDSA The following two (2) alternatives are
northbound flyover is 286m. proposed as the most suitable for
EDSA Northbound comparison:
The total length of the project section and the Scheme-1 : Flyover with 342m long
flyover are 569m and 343m, respectively. north bound and 319m long south
EDSA–North Avenue Left Turn Flyover bound.
North Avenue Straight Scheme-2 : Cut and cover tunnel with
Total length of project section = 1,228m; 231m long north bound and 131m long
Length of flyover = 1,011m south bound.
North Avenue–Mindanao Avenue Between the two (2) schemes, the flyover
Total length of project section = 306m; scheme was selected due to cheaper
Length of flyover = 180m construction cost, no ROW acquisition,
West Avenue–North Avenue Flyover shorter construction duration and no
The flyover has two lanes and horizontal specific O & M.
alignment of 80m radius right curve at the
4.4.3 Preliminary Design (North/Mindanao
intersection which merges with EDSA–North
Interchange)
Avenue Left Turn Flyover after the curve. The
(1) Comparative study
lengths of the project section and flyover are
The following two (2) alternatives are
483m and 392m, respectively.
proposed as the most suitable for
Identified Problems
comparison:
(a) Requires total re-planning and redesign
Scheme-1 : Left turn flyover from North
due to the planned construction of the
Ave to Mindanao Ave (3rd level) and left
Common Station along LRT-1 in front of
turn flyover from Mindanao Ave to
SM North, and MRT-7 which will pass
North Ave (2nd level)
along North Avenue.
Scheme-2 : Left turn cut and cover
(b) The construction of a Left Turn Flyover
tunnel from North Ave to Mindanao Ave
from EDSA to North Avenue will not be
(under pass) and left turn flyover from
possible with the planned construction of
Mindanao Ave to North Ave (2nd level).
the Common Station.
Between two (2) schemes, scheme-2 was
Recommendations
selected due to cheaper construction cost b) Subtle curve alignments along C5 for
and better environmental and traffic thru traffic in both directions were
conditions. observed around the U-turn flyover.
(2) Cost Estimate and Construction c) Traffic survey data shows that passing
Duration vehicles along U-turn flyover at south
Estimated cost and construction duration side and north side are 25,132
for the above two interchanges are P1,166 vehiclesper day and 18,600 vehicles per
M and 24 months, respectively. day, respectively. Summarized actual
4.5 C-5/Kalayaan Avenue traffic intersection flow graphic are
shown as follows:
4.5.1 Review of Previous Detailed Design
Identified Problems
The U-Turn Flyovers constructed at both sides
of the intersection along C-5 are considered to
be substandard structures under the design code.
Recommendations
A more comprehensive study of actual traffic
flow and volume at the intersection needs to be
undertaken to identify the cause of traffic jam
and to study proper counter measures. Source: JICA Study Team
4.5.2 Advice for Technical Issue and Design (2) Technical study maintaining existing
Option U-turn flyover
(1) Site Condition and Traffic survey Maintaining existing U-turn flyover and
Three (3) issues were identified: from above traffic data, the following five
a) Carriageway width of C5 thru traffic is (5) schemes were studied:
substandard.
Among the above five (5) schemes, the most New intersection plans provide for three (3)
effective option is to construct left turn flyover lanes in each direction with underpass
from Kalayaan Ave. to C5 north direction but it scheme along C5 for thru traffic. Based on
should be noted that the Tibagan elementary the traffic volume and traffic flow at the
school is located just beside of road along C5 intersection, four (4) schemes as new
north direction. intersection plans can be considered as
(3) Technical study with demolition of shown in the comparison table hereunder.
existing U-turn flyover
ix Executive Summary
Preparatory Survey for Metro Manila Interchange Construction Project (VI)
x Executive Summary
Preparatory Survey for Metro Manila Interchange Construction Project (VI)
xi Executive Summary
Preparatory Survey for Metro Manila Interchange Construction Project (VI)
2 months
2. Review and Evaluation of EIA/RAP in DENR EMB
6 months
4. Processing in NEDA for Approval
5 months
5. Loan Negotiation
6. Loan Agreement
12 months
7. Selection of Consultant (D/D)
12 months
8. Detailed Design
12 months
9. Selection of Consultant (C/S)
10. 1st Contract Package
(EDSA/WEST/NORTH/MINDANAO)
12 months
- Bidding
3 months
- Preparation and Approval of Contract Documents
24 months
- Implementation
12 months
- Bidding
3 months
- Preparation and Approval of Contract Documents
24 months
- Implementation
3 months
- Preparation and Approval of Contract Documents
22 months
- Implementation
15 months
13. R.O.W. Acquisition
5.5 IDEA AND BASIC CONCEPT FOR Procurement Amount from Japan for the
STEP SCHEME Project
(Unit: Pesos)
Proposed use of steel bridge, with steel box No. Description Amount %
girder, steel slab deck and steel piers utilizing 1. Cement (Material Only) 82,631,608 2.61
Reinforcing Steel Bar
Japanese technology, as shown in Figure, will 2.
(Material Only)
414,488,550 13.08
5.6 Summary of Comparison between STEP Loan and Regular Yen Loan
The characteristics and advantages of both types of loans are shown in the table below.
(c) PHP 92 M estimated cost of detailed design will be undertaken under JICA Grant;
(d) Very low and fixed interest rate (0.2%) and long-term repayment period.
xv Executive Summary
Preparatory Survey for Metro Manila Interchange Construction Project (VI)
order to apply the Environmental Compliance residential zones. Trees should be planted in
Certificate (ECC). central reserves and sidewalks to improve the
Noise, air pollutants and CO2 emissions local aesthetic views and mitigate the noise
emitted from vehicles are predicted based on and air pollutants emitted from vehicles.
the projected traffic in 2018. The results of In order to ensure the effectiveness of
prediction show that the noise levels may mitigation measures and monitor the
exceed the Philippine maximum permissible unexpected impacts, the Environmental
levels due to the increase of traffic volume. Management Plans for the construction and
Because of the increase of average travel operation phases should be drawn up. After
speeds and the decrease of vehicle hours, the opening of the interchanges, replanted
emissions of air pollutants and CO2 will be trees, ambient air quality, and noise and
reduced by approximately 10 - 20% vibration should be regularly monitored.
compared with the zero option case. Air Land Acquisition and Resettlement Action Plan
pollutant concentrations might not exceed the (RAP)
maximum permissible levels of the Philippine The results of the census survey and inventory
Clean Air Act of 1999. (assets and land) survey are shown in Table
Technically feasible mitigation measures 7.1. No involuntary resettlement is anticipated.
during the construction and operation phases The JICA Study Team supported the DPWH
are drawn up and proposed for the four in preparing the Abbreviated Resettlement
interchange projects. After opening, the Action Plan in line with DPWH’s Land
interchange, noise levels should be regularly Acquisition, Resettlement, Rehabilitation and
monitored. Installation of noise barriers shall Indigenous Peoples’ Policy and JICA
be considered where the noise levels Guidelines/World Bank Operational Policies.
significantly exceed the permissible levels in
Interchange Land Acquisition Resettlement Affected Structure
C-3/E. Rodriguez None None None
EDSA/Roosevelt/Congressional None None 5 stalls (marginal*1)
Additional ROW for
EDSA/North/West/Mindanao None 25 stalls (marginal*1)
sump pit (100 sq.m)
C-5/Green Meadows/Acropolis/
None None None
Calle Industria
Table 7-1 Land Acquisition, Involuntary Resettlement and Affected Structure for MMICP
Source: JICA Study Team
Note : the impact is only partial and the remaining portion of the property or asset is still viable for continued use.
Support DPWH to hold Public Consultation comments on the implementation of the
Meetings Traffic Management Plan during
DPWH assisted the JICA Study Team with construction, noise mitigation measures and
the Public Consultation Meetings at four restoration of cut trees. DPWH will draw up
interchange project sites. The stakeholders the proper countermeasures in the planning
favored the interchange projects to ease the stage of the interchange projects against
present traffic congestion. There were the these issues raised by stakeholders.
The conducted environmental study for all 8.4.6 Rough Cost Estimate
proposed alignments considered road side air
The estimate of construction cost and cost of
pollution and noise impact, sun light easement
R.R.O.W. acquisition were calculated based on
and water quality deterioration.
similar completed and on-going projects data.
All of these items are conditions judged having
Estimated cost is as follows:
The comparative study of the six alignments for the C-3 Missing Link is presented as follows:
Construction Environmental Impact Project
ROW Acquisition
Ref Description Aspects &Pasig River Affected Comment
(excluding ramps)
and Cost Navigation People
Adequate traffic Since the route is Very substantial ROW Maximu Large area of ROW
1 Original management established in the acquisition (102,000 sqm). m acquisition and
during populated residential Requires wholescale estimated largest number of
Alignment construction will area, the impacts of demolition at: Olympia Ville, number of PAPs makes this one
be crucial. emission gases, noise Mandaluyong Cemetery, Core PAPs at of the least favored
(6 Lane, 5.8 km.) and sunlight shading Oil Gas Station, Barangay Hall 4,430. routes.
COST: 17,600MP will be the most Bagong Silang, and residential
significant among the blocks from Valenzuela to N.
alternatives and must be Domingo.
mitigated. Encroachment into Manila
Number of impacts: 8 South Cemetery is avoided
with double deck viaduct along
South Ave.
Adequate traffic Since the route is Greatest ROW acquisition Second Largest area of
2 1STRevised management established in the (105,000 sqm). Requires largest ROW acquisition
during populated residential wholescale demolition at: estimated and very large
Alignment construction will area, the impacts of Olympia Ville, residential number of number of PAPs
be crucial. emission gases, noise blocks at corner of PAPs at makes this one of
(6 Lane, 7.3 km.) and sunlight shading Coronado-San Francisco, along 3,925. the least favored
COST: 20,400MP will be the most Maytunas Creek (partial), and routes.
significant among the residential blocks from
alternatives and must be Valenzuela to N. Domingo.
abated. Encroaching into Manila South
Number of impacts: 8 Cemetery is avoided with
double deck viaduct along
South Ave.
Access along both Piers will be Least ROW acquisition (35,000 Smallest Most favored in
3 2ND Revised waterways will be constructed on the sqm) given that most of estimated terms of limiting
required for riverbeds in Pasig River alignment is in Pasig and San number of area of ROW
Alignment a1 construction. and San Juan River. Juan River. PAPs at acquisition and
Barges could be Installation of piers and There is a requirement to 550. number of PAPs.
(6 Lane, 6.3 km.) used both to untreated storm runoff partially demolish Olympia However
deliver materials may deteriorate river Ville, between Kalayaan construction along
and as a platform water quality. Avenue and J.P. Rizal. sections of Pasig
for construction Ease of navigation Encroachment into Manila River may not be
equipment along along Pasig River will South Cemetery is avoided possible given the
Pasig River. be severely impacted with double deck viaduct along existing critical
Craneways may be especially where the South Ave. navigation problems.
necessary along river narrows and at the
San Juan River point where the rivers
given that the river bends 90 degrees on the
is not navigable. approach to Lambingan.
Number of impacts: 3
COST: 18,500MP
xx Executive Summary
Preparatory Survey for Metro Manila Interchange Construction Project (VI)
Construction Since the route is Still substantial ROW Second Reasonably favored
4 2ND Revised access along the established in the acquisition (92,000 sqm) given smallest in terms of limiting
river banks can be populated residential the need to acquire ROW along estimated number of PAPs.
Alignment a2 made after the area, noise abatement the river banks of Pasig and number of No adverse impacts
easement has been measures will be San Juan River. Substantial PAPs at on river waterway or
(6 Lane, 6.3 km.) cleared. needed. demolition of industrial and 950. navigation.
No construction Number of impacts: 4 residential properties. However
activities are There is a requirement to construction along
required in the partially demolish Olympia the banks will still
river waterways. Ville, between Kalayaan require substantial
Avenue and J.P. Rizal. ROW acquisition.
COST: 19,300MP Encroachment into Manila
South Cemetery is avoided
with double deck viaduct along
South Ave.
Adequate traffic Since the route is Double deck configuration Estimated Route not favored
5 PIDC-TPLEX management established in the limits ROW acquisition number of since it does not
during commercial and (74,000 sqm). PAPs still extend to Gil Puyat.
Alignment b1 construction will residential area, the However many properties substantia
be crucial. impacts of emission affected including commercial l at 1,765.
(6 Lane, 5.1 km.) gases, noise and buildings especially along New
COST: 13,700MP sunlight shading should Panaderos and F. Bulmentritt.
be mitigated. Curved alignment cuts the
Number of impacts: 6 corner at F. Blumentritt
requiring wholescale
demolition in one section.
Adequate traffic Since the route is Double deck configuration Estimated Route not favored
6 PIDC-TPLEX management established in the limits ROW acquisition number of given the need for
during commercial and (77,000 sqm). PAPs still ROW acquisition
Alignment b2 construction will residential area, the Affected properties same as substantia along commercial
be crucial. impacts of emission above. l at 2,085. strips, despite double
(6 Lane, 6.4 km.) gases, noise and In addition ROW acquisition deck construction,
COST: 18,300MP sunlight shading should along Kalayaan Avenue will be and wholescale
be mitigated. required.Encroachment into demolition in
Number of impacts: 6 Manila South Cemetery is Blumentritt to
avoided with double deck accommodate the
viaduct along South Ave. curved alignment.
Source: JICA Study Team
9.1 Background of the Project The study will confirm in outline the availability
The 24 km length of EDSA is the main of open space to accommodate the support
circumferential road of Metro Manila and has structures of high level viaduct solutions and
average traffic of more than 200,000 vehicles tunnel solutions at critical locations along
per section every day. Notwithstanding the EDSA. The basic concept in assessing available
improvements to EDSA brought by the space is to develop outline solutions that will
construction of several interchanges, in addition minimize occupation of width along EDSA and
to the MRT-3 and LRT-1 North Extension, the also minimize ROW acquisition where and if
Source: JICA Study Team For site conditions requiring long spans and
Location Map of MRT-3, LRT-1 Stations, high piers, steel box girders supported by
Flyover and Underpass rectangular steel columns are recommended.
9.8.1 Proposed Plan and Typical Cross Source: JICA Study Team
The beginning and endpoint of the tunnel are 9.8.4 Ventilation System
located Roxas Boulevard, and Monumento
The main function of the tunnel ventilation
Circle and Balintawak, respectively. The main
system is to discharge the vehicle exhausted
tunnel consists of 2-lane tunnels at both sides of
fumes and smoke from fire. Airflow shall be
the entrance and exit while 3-lane tunnels shall
diverted into two (2) sections underneath the
be used for the entire middle section. 1-lane
deck slab of carriageway: one to discharge
ramps shall be provided at four (4) locations.
smoke and the other to take in fresh air which
9.8.2 Standard Earth Covering of Tunnel will also be utilized for people access to
Computation of earth covering underground and evacuation. General concepts of this system
CHAPTER 1
INTRODUCTION
Metro Manila has a strategic foothold for the economic activities of the Philippines that attracts
13% of the population and generates 37% of the total GDP of the country. 1 Metro Manila has
been developing its transport sector infrastructure and pursuing traffic network improvements
such as construction of circumferential roads, expressways and LRT etc., but still is faced with
the problems of heavy traffic congestion and increased travel times until now. Such a situation
creates a bottleneck in the distribution of goods and hampers the movement of people, resulting in
huge economic losses, and is one of the reasons frequently cited for the deterioration of the
economic competiveness of the country. At the same time, chronic traffic congestion causes in an
increase in air pollution and noise.
The Department of Public Works and Highways (DPWH) has put a high priority in the
construction of grade separated interchanges along with major interchanges intended to solve
such negative issues which are identified as priority concerns in the Public Investment program
(2011~2016) of DPWH. The construction of Circumferential Road 3 (C-3) missing link between
N. Domingo Ave. in San Juan City and S. G. Puyat Ave. in Makati City over 6 km is expected not
only to improve mobility of the residents along the road but also greatly relieve traffic congestion
of EDSA and the metropolis. Furthermore, traffic capacity expansion of C-4 (EDSA), by
construction of either elevated viaduct or underground tunnel, in addition to grade separation of
major intersections and construction of C-3 missing link, is expected to provide fundamental
solution to the chronic traffic congestion of EDSA.
In view of the above, the DPWH has requested the Japan International Cooperation Agency
(JICA) to evaluate the possibility to finance the said high priority grade separated interchange
construction projects in Metro Manila. The JICA has responded favorably to this DPWH request
and has mobilized consultants to undertake Preparatory Survey for Metro Manila Interchange
Construction Project (VI).
