Commissioning and Testing of AVR and PSS
Commissioning and Testing of AVR and PSS
and Testing of
AVR and PSS
Excitation System Upgrade
and commissioning challenges
Challenges
AVR testing challenges
3. 15 DECEMBER 2017
Excitation System
Replacement
4. 15 DECEMBER 2017
Excitation System Replacement
Challenges with life cycle management
Takes over two years to achieve it; justification, status of asset condition,
budget allocation, resources availability, etc..
5. 15 DECEMBER 2017
Excitation System Replacement
First activity: prepare for Model building
Key information required for proposed model build; (in addition to technical spec)
• Generator parameters
• Gen Transformer parameters
• Grid info at the connection point
6. 15 DECEMBER 2017
Excitation System Replacement
Design and design approvals
Design Phase
• New system supplier system design
• Customer interface design (DCS or SCADA interface) control, etc..
• Grid requirements (dialogue with SO)
Design approval
• Owner’s requirements approval
• SO approvals for the proposed AVR settings (3 months)
7. 15 DECEMBER 2017
Excitation System Replacement
- Asset Life Cycle Management
AVR Cabinet
DC Exciter
Original DC exciter from 40’s • Analogue AVR installed over 25 years ago
coupled to the main shaft • Electronics drifting with ageing
8. 15 DECEMBER 2017
Excitation System Replacement
- Replacement digital excitation system
Excitation Transformer
9. 15 DECEMBER 2017
Excitation System Replacement
- Decommission old equipment
• Removal of exciter
• Removal of old AVR cabinets and cables
• Purpose of Test:
As stipulated in the ancillary services contract, testing is required to determine if the service meets the performance
standards. The system operator needs to ensure the integrity of the voltage-support ancillary-service provision by
issuing requirements to service providers for assessing the voltage support capability of their assets.
To ensure the asset complies with the performance standards outlined in ancillary services
contract
• Outcome:
The required outcome of AVR testing is to provide the system operator with a verified mathematical model that
describes the steady state and dynamic behaviour of the equipment. An accurate representation allows the system
operator to model interactions with the system and other generating stations, when subjected to disturbances on the
system, and thereby control the voltage stability of the system.
To validate the mathematical model
The PSS function improves the stability of the generator and the transmission system as
a whole by using the excitation to damp power oscillations
Rangipo
32. 15 DECEMBER 2017
AVR Testing
In summary
• Peak hours
• Grid emergency
• Parallel activities (other major outages)
• Ops shift change
• Weak Grid
• Plant / hydrology limitations