1. The objective of the Study is to conduct screening of the proposed improvement as Japanese
ODA Loan Project focusing on the items such as the purpose of the project, scope of works,
project cost, project implementation organization, operation and maintenance organization
1
National Census in 2007 by National Statistics Office of the Philippines
and social and environmental aspects based on previous detailed design and other related
studies.
2. Conduct review and study for the preliminary engineering study on construction of
Circumferential Road-3 (C-3) missing link includes of impact to the proposed flyover.
In order to achieve the above objectives, the Study covered the following:
(2) Study of the C-3 missing link includes of impact to the proposed flyover.
(3) Study on C-4 traffic capacity expansion includes of find space for proposed viaduct
structures.
Study on traffic capacity expansion for the construction of viaduct and tunnel schemes.
The study commenced in November 2011 and with be completed by end of November 2012 as
shown in Table 1.5-1
Table 1.5-1 Study Schedule
Year/Month 2011 2012
Work Item 11 12 1 2 3 4 5 6 7 8 9 10 11
CHAPTER 2
This Project is consistent with the traffic plans of other agencies such as MMDA and DOTC. There
is no conflict with traffic plan of other agencies; it is supportive of the traffic plans of the LGUs and
other agencies. However, the following issues are to be noted:
The five interchange locations are included in the list of priority projects for NCR under DPWH’s
Public Investment Program 2011-2016. Proposed budget for the Metro Manila Interchange
Construction Project is about P7.36 Billion. The construction of five interchanges has a total
allocation of P5.17 Billion excluding consultancy services.
The ex-post evaluation study for Metro Manila Interchange Construction Project (IV) dated June
2008 was undertaken jointly by JBIC Consultants and the National Economic and Development
Authority (NEDA). The Report identified following three lessons and recommended the action to
be taken into account in future project implementation:
Consolidated Report in January 2011 for Metro Manila Urban Transport Integration Project
(MMURTRIP) financed by the World Bank identified that bureaucratic processes, changes in
administration, and ensuing changes in development policy are main causes of delay in project
implementation.
The DPWH Public Investment Plan (2011-2016) allocated 84% of the total investment program for
highway sector and gets the biggest share. Of the P 698 Billion total investment requirement, P 586
Billion is earmarked for the highways sector.
Mandate
The DPWH is one of the three government agencies tasked to develop social infrastructures and
specifically mandated to undertake planning, design, construction and maintenance of national
roads and bridges, flood control, water resources projects and other public works,
Functions
As the engineering and construction arm of the Government, the DPWH is tasked to continuously
develop its technology for the purpose of ensuring the safety of all infrastructure facilities and
securing for all public works and highways with the highest efficiency and quality in construction.
Vision
By 2030, DPWH is an effective and efficient government agency, improving the life of every
Filipino through quality infrastructure.
Mission
To provide and manage quality infrastructure facilities and services responsive to the needs of the
Filipino people in the pursuit of national development objectives.
2.6.2 Annual Budget
DPWH budget for Fiscal Year (FY) 2012 is P 99.5 Billion where P 78.1 Billion is allocated (79%)
for highway sector, and P 10.8 Billion (11%) for flood control, respectively.
2.6.3 Technical Level for Construction and Maintenance of Flyover of the DPWH
Flyover construction is undertaken by the PMO-URPO and maintenance is by Regional Office of
NCR. The technical level of both agencies is fairly high and capable of constructing and
maintaining flyovers, but these is room for improvement in the following process.
Among the funding institutions, JICA has the biggest share of financing at 12.44% followed by
France at 2.97%, World Bank at 2.20%, ADB at 1.95% , UK at 1.75%, Saudi Arabia at 0.39%,
KEDCF at 0.76%, MCC at 0.12%, PROC at 0.17%, Kuwait at 0.49%, Spain at 0.49% and Australia
at 0.10%.
CHAPTER 3
The traffic surveys shown in Table 3.1-1 were conducted to grasp the present traffic flow
characteristics of the project sites.
To Sta. Mesa
Seminary Road
L-2
L-4
L-3
L-1
Eastwood
Green Meadows
ITC-ER1 2 Sta. Mesa Sgt. Rivera 22,340 1,092 1,620 10 52 853 492 361 4,881 572 32,272
Sub-total 27,353 1,115 1,901 13 60 951 502 403 5,839 635 38,773
ITC-ER1 5 Quzon Ave. Sta. Mesa 12,239 1,105 2,310 2 15 966 253 166 6,991 780 24,826
Sub-total 14,529 1,165 2,541 2 19 1,013 261 169 7,538 820 28,059
ITC-ER1 11 Cubao Welcome 17,598 2,760 1,445 0 117 347 14 6 3,306 74 25,667
UTC-ER1 1 C-3 Sta. Mesa U-Turn 2,483 66 414 3 8 134 23 6 633 157 3,926
UTC-ER1 2 C-3 Sgt. Rivera U-Turn 4,712 91 750 1 7 166 38 11 551 79 6,405
ITC-ERC1 3 Quezon Ave. Cubao 5,278 2,068 1,062 0 4 340 54 0 2,771 18 11,597
ITC-ERC1 6 Mindanao Ave. Balintawak 14,280 2,360 1,376 1 842 984 313 74 3,753 7 23,990
ITC-ERC1 8 Balintawak Cubao 33,768 2,495 5,026 1 5,086 2,694 1,235 780 5,456 7 56,550
ITC-ERC1 9 Balintawak Quezon Ave. 4,045 2,136 799 1 3 198 32 27 2,462 0 9,702
Sub-total 37,813 4,631 5,825 2 5,089 2,892 1,267 808 7,919 7 66,252
ITC-ERC1 11 Cubao Balintawak 33,340 2,930 3,891 22 4,310 2,352 527 179 4,600 0 52,149
ITC-ERC1 12 Cubao Mindanao Ave. 12,325 2,228 1,692 0 750 601 88 13 3,152 8 20,858
Sub-total 45,665 5,158 5,582 22 5,060 2,953 615 192 7,752 8 73,007
ITC-ERC2 2 Seminary Road EDSA 2,218 188 385 0 11 163 10 4 685 2 3,665
UTC-ERC1 3 EDSA Balintawak U-Turn 7,042 2,591 730 0 955 353 26 0 2,727 0 14,424
In fromt of Inc
UTC-ERC1 4 EDSA 9,802 3,709 1,803 5 15 838 64 12 4,421 0 20,670
U-Turn
ITC-SM1 2 Cubao Balintawak 100,058 1,070 2,618 0 6,864 2,993 278 60 4,629 0 118,571
ITC-SM1 3 Cubao Quezon Circle 23,994 3,443 1,897 3 8 615 92 6 3,669 0 33,727
ITC-SM1 5 Balintawak Cubao 47,524 2,270 5,091 16 5,026 3,360 1,524 1,159 8,637 0 74,607
ITC-SM1 6 Balintawak Quezon Ave. 10,368 2,174 744 11 9 186 12 0 1,360 2 14,864
Sub-total 57,892 4,443 5,835 28 5,035 3,545 1,536 1,159 9,997 2 89,471
ITC-SM1 12 Quezon Circle Balintawak 16,164 2,808 987 0 4 467 174 72 2,639 1 23,316
UTC-SM1 1 EDSA Trinoma U-Turn 16,512 3,210 2,216 1 12 308 85 24 2,822 0 25,190
UTC-SM1 2 EDSA SM Annex U-Turn 16,382 2,100 894 2 14 367 34 5 2,158 2 21,957
ITC-M1 4 Pagaasa Quezon Circle 8,229 40 1,373 1 24 1,050 1,548 375 4,480 226 17,344
ITC-M1 8 EDSA Quezon Circle 8,601 1,914 1,218 3 13 646 134 28 1,596 0 14,153
ITC-M1 11 Quezon Circle EDSA 8,286 2,312 530 1 20 360 171 67 2,153 0 13,901
ITC-M1 12 Quezon Circle Pagasa 6,685 94 799 16 7 995 1,097 627 3,256 266 13,843
Sub-total 14,971 2,405 1,330 17 28 1,355 1,268 694 5,410 266 27,744
ITC-K 2 EDSA Elevated U-Turn 11,507 870 1,042 1 8 707 384 82 3,744 0 18,344
ITC-K 3 Global/SLEX Pasig/Quezon City 35,418 2,813 4,800 15 117 3,096 2,450 902 12,762 0 62,372
Sub-total 44,512 3,879 5,549 17 140 3,402 3,048 964 15,164 0 76,674
ITC-K 11 Pateros Pasig/Quezon City 4,232 0 259 1 0 216 237 92 2,016 0 7,054
ITC-K 12 Pateros Elevated U-Turn 4,282 820 623 2 10 338 310 166 2,424 0 8,973
ITC-K 13 Pasig/Quezon City EDSA 10,171 0 833 3 21 338 223 3 5,013 0 16,604
ITC-K 16 Pasig/Quezon City Global/SLEX 39,255 0 4,268 19 62 3,164 2,257 851 10,382 0 60,257
ITC-K 9 Elevated U-Turn Pateros 6,765 628 761 0 0 333 391 84 2,225 0 11,187
ITC-K 10 Elevated U-Turn Pasig/Quezon City 7,905 0 1,090 0 6 677 221 431 2,526 0 12,856
ITC-K 18 Elevated U-Turn Global/SLEX 4,582 93 306 1 9 301 240 92 2,087 0 7,713
ITC-K 19 Elevated U-Turn EDSA 5,552 3,230 363 5 1 216 158 8 1,758 0 11,291
ITC-K 6 Global/SLEX Pateros 3,479 823 447 1 23 302 569 60 1,245 0 6,949
ITC-K 4 Global/SLEX Elevated U-Turn 5,893 2,053 112 0 1 197 44 1 1,327 0 9,627
ITC-K 17 Pasig/Quezon City Elevated U-Turn 3,678 0 812 0 1 311 318 81 1,587 0 6,789
ITC-G1 2 Pasig Eastwood 36,880 2,075 9,118 19 72 4,005 1,927 884 13,298 0 68,279
ITC-G1 3 Calle Industrial Pasig 47,509 2,216 6,020 11 114 3,122 1,750 597 12,696 0 74,035
Sub-total 54,411 2,216 6,570 11 115 3,128 1,761 598 14,015 0 82,826
ITC-G2 7 C5 Calle Industrial 7,830 308 1,072 5 14 486 168 85 2,929 2 12,900
ITC-G2 8 Calle Industrial C5 6,136 325 1,346 0 11 585 406 179 2,637 2 11,627
Three U-Turn slots are installed at the intersection; two slots along C-3 and one slot along E. Rodriguez
in front of Quezon Institute.
1.2 Traffic Volume
Major traffic movements are:;
OD (B⇔D) Cubao ⇔ Welcome with 8,340/6,234 vehicles/6 hours along E. Rodriguez.
OD (F⇔C) Sta. Mesa ⇔ Quezon Avenue with 6,978/6,930 vehicles/6 hours along C-3.
1.3 Traffic Congestion
Queue length along E. Rodriguez is longer than C-3
Average travel speed along C-3 and E. Rodriguez that pass through the intersection is approximately
15km/hour during morning, noon time and afternoon peak hours.
2. EDSA/Roosevelt/Congressional Intersection
2.1 Traffic Control
There is no traffic signal control at the intersection. Straight and left turn movements along Roosevelt
and Congressional Avenue are prohibited. Left turn movement along EDSA is also prohibited.
Straight and left turn movements at the intersection will be hampered by pier of LRT viaduct that was
constructed at center of the intersection
2.2 Traffic Volume
Major traffic movements are;
Construction of simple flyover along EDSA may be the most suitable flyover Scheme for the
intersection.
4. C-5/Kalayaan Intersection
4.1 Traffic Control
There is no traffic signal control at the intersection. Straight and left turn movements along Kalayaan
Avenue are prohibited. Left turn movement from C-5 is also prohibited.
The substantial number of traffic may be eliminated from at-grade intersection if through traffic flyover
will be constructed.
The traffic demand forecast for four intersections, namely C-3/E. Rodriguez, EDSA/ Roosevelt/
Congressional Ave., EDSA/North/West/Mindanao and C-5/Green Meadows/Acropolis/Calle
Industria have been carried out till 2018, the expected opening year of the interchanges, and till
2028, 10 years after opening the interchanges.
The traffic demand forecast was undertaken by the following two steps:
Step 1: Estimation of traffic volume growth rate considering future road network in Metro
Manila
Traffic growth rate at each intersection was estimated through analysis on overall traffic flow in
Metro Manila considering the future road network development plan proposed by MMUTIS. The
result of the analysis was used to forecast future traffic volume at each intersection.
Micro-simulation at each intersection was carried out using present traffic count data and the
growth rates derived in the Step 1.
The estimated traffic growth rate used in traffic analysis is shown in Table 3.3-1.
2011 Road Network: The 1996 MMUTIS road network was used for analysis of 2011 traffic
since no major changes of the network was reported.
2018 Road Network: The “C-3 Missing Link” is to be added to the 2011 road network for the
2018 road network.
2028 Road Network: The MMUTIS master plan road network is used as the 2028 road
network.
2028/2018 0.64 0.93 0.93 1.48 Car, Utility Vehicle, Bus, Truck
Daily vehicle-km, daily-vehicle hour and average travel speed of each interchange are shown in
Tables 3.3-3 to 3.3-6.
CHAPTER 4
Design standards for Highway and Flyover adapted prevailing DPWH design standards, except for
seismic acceleration coefficient which was increased from 0.4g to 0.5g due to scheduled change in
the ASEP design code.
The detailed design of the interchange was prepared by Nippon Engineering Consultant Co., Ltd.
in association with DCCD Engineering Corporation and Pertconsult International in February
2005 (original contract) and July 2006 (Supplemental Contract).
There were no significant changes noted in the topographic conditions of the area between the
time of the detailed design to the present.
The bearing stratum in the proposed area is tuffaceous rock sequence that underlie, deeper than
2–7m from ground surface.
Based on interviews with local residents, the flooding area for the 2 years return period is
generally consistent with the flooding area.
Along C-3
The total length of the project section along this road segment is 2,105m, consisting of 275m of
4-lanes flyover, 205m of approach roads and 1,625m of embankment roads. The highest
embankment height to Quezon City direction is 2.50m and 1.85m height to Sta. Mesa direction.
Type of Flyover is RC voided slab and PC box girder.
The road is 827m long and four lanes with a total width of 20.0m and highest embankment
The Environmental Compliance Certificate (ECC) had been issued by the DENR-EMB in
January 2005. It stated that 94 informal settlers in 2 Barangays will be affected.
Identified Problems
There has been no study yet on the possible impacts of flooding to the people living within the
vicinity of the project area and also no documents showing public acceptance on the proposed
raising of the current road elevation.
Recommendations
(b) The most appropriate countermeasure(s) against flood, like raising the present road
elevation, should be thoroughly studied.
The following two studies took into consideration river channel improvement:
When the road surface elevations are raised, the following issues will become a major concern:
The access of the public/residents to the road from the roadside land will be difficult.
The inundation inside a levee will be increased at the upstream side of the road because
the elevated roads obstruct the surface flow as sort of a dam.
In conclusion, the elevated highway should be provided proper counter measure for the problem
of flooding and the fundamental problem of flood should be properly addressed by a flood
control management project.
The following three (3) alternatives are proposed as the most suitable schemes for comparison
based on the site and traffic conditions:
Scheme-1 : 275.0m long flyover with 2 lanes per direction (PC Box and PC Voided
Slab Bridge) and 630m long 6 lanes additional approach road (Original
Design).
Scheme-2 : 280.0m long (PC Box and RC Voided Slab Bridge) with 2 lanes per
direction.
Scheme-3 : 280.0m long (PC Box and RC Voided Slab Bridge) with 2 lanes per
direction and 690m long 4 lanes additional approach with RCBC
Among three (3) schemes, scheme-3 was selected though it was more expensive than scheme-2
by approximately 22% due specifically to the 690m extent of elevated road that will prevent
flooding during heavy rains and typhoon and this scheme can provide 2-lanes per direction of
service road at-grade section which will be deemed sufficient for any activity of the people along
the road section.
LEGEND : c advantage
disadvantage
Preliminary design was conducted based on the conditions previously discussed in the
comparative study.
Construction plan, PERT/CPM and traffic management has been studied. PERT/CPM shows that
construction duration of this flyover is 17 months.
The Civil Works cost was estimated based on the following and other factors:
- Unit price of similar GOP and BOT projects implemented or tendered from 2010-2011
was used and but unit price of major item was estimated based on 2011 price.
- Procedures and composition for the derivation of base construction cost referred to and
based on similar projects.
Estimated cost of this flyover is as follows:
Civil work cost PhP 468,206,728
Foreign currency PhP 167,216,689
Local currency PhP 250,825,033
Tax PhP 50,165,006
Implementation of the C-3/E. Rodriguez Interchange was cancelled by the DPWH to give
priority to the construction of Skyway Stage 3, second level, along C-3 under BOT scheme.
The detailed design of the project was done by Katahira & Engineers International in association
with Proconsult, Inc. and United Technologies, Inc. in February 2001.
There are no significant changes in the topographic conditions of the area from the time of the
detailed design to the present, except for the construction of MRT-3, Muñoz Station, the bus stop
lanes on both directions and pedestrian bridges at the intersection.
The bearing stratum in the proposed area is tuffaceous rock sequence that underlies 16m deeper
than ground surface.
The San Francisco River crosses the EDSA at 50m Balintawak side from the proposed
intersection. There are no specific issues on the hydrological conditions in the proposed area
since there is no record of flooding.
Northbound
(a) Horizontal alignment is passing through the right side of MRT-3 with 1,075m radius
curve. Vertical grade at each side of the approach sections is 5.0%.
(b) Total length of the project section is 729m and total length of flyover is 502m with RC
and PC voided slab for superstructures.
Southbound
(a) Horizontal alignment is passing thru the left side of MRT-3 with 1,055m radius curve.
Vertical grade of each side of the approach sections is 5.0%.
(b) Total length of the project section is 729m; total length of flyover is 500m with RC and
PC voided slab for superstructures.
The ECC for EDSA/North Avenue-West Avenue and EDSA/Roosevelt Interchanges Project had
been issued by DENR-EMB in January 2002. Approximately, the total area that will be affected
is around 1,769 sq. m.
Identified Problems
No problems were identified in the completed plans and detailed design of this interchange, but
total re-planning and redesign will be required due to the constructed MRT-3 and Muñoz Station
and the Pedestrian Bridges at the intersection.
Recommendations
A careful study of the vertical and horizontal clearances against the constructed Muñoz Station
and MRT-3 viaduct structures should be undertaken.
The following three (3) alternatives are proposed as the most suitable schemes for comparison
based on the site traffic conditions.
Scheme-1 : Flyover with 422m long and 3 lanes per direction while maintaining all
pedestrian bridges. Superstructure is PC voided slab
Scheme-2 : Flyover with 366m long and 3 lanes per direction without pedestrian bridges
near Muñoz Station. Superstructure is PC voided slab
Scheme-3 : Flyover with 719m(NB) and 880m(SB) long and 3 lanes per direction while
maintaining all pedestrian bridges and improving at grade intersection.
Superstructure is steel box girder and PC voided slab
Among the three (3) alternatives, scheme-2 was selected due to cheapest construction cost,
shorter construction duration and superior vertical grade against the other schemes.
Flyover MP 633.6 (P1,500,000/ m /6 Lane) Flyover MP 549.0 (P1,500,000/ m/6 Lane) Flyover MP 1.439.6 (P900,000/ m/3 Lane)
Approach MP 53.7 (P240,000/ m /6 Lane) Approach MP 49.8 (P240,000/ m/6 Lane) Approach MP 66.3 (P120,000/ m/3 Lane)
Construction
Cost
Pedestrian Bridge MP 15.0 (P100,000/ m ) Pedestrian Bridge MP 9.5 (P100,000/ m ) Pedestrian Bridge MP 15.0 (P100,000/ m )
Others MP 25.0 Others MP 21.7 Others MP 54.0
Total MP 727.3 (115.4%) Total MP 630.0 (100.0%) Total MP 1,574.9 (250.0%)
23 Months 22 Months 30 Months
Construction Construction method and procedure is standard Construction method and procedure is standard Construction method and procedure is standard
Performance and Requires demolition and reconstruction of 4 existing Requires demolition of 4 existing pedestrian bridges but Requires demolition and reconstruction of 4 existing
Duration pedestrian bridges reconstructionis only 3 Pedestrian Bridges. pedestrian bridges
(Can't construct one bridge at near side of Muñoz Station, Too closer construction activities to existing
due to lower vertical grade) Muñoz Station
No additional R.O.W No additional R.O.W No additional R.O.W
Environmental
Lower volume of exhaust fumes than Scheme-3 Low volume of exhaust fumes and noise due to lowest Very high volume of exhaust fumes and noise due
and Social
Condition vertical grade to longer vertical grade
No regular traffic flow alignment at the at-grade I/C No regular traffic flow alignment at the at-grade I/C due to Better traffic flow alignment at grade movement
due to pier of Line 1 was located within I/C but still pier of Line 1 was located within I/C but still manageable compare to other 2 schemes
Traffic Condition manageable by 4 phase-signalization by 4 phase- signalization
at Grade I/C Long route for pedestrian over EDSA given us no
construction of pedestrianbridge at near side of Muñoz
Station but pedestrian can utilize Muñoz Station
Expensive than Scheme -2 Cheapest among the schemes Most expensive among the schemes
Reconstruction of 4 Pedestrian Bridges Shorter construction duration Reconstruct of 4 pedestrian bridges
Over all Higher volume of exhaust fumes and noisier than Reconstruct 3-pedestrian bridges but no construction of Heavily affects traffic during construction of high
Evaluation Scheme - 2 due to higher vertical grade pedestrian bridge at near side of Muñoz Station pier and construction activities are too closer to
Lower vertical grade among the schemes existing Muñoz Sta.
Longer Construction duration
LEGEND : c advantage
disadvantage
Preliminary design was conducted based on the conditions which were previously discussed in
the comparative study.
Construction plan, PERT/CPM and traffic management have been studied. PERT/CPM shows
that construction duration of this flyover is 22 months.
Civil Works Cost for EDSA/Roosevelt/Congressional IC has been estimated based on similar
conditions of C-3/E. Rodriguez IC.
The detailed design of this proposed interchange was prepared by Katahira & Engineers
International in association with Proconsult, Inc. and United Technologies, Inc. in February 2001.
There are no significant changes in topographic conditions from the time of the detailed design to
present, except for the construction of pedestrian bridges and bus stop lanes at the intersection.
The bearing stratum is tuffaceous rock sequence that underlie, 1-4m deeper than from ground
surface. Foundation type of all of substructures were spread type foundation.
There are no rivers and creeks nearby and elevations are higher than the surroundings. Therefore,
there are no specific issues on the hydrological conditions in the proposed area.
The road alignments and structural conditions have the following characteristics:
EDSA Southbound
The total length of the project section and the flyover are 854m and 361m, respectively. The
length of the left turn flyover (EDSA–North Avenue) which is located above the EDSA
northbound flyover is 286m with RC and PC voided slab type of superstructure.
EDSA Northbound
The total length of the project section and the flyover are 569m and 343m, respectively, and the
type of superstructures are RC and PC voided slab.
The flyover has two lanes and horizontal alignment of 80m radius right curve at the intersection
which merges with EDSA–North Avenue Left Turn Flyover after the curve. The lengths of the
project section and flyover are 483m and 392m, respectively, and type of superstructures are RC
and PC voided slab.
The ECC for EDSA/North Avenue-West Avenue and EDSA/Roosevelt Interchanges Project had
been issued by DENR-EMB in January 2002. Based on the ROW Map 2001, the affected area is
approximately 5,768 sq. m.
Identified Problems
(a) No problems were identified in the completed plans and detailed design of this interchange
but total re-planning and redesign are required due to the planned construction of a new
station, the Common Station along LRT-1 in front of SM North, and of MRT-7 which will
(b) The construction of a Left Turn Flyover from EDSA to North Avenue will not be possible
with the planned construction of the Common Station.
Recommendations
Proper coordination and discussions with the DOTC, LRTA and other concerned agencies should
be made and the necessary data and information on the MRT-3 and LRT Line-1 extension and
detailed design of the Common Station and MRT 7 should be obtained for Preliminary Design.
The following two (2) alternatives are proposed as the most suitable for comparison based on site
and traffic conditions.
Scheme-1 : Flyover with, 342m long north bound and 319m long south bound.
Scheme-2 : Cut and cover tunnel with, 231m long north bound and 131m long south bound.
Between the two (2) schemes of flyover and cut and cover tunnel, the flyover scheme was
selected considering that construction cost is much cheaper, no ROW acquisition required,
construction duration is shorter and specific O & M will not be needed.
Traffic
Easier traffic management during construction Difficult traffic management during construction
Condition at
Grade I/C
O&M No specific O & M required Requires periodic monitoring and maintenance of sump pit drain water
pump up system and illumination
Much cheaper than scheme-2 More than 3-times expensive than scheme-1
Shorter construction duration and easier to manage existing Longer construction duration and hard to manage existing traffic during
Over all traffic during construction construction
Evaluation No specific O & M required Sump pit requires 400m2 of R.O.W and difficult construction
No R.O.W. acquisition method and sequence
LEGEND : c advantage
disadvantage
Preliminary design was conducted based on the conditions discussed previously in the
comparative study.
Construction plan, PERT/CPM and traffic management has been studied. PERT/CPM shows that
construction duration of this flyover is 22 months.
The following two (2) alternatives are proposed as the most suitable for comparison based on site
and traffic conditions:
Scheme-1 : Left turn flyover from North Ave to Mindanao Ave (3rd level) and left turn
flyover from Mindanao Ave to North Ave (2nd level)
Scheme-2 : Left turn cut and cover tunnel from North Ave to Mindanao Ave (under
pass) and left turn flyover from Mindanao Ave to North Ave (2nd level)
Between two (2) schemes, scheme-2 was selected due to the following reasons:
Preliminary design was conducted based on the conditions previously discussed in the
comparative study.
Construction plan, PERT/CPM and traffic management have been studied. PERT/CPM shows
that construction duration of this flyover is 24 months.
Civil Works Cost for EDSA/North/West/Mindanao IC has been estimated based on the similar
conditions of C-3/E. Rodriguez IC.
The detailed design of the interchange was prepared by Nippon Engineering Consultant Co., Ltd.
in association with DCCD Engineering Corporation and Pertconsult International in March 2003.
There are no significant changes in the topographic conditions of the area between the time of the
detailed design to the present, except for the U-Turn Flyovers constructed on both sides of the
interchange along C-5 and the on-going construction of another flyover from Bonifacio Global
City to C-5 toward Pasig City.
The bearing stratum in this proposed area is tuffaceous rock sequence that underlies 1-3m deeper
than from ground surface. Therefore, type of foundation for all substructures is spread type
foundation.
There is a creek located 250m eastside from the C-5–Kalayaan intersection. However, it is noted
that this area is not prone to flooding because elevations of the proposed area are 5m higher than
the ground elevations near the creek.
(a) 490m of depressed structure will have a horizontal straight alignment along C-5
(b) The standard section along C-5 has three lanes for each direction at the depressed section
and two lanes for each direction at the ground section.
The ECC for C-5/Lanuza St.-Julia Vargas St. and C-5/Kalayaan Ave. Interchanges Project had
been issued by DENR-EMB in December 2001.
Identified Problems
(a) No problems were identified in the detailed design. However, the U-Turn Flyovers
constructed at both sides of the intersection along C-5 are considered to be substandard
structures under the design code.
(b) Traffic conditions should be studied after completion of the on-going construction of the
flyover from Bonifacio Global City toward Pasig City, which will merge in front of the
southern side U-Turn Flyover.
Recommendations
After completion of the flyover construction, a more comprehensive study of actual traffic at the
intersection might be necessary to ensure that its smooth flow is maintained.
DPWH will implement the Feasibility Study on the Completion of Metro Manila Circumferential
Road 5 and Other Priority Road/Interchange Projects and Traffic Mitigation Measure Cum
Environmental, Social and Gender Aspects.
These projects are categorized with the following three (3) schemes;
In view of the above, C-5 improvement projects by the DPWH will not be affected by the
proposed flyover projects.
Two (2) issues were found during the site investigation and detailed topographic survey which
may cause a bottleneck at the intersection of C-5 thru traffic:.
(b) Subtle curve alignments along C-5 thru traffic of both directions were observed around
U-turn flyover.
Traffic survey was conducted last March 6 2012.after the opening of the new flyover from global
city to north bound of C-5 road. The traffic survey data shows that vehicle passing along U-turn
flyover at south side and north side are 25,132 vehicles per day and 18,600 vehicles per day,
respectively. The summarized and actual traffic intersection flow graphics are shown in Figure
4.5-1.
Maintaining the existing U-turn flyover and from the above traffic data, a summary of available
options and findings for improving future traffic flows and capacities are shown in Table 4.5-1.
In view of the above summary, the most effective option is to construct left turn flyover from
Kalayaan Ave. to C-5 north direction which noting that the Tibagan elementary school is located
just beside the road along C-5 north direction.
The new intersection plans should provide three (3) lanes in each direction with underpass
scheme along C-5 thru traffic. Based on the traffic volume and traffic flow at the intersection, the
following four (4) schemes can be considered as new potential intersection plans:.
Traffic Flow by Scheme is shown in Figure 4.5-2 and the Scheme Comparison table is presented
in Table 4.5-2.
・ Existing substandard carriageway widths and subtle curve alignments are the cause of
unsmooth traffic around both sides of the U-turn flyover and a bottleneck for C-5 thru
traffic and that remedial solution to these will require demolishing the existing u-turn
flyover.
・ Most optimum option among the proposed improvement options is the construction of
left turn flyover from Kalayaan Ave to C-5 both directions but the existence of the
ROW problem should be noted: the Tibagan elementary school is located at just beside
of north bound of C-5.
(6) Recommendation
・ To find an appropriate solution for ROW problem (Tibagan elementary school) for
improvement of the intersection with present condition of U-turn flyover.
・ To construct 6-lanes underpass for C-5 thru traffic and 2-lanes left turn flyover from
Kalayaan Ave. to C-5 for both directions. Traffic flow system to resolve problems of
traffic flow conflict, unsmooth thru traffic alignments and substandard carriageway
should also be addressed.
Total Recommendation
The detailed design of the project was prepared by the Japan Overseas Consultants Co., Ltd. in
association with TCGI Engineers in October 2004.
There are no significant changes noted in the topographic conditions of the area between the time
of the detailed design to the present.
In the section from Green Meadows to Calle Industria, the subsoil is distributed until the depth of
0.7-1.0m below ground surface. On the other hand White Plains Creek to end section, the subsoil
(sandy silt and silty sand) is distributed until the depth of 12.0m below ground surface.
No flooding will be experienced in the proposed area because the elevation of the crossing point
with the road is about 5m higher by than the elevation of the confluence with Marikina River.
The 925m long cut and cover tunnel will start in front of Green Meadows Avenue intersection
and terminate after Eastwood Avenue intersection. The tunnel has four lanes, with
two-directionals, and 5.0m vertical clearance.
The detailed design did not cover the environmental aspect of the project.
Identified Problems
(a) 13m height of sump pit to be located under carriageway and sidewalk will make it hard to
arrange or manage traffic during construction.
(b) There is no study yet on the complicated construction procedure of tunnel underneath the
existing creek.
Recommendations
Based on the problems identified above, careful and thorough study should be undertaken for this
improvement option.
The proposed inverted siphon cannot be adopted for the following reasons:
The calculation result of the loss of head of inverted siphon is 1.3 m. Therefore, at the time of
freshet, the water level will rise to 1.3m higher than the present condition at the upstream side
of the road and will cause flooding.
It is expected that much garbage will flow at the time of freshet because the creek is flowing
through a residential area.
The following three (3) alternatives are proposed as the most suitable options for comparison
based on site and traffic condition.
Among the three (3) schemes, scheme-1 was selected due to following reasons:
Preliminary design was conducted based on the conditions discussed previously in the
comparative study.
Construction plan, PERT/CPM and traffic management has been studied. PERT/CPM shows that
construction duration of this flyover is about 24 months.
Civil Works Cost for C-5/Green Meadows/Acropolis/Calle Industria Interchange has been
estimated based on the following factors:
- Unit price used for similar GOP and BOT projects implemented or tendered from
2010-2011 and the one for major item was re-estimated based on 2011 prices.
- Procedures and composition for the derivation of base construction cost, were referred to
similar projects.
CHAPTER 5
The proposed contract packages should be decided considering the size of contract and location of
each flyover as follows:
C-3/E. Rodriguez Interchange was canceled due to conflict with on-going project of Skyway
Stage-3.
The consultancy services for MMICP that are required are; Detailed Design Stage (12 months),
Tender Assistance Stage (12 months), and Construction Supervision Stage (26 months). The
proposed man-month is 118 M/M for Foreign Expert, 469 M/M for Local Expert and 450 M/M
for Technical Support staff. Total amount of proposed consultancy cost is 348,475,364 pesos
(651,648,930 Yen) including 2% contingency.
Total project cost is 3,266.51 million Pesos and loan amount is 5,336.75 million Yen, Government
of the Philippines equity counterpart is about 412.64 million Pesos.
RROW shall be acquired for 100 m2 at the proposed North/Mindanao Interchange and cost is
about 4 million pesos which is already included in the above estimated cost. The summary and
breakdown of the project cost are shown in Tables 5.3-1 and 5.3-2, respectively.
6 months
2. Review and Evaluation of EIA/RAP in DENR EMB
3 months
4. Processing in NEDA for Approval
4 months
5. Loan Negotiation Agreement
6. Loan Agreement
E/N L/A 12 months
7. Selection of Consultant (D/D)
12 months
8. Detailed Design
12 months
9. Selection of Consultant (CS)
10. 1st Contract Package
(EDSA/WEST/NORTH/MINDANAO)
10 months
- Bidding
2 months
- Preparation and Approval of Contract Documents
42
24 months
- Implementation
10 months
- Bidding
2 months
- Preparation and Approval of Contract Documents
24 months
- Implementation
(EDSA/ROOSEVELT/C3/E. RODRIGUEZ)
10 months
- Bidding
2 months
- Preparation and Approval of Contract Documents
22 months
- Implementation
14 months
12. R.O.W. Acquisition
Taking into account the scheme repayment conditions of ODA loans of both STEP loan schemes
and regular loan condition schemes, the total repayment amount of the loan will become the same
for both schemes when the loan amount of the STEP scheme is 12% more costly than the regular
loan condition scheme. Notwithstanding the above, a project with a lower increase in cost under
STEP scheme when compared to regular loan condition scheme is much appreciated by the
borrower.
In view of the above, the STEP loan scheme requires proper arrangement that should utilize
Japanese technology with lower investment cost as much as possible.
The proposed project is to construct flyovers to mitigate traffic congestion at intersections with
heavy traffic conditions in urban areas. Therefore, the focus is to minimize impact on traffic
during construction and to complete the project within the shortest possible construction duration.
Proposed items to investigate under the project to facilitate a STEP loan scheme are the type of
flyover superstructure at the intersection and type of retaining wall along the approach sections.
(2) Proposal of Steel Box and Slab Type Bridge for the type of superstructure at the
Intersection
The original detailed design proposed PC voided slab type superstructure at the intersection.
This superstructure type is economical type but requires the erection of special type of shoring,
scaffolding, form works and dismantling of those materials following construction. Such
works will very much adversely influence the traffic flow during construction and be the
cause of heavy traffic congestion. (Refer to Figure 5.5-1 special type of frame support).
Enclosed by red line in the Table 5.5-1 is the implementation schedule of such an intersection
which shows that the installation of the special type of shoring/scaffolding requires 11 months
and that there is a need to temporarily close the road to traffic during dismantling of the
shoring/scaffolding. In addition there is high risk of damage to the main body of the structure,
in the event of vehicle collision with the special type of shoring and scaffolding.
Moreover, this type of special shoring/scaffolding is also at risk of collapse from vibration
during the concrete pouring, which will result in serious damage once collapse occurs. (In fact,
the same type of frame support suffered collapse during the concrete pouring for the
construction of an expressway in Japan).
(b) Proposal of steel box and steel deck slab type bridge and steel pier
Proposed use of steel bridge, with steel box girder, steel slab deck and steel piers utilizing
Japanese technology, as shown in Figure 5.5-2, will remove the risks of the original detailed
design plan mentioned above and minimize traffic congestion during the construction of
superstructure.
a. 70m long maximum span steel box and slab type bridge, which is much longer than the
30m long maximum span length of PC voided slab bridge, can provide wider available
space for proper arrangement of the at grade intersection.
b. Affect to existing traffic is only from the girder launching operations during night works
given that the steel type structures of the substructure and superstructure are fabricated at
off-site yards (refer to Figure 5.5-3 to 5.5-4). In addition the erection duration for
launching girders is only nine (9) days, indicated by red line in the implementation
schedule of the original plan as shown in Table 5.5-2. Therefore, the impact on traffic
during construction can be minimized.
c. Construction duration at the site can be minimized to 6.5 months instead of the original
plan of 9 months.
d. Steel box and steel deck slab type bridge is superior to PC voided slab with regard to
reduced seismic demand given that steel structures are less heavy.
e. No concrete slab. The steel deck plate construction is overlaid with guss or stone mastic
asphalt as first layer and regular asphalt on top of guss or stone mastick asphalt following
launching of the girders.
a. Cannot adopt steel deck form for entire length of flyover given that the steel box and
steel deck slab type bridge is more expensive than PC voided slab type.
Comparison between original plan and steel box and slab type bridge is shown in Table 5.5-3.
Figure 5.5-2 General View of Steel Box and Slab Type Bridge
Preliminary 3
Concrete curing(21 days)
UAS Installation P11,P12 2 Note
1)Paving & Piling is excluded
Bearing Installation P10,P13 1 2)Downtime of 20% is taken into account
P10-P11 B1 B2 Removal
HSFG Bolt 10
In Situ Painting 18
Steel Pier Filling &
P11,P12 14
Protection Concrete
47
Vehicle Clash Barrier 18
Site Cleaning 4
Day long
75 Used as Works Area
Arrangement
Temporary Traffic Night time
7 Erection of J8~J11
Arrangement Arrangement①
Night time
2 For Deck Closure
Arrangement②
Table 5.5-3 Comparison between Original Plan and Steel Box and Slab Type Bridge
Steel box and slab type bridge Original Plan
Maximum Span L=70m Maximum Span L=30m
・70m long maximum span of steel box and slab ・Economical given construction cost is lower
type bridge is much longer than 30m long ・Can be constructed by local regular contractor
maximum span length of PC voided slab which can due to common type of super structure.
provide wider available space for proper
arrangement of at grade intersection.
・Affect to existing traffic is only from launching of
girders during night works given that steel type
structures of substructure and superstructure are
fabricated at off-site yards. In addition the duration
of launching girders is only nine (9) days.
Therefore, impact on existing traffic can be
Merit
minimized.
・Construction duration at site can be minimized to
6.5 months instead of original plan of 9 month.
・Steel box and slab type bridge is superior to PC
voided slab with regard to reduced seismic demand
given that steel structures are less heavy.
・No concrete slab. The steel deck plate
construction is overlaid with guss asphalt as first
layer and regular asphalt on top of guss asphalt
following launching of the girders.
・Allows transfer of Japanese technology.
・Cannot adopt steel deck form for entire length of ・Requires erection and dismantling of special type
flyover given that the steel box and slab type of shoring/scaffolding and formworks for voided
bridge is more expensive than PC voided slab type. slab at the intersection, these activities will affect
the existing traffic and cause heavy traffic
congestion.
・The erected shoring/scaffolding will reduce the
number of available traffic lanes which will cause
heavy traffic congestion until the
Demerit
shoring/scaffolding is dismantled.
・There is a risk of damage or collapse of the
voided slab in the event of passing vehicle
collision with the shoring/scaffolding which will
result in great damage to the structure.
・There is a risk of collapse of the voided slab due
to vibration during the concrete pouring leading to
loss of stability of the shoring/scaffolding.
Construction 24 Month 26 Month
Duration
Construction JPMY 6,319 JPMY 5,498
Cost <1.149> <1.000>
Source: JICA Study Team
Note: Not included C3-E. Rodrigeuz Flyover for Construction Cost
(3) Proposal for Earthquake Resistant Type Mechanically Stabilized Earth Wall (ERMSE) at
the flyover approach section
Earthquake resistant MSE wall at the flyovers approach sections is proposed instead of the
prevailing type MSE wall. This new type MSE wall (ERMSE) provides high seismic resistance
utilizing new wide strips and an improved attachment system between the new wide strip and the
concrete skin wall. The proposed use of ERMSE is also an opportunity for Japanese technology
transfer. The material cost of ERMSE wall is about 5% only of the total Japanese content. The
outline of the proposed ERMSE wall is explained below.
To improve the reinforcement mechanism inside the embankment with core technology,
without change to the exterior appearance of the prevailing type, the system:
a. Improvement of friction resistance and ease of construction. (Prevailing type used 60mm
width of strip with ribs.)
The development of 80mm wide strip with ribs improves friction resistance by approximately
30% in comparison with the prevailing type. Construction will also be easier due to the
reduction in the number of strips to be installed.
The strips that connect to the concrete skin with the prevailing type are fixed in four
configurations of 4, 6, 8 and 12 pieces. However the new type allows seven configurations
with the possibility to also connect 3, 5 and 7 pieces strips. This improves the efficiency of the
design and optimizes use of materials.
The proposed ERMSE type provides superior seismic resistance. The effectiveness of this
proposed type (no embankment type) was safely confirmed for a similar application during
the Higashi Nihon earthquake (Japanese intensity level 6~7).
The construction of ERMSE in urbanized areas is especially effective due to high seismic
resistance and attractive appearance. The investigation report shown in Figure 5.5-5 is one
out of 1,423 reports which have confirmed the safety for all of the no embankment type walls.
Reinforcing steel bar : The Philippines is producing reinforcing steel bars using electric
blast furnace methods. However large scale infrastructure projects rely upon imported
reinforcing steel bars because of local low production capacity and quality. Japanese
Contractor is involved STEP Loan scheme, therefore considering the steel bar to be
imported from Japan.
Procurement of structural steel members (steel box and slab type bridge elements) from
Japan.Materials for high seismic resistance reinforced type ERMSE wall imported from
Japan.Over head of Japanese contractor (7.22%)
Amount procured from Japan for the Project is shown in Table 5.5-4 in the case of procurement
of all of the above items.
The total amount of Japanese content, at 2,155 million yen, is 36.39% of the total 5,572 million
yen construction cost under STEP scheme. Furthermore, procurement ratio becomes 43.61%
once the 7.22% of overhead of the Japanese contractor is added. The Japanese content proposed
above therefore is adequate to satisfy the required 30% procurement ratio under STEP scheme
condition.
(1) Steel box-girder bridge with steel decks for overpasses at intersections (Non concrete
deck slab type)
The erected shoring/scaffolding will reduce the number of available traffic lanes which
will cause of heavy traffic congestion until the shoring/scaffolding is dismantled.
There is a risk of damage or collapse of the voided slab in the event of passing vehicle
collision with the shoring/scaffolding which will result in great damage to the structure.
Above cross section and picture is shown for ordinary type of shoring/scaffolding for voided slab.
Above picture is shown for shoring/scaffolding of voided slab during construction for similar project.
Traffic lane become 2 lanes from existing 3 lanes and cause of heavy traffic jam during construction
Proposal method
Rigid-frame box-girder bridge with steel decks and steel Pier at intersection
No concrete slab and reduction of dead load. The steel deck plate construction is overlaid
with special asphalt such as guss asphalt as first layer and overlaid regular asphalt.
Affect existing traffic is only from launching of girders during night time works given that
steel substructure and superstructure are fabricated at off-site yards.
Duration of launching girders is only 9 days and impact on existing traffic can be
minimized
Proposal Method
Steel Girder
Steel Pier
UAS
Above cress section and prospective drawing are proposed Rigid Frame Box Girder with Steel
Deck and Steel Pire at intersection.
Erection Method
Day Time Night Time Erection
Above picture is shown for day time and night time condition during erection of superstructure
and this erection work is takes only 9 days at intersection.
After Completion
(2) Steel piers and connection of pile foundation for Special Method in Japan
Conventional method
Proposal method
UAS is simpler and more compact than the conventional connection system
The use of a steel shell reduces the amount of on-site construction work required, such as
that involved in form and re-bar assembly
Reduction of the on-site construction period and the area of the work yard
Scope of the works for four intersections under STEP scheme as follows;
Structural type : 3 lane individual flyover ( south and north directions are same type and same
length)
Pedestrian Bridge : 3 direction (except near side of Munoz station side), total length 95m
Interchange plan for this intersection will be plan to construct individually due to new plan of
MRT-7 station in-front of SM north and new development that Mindanao Ave. direct
connected to North Luzon Expressway.
Structural type : 3 lane individual flyover (south and north directions are same type but
different length)
Span and bridge length : North to Mindanao : 95m under pass + 363.5m open cut=458.5m
RROW: required 100m2 ROW acquisition at the corner of Veterans Golf Club
Estimated costs under STEP scheme are shown in Table 5.5-5 and Table 5.5-6.
5.5.5 Draft Estimated Cost for the Consultancy Services for Pre-Construction and
Construction Supervision
Recapitulation of Draft Estimated Cost for the Consultancy Services for Pre-Construction and
Construction Supervision is shown in Table 5.5-7.
Table 5.5-7 Recapitulation of Draft Estimated Cost for the Consultancy Services for
Pre-Construction and Construction Supervision
FOREIGN CURRENCY VAT LOCAL
DESCRIPTION CURRENCY
YEN COMPONENT PESO COMPONENT (PESO)
I. PRE-CONSTRUCTION STAGE
A. Yen Component
A.1 Remuneration Cost ¥ 20,496,000
A.2 Reimbursable Cost ¥ 3,140,000
B. Peso Component
Remuneration Cost P 8,310,000
Reimbursable Cost P 3,220,000
TOTAL ¥ 23,636,000 P 11,530,000 P 997,200
A. Yen Component
A.1 Remuneration Cost ¥ 179,340,000
A.2 Reimbursable Cost ¥ 24,250,000
B. Peso Component
Remuneration Cost P 58,350,000
Reimbursable Cost P 41,172,000
TOTAL ¥ 203,590,000 P 99,522,000 P 7,002,000
VAT ¥ P P 7,999,200
¥ P P
231,770,520 113,273,040 7,999,200
237,214,495
P
Source: JICA Study Team
5.5.6 Proposed Implementation Plan (STEP Scheme & General Loan Scheme)
MONTHS
No. Activity
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26
C4/Roosevelt
1. Preparation Work (Mobilization)
2. Earth Work (MSE Wall)
63
2. STEP LOAN
MONTHS
No. Activity
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26
C4/Roosevelt
1. Preparation Work (Mobilization)
2. Earth Work (MSE Wall)
3. Pavement Work
Proposed implementation schedule is shown in Table 5.5-9.
4. Bored Pile
5.5.7 Proposed Implementation Schedule for Each Interchange
5. Steel Fablication
6. Abutment, Pier & Slab
North Bound
1) Segment 1 (A1, P1, P2, P3)
2) Segment 2 (P4, P5, P6, P7)
3) Segment 3 (P8, P9, P10)
4) Segment 4 (P11, P12, A2)
South Bound
1) Segment 1 (A1, P1, P2, P3)
2) Segment 2 (P4, P5, P6, P7)
3) Segment 3 (P8, P9, P10)
4) Segment 4 (P11, P12, A2)
7. Miscellaneous Work
MONTHS
No. Activity
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26
C4/North West
1. Preparation Work (Mobilization)
2. Earth Work (MSE Wall)
3. Pavement Work
North Bound
1) Segment 1 (A1, P1, P2, P3)
2) Segment 2 (P4, P5, P6)
3) Segment 3 (P7, P8, P9)
4) Segment 4 (P10, P11, A2)
South Bound
1) Segment 1 (A1, P1, P2, P3)
2) Segment 2 (P4, P5, P6)
3) Segment 3 (P7, P8, P9)
4) Segment 4 (P10, P11, A2)
6. Miscellaneous Work
2. STEP LOAN
64
MONTHS
No. Activity
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26
C4/North West
1. Preparation Work (Mobilization)
2. Earth Work (MSE Wall)
3. Pavement Work
4. Bored Pile
5. Steel Fablication
6. Abutment, Pier & Slab
Proposed implementation schedule is shown in Table 5.5-10.
North Bound
1) Segment 1 (A1, P1, P2)
2) Segment 2 (P3, P4)
3) Segment 3 (P5, P6, P7)
4) Segment 4 (P8, P9, A2)
South Bound
1) Segment 1 (A1, P1, P2)
2) Segment 2 (P3, P4, P5)
3) Segment 3 (P6, P7, P8)
4) Segment 4 (P9, A2)
6. Miscellaneous Work
MONTHS
No. Activity
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26
North Mindanao
1. Preparation Work (Mobilization)
2. Earth Work (MSE Wall)
3. Pavement Work
2. STEP LOAN
MONTHS
65
No. Activity
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26
North Mindanao
1. Preparation Work (Mobilization)
2. Earth Work (MSE Wall)
3. Pavement Work
4. Bored Pile
5. Steel Fablication
6. Tunnel, Abutment, Pier & Slab
A. Depressed (Tunnel)
Proposed implementation schedule is shown in Table 5.5-11.
MONTHS
No. Activity
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26
C5/Green Meadows
1. Preparation Work (Mobilization)
2. Earth Work (MSE Wall)
3. Pavement Work
66
2. STEP LOAN
(4) C5-Green Meadows/Acropolis/Calle Industria.
MONTHS
No. Activity
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26
C5/Green Meadows
1. Preparation Work (Mobilization)
2. Earth Work (MSE Wall)
3. Pavement Work
Proposed implementation schedule is shown in Table 5.5-12.
4. Bored Pile
5. Steel Fablication
6. Abutment, Pier & Slab
1) Segment 1 (A1, P1, P2, P3)
2) Segment 2 (P4, P5, P6)
3) Segment 3 (P7, P8, P9, P10)
4) Segment 4 (P11, P12)
5) Segment 5 (P13, P14, P15, P16, P17)
6) Segment 6 (P18, P19, P20, P21)
7) Segment 7 (P22, P23, P24, P25, P26)
8) Segment 8 (P27, P28, P29, P30)
9) Segment 9 (P31, P32, P33, P34)
10) Segment 10 (P35, P36, P37, P38)
11) Segment 11 (P39, P40, P41)
12) Segment 12 (P42, P43, P44, P45)
13) Segment 13 (P46, P47, A2)
7. Miscellaneous Work
Preparatory Survey for Metro Manila Interchange Construction Project (VI)
5.5.8 Summary of Comparison between STEP Loan and Regular Yen Loan
The characteristics and advantages of both types of loans are shown in the table below.
Initial investment is high under STEP loan and, correspondingly, low EIRR, but it has the
following advantages:
(c) PHP 92 M estimated cost of detailed design will be undertaken under JICA Grant;
(d) Very low and fixed interest rate (0.2%) and long-term repayment period.
CHAPTER 6
Economic Internal Rate of Return (EIRR) will be a major index to measure investment
feasibility, while taking in view the following prepositions of (i) “with and without” the
project analysis (incremental analysis), (ii) time discount method converting all of costs and
benefits accrues in the future to the present value, and (iii) cash-flow analysis. Variables and
assumptive parameters applied to the analysis are summarized in the following set of model
configuration presented in Table 6.1-1.
Economic benefit includes (i) Vehicle Operation Cost (VOC): Running cost saving, and (ii)
VOC: Time cost saving All the benefits and costs were adjusted to 2012 price level.
The DPWH Basic Vehicle operation Cost (2008) based on HDM-4 toolkit (The World Bank,
version 2.05 in 2006) was applied to numerate the running and time costs, as guided by DPWH
and NEDA procedures. In doing so, 10 types of vehicles in the DPWH basic Vehicle Operation
Cost table have been realigned to 6 categories in line with the modeling of traffic and demand
analysis in the study. The VOC by vehicle type is given in Table 6.1-2 below.
The annual investment schedule for all of the intersections had been assumed as shown in Table
6.1-3.
Economic cost and benefit are given in Tables 6.1-4 and 6.1-5 below. Economic Benefit by
value is depicted as Figure 6.1-2.
Table 6.1-4 Financial and Economic Costs of C-3 E. Rodriguez (PhP million)
Financial Cost Economic Cost
FC LC Total FC LC Total
Construction 167.20 250.80 418.00 167.20 209.00 376.20
Land Compensation
Administration cost 16.38 16.38 13.65 13.65
Engineering Fee 25.80 21.60 47.40 25.80 18.00 43.80
Tax and Duties 51.62 51.62
Base Cost 193.00 340.40 533.40 193.00 240.65 433.65
Physical Contingency 3.86 6.81 10.67 3.86 4.81 8.67
BC+PhyC 196.86 347.20 544.06 196.86 245.46 442.32
Price Contingency 20.18 44.50 64.68
Total 217.04 391.70 608.75 196.86 245.46 442.32
Source: JICA Study Team
Table 6.1-5 Economic Benefit - VOC Saved of C-3/ E. Rodriguez (PhP million, 2018-37)
Passenger Utility
Jeepney Bus Truck Motorcycle Total
Car Vehicle
Running Cost Saved (v-km, mil) 9.0 0.0005 1.5 -0.2 0.51 -59.7
BVOC (PhP/v-km) 8.63 7.05 7.54 23.10 31.58 1.54
Running Cost saving (PhP mil) 77.8 0.004 11.0 -5.3 16.1 -92.0 7.6
Time Saved (v-hr mil 10.4 1.5 1.3 0.04 0.5 10.1 23.7
BVOC (k-hr) 408.4 446.6 154.2 1,669.2 109.7 89.9
Time Cost Saving (PhP mil) 4,230.3 656.3 195.0 69.7 50.3 907.5 6,109.0
Total VOC Benefit 4,308.1 656.3 205.9 64.3 66.4 815.5 6,116.6
Source: JICA Study Team
(b) EDSA/Roosevelt/Congressional
Economic cost and benefit are given in Tables 6.1-6 and 6.1-7 below. Economic Benefit by
value is depicted as Figure 6.1-2.
300
Economic Benefits (PhP Mil)
250
100
Running
50 Cost Saved
0
2013
2016
2019
2022
2025
2028
2031
2034
2037
Economic cost and benefit are given in Tables 6.1-8 and 6.1-9. Economic Benefit by value is
shown as Figure 6.1-3.
Table 6.1-8 Financial and Economic Costs of EDSA/ North/West (PhP million)
Financial Cost Economic Cost
FC LC Total FC LC Total
Construction 200.66 301.00 501.66 200.66 250.83 451.49
Land Acquisition 0.00 0.00 0.00 0.00
Administration cost 19.67 19.67 16.39 16.39
Engineering Fee 36.83 30.21 67.04 36.83 25.18 62.01
Tax and Duties 71.44 71.44
Base Cost 237.49 422.32 659.81 237.49 292.40 529.89
Physical Contingency 4.75 8.45 13.20 4.75 5.85 10.60
BC+PhyC 242.24 430.76 673.01 242.24 298.24 540.49
Price Contingency 24.89 55.32 80.21
Total 267.13 486.09 753.22 242.24 298.24 540.49
Source: JICA Study Team
Table 6.1-9 Economic Benefit - VOC Saved of EDSA/North/West (PhP million, 2018-37)
Passenger Utility Motorc
Jeepney Bus Truck Total
Car Vehicle ycle
Running Cost Saved (v-km, mil) 50.8 23.1 10.0 0.9 2.9 7.6 95.22
BVOC (PhP/v-km) 8.63 7.05 7.54 23.10 31.58 1.54 -
Running Cost saving (PhP mil) 438.3 162.7 75.5 19.6 92.7 11.7 800.5
Time Saved (v-hr mil 15.00 0.96 1.50 0.71 1.94 5.95 26.1
BVOC (k-hr) 408.4 446.6 154.2 1,669.2 109.7 89.9 -
Time Cost Saving (PhP mil) 6,127.2 429.6 231.8 1,183.4 212.8 535.3 8,720.23
Total VOC Benefit 6,565.5 592.3 307.3 1,203.1 305.5 547.0 9,520.7
Source: JICA Study Team
700
600
Economic Benefits (PhP Mil)
500
Time Cost
400 Saved
300
200 Running
100 Cost Saved
0
2033
2013
2015
2017
2019
2021
2023
2025
2027
2029
2031
2035
2037
Economic cost and benefit are given in Tables 6.1-10 and 6.1-11. Economic Benefit by value
is shown as Figure 6.1-4.
Table 6.1-10 Financial and Economic Costs of North/ Mindanao (PhP million)
Financial Cost Economic Cost
FC LC Total FC LC Total
Construction 195.90 293.85 489.75 195.90 244.88 440.78
Land Acquisition 4.00 4.00 3.33 3.33
Administration cost 19.20 19.20 16.00 16.00
Engineering Fee 35.96 29.50 65.45 35.96 24.58 60.54
Tax and Duties 69.75 69.75
Base Cost 231.86 416.30 648.15 231.86 288.79 520.65
Physical Contingency 4.64 8.33 12.96 4.64 5.78 10.41
BC+PhyC 236.49 424.62 661.12 236.49 294.57 531.06
Price Contingency 24.25 54.42 78.67
Total 260.74 479.05 739.79 236.49 294.57 531.06
Source: JICA Study Team
Table 6.1-11 Economic Benefit - VOC Saved of North/ Mindanao (PhP million, 2018-37)
Passenger Utility Motorcy
Jeepney Bus Truck Total
Car Vehicle cle
Running Cost Saved (v-km, mil) 14.3 6.5 2.8 0.2 0.8 2.1 26.9
BVOC (PhP/v-km) 8.63 7.05 7.54 23.10 31.58 1.54 -
Running Cost saving (PhP mil) 123.7 45.9 21.3 5.5 26.2 3.3 225.9
Time Saved (v-hr mil 4.23 0.27 0.42 0.20 0.55 1.68 7.36
BVOC (k-hr) 408.4 446.6 154.2 1,669.2 109.7 89.9 -
Time Cost Saving (PhP mil) 1,729.2 121.3 65.4 334.0 60.0 151.1 2,461.0
Total VOC Benefit 1,852.9 167.2 86.7 339.5 86.2 154.4 2,686.9
Source: JICA Study Team
180
160
Economic Benefits (PhP Mil)
140
120 Time Cost
100 Saved
80
60
Running
40
Cost Saved
20
0
2017
2013
2015
2019
2021
2023
2025
2027
2029
2031
2033
2035
2037
Economic cost and benefit are given in Tables 6.1-12 and 6.1-13. Economic Benefit by value
is depicted as Figure 6.1-5.
Table 6.1-12 Financial and Economic Costs of Green Meadows (PhP million)
Financial Cost Economic Cost
FC LC Total FC LC Total
Construction 373.37 560.05 933.41 373.37 466.71 840.07
Land Acquisition
Administration cost 36.59 36.59 30.49 30.49
Engineering Fee 68.53 56.22 124.75 68.53 46.85 115.38
Tax and Duties 132.93 132.93
Base Cost 441.89 785.79 1,227.68 441.89 544.05 985.94
Physical Contingency 8.84 15.72 24.55 8.84 10.88 19.72
BC+PhyC 450.73 801.50 1,252.23 450.73 554.93 1,005.66
Price Contingency 46.21 102.73 148.94
Total 496.94 904.23 1,401.17 450.73 554.93 1,005.66
Source: JICA Study Team
Table 6.1-13 Economic Benefit - VOC Saved of C-5/Green Meadows (PhP million, 2018-37)
Passenger Utility
Jeepney Bus Truck Motorcycle Total
Car Vehicle
Running Cost Saved (v-km,
60.8 0.7 3.4 0.003 1.7 3.7 70.3
mil)
BVOC (PhP/v-km) 8.63 7.05 7.54 23.10 31.58 1.54 -
Running Cost (PhP mil) 524.9 4.8 25.6 0.6 53.1 5.7 614.7
Time Saved (v-hr mil 12.4 0.9 3.3 0.05 2.2 3.8 22.5
BVOC (k-hr) 408.4 446.6 154.2 1,669.2 109.7 89.9 -
Time Cost Saving
5,007.4 411.5 510.3 88.0 241.7 341.2 6,600.1
(PhP mil)
VOC Total Benefit 5,532.3 416.2 535.9 88.6 294.9 346.9 7,214.8
Source: JICA Study Team
450
400
Economic Benefits (PhP Mil)
350
300 Time Cost
250 Saved
200
150 Running
100 Cost Saved
50
0
2013
2015
2017
2019
2021
2023
2025
2027
2029
2031
2033
2035
2037
(f) Aggregate
Implementation of the C-3/E. Rodriguez Interchange was cancelled by the DPWH to give
priority to the construction of Skyway Stage 3, second level, along C-3 under BOT scheme.
However, the aggregate analysis was conducted for five interchanges including C-3/E.
Rodriguez. Aggregate economic costs and benefits are given in Tables 6.1-14 and 6.1-15.
Economic Benefits by value are shown in Figure 6.1-6.
1,600
1,400
Economic Benefits (PhP Mil)
1,200
Time Cost
1,000
Saved
800
600
Running Cost
400 Saved
200
0
2015
2021
2013
2017
2019
2023
2025
2027
2029
2031
2033
2035
2037
6.1.2 Results
The Economic Internal Rate of Return (EIRR) and Economic Net Present Value (ENPVs) by
intersection are presented in Table 6.1-16, followed by figures depicting cost-benefit streams
(Figures 6.1-7 through 6.1-12). In the estimation of ENPV, a 15 percent social discount rate was
applied, as guided by NEDA procedures.
EIRR and ENPV stand at 52.2 percent and PhP 732.6 million, respectively. The chronological
inputs and outputs streams of economic resources are depicted as Figures 6.1-7.
500 60%
50%
300
40% Running cost
200
saved
EIRR
100 30%
OM
0
20%
2013
2016
2019
2022
2025
2028
2031
2034
2037
(100)
Initial Investment
10%
(200)
(300) 0% EIRR
(2) EDSA/Roosevelt/Congressional
EIRR and ENPV were evaluated at 35.9 percent and PhP 452.8 million, respectively. It would be
noteworthy that the completion of C-3 Expressway (2028) will have little effect on traffic
diversion on the concerned intersection. The chronological inputs and outputs streams of
economic resources are shown in Figures 6.1-8.
350 40%
Time cost saved
35%
Cost and Benefit (PhP Million)
250
30%
150 Running cost
25% saved
50
EIRR
20% OM
(50)
2013
2016
2019
2022
2025
2028
2031
2034
2037
15%
(150) Initial
10%
Investment
(250) 5%
EIRR
(350) 0%
(3) EDSA/North/West
EIRR and ENPV were evaluated at 68.3 percent and PhP 1244.2 million, respectively. The
chronological inputs and outputs streams of economic resources are shown in Figures 6.1-9.
700 80%
Time cost saved
70%
Cost and Benefit (PhP Million)
500
60%
300 Running cost
50% saved
100
EIRR
40% OM
(100)
2013
2016
2019
2022
2025
2028
2031
2034
2037
30%
(300) Initial
20%
Investment
(500) 10%
EIRR
(700) 0%
(4) North/Mindanao
EIRR and ENPV were evaluated at 23.4 percent and PhP 147.3 million, respectively. The
chronological inputs and outputs streams of economic resources are shown in Figures 6.1-10.
300 25%
Time cost saved
200
2013
2016
2019
2022
2025
2028
2031
2034
2037
(100) 15%
EIRR
(200) OM
(300) 10%
(400)
Initial
(500) 5% Investment
(600)
EIRR
(700) 0%
EIRR and ENPV were evaluated at 25.1 percent and PhP 416.4 million, respectively. The
chronological inputs and outputs streams of economic resources are shown in Figures 6.1-11.
600 30%
Time cost saved
Cost and Benefit (PhP Million)
400 25%
200
20% Running cost
saved
0
EIRR
15%
2013
2016
2019
2022
2025
2028
2031
2034
2037
OM
(200)
10%
(400)
Initial
5% Investment
(600)
EIRR
(800) 0%
(6) Aggregate
Implementation of the C-3/E. Rodriguez Interchange was cancelled by the DPWH to give
priority to the construction of Skyway Stage 3, second level, along C-3 under BOT scheme.
Therefore, the aggregate analysis was conducted for three interchanges except C-3/E.
Rodriguez.
Aggregate EIRR and ENPV was estimated at 41.4 percent and PhP 3124.9 million, respectively.
The aggregate chronological streams of economic inputs and outputs and EIRR schedule is
shown in Figure 6.1-12.
1,800 45%
800 35%
30% Running cost
300
saved
25%
EIRR
(200)
2013
2016
2019
2022
2025
2028
2031
2034
2037
20% OM
(700)
15%
(1,200) 10% Initial
(1,700) 5% Investment
(2,200) 0% EIRR
Sensitivity analysis has been undertaken to indicate resiliency against risks, specifically, (i)
downsizing benefits by 15 percent, (ii) cost increase or overrun by 15 percent, and (iii)
combination of (i) and (ii). The results are presented in Table 6.1-17. The results reveal profoundly
robust viability and resiliency of each of the MMICP against project risks that would take place
during their construction and operation period.
6.1.4 Conclusion
From the assessments undertaken by the Study Team, all of the intersection construction projects
are economically feasible, viable, and highly exceed the cut-off rate of allocative-efficiency of 15
percent. Of this, North-West-Mindanao intersections posted extremely high efficiency rates due
largely to (i) large volume of aggregate traffic, (ii) high growth rate of traffic volume2 (2018-27),
and (iii) Low project cost. Major attributes affecting the size of efficiency (EIRR) of each of the
intersections are summarized in Table 6.1-18.
EIRR analysis and sequential sensitivity analysis numerically proved the worthiness of MMICP in
the light of the national economy. As such, the commencement of the project at an early stage of
time would profoundly be recommendable by securing the financing facilities inclusive of the
Japan’s ODA loan as an option.
This section deals with economic analysis of the MMICP under the Japan’s STEP loan scheme
with EIRR as efficiency measurement index. Analytical framework and methodology are all
identical to Japan’s Middle Income Countries General Condition Loan (GC) Loan in view. Note
that the EIRR analyses assume different initial investment costs under the two loan schemes of GC
Loan and STEP Loan. In addition, the implementation of the C-3/E. Rodriguez Interchange was
cancelled by the DPWH to give priority to the construction of Skyway Stage 3, second level, along
C-3 under BOT scheme.
As previously noted in Section 6.1.1, prepositions of the analysis include (i) “with and without”
the project analysis (incremental analysis), (ii) time discount method, and (iii) cash-flow
analysis. Variables and assumptive parameters applied to the analysis are summarized in
Table 6.2-1.
2
Current analysis of demand forecast and sequential efficiency analysis assumes an increase (2018) and downsizing (2028) of traffic
volume at each of the intersections taking in view the completion of C-3 missing link construction and C-3 Expressway, respectively.
Note that Green Meadows was assumed to have little influence on the C-3 expressway in the light of traffic volume.
The annual investment schedule for all of the intersections had been assumed as shown in Table
6.2-2.
Economic benefit includes (i) Vehicle Operation Cost (VOC): Running cost saving and (ii)
VOC: Time cost saving. All the benefits and costs are as per 2012 price. The VOC by vehicle
type is given in Table 6.1-2. Meanwhile, the annual investment schedule for all of the
intersections had been assumed as same as Table 6.1-3.
(a) EDSA/Roosevelt/Congressional
Economic cost and benefit are given in Tables 6.2-3 and 6.2-4 below. Economic Benefit by
value is depicted as Figure 6.2-1.
350
300
Economic Benefits (PhP Mil)
250
100
Running
50 Cost Saved
0
2013
2016
2019
2022
2025
2028
2031
2034
2037
Economic cost and benefit are given in Tables 6.2-5 and 6.2-6 below. Economic Benefit by
value is depicted as Figure 6.2-2.
Table 6.2-5 Financial and Economic Costs of EDSA/North/West (STEP Loan, PhP million)
Financial Cost Economic Cost
FC LC Total FC LC Total
Construction 224.42 392.16 616.58 224.42 326.80 551.22
Land Acquisition
Administration cost
Engineering Fee 37.88 29.52 67.39 37.88 24.60 62.47
Tax and Duties 78.45 78.45
Base Cost 262.30 504.13 766.43 262.30 351.40 613.69
Physical Contingency 5.25 10.08 15.33 5.25 7.03 12.27
BC+PhyC 267.54 514.21 781.76 267.54 358.42 625.97
Price Contingency 16.15 38.63 54.78
Total 283.69 552.84 836.54 267.54 358.42 625.97
Source: JICA Study Team
700
600
Economic Benefits (PhP Mil)
500
Time Cost
400 Saved
300
200 Running
100 Cost Saved
0
2017
2013
2015
2019
2021
2023
2025
2027
2029
2031
2033
2035
2037
Economic cost and benefit are given in Tables 6.2-7 and 6.2-8 below. Economic Benefit by
value is depicted as Figure 6.2-3.
Table 6.2-7 Financial and Economic Costs of North/Mindanao (STEP Loan, PhP million)
Financial Cost Economic Cost
FC LC Total FC LC Total
Construction 207.55 364.13 571.68 207.55 303.44 511.00
Land Acquisition 4.00 4.00 3.33 3.33
Administration cost 20.34 20.34 16.95 16.95
Engineering Fee 35.03 27.30 62.33 35.03 22.75 57.78
Tax and Duties 72.56 72.56
Base Cost 242.58 488.33 730.91 242.58 343.14 585.73
Physical Contingency 4.85 9.77 14.62 4.85 6.86 11.71
BC+PhyC 247.44 498.09 745.53 247.44 350.00 597.44
Price Contingency 14.93 37.42 52.36
Total 262.37 535.51 797.88 247.44 350.00 597.44
Source: JICA Study Team
180
160
Economic Benefits (PhP Mil)
140
120 Time Cost
100 Saved
80
60
Running
40
Cost Saved
20
0
2017
2013
2015
2019
2021
2023
2025
2027
2029
2031
2033
2035
2037
Economic cost and benefit are given in Tables 6.2-9 and 6.2-10 below. Economic Benefit by
value is depicted as Figure 6.2-4.
Table 6.2-9 Financial and Economic Costs of C-5/Green Meadows (STEP Loan, PhP million)
Financial Cost Economic Cost
FC LC Total FC LC Total
Construction 552.95 581.97 1,134.92 552.95 484.98 1,037.93
Land Acquisition
Administration cost 44.49 44.49 37.07 37.07
Engineering Fee 76.62 59.71 136.33 76.62 49.76 126.38
Tax and Duties 139.60 139.60
Base Cost 629.57 825.77 1,455.34 629.57 571.81 1,201.38
Physical Contingency 12.59 16.52 29.11 12.59 11.44 24.03
BC+PhyC 642.16 842.29 1,484.45 642.16 583.25 1,225.41
Price Contingency 38.76 63.28 102.04
Total 680.92 905.57 1,586.49 642.16 583.25 1,225.41
Source: JICA Study Team
450
400
Economic Benefits (PhP Mil)
350
300 Time Cost
250 Saved
200
150 Running
100 Cost Saved
50
0
2013
2015
2017
2019
2021
2023
2025
2027
2029
2031
2033
2035
2037
(e) Aggregate
Implementation of the C-3/E. Rodriguez Interchange was cancelled by the DPWH to give
priority to the construction of Skyway Stage 3, second level, along C-3 under BOT scheme.
Therefore, the following analysis was conducted for aggregation of four interchanges except
C-3/E. Rodriguez. Economic cost and benefit are given in Tables 6.2-11 and 6.2-12 below.
Economic Benefit by value is depicted as Figure 6.2-5.
Table 6.2-11 Financial and Economic Costs (STEP Loan, PhP million)
Financial Cost Economic Cost
FC LC Total FC LC Total
Construction 1,274.96 1,553.61 2,828.57 1,274.96 1,294.68 2,569.63
Land Acquisition 4.00 4.00 3.33 3.33
Administration cost 110.88 110.88 92.40 92.40
Engineering Fee 190.96 148.81 339.77 190.96 124.01 314.97
Tax and Duties 395.52 395.52
Base Cost 1,465.92 2,212.83 3,678.75 1,465.92 1,511.09 2,977.01
Physical Contingency 29.32 44.26 73.57 29.32 30.22 59.54
BC+PhyC 1,495.24 2,257.08 3,752.32 1,495.24 1,541.31 3,036.55
Price Contingency 90.25 169.57 259.82
Total 1,585.49 2,426.65 4,012.14 1,495.24 1,541.31 3,036.55
Source: JICA Study Team
Table 6.2-12 Economic Benefit - VOC Saved (STEP Loan, PhP million, 2018-37)
Passenger Utility
Jeepney Bus Truck Motorcycle Total
Car Vehicle
Running Cost saving (PhP million) 1,451.8 488.1 173.6 212.4 324.3 40.1 2,690.4
Time Cost Saving
13,993.9 1,933.0 868.2 3,287.9 554.2 1,158.7 21,686.9
(PhP million)
VOC Total Benefit 15,445.7 2,421.1 1,041.8 3,500.3 878.5 1,198.8 24,377.3
Source : JICA Study Team
1,600
1,400
Economic Benefits (PhP Mil)
1,200
Time Cost
1,000
Saved
800
600
Running Cost
400 Saved
200
0
2015
2021
2013
2017
2019
2023
2025
2027
2029
2031
2033
2035
2037
6.2.2 Results
The Economic Internal Rate of Return (EIRR) and Economic Net Present Value (ENPV) by
intersection are presented in Table 6.2-13, followed by figures depicting cost-benefit streams
(Figures 6.2-6 through 6.2-10). In the estimation of ENPV, 15 percent of social discount rate was
applied, as guided by NEDA.
(a) EDSA/Roosevelt/Congressional
EIRR and ENPV were figured out at 22.5 percent and PhP 303.01 million, respectively. It
would be noteworthy that the completion of C-3 Expressway (2028) has little effect of traffic
diversion on the concerned intersection. Chronological inputs and outputs of economic
resources are depicted as Figures 6.2-6.
350 25%
Time cost saved
Cost and Benefit (PhP Million)
250
20%
150 Running cost
saved
50 15%
EIRR
OM
(50)
2013
2016
2019
2022
2025
2028
2031
2034
2037
10%
(150) Initial Investment
5%
(250)
EIRR
(350) 0%
EIRR and ENPV were figured out at 37.4 percent and PhP 1,102.31 million, respectively.
Chronological inputs and outputs of economic resources are depicted as Figures 6.2-7.
700 40%
Time cost saved
35%
Cost and Benefit (PhP Million)
500
30%
300 Running cost
25% saved
100
EIRR
20% OM
(100)
2013
2016
2019
2022
2025
2028
2031
2034
2037
15%
(300) Initial Investment
10%
(500) 5%
EIRR
(700) 0%
Figure 6.2-7 Economic Cost and Export Parity Benefit, and EIRR
(EDSA/North/West, STEP Loan)
EIRR and ENPV were figured out at 15.7 percent and PhP 20.44 million, respectively.
Chronological inputs and outputs of economic resources are depicted as Figures 6.2-8.
300 18%
Time cost saved
200 16%
Cost and Benefit (PhP Million)
100 14%
0 Running cost
12% saved
2013
2016
2019
2022
2025
2028
2031
2034
2037
(100)
10%
EIRR
(200) OM
8%
(300)
6%
(400)
Initial
4%
(500) Investment
(600) 2%
EIRR
(700) 0%
Figure 6.2-8 Economic Cost and Export Parity Benefit, and EIRR
(North/ Mindanao, STEP Loan)
EIRR and ENPV were figured out at 16.4 percent and PhP 104.02 million, respectively. It
would be noteworthy that the completion of C-3 Expressway (2028) has little effect of traffic
diversion on the concerned intersection. Chronological inputs and outputs of economic
resources are depicted as Figures 6.2-9.
600 18%
16% Time cost saved
Cost and Benefit (PhP Million)
400
14%
200
12% Running cost
saved
0 10%
EIRR
2013
2016
2019
2022
2025
2028
2031
2034
2037
8% OM
(200)
6%
(400)
4% Initial
Investment
(600)
2%
EIRR
(800) 0%
(e) Aggregate
Implementation of the C-3/E. Rodriguez Interchange was cancelled by the DPWH to give
priority to the construction of Skyway Stage 3, second level, along C-3 under BOT scheme.
Therefore, the following analysis was conducted for aggregation of three interchanges
except C-3/E. Rodriguez. EIRR and ENPV stood at 23.2 percent and PhP 1,573.7 million,
respectively. Chronological economic input and output with EIRR schedule is depicted as
Figure 6.2-10.
1,800 25%
EIRR
(200) 2013
2016
2019
2022
2025
2028
2031
2034
2037
OM
(700) 10%
(1,200)
5% Initial
(1,700) Investment
(2,200) 0% EIRR
Sensitivity analysis has taken place to indicate resiliency of the concerned intersections against
risks, specifically, (i) downsizing benefit by 15 percent, (ii) cost overrun by 15 percent, and (iii)
combination of (i) and (ii). The results are given below Table 6.2-14. The results reveal profoundly
robust resiliency of each of the MMICP against project risks that would take place during
construction and operation period.
6.2.4 Conclusion
EIRR analysis and sequential sensitivity analysis under the STEP loan scheme also numerically
proved the worthiness of MMICP in the light of the national economy. As such, the
commencement of the project in an early stage of time would profoundly be commendable
under the secure financing scheme inclusive of the Japan’s ODA loan, either General Condition
or STEP loans, as an option.
Besides the quantification of VOC, CO2 emission reduction effects, and improved road safety
through the reduction of traffic accidents at the intersections are likewise envisaged. At three of the
concerned intersection In Quezon City, fatal and non-fatal injuries, and damages to facilities were
recorded at 99, 3,668, and 15,396, in that order3. Conservatively assuming rate of accident of the
four intersections at 5 percent, and further the cost of traffic accident at around PhP 60,000 4, the
social cost saved by the reduction of traffic accidents would be around PhP 57.5 million per year5.
This figure, as well as air quality improvements, remains indicative and hence were not used in the
quantitative analysis undertaken, Nonetheless, MMICP profoundly implies economic benefits of
social cost savings through the reduction of traffic accidents.
Furthermore, with the current management transformation efforts of the DPWH, the project will
generate greater economic benefits coming from enhanced DPWH institutional and human
resources capacity that will bring about lower cost and better quality of construction and
maintenance works for road projects in the future.
Operation and effect of the Project will be monitored by measuring traffic volume and average
travel speed as indicators. The targets of the indicators are estimated as of the planned monitoring
timing as shown in Table 6.4-1 conducting monitoring by DPWH in 2019 two years after
completion of the project. Figure 6.4-1 through 6.4-4 show monitoring location of each
intersection.
3
Source: Metro Manila Development Authority (MMDA), Metro Manila Accident Reporting and Analysis System (MMARAS), Traffic
Accident Report January to December 2009
4
The World Bank, The Bank Operation of Project Financing (Japanese), 2007, p. 46, The case of PRC
5
(99+3,668+15,396) x 0.05 x 60,000 = (around) PhP 57.5 million
* Target Year is two years after the completion of the Project, which is defined as the time when the Project is open to traffic.
Source: JICA Study Team
Monitoring Location of
Traffic Volume
Monitoring Location
(Both Flyover and At-grade
of Travel Speed
Traffic at Both Direction)
(Northbound Flyover)
Figure 6.4-1 Monitoring Location for Traffic Volume Count and Travel Speed
(EDSA/Roosevelt/Congressional Ave. Intersection: Along EDSA – Cubao Side)
Monitoring Location
of Travel Speed
(Northbound Flyover)
Figure 6.4-2 Monitoring Location for Traffic Volume Count and Travel Speed
(EDSA/North Ave./West Ave. Intersection: Along EDSA – Cubao Side)
To: EDSA/SM
Figure 6.4-3 Monitoring Location for Traffic Volume Count and Travel Speed
(North Ave. /Mindanao Ave. Intersection: Along North Avenue – EDSA/SM Side)
Monitoring Location
of Travel Speed
(Northbound Flyover)
Figure 6.4-4 Monitoring Location for Traffic Volume Count and Travel Speed
(C-5/Greean Meadows/Acropolis/Galle Industria – Pasig City Side)
The purpose of the survey is to verify positive impacts and benefits brought about by the project
implementation on Japanese companies that are operating in Metro Manila and adjacent provinces.
Expected benefits are mostly reduction of transportation cost for delivery of goods and services
passing the project interchanges and adjacent roads within influenced area.
The survey was conducted mainly through interview to the selected Japanese firms that may use
project interchanges for their business. Among 600 Japanese firms operating in Metro Manila area
and adjacent provinces, 8 to 10 Japanese representative firms, that have long time business
operation in the Philippines covering wide areas of Metro Manila with fairly large business
transactions, were selected for interview to identify impacts and benefits on their business with the
implementation of the project.
1) Current status of transportation system of the firm and potential issues and problems
currently facing in the field of transportation.
2) Expected improvements on access between port/factory and clients and vice versa brought
about by implementation of the Project.
3) Expected reduction of transport related costs owing to implementation of the Project.
4) Expected change in distribution pattern and business perspectives due to implementation of
the project, if any.
The eight (8) representative firms shown in Table 6.5-1 are identified for interview.
Expert oriented firms are not frequent user of project intersections. These firms are find their
business centers free from traffic congestion, therefore they are avoiding travel in Metro Manila.
On the other hand, firms handle products for domestic consumption necessarily use project
intersections since Metro Manila is the biggest market in the country and they have to transport
their products to consumers in Manila through project intersections.
6. Nippon Express Philippines Head Office: Pascor Drive, Parannaque City Freight transport
Corporation Warehouse: Calamba in Languna
7. Suzuki Philippines, Incorporated Head Office, Factory: Danny Floro St., Bagong Motorcycle assembly and sales,
Ilog, Pasig City, MM Passenger car sales
8. Honda Philippines Inc. Head Office, Factory:First Philippine Industrial Motorcycle assembly and sales,
Park, Tanauan City, Batangas Generator sales
Source: JICA Study Team
The most commodity flow has origin and/or destination from/to Metro Manila, few commodities
are directly transported between north area and south area. However, some firms who were
interviewed mentioned that electrical and mechanical parts manufactured in the south are
transported to factories in the north for assembling via C-3, C-4 (EDSA) and C-5. There is a
tendency that assembling factories are located in the north and parts manufacturing factories are
located in the south. Transporting parts from south to the north is becoming bigger every year.
Mitigation of traffic congestion in Metro Manila will help commodity flow between north and
south.
(3) Poor Access between Expressways and Manila Seaport and Airport
Many Japanese firms raise their concern about poor access to expressways from Manila Seaport
and Airport. Cargos arrive at the seaport and airport has to be transported to their factories
through South Luzon and North Luzon expressways via heavily congested city roads. Travel
along congested city roads hampers timely and efficient transport of imported materials to the
respective factories. Furthermore, transport of goods between factories in the north and south is
also hampered due to absence of city expressways that connects south and north expressways.
Improvement of Major circumferential roads including EDSA to the high standard urban road
and/or construction of new urban expressway is expected to promote commodity flow between
north and south.
In addition to heavily congested city roads to the expressways, the law enforcement widely
known as “Truck Ban” that restricts travel of trucks along designated roads during designated
time adds another drawback to transport activities of Japanese firms.
6.5.5 Conclusion
Most firms that engage in delivery of goods and services in Metro Manila express favorable
opinion on interchange construction as quick impact project, but they also desire fundamental
solution to the Metro Manila traffic by introducing modal sift from vehicular transport to rail
transport for passenger movements and introduction of city expressways including construction
elevated expressways along EDSA and city expressway connecting North and South Expressways
for cargo movements.
CHAPTER 7
EIA procedure and EIA related Laws and Regulations in the Philippines: The Philippine
Environmental Impact Statement System (PEISS) has been established by the Presidential
Decree No. 1586 (1978), and implemented by the Department of Environment and Natural
Resources (DENR) Administrative Order No. 30 Series of 2003 (DAO 03-30) and its
Revised Procedural Manual (2007). The review and supervision of PEISS are conducted by
the Environmental Management Bureau (EMB) of the DENR.
Scoping: In accordance with the “JICA Guidelines for Environmental and Social
Considerations (2002 April)” (hereafter referred to as JICA Guidelines), scoping was
conducted with the analysis of alternatives. The results of scoping show that there are no
significant adverse impacts on natural environment and socio-economic conditions. Items
which are expected to have some negative impacts are listed in Table 7.1
Prediction and Assessment: Noise and air pollutants (TSP、SO2、NO2) emitted from vehicles
are predicted based on the projected traffic in 2018. The results of prediction show that:
・ Noise level: Due to the increase of traffic volume, the noise levels will be about
79dB(A) during the day (6.00-22.00) and 75-78dB(A) in the night (22.00-6.00), which
are almost the same as the present noise levels . The predicted noise levels at all four
interchanges may exceed the maximum permissible levels (for commercial area) by
10dB(A) during the day and by 20dB(A) in the night.
・ Air Pollutants: Because of the increase of average travel speeds and the decrease of
vehicle hours, TSP and NO2 emissions of the with-project-case will reduce by
approximately 10 - 20% compared with the zero option case. The emissions of SO2 will
increase by the same amount for both with- and without-project cases. Assuming all
other factors being equal to the present conditions, air pollutant concentrations might
not exceed the maximum allowable limits of 24 hours average of the Philippine Clean
Air Act of 1999 because the present concentrations are well below the limits.
・ CO2 emission: Because of the increase of average travel speeds and the decrease of
vehicle hours, the with-project-case will reduce CO2 emissions by approximately 10-
20% compared with the zero option case.
Mitigation Measures: Technically feasible mitigation measures during the construction and
operation phases are drawn up and proposed for four interchange projects.
・ After opening the interchange, noise levels are regularly monitored. Installation of
noise barriers should be considered where the noise levels significantly exceed the
permissible levels in residential zones.
Monitoring: In order to ensure the effectiveness of mitigation measures and monitor the
unexpected impacts, the Environmental Monitoring Plans for the construction and operation
phases are drawn up. After opening the interchanges, replanted trees, ambient air quality,
and noise and vibration should be regularly monitored.
According to the criteria of PEISS, DPWH will submit the Initial Environmental
Examination (IEE) reports to DENR EMB for each interchange project in order to apply the
Environmental Compliance Certificate (ECC).
In comparison to JICA Guidelines and World Bank Operational Policies, there are no
variances in terms of the objectives of the JICA Guidelines/WB OP 4.01 and the Philippine
laws/regulations and DPWH policy on land acquisition and RAP. The Project Policy on
compensation is based on the full replacement cost.
The results of the census survey and inventory (assets and land) survey are shown in Table
7.2-1. At the C-3/E. Rodriguez Interchange, 94 informal settlers had been already relocated
to the outside of the ROW by the MMDA’s METRO GWAPO Program.
The JICA Study Team supported DPWH to prepare the Abbreviated Resettlement Action
Plan (ARPA) in line with DPWH’s Land Acquisition, Resettlement, Rehabilitation and
Indigenous Peoples’ Policy (LARRIPP) and JICA Guidelines.
Table 7.2-1 Land Acquisition, Involuntary Resettlement and Affected Structure for MMICP
Interchange Land Acquisition Resettlement Affected Structure
C-3/E. Rodriguez None None None
EDSA/Roosevelt/Congressional None None 5 stalls (marginal*1)
Additional ROW for
EDSA/North/West/Mindanao None 25 stalls (marginal*1)
sump pit (100 sq.m)
C-5/Green Meadows/Acropolis/
None None None
Calle Industria
Source: JICA Study Team
Note : the impact is only partial and the remaining portion of the property or asset is still viable for continued use.
In accordance with JICA Guidelines, DPWH assisted with JICA Study Team hold Public
Consultation Meetings for Barangays communities and stakeholders at four interchange
project sites.
The communities and stakeholders favored the interchange projects to ease the present
traffic congestion. There were the comments on the implementation of the Traffic
Management Plan during construction, noise mitigation measures for the flyovers and
restoration of cutting trees due construction. DPWH will draw up the proper
countermeasures in planning of the interchange projects against these issues raised by
stakeholders.
CHAPTER 8
The southern segment (hereafter referred to as the C-3 Missing Link) has not yet been
implemented. The circumferential road network serving south-central Metro Manila is, therefore,
still not functioning effectively resulting in heavily congested traffic conditions on EDSA.
Construction of the C-3 missing link, together with the construction of the flyovers proposed
under this preparatory survey, is expected to significantly contribute to the decongestion of heavy
traffic along the circumferential roads. The study involved review of the C-3 missing link
construction report and also study of influence to the proposed flyovers by the captioned project.
The proposed alternative alignments run through four (4) cities in the Metropolitan Manila,
namely San Juan City, Mandaluyong City, Manila City and Makati City. All affected cities are
primarily highly urbanized with scattered factory/industrial developments.
Informal settlements are located beside SM City Sta. Mesa near C-3 Road side.
The topography of Metro Manila can be classified into three zones, namely; (1) the Coastal
Lowland along Manila Bay, (2) the Central Plateau and (3) Marikina Plain. The surface geology
of the Central Plateau consists of deposits of the Guadeloupe Tuff formation. On the other hand,
the Coastal Lowland and the Marikina Plain mainly consist of alluvium deposits.
The 27km of Pasig River is technically a tidal estuary, as the flow direction depends upon the
water-level difference between Manila Bay and Laguna de Bay. The average width of Pasig
River is 91m and average depth is 4m with the deepest sections being 6m. Flow volume can be
as low as 12cum/sec in the dry season whereas during the rainy season flow can increase to
275 cum/sec.
The lowest bridge, with a vertical clearance of only 3.5m above high water level, is the Ayala
Bridge that can only be navigated by larger vessels during periods of low tide.
The channel length of San Juan River is 11.0km and the width of the river in the project area is
typically 40m-50m. The river is flood prone over most of its length with wide areas of
The San Juan River is not navigable and is outside of the mandate of the Philippine Coast
Guard.
The six (6) alternative alignments for the C-3 Missing Link were presented to the Secretary of
DPWH in July 2011, together with a comparative study prepared by its URPO. These
alignments are presented in Figure 8.3-1.
Source : URPO
Figure 8.3-1 Alternative Alignments – DPWH Study
6 alternatives were presented by URPO-DPWH considering following items such as length of each
alternatives, number of lane, structural type, cost of RROW, construction cost and total cost.
The report also presented advantages and disadvantages for all alternatives but there was no
mention which alternative was superior or even did not make ranking among the alternatives.
The Study Team established the following evaluation criteria for the review of the DPWH
alignment study. 1) Proposed Scope of Work 2) Construction Issue 3) R.O.W. Acquisition 4)
Resettlement Issue 5) Environmental Issue 6) Navigation Issue in Pasig River and 7) Construction
Cost.
Number of lanes is 6-lanes under the original plan and the other five alternatives were only
4-lanes.
Adoption of viaduct section under the original plan is for limited section only while the other
five alternatives were to adopt viaduct into longer sections.
Regarding double deck type viaduct, under the original plan and alternatives 5 and 6, this
was not mentioned, while alternative 2 discussed the potential of a double deck type viaduct.
On the other hand, alternatives 3 and 4 were planned as single deck type viaduct.
Regarding RROW, costs of RROW were presented but breakdown and also any descriptions
of affected buildings, houses and number of people were not provided.
Regarding environmental issues, some reference were made on environmental issues such as
scouring and obstructions in the river.
Estimated costs for each of the alternatives had no detailed cost breakdown.
The proposed geometric design standards for the C-3 Missing Link are adopted from DPWH
Sstandard Design Criteria.
The number of lanes assumed for the alternative alignments is the same as the existing C-3
Northern Segment, which is a 6 lane divided road.
Proposed viaduct structure should take into consideration certain distances from existing
structures, noise and fire, which is regulated under the Water Code of the Philippines.
A road bridge over inland waterways must have a minimum vertical clearance of 3.75m from the
highest water level while San Juan River is not navigable.
Based on above conditions, the Study Team prepared five (5) types of typical cross sections,
namely: 1) at grade section, 2) viaduct on ground, 3) double deck viaduct on ground, 4) along Pasig
River and 5) along San Juan River.
Table 8.4-1 Scope of Work of the Alternative Alignments, C-3 Missing Link
Elevated Single Elevated Double R.O.W.
At Grade Total
Deck Deck Acquisition
Single level viaduct structures are proposed as a preferred configuration. However, where
available ROW is limited, double deck viaducts have been proposed for consdiration.
Long span bridges, in the order of 50m to 100m or so, will be necessary to cross the Pasig River,
and the San Juan River.
The interconnectivity of the proposed alternative alignments with local roads is a key aspect in
promoting the functionality of each route.
2- ramps were planned to be provided for each of the alternatives, namely Boni. Ave. and New
Panaderos on the south side and Shaw Blvd. on the north side.
There are typically between 150 to 200 vessel movements along the river every day.
The section of Pasig River just upstream of Lambingan Bridge is already posing navigational
problems for the larger vessels plying the river. At this location, the river bends 90 degrees to the
right and narrows down from 100m to less than 60m. Any obstructions in the river reducing the
navigable width will further exacerbate the already difficult situation.
San Juan River is not navigable and therefore not subject to consideration of vessel navigation
and ship collision forces.
San Juan River will have to address hydraulic capacity issues since areas along the river are already
flood prone.
Assessment on the numbers of affected buildings and building landmarks have been made from
open source satellite images.
The numbers of Project Affected People (PAPs) have been estimated by assuming that the typical
average number of persons per household is approximately five (5) based on the data of 2007
Census of Population.
Among the alternatives, considering that the length of the routes passing through the residential
area of Alignments 1 and 2 are longer than other alternatives, the impacts of emission gases will
be more significant than other alignments.
Since Alignments 1 and 2 are established in the populated residential area, noise impact will be
the most significant among all the alternatives while for Alignments 3 and 4, which are
established along the rivers or on the river banks, noise impact on roadside residences will be
less significant than that of the other alternative alignments.
For Alternatives 3 and 4, the elevated viaducts are constructed along the river thus areas in
shadow will be smaller than those of other alternative alignments.
In Alignment 3, piers will be constructed on the riverbeds in Pasig River and San Juan River.
Installation of piers may deteriorate river water quality during the construction and also during
its operation.
Estimated construction cost and cost of R.R.O.W. acquisition were calculated based on similar
completed and on-going project data. Estimated cost is shown as follows:
Construction
12,000 14,700 16,400 14,600 9,600 13,900
Cost
ROW
Acquisition
and Land 5,600 5,700 2,100 4,700 4,100 4,400
Improvement
Cost
The comparative study of the six potential alignments for the C-3 Missing Link is presented in
Table 8.4-3.
8.4.8 Effect on the Project Interchanges due to Construction of the Missing Link
The effect on the Project interchanges due to construction of the Missing Link was analyzed using
MMUTIS6 data.
MMUTIS is the “Metro Manila Urban Transportation Integration Study” undertaken by the JICA in
1998. MMUTIS data is currently the latest available traffic study regarding the whole of Metro
Manila area arterial traffic through the MMUTIS Traffic Demand Forecast Model of the transport
network that covers the entire Manila Metropolitan Area.
MMUTIS covers the transport network in the metropolitan area and includes the project coverage of
the 5 interchanges (C-3/E Rodriguez, EDSA/Roosevelt/Congressional, EDSA/North/West/Mindanao,
C-5/Kalayaan, C-5/Green Meadows/Acropolis/Calle Industria) and the C-3 Missing Link is therefore
deemed suitable for the effect analysis. Effect analysis was done for the C-3 Missing Link assuming
the opening year at 2018.
Figure 8.4-1 shows the traffic volume increase/decrease percentage (with Project/without Project)
for the case of C-3 Missing Link construction in 2018 as its opening year.
Due to C-3’s connection to other roads, much traffic running on other ring roads will divert to C-3
with the Missing Link in place. Therefore, traffic volumes of other ring roads will tend to decrease.
6
MMUTIS - “Metro Manila Urban Transportation Integration Study” done by JICA in 1998.
Figure 8.4-1 Effect on Traffic Volume for the Project Interchanges due to Construction of the
C-3 Missing Link
The south road connects to the Missing Link; therefore, the effect is substantial. Traffic between
the north and south (Gregorio Araneta Avenue) will increase by 26-56%.
(2) EDSA/Roosevelt/Congressional
It is located in the north area far from the Missing Link. The traffic on Roosevelt Avenue
connecting to the Missing Link will increase by 46%, but the effects on traffic volume for other
roads connecting to the interchange will be minimal.
(3) EDSA/North/West/Mindanao
It is located in the north area far from the Missing Link. Traffic on West Avenue will divert to
Roosevelt Avenue at EDSA/Roosevelt/Congressional interchange. The traffic volume will be
reduced by about 30%. Roosevelt Avenue is closer to C-3 than West Avenue. Effects on traffic
(4) C-5/Kalayaan
It is on a ring road (Carlos P. Garcia Avenue) parallel to the Missing Link. Traffic on Kalayaan
Ave. will increase by about 10%. Traffic on Carlos P. Garcia Ave. will decrease by about 10%.
It is on a ring road (Eulogio Rodriguez Jr. Avenue) parallel to the Missing Link but it is far from
the Missing Link. The effect on traffic volume will be minimal.
8.4.9 Recommendations
Several alternative alignments for the C-3 missing link have been proposed and studied since the
early 1970s, but the project has not been pursued due to the huge RROW requirement, the large
number of PAPs, the high cost of the project, and the long duration it will take from the study stage
until completion of implementation. Further delay in the construction of said missing link will not
acceptable considering its expected impacts on the present traffic situation in Metro Manila.
The most favored alignments are those that follow the Pasig and San Juan Rivers. These alignments
are favored given that both of the number of affected buildings and PAP’s are minimized and also
the environmental impacts of these alignments are the least.
However, both alternatives have drawbacks: the navigation problems in Pasig River; obstruction of
waterway area in San Juan River for the scheme occupying the waterways, and, a need for
substantial ROW acquisition for the scheme occupying the river banks.
It is recommended that the Study on the C-3 Missing Link should be the subject of a feasibility
study. The scope of the feasibility study should be:
In addition to the DPWH proposal for a C-3 Missing Link Project, there are several other proposals,
from the private sector and other government agencies, to provide elevated roadways serving a
similar function or occupying corridors that may intersect with the C-3 Missing Link Project.
Refer to Figure 8.4-2 for a location plan of the related proposed projects.
The C-3 Expressway involves a 16.2 km., 6 lane divided roadway. It will keep the existing
segments of C-3 road as public access roads with grade separation improvements at the major
proposed intersections along the line (E. Rodriguez, Quezon Avenue, Del Monte, A Bonifacio
and 5th Avenue W/Rizal Avenue).
Southern section this proposed project effectively overlaps with the preferred DPWH
alignment for the C-3 Missing Link.
The 13.3 km NLEX-SLEX Connector is a 4 lane divided elevated tolled roadway that starts at
Skyway Buendia, and the alignment follows PNR tracks up to Caloocan and terminates at the
connection to the NLEx via Segment 10 of the NLEx Phase 2 project at 5th Avenue.
The proposed elevated road will not share any section of the C-3 Missing Link Project
corridor.
The 14.5km Metro Manila Skyway Stage 3 is a 6 lane divided elevated tolled roadway that
starts at Skyway Buendia,, turns right on Quirino Avenue, turns left at San Juan Bridge,
follows G Araneta Avenue and then right at A Bonifacio. The proposed roadway terminates at
Balintawak on EDSA, linking to NLEX.
This proposed elevated road will occupy the same corridor as the C-3 Missing Link at the
junction of N. Domingo with G. Araneta.
The Skybridge will be an 8.3km 6 lane divided elevated roadway following the route of the
preferred DPWH alignment, from JP Rizal Avenue, following the route of the Pasig River and
San Juan River and terminating at the Quezon Avenue.
This proposed project effectively overlaps with the preferred DPWH alignment for the C-3
Missing Link extending the scope of the project to Quezon Avenue.
CHAPTER 9
The 24 km length of EDSA is the main circumferential road of Metro Manila and more than
200,000 vehicles per section on average passes every day. Notwithstanding the improvements to
EDSA brought by the construction of several interchanges, in addition to the MRT Line-3 and LRT
Line-1 North Extension, the limited capacity of EDSA to handle the large daily volumes of traffic
from early morning to late evening has resulted in severe congestion and low traffic speeds. Such a
situation is severely hampering the socio-economic development of Metro Manila and is an
impairment to the environment.
In view of the above critical condition, a Conceptual Study on Traffic Capacity Expansion along
EDSA has been proposed.
The main objective of the study of the capacity expansion of EDSA is to determine the availability
of space and identify possible problem(s) in the construction of a viaduct/tunnel along EDSA
considering the existing structures and also the proposed flyovers.
Some existing plans of trunk roads, expressways and railways are related to the proposed study with
regards to the share of traffic volume but these should not be affected or disturbed much in the
implementation of the proposed project.
9.4 CONFIRMATION OF OPEN SPACES FOR TUNNEL PLAN AND VIADUCT PLAN
The study will confirm in outline the availability of open space to accommodate the support
structures of high level viaduct solutions and tunnel solutions at critical locations along EDSA. The
basic concept in assessing available space is to develop outline solutions that will minimize
occupation of width along EDSA and also minimize ROW acquisition where and if necessary.
The following hindrance structures for both directions on EDSA have been identified:
(1) Topology
EDSA generally has a 50.0m road right of way (RROW). It commonly has ten (10) lanes with
five (5) equal lanes per direction divided by a median separator. Within the 3.0 m sidewalks,
street lights, various utility posts and other overhead cables are found. Several other utility lines
for water, sewerage, etc., are encased in pipes below ground beneath both sidewalk and the road
itself. A median separator exists throughout EDSA. Both the MRT-3 and LRT-1 North Extension
fully occupies this corridor.
Various commercial buildings (malls, markets, shops, etc.), residential structures (hotels,
condominiums, apartments, houses), government and private office buildings are lined up along
EDSA and there are two military camps also located along EDSA.
To ease traffic flow on EDSA slow moving cargo trucks have been prohibited on its major
sections, between Pasong Tamo in Makati and Balintawak in Quezon City/Caloocan City. This is
imposed except on a specific time window which is from 9:00pm to 6:00am daily except Sundays,
and Holidays. To further decongest EDSA, a volume reduction scheme has been implemented to
reduce daily traffic theoretically by twenty percent (20%) by prohibiting all vehicle types on the
basis of its last digit plate number from 7:00am to 7:00pm. On year 2008 the AADT on several
segments of EDSA have already reached more than 200,000 vehicles. For a roadway with
ten-lane capacity this corresponds to a level of service (LOS) F. With the above conditions
prevailing: EDSA at over capacity, prohibitive cost in acquiring additional RROW, and
alternative routes also congested, a capacity expansion scheme via elevated or underground
expressway is seriously being considered.
As described above, improvement of traffic flow along EDSA especially at major intersections
necessitated construction of several grade level separation structures.
As earlier discussed, there are numerous MRT-3 and LRT-1 stations on EDSA which straddle
over its northbound and southbound lanes. The locations of these grade level separation
structures and stations should be considered.
It is proposed that a 23.36km six (6) lane expressway be erected over EDSA to increase its traffic
capacity. This concept will require columns and foundations, over the current roadway. This will
diminish the number of at-grade lanes per direction from five to four. However after the
construction of the elevated viaduct, EDSA will have seven total lanes per direction.
The viaduct layout over the middle lane is preferred as it requires the least impact on existing
overhead and underground utilities and the least reconstruction of existing drainage structures.
The elevation or height of the viaduct is maintained at second level where possible. It is proposed
that the viaduct generally traverse above all pedestrian footbridges with sufficient vertical
headroom.
For site conditions requiring long spans and high piers, steel box girders supported by rectangular
steel columns are recommended. Although costly these are more effective structurally and faster
and easier to construct.
In case of double deck type, viaduct pier supports a three lane upper thoroughfare on top of another
three lane thoroughfare for the opposing traffic direction at its lower deck. These steel viaduct piers
are shown in Figure 9.7-1
The ramps give access to the major central business districts (CBD) of Makati and Ortigas, and the
hub of government offices in Quezon City and distance between each ramps are about 5.3km each.
Construction of ramps are absolutely necessary to secure additional RROW either along EDSA or
along the selected secondary roads deemed suitable as proposed ramp location. The estimated
additional RROW requirement for an elevated viaduct scheme on EDSA is roughly140,000 sq m.
The stretch of EDSA was examined to identify the five most difficult locations for a viaduct
construction. A list ranking first the site assessed with the major hindrance and the most difficult
construction is presented below:
The difficulty at this site is the co-existence of several transport facilities (ie., Skyway’s Toll
Expressway, DPWH’s Magallanes Interchange, and DOTC’s Philippine National Railway
(PNR) train tracks, and MRT-3 light rails). Each entity requires vertical and horizontal clearances
to their transport corridor. Thus at this setting, it is more than likely that the viaduct shall have
long spans (45m to 60m) and tall piers (24m to 32m) because of the said restrictions. For this
viaduct configuration steel structures are recommended.
At this intersection there are multi-level grade separation structures. An underpass road along
EDSA and a third level flyover across EDSA along Shaw Blvd above the second level viaduct of
the MRT-3. A platform station is also located very near the intersection South of EDSA. The
following malls; Rustan’s Shangrila, Starmall, and EDSA Central occupy the three corner lots of
the intersection.
If the viaduct alignment is confined within EDSA RROW, the necessary viaduct length spanning
the covered segment of EDSA is 130m long with pier height at 24m above level ground. To
reduce the required span length, the alignment is shifted West of EDSA and a double deck steel
viaduct is proposed so that this reduces the superstructure span to 60.0m. But still at this
intersection, acquisition of RROW is required.
The interchange at Ortigas intersection has the main flyover on the second level of EDSA. The
left turn flyovers to Pasig and Mandaluyong cross over at the third level. The MRT-3 viaduct also
runs along EDSA at second level above the southbound service lanes and these structures fully
obstruct the passage southbound. The only usable corridor is above the northbound two-lane
service road adjacent to the EDSA National Shrine.
To fit six lanes over two available at-grade lanes and acquire the least RROW, a double deck
viaduct is proposed. For high piers and long spans, steel members are suitable viaduct
components because lighter materials are more manageable to handle and easily erected.
MRT-3 is along EDSA at second level, whereas LRT-2 is along Aurora Blvd at third level
crossing EDSA. Both are above the six lane depressed road along the centerline of EDSA.
Therefore, both the northbound and southbound viaducts will have three lanes and are raised
almost at fifth level as they cross Aurora Blvd. The recommended steel viaduct will have tall
piers with heights near 30m and long spans approximately 50m to 60m.
On EDSA a three-lane flyover on both northbound and southbound directions concurrently with
a four-lane divided underpass, crossing below EDSA along Quezon Avenue, while on the other
hand, the MRT-3 trains run on a viaduct between these flyovers. The construction of proposed
flyovers leave only two traffic lanes on either direction at the outer service lanes.
Therefore, the proposed viaduct will utilize the available space above the service lanes which
will be at third level or 16m above ground. The maximum span will be at approximately 45m to
55m enough to span over Quezon Avenue.
Result of study of five (5) intersections which identified most difficult locations shows that found
spaces for proposed viaduct structures which means that also can be found space for the proposed
flyovers due to difficulty of the proposed flyover are equal or lower than five(5) study conducted
intersections.
The beginning and endpoint of the proposed tunnel are located between Roxas Boulevard and Taft
Avenue, and Monumento Circle and Balintawak, respectively. The main tunnel consists of 2-lane
tunnels (inside diameter D=10.1m) at both sides of the entrance and exit while 3-lane tunnels
(inside diameter D=13.3m) shall be used for the entire middle section. 1-lane ramps (inside
diameter D=6.7m) shall be provided at four (4) locations. There are no problems regarding
horizontal alignment of the tunnel since EDSA does not have steep or extreme variations in
alignment. The tunnel should have enough earth covering due to many structures located along
EDSA; such as MRT stations and flyovers, which are supported by foundation piles. Figure 9.8-1
shows the typical cross sections of 3-types of tunnels, and Figure 9.8-2 shows Tunnel Layout (Plan
and Profile).
To have proper distance of earth covering of tunnel from the hindrance of existing structures.
The main function of the tunnel ventilation system is to discharge the vehicle exhausted fumes and
smoke from fire. Airflow shall be diverted into two (2) sections underneath the deck slab of
carriageway: one to discharge smoke and the other to take in fresh air which will also be utilized for
access of people during an emergency evacuation. Ventilation towers shall be constructed at about
3km intervals because each ventilation tower will not only be used for smoke ventilation but also
for electric supply, water deposit, and access for people. General concepts of this system are shown
in Figure 9.8-3 General Concept of Ventilation System.
Tunnel excavation will be done by one shield machine per direction between departure vertical
shaft and arrival vertical shaft. Shield tunnel construction works are routine works of excavation,
assembly of precast concrete segments and grouting between concrete segment and soil. Process of
shield tunnel is as shown below.
Proper and efficient planning for carrying out and delivery shall be done while also considering
minimizing the influence on existing traffic flow due to the utilization of heavy equipment, such as
trucks and cranes (Please refer to Figure 9.8-4 General Concept of Vertical Shaft).
Based on “installation standards of Emergency Facilities for Road Tunnel” issued by Japan Road
Association, proposed tunnel is classified at the most high rank of “AA” which requires the
provision of all type of facilities such as:
1) Emergency call and warning devices 2) Fire extinguisher equipment 3) Evacuation facilities 4)
Communication system 5) Water spray system, etc.
In consideration of budget and traffic management, the 22.8 km total length of tunnel shall be
divided into 3 packages, as follows:
Based on previous experience of past projects in Japan, the Consultant’s proposed schedule is
shown in Table 9.8-1 Rough Estimated Construction Schedule.
1. Rough cost will be estimated based on completed projects and past experiences in Japan
considering similar site condition of EDSA
2. Exchange rate between peso and yen is 1 peso = 1.90 yen
3. Instead of lease, 10m x 1,000m = 10,000m2 of R.O.W acquisition of ramp will be
considered.
4. Vertical Shaft will be constructed phase by phase to minimize traffic congestion along
EDSA. The present 5-lanes traffic and side walk will be maintained during the construction
with the provision for steel temporary deck plate on the top of vertical shaft. 3,000m2 of
temporary construction yard beside of vertical shaft will be considered as land rental.
5. Land acquisition for ventilation shaft will be considered.
6. 26% is commonly used as indirect cost for general construction projects in the Philippines.
However, 30% will be used as indirect cost considering that this will be the first time to
construct a major tunnel in the Philippines and especially in a major Urban City
environment.
7. Rough Estimate Cost shall consider following five (5) schemes:
Scheme-1 Entire Section of both directions
Main tunnel (3-lane) : 15.5 km x 2-direction
Entrance/exit at both end (2-lane) : 7.3 km x 2-direction
Scheme-2 Package-1 of Scheme-1
Main tunnel (3-lane) : 4.7 km x 2 direction
Entrance/exit (2-lane) : 3.9 km x 2 direction
Scheme-3 Only one (1) direction of scheme-1
Main tunnel (3-lane) : 15.5 km x 1-direction
Entrance/exit at both end (2-lane) : 7.3 km x 1-direction
Scheme-4 Construct 2-lane for both directions
Maintain tunnel (2-lane) : 22.8 km x 2-direction
Scheme-5 Only one (1) direction of scheme-4
Main tunnel (2-lane) : 22.8 km x 1-direction
8. Summary of rough estimated cost of each scheme is shown in Table 9.8-2.
CHAPTER 10
10.1 OBJECTIVES
The objective of the seminar is to introduce the latest Japanese technologies of road and bridge
construction for understanding technical supervision of STEP scheme for the proposed flyover
project and also Filipino engineers to apply these to on-going and/or future projects. Said
technologies are related to tunnel construction, asphalt pavement, rapid construction methods,
bridge rehabilitation and improvement and quality control systems.
DAY2(7th March)
Mr.Nobuhiro HONDA
1. Quality Control of
Quality Control The Overseas Construction Association of Japan,
14:00 - 14:20 Highway and Bridge
Seminar-7 System Inc.
Construction
Technology (SHIMIZU CORPORATION)
14:20 - 14:30 Question / Answer
14:30 - 14:40 Fill up Questionnaire - DPWH Secretariat / KEI
Conclusion and DPWH Under Secretary
14:40 - 14:50 Wrap-up
Recommendations Raul C. Asis
Mr.Yuuki ARATSU
Deputy Director General,
14:50 - 15:00 Closing Statement -
and Group Director for Transportation and ICT
JICA Economic Infrastructure Department
10.3 ATTENDANCE
(1) PHILIPPINES
Attendance from DPWH and other Offices are shown in Table below:
Day 1 Day 2
Attendance
(March 6, 2012) (March 7, 2012)
DPWH Secretary Under Secretary Assistant Secretary 8 8
Regional Directors 16 15
Bureau/Service Directors 13 13
Project Management Office 23 24
Government Agencies 4 4
Local Government Units 13 11
Private Institutions and Academe 7 5
Total 84 80
(2) JAPAN
The list of the Guest Speakers is shown in the aforementioned Seminar Program. The other
attendees from Japan are as follows:
Q&A
The answers given on the questionnaire sheets showed the participants’ high interest on the high
level of technology that was imparted by each topic, as well as their satisfaction on the management
of the Seminar as a whole.
Thirty nine (39) Questionnaire were submitted among the attendees which are summarized
below.
Among the seven (7) topics, the most interesting topics discussed during the seminar were on:
Tunneling Construction Technology ranked first with 17 persons, second was Pavement
Technology, followed by Rapid construction Method (steel bridge) as 3 third in rank.
Q2- What subjects would you consider for future projects or activities, and why?
Among the seven (7) topics, what is to be considered for future projects and activities are
Tunneling Construction Techniques, Pavement Technology ranked the first with 10 persons each,
the second was Rapid Construction Method (Steel Bridge), followed by Rapid Construction
Method (Concrete Bridge) as 3 third 4 in rank. This answer was similar to question-1 above.
Almost all of the attendants were satisfied with each topic, imparted knowledge of new
technology, excellent handouts and the way how to manage the seminar. Some useful comments
were presented: time given to each topic was relatively short; presenters should further explain
how the new technology will be applied and effective in the Philippines context; its trainings in
Japan should be arranged, and venue and comfort rooms was narrow/a little.
10.6 CONCLUSION
The Seminar was satisfactorily conducted because the Guest Speakers lectured on interesting topics
and a lively exchange of questions and answers took place between the Guest Speakers and the
participants during the lecture.
The following are the likely reasons why the Seminar was satisfactorily conducted:
c) Arrangement for inviting relevant offices regarding road and bridge construction was
properly done.
d) Almost all of the top officials from DPWH attended, including the Honorable DPWH
Secretary, attended.
f) Invitation letters were issued in the name of the Honorable DPWH Secretary
The following suggestion for improving the next seminar are from comments on the questionnaire:
a. Should have given more time for each topic (20 minutes presentation is a bit short).
b. Should have considered more applications and knowledge under Philippine setting.
c. Should have provided more comfortable conditions in preparing food and arranging
sufficient number of toilets for the attenders
The following pictures present highlights of attendance of top officials of DPWH, Guest Speaker,
and Japanese experts/resource persons in the Seminar hall